CN102879206B CN201210354955.8A CN201210354955A CN102879206B CN 102879206 B CN102879206 B CN 102879206B CN 201210354955 A CN201210354955 A CN 201210354955A CN 102879206 B CN102879206 B CN 102879206B
Authority
CN
China
Prior art keywords
loading force
retarder
force
chassis dynamometer
loading
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210354955.8A
Other languages
English (en)
Other versions
CN102879206A (zh
Inventor
吴明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Linyi High Tech Zone Talent Vocational Training School Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201210354955.8A priority Critical patent/CN102879206B/zh
Publication of CN102879206A publication Critical patent/CN102879206A/zh
Application granted granted Critical
Publication of CN102879206B publication Critical patent/CN102879206B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Force Measurement Appropriate To Specific Purposes (AREA)

Abstract

台架电涡流机加载力验证方法,在已有的电涡流机底盘测功机上增加一套力传感器的信号处理系统和验证计算机,并把验证计算机的计算加载力作为真值,当对应检测加载力相对真值加载力误差较大或者真值加载力相对规定加载力误差较大,则验证检测不规范或设备出故障,从而确保车辆在底盘测功机上加载进行各种性能检测的准确性和真实性,具有准确、简便、快捷、价格低等优点。

Description

台架电涡流机加载力验证方法
技术领域
台架电涡流机加载力验证方法,是车辆在电涡流机底盘测功机上进行废气排放、燃料经济性、动力性检测时,防止单片机、计算机等不规范、监管设备的完好性、验证台架电涡流机检测加载力的一种方法,属于车辆性能台试检测监管验证技术领域。
背景技术
车辆在电涡流机底盘测功机上加载负荷工况下进行各种性能检测时,为防止人为修改加载力,确保设备完好,保证规范检测,监管部门需要对加载力进行验证,现有的验证技术通常有两种方式:一种方式是直接接收检测站计算机传送的检测加载力;另一种方式是读取经单片机处理后的数据;两种方式都有可能通过计算机或单片机修改数据,难以有效验证。为克服现有技术的不足,采用台架电涡流机加载力验证方法,实现准确、简单、快捷、有效地验证电涡流机检测加载力。
发明内容
现有底盘测功机大多数采用电涡流机作为功率吸收装置,车辆在底盘测功机上进行加载工况检测时,转子对滚筒产生的加载扭矩,其反作用力通过定子作用在力传感器上,从而测量电涡流机的加载扭矩和加载力。当车辆进行废气排放、燃料经济性、动力性检测时,如果电涡流机检测加载力比验证真值加载力或标准规定加载力更小,检测废气排放减小、油耗减小,实际功率比检测功率更小,从而造成错检错判。
