CN102877537A - Establishment and construction of sewer of road fixed well - Google Patents

Establishment and construction of sewer of road fixed well Download PDF

Info

Publication number
CN102877537A
CN102877537A CN2012103306043A CN201210330604A CN102877537A CN 102877537 A CN102877537 A CN 102877537A CN 2012103306043 A CN2012103306043 A CN 2012103306043A CN 201210330604 A CN201210330604 A CN 201210330604A CN 102877537 A CN102877537 A CN 102877537A
Authority
CN
China
Prior art keywords
construction
template
sewer
solid power
handing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012103306043A
Other languages
Chinese (zh)
Inventor
李尚喜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2012103306043A priority Critical patent/CN102877537A/en
Publication of CN102877537A publication Critical patent/CN102877537A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The invention relates to establishment and construction of a sewer of a road fixed well, which comprises the combination of a planar upper template and a planar lower template, a plug double-head template and an in-length double-head template. The establishment and construction of the sewer of the road fixed well are characterized in that the combination of the planar upper template and the planar lower template is used for forming the construction of the template of the road sewer fixed well; a base-angle joining method is used for a plug to implement the blunt-head joint method in the length direction; the detachment is convenient; top and bottom vertical seams adopt inclined joining and male and female joining methods; and the upper template and the lower template adopt a half-press and half-joining method to be combined into a completed sewer fixed well. The establishment and construction of the sewer of the road fixed well solve the problem of repeated construction on roads, are new reformation and development for the current road establishment, and can improve the engineering quality and accelerate the construction period.

Description

Solid power down-hole, highway roadside water channel is built and construction
Technical field:
Solid power down-hole, highway of the present invention roadside water channel is built and construction, relates to the highway communication field, and the solid power down-hole water channel facility that relates in particular in the highway construction is particularly important.
Technical background
Solid power down-hole, highway of the present invention roadside water channel is built and construction, relate to highway construction and construction in present highway construction trouble, what repeat to take a lot of work most has been exactly the facility of highway roadside sewer, in the highway construction construction, a solid power down-hole water channel, just repeatedly construction, repeatedly recruitment added and dug, dug and added, duplication of labour intensity is large, has brought huge overlapping investment to repeat construction to highway construction, has caused significant wastage in construction manpower, raw material, time, economy.
Summary of the invention:
Solid power down-hole, highway of the present invention roadside water channel is built and construction, and problem to be solved is, has just in time overcome the deficiency in the above-mentioned technology, utilizes template construction to solve the problems referred to above.
Solid power down-hole, highway of the present invention roadside water channel is built and construction, the favourable measure that the problems referred to above are taked is, comprise road surface bolster combination, plug two template, suitable long two template, it is characterized in that utilizing the solid power well template construction of roadside sewer of combination forming, angle handing-over method is built in the plug utilization, and along the blunt nosed handing-over method of long enforcement, it all is empty making the Jing Neimobanjiao place, dismantle very conveniently, be combined into a complete sewer Gu Lijing.
Solid power down-hole, described highway roadside water channel is built and construction, and feature is that angle handing-over method is built in the plug utilization, utilizes the base angle head to make the template face, and the well inner face leaves empty angle and is beneficial to convenient disassembly during dismounting.
Shown in solid power down-hole, highway roadside water channel build and construction, feature is to implement blunt nosed handing-over method along long, is to build the Angle formwork convenient disassembly, oblique skin handing-over of vertical design and male and female join two kinds of methods in the middle of the polylith template.
Solid power down-hole, described highway roadside water channel is built and construction, and feature is that sewer solid power well method in the design roadside is criticized the dual-purpose solid power well lid of temporary supporting.
Solid power down-hole, described highway roadside water channel is built and construction, and feature is that template saves up and down, presses the outer half handing-over method of partly pressing in handing-over is implemented.
The beneficial effect of the solid power down-hole water channel construction in highway of the present invention roadside and construction is, 1 utilizes template to solve the in batches construction overlapping investment duplication of labour problem of sewer, 2 energy conservation reduce rubbish, 3 accelerate speed of application, guarantee construction quality, 5 in time alleviate traffic pressure, improve the highway maximum value.
Description of drawings
Solid power down-hole, highway shown in Figure 1 roadside water channel is built and solid power down-hole, construction roadside water channel stencil plane foundation drawing.
Solid power down-hole, highway shown in Figure 2 roadside water channel is built and the long face die plate schematic diagram of construction.
Solid power down-hole, highway shown in Figure 3 roadside water channel is built and wide locking plug template schematic diagram of construction.
Solid power down-hole, highway shown in Figure 4 roadside water channel is built with the interim Gu Ligai of construction and is directly utilized interim admittedly power lid stereogram.
The solid power down-hole water channel construction in highway shown in Figure 5 roadside and construction up and down joint handing-over are implemented half and are pressed and partly join the method schematic diagram.
The specific embodiment
Consolidate the water channel construction of power down-hole and execute solid power down-hole, highway limit water channel stencil plane foundation drawing referring to highway shown in Figure 1 roadside, in construction of the highway, utilize template to highway bed construction layering template construction, Gu Lijing is carried out the layering adjunction, save up and down in template, the junction utilizes the half handing-over method of partly pressing, designed an oblique skin handing-over and two kinds of handing-over methods of male and female in the middle of this template, to the interim cross hang of enforcement in the well, and designed layering and supported dual-purpose interim admittedly power well lid.
Build and the long face die plate schematic diagram of construction referring to solid power down-hole, highway shown in Figure 2 roadside water channel, the obtuse angle has been designed at the solid microscler template of the power well two of sewer, the design is oblique skin handing-over male and female handing-over fado piece splice template face, designed an oblique skin handing-over in the middle of each solid power well, during the template dismounting, begin dismounting from oblique skin, support with cross in the well, to implementing the mounted split pattern construction in the solid power well well, the direct and pavement concrete handing-over in outside.
Build and wide the locking plug template schematic diagram of constructing referring to solid power down-hole, highway shown in Figure 3 roadside water channel, the solid power well plane of structure plug of sewer is implemented to build the angie type template construction, to being abutted against near that face of concrete and along long face, the well inner face leaves empty angle convenient disassembly.
Consolidate power lid stereogram referring to the water channel construction of solid power down-hole, highway shown in Figure 4 roadside and the interim Gu Ligai of construction with directly utilizing temporarily, after every layer of template adjunction, cover again layering and consolidate the power well lid temporarily, this Gu Lijing should, 1 plays the covering construction after covering, and 2 directly play the effect of well inner support.
Referring to the solid power down-hole water channel construction in highway shown in Figure 5 roadside and construction up and down male and female handing-over schematic diagram the design save up and down the template utilization and partly press the handing-over of half handing-over method, by on depress [interior pressure is outer] handing-over method.

Claims (5)

1. solid power down-hole, highway roadside water channel is built and construction, comprise bolster combination, plug two template, suitable long two template, it is characterized in that utilizing the solid power well template construction of roadside sewer of combination forming, angle handing-over method is built in the plug utilization, along the blunt nosed handing-over method of long enforcement, convenient disassembly is combined into a complete sewer Gu Lijing, this template is for once dropping into, repeatedly application and construction.
2. solid power down-hole, highway roadside water channel is built and is constructed as claimed in claim 1, and feature is that angle handing-over method is built in the plug utilization, utilizes the base angle head to make the template face, and interior well face leaves empty angle and is beneficial to dismounting during dismounting.
3. the water channel construction of solid power down-hole, highway roadside and construction shown in claim 1, feature are along the blunt nosed handing-over method of long enforcement, are to build the Angle formwork convenient disassembly, have designed an oblique skin handing-over and male and female handing-over method in the middle of the polylith template.
4. solid power down-hole, highway roadside water channel is built and construction as claimed in claim 1, and feature is that sewer solid power well method in the design roadside is criticized the dual-purpose solid power well lid of temporary supporting.
5. solid power down-hole, highway roadside water channel is built and construction as claimed in claim 1, it is characterized in that the bolster combination utilizes half pressure half, the diplomatic connection of interior pressure.
CN2012103306043A 2012-08-28 2012-08-28 Establishment and construction of sewer of road fixed well Pending CN102877537A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012103306043A CN102877537A (en) 2012-08-28 2012-08-28 Establishment and construction of sewer of road fixed well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012103306043A CN102877537A (en) 2012-08-28 2012-08-28 Establishment and construction of sewer of road fixed well