台架电涡流机加载力验证方法,是车辆在底盘测功机台架上进行各种性能检测时,实现远程验证和监管电涡流机加载力的一种方法。其特征在于:在已有的电涡流机底盘测功机上增加一套力传感器电信号的处理系统,直接读取电涡流机力传感器的输出电信号,经放大和单片机A/D转化处理后把所需数据远距离传送给验证计算机,验证计算机自动计算出电涡流机力传感器的加载力,并作为验证电涡流机检测加载力的真值。按车辆不同的性能检测规范要求,确定或计算不同检测工况的真值或规定值,检测站计算机把检测工况的所需检测加载力数据以及规定加载力或计算规定加载力所需参数也远距离传送给验证计算机,如检测加载力相对真值加载力误差较大、或者真值加载力相对规定加载力误差较大,可以验证检测不规范或设备出现故障。
台架电涡流机加载力验证方法,相同的力传感器信号供两个不同的系统进行转换和处理,一个是原设备的系统,检测加载力存在人为修改数据等可能性;另一个是验证和监管系统,没有人为修改数据等不规范,其数据作为真值用于验证检测加载力,以防止设备系统的单片机或计算机人为的修改数据,同时也可监管设备系统是否出现故障。两套系统在相同的力传感器标定下力系数可能不同,但力值基本相等。验证和监管系统只是信号的采集和数据处理,相比设备系统更简单、费用更低。其主要优点如下:
(1)采用单片机自动转换和传输数据给验证计算机,按不同的性能检测规范要求,可全自动验证每一台车辆的检测加载力,而且可以对验证不规范或设备出故障的情况自动报警等,大大提高了验证的效率、准确性和自动化。
(2)验证和监管系统仅与电涡流机底盘测功机的力传感器相关,与底盘测功机的其它硬件和软件都没有关系,并监控了它们的规范性。
(3)通过规范底盘测功机硬件和软件的取样、数据处理等,首先确保验证和监管系统达到规范要求,从而可以检验底盘测功机系统的硬件和软件是否达到规范要求。
(4)可以控制检测值相对真值或者真值相对规定值在一定误差范围内,从而保证电涡流机加载力的准确性和真实性。
(5)虽然仍然存在更换力传感器的可能性,采用一次性唯一标识很容易对其验证和监管。如果制动台每年检定增加验证系统的力系数,验证人员也无需到现场标定。
具体实施方式
分别以废气排放、动力性、燃料经济性三种性能检测举例,来说明台架电涡流机加载力验证方法的具体实施方式。先对力传感器标定确定两套系统的力系数。
(1)按照国标GB18285-2005《点燃式发动机汽车排气污染物排放限值及测量方法(双怠速法及简易工况法》第BA.1款要求,基准质量1230kg的乘用车在ASM5025工况25km/h车速稳态检测时,所需底盘测功机的加载总功率为1230/148=8.31kW,总加载力为8.31×3600/25=1196.6N,减去25km/h台架阻力86.4N,则电涡流机的规定加载力为1196.6-86.4=1110.2N。验证计算机要接收规定加载力或计算规定加载力所需的车速、车辆基准质量等参数,当电涡流机检测加载力838N,而验证计算机的真值670N,则检测加载力838N相对验证计算机的真值670N误差较大,真值670N相对规定值1110N误差较大,可以验证检测不规范或设备出现故障。只有检测加载力、真值加载力相对规定加载力都在一定的误差范围内,则可以验证加载力合格。
(2)一辆柴油车台试检测稳态功率(不含台架阻力功率)为52.3kW,稳态车速为76.8km/h,电涡流机检测加载力为52.3×3600/76.8=2452N,验证计算机在该车速点的真值为1962N,其原因是检测不规范,或者是计算机加大了力系数,或者是用计算机修改了功率值,或者是设备出现故障。
(3)一辆货车台试模拟全质量路试50km/h等速检测百公里油耗,验证计算机要接收规定加载力或计算规定加载力所需的检测登录的相关参数等,检测加载力约等于规定加载力,但是验证计算机的真值加载力比规定加载力减小约20%,则验证检测不规范。
(4)检测车速值不规范也会造成车辆各种性能错检错判,同理,也可以直接读取转速传感器电信号,经单片机A/D转化处理后传送给验证计算机,用真值验证检测值。
(5)当验证合格,则验证计算机可以允许检测站打印出检验报告单,如验证不合格,则验证计算机可以不允许检测站打印出检验报告单,需要查找原因。
台架电涡流机加载力验证方法,增加一套力传感器的信号处理系统和验证计算机,并把它的计算加载力作为真值来验证检测值,从而确保车辆在底盘测功机上加载进行各种性能检测的准确性和真实性,具有准确、简便、快捷、自动等优点。

Claims (1)

1.台架电涡流机加载力验证方法,是车辆在底盘测功机台架上进行各种性能检测时,实现远程验证和监管电涡流机加载力的一种方法,其特征在于:在已有的电涡流机底盘测功机上增加一套力传感器电信号的处理系统,直接读取电涡流机力传感器的输出电信号,经放大和单片机A/D转化处理后把所需数据远距离传送给验证计算机,验证计算机自动计算出电涡流机力传感器的加载力,并作为验证电涡流机检测加载力的真值加载力;按车辆不同的性能检测规范要求,确定或计算不同检测工况的真值或规定值,检测站计算机把检测工况的所需检测加载力数据以及规定加载力或计算规定加载力所需参数也远距离传送给验证计算机,如检测加载力相对真值加载力误差较大、或者真值加载力相对规定加载力误差较大,可以验证检测不规范或设备出现故障;验证和监管系统仅与电涡流机底盘测功机的力传感器相关,与底盘测功机的其它硬件和软件都没有关系,并监控了它们的规范性。
CN201210354955.8A 2012-08-02 2012-09-10 台架电涡流机加载力验证方法 Active CN102879206B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210354955.8A CN102879206B (zh) 2012-08-02 2012-09-10 台架电涡流机加载力验证方法

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
CN201210284585 2012-08-02
CN2012102845855 2012-08-02
CN201210284585.5 2012-08-02
CN201210354955.8A CN102879206B (zh) 2012-08-02 2012-09-10 台架电涡流机加载力验证方法

Publications (2)

Publication Number Publication Date
CN102879206A CN102879206A (zh) 2013-01-16
CN102879206B true CN102879206B (zh) 2015-04-08

Family

ID=47480617

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210354955.8A Active CN102879206B (zh) 2012-08-02 2012-09-10 台架电涡流机加载力验证方法

Country Status (1)

Country Link
CN (1) CN102879206B (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112379193B (zh) * 2020-10-27 2022-02-08 山东大学 一种测试简易瞬态工况法系统精度的检验方法
CN113281061B (zh) * 2021-05-23 2023-06-27 朱卫萍 汽车稳态工况检测加载力的验证方法

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5465612A (en) * 1994-06-16 1995-11-14 Clayton Industries Method and apparatus for testing motor vehicles under simulated road conditions
CN2281531Y (zh) * 1996-11-26 1998-05-13 田作友 一种汽车底盘测功机
CN101581613B (zh) * 2009-06-16 2011-05-11 深圳市万德源科技发展有限公司 汽车底盘测功机及其测量控制方法
CN101871845B (zh) * 2010-02-01 2012-01-25 华东交通大学 一种汽车传动系传动效率不拆卸测量装置及测量方法
CN101858828B (zh) * 2010-05-31 2011-07-27 吴明 轻重车型通用底盘测功机

Also Published As

Publication number Publication date
CN102879206A (zh) 2013-01-16

Similar Documents

Publication Publication Date Title
US10006895B2 (en) System and method for monitoring atmospheric pollution
CN103308324A (zh) 汽车智能化综合性能检测系统
CN109900483A (zh) 一种汽车在线检测系统
CN102563362A (zh) 压缩空气系统管网泄漏智能检测方法及系统
CN105115578A (zh) 一种通过测量钢板形变检测车辆载重的方法及测量系统
CN102879206B (zh) 台架电涡流机加载力验证方法
CN105973591B (zh) 一种变速箱的测试系统
CN104165676A (zh) 通过轴动态监控、轴组秤量的动态车辆高精度称重方法
CN206683703U (zh) 一种柴油车碳平衡法油耗检测系统
CN204359419U (zh) 一种车辆应变称重系统
CN105351755A (zh) 汽车供气系统天然气泄漏检测方法
CN108572077A (zh) 一种汽车发动机检测系统
CN105988460A (zh) 车辆跑道动态检测方法、装置和系统
CN104501929A (zh) 车辆应变称重系统
CN202757787U (zh) 汽车安全性能检测线装备
CN107807056A (zh) 一种基于加速度载荷谱的汽车零部件损伤评估系统
CN110618100A (zh) 汽车尾气对大气污染的随车、道路实时监测装置及方法
CN102486399A (zh) 汽车载重量远程检测装置
CN202501984U (zh) 一种机动车检测线过程记录仪
CN204241506U (zh) 滚筒式速度表检查台测量装置
CN204964002U (zh) 复杂动态称重传感网络的远程自诊断系统
CN102879207B (zh) 滚筒制动台检测力验证方法
KR20100073239A (ko) 제동 시험기의 교정 장치
CN115172911A (zh) 一种汽车锂电池用分析预测系统及警示方法
CN107655801A (zh) 一种粉尘传感器检测系统

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201016

Address after: Suzhou City, Jiangsu province 215600 Zhangjiagang Yang Binhe Road, No. 5 ikang B building

Patentee after: SUZHOU COFFMAN MACHINERY Co.,Ltd.

Address before: 528415, Xiaolan Town, Xiaolan Town, Zhongshan, Guangdong, No. 16 vehicle Siu Lam inspection station

Patentee before: Wu Ming

TR01 Transfer of patent right

Effective date of registration: 20240919

Address after: 276000 413, block B, Chuangxin building, high tech Industrial Development Zone, Linyi City, Shandong Province

Patentee after: Linyi high tech Zone Talent vocational training school Co.,Ltd.

Country or region after: China

Address before: 215600 building B, Aikang building, No.5 Binhe Road, yangshe Town, Zhangjiagang City, Suzhou City, Jiangsu Province

Patentee before: SUZHOU COFFMAN MACHINERY CO.,LTD.

Country or region before: China