Publications (1)

Publication Number Publication Date
CN102877537A true CN102877537A (en) 2013-01-16

Family

ID=47479037

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012103306043A Pending CN102877537A (en) 2012-08-28 2012-08-28 Establishment and construction of sewer of road fixed well

Country Status (1)

Country Link
CN (1) CN102877537A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58199939A (en) * 1982-05-13 1983-11-21 Yanagisawa Concrete Kogyo Kk Formwork for vertical wall of manhole
CN2398376Y (en) * 1999-09-02 2000-09-27 赵景 Easy disassembling mould
CN2635736Y (en) * 2003-08-12 2004-08-25 张东川 Shaping mould for manhole
KR20070006541A (en) * 2005-07-08 2007-01-11 세종산업개발(주) Formwork for integral coupling of manhole and tube and manhole structure produced by it
KR200443682Y1 (en) * 2007-08-31 2009-03-06 영남콘크리트 (주) A Manhole mold device
CN201722706U (en) * 2010-06-03 2011-01-26 文彦 Concrete fragment combined inspection well
CN102155025A (en) * 2011-03-23 2011-08-17 东南大学 Late poured band type assembled pipe jacking working open caisson

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58199939A (en) * 1982-05-13 1983-11-21 Yanagisawa Concrete Kogyo Kk Formwork for vertical wall of manhole
CN2398376Y (en) * 1999-09-02 2000-09-27 赵景 Easy disassembling mould
CN2635736Y (en) * 2003-08-12 2004-08-25 张东川 Shaping mould for manhole
KR20070006541A (en) * 2005-07-08 2007-01-11 세종산업개발(주) Formwork for integral coupling of manhole and tube and manhole structure produced by it
KR200443682Y1 (en) * 2007-08-31 2009-03-06 영남콘크리트 (주) A Manhole mold device
CN201722706U (en) * 2010-06-03 2011-01-26 文彦 Concrete fragment combined inspection well
CN102155025A (en) * 2011-03-23 2011-08-17 东南大学 Late poured band type assembled pipe jacking working open caisson

Similar Documents

Publication Publication Date Title
CN105908862B (en) A kind of production method of masonry shell in 3D printing reinforced masonry shear wall
CN103009477A (en) Construction method for prefabricated components for prefabricated component factory
CN102873072A (en) Mobile production system capable of demolishing buildings selectively on site and recycling construction waste
CN201713970U (en) Structural system with light multi-ribbed plates and light multi-ribbed floor systems
CN102877537A (en) Establishment and construction of sewer of road fixed well
CN103072194B (en) A kind of prefabricated reinforced concrete anticollision barrier mould
CN207672389U (en) Roadbed concrete curb cast-in-place mould
CN202849893U (en) Concrete slab pavement structure
CN102877487B (en) The construction method of the solid power well template Facilities Construction of highway
CN203462669U (en) Integrated stair
CN104294904A (en) Road side fixing well sewer building and construction method
CN104988839B (en) Subgrade and pavement pave edge no formwork erection construction paving help plant equipment
CN203213111U (en) Cap of prefabricated static-pressure square pile
CN209350489U (en) A kind of wire box precast concrete block structure of transvers plate for building
CN203994166U (en) A kind of water storage square brick mould
CN205954643U (en) Concrete bank protection suppression instrument
CN209273674U (en) Mobile down-pressing laminated floor slab production equipment structure with shear key
CN202727092U (en) Plugging device for position of straight rib of side mold of precast concrete component of wall
CN206220057U (en) One-step forming die for open drain
CN206718140U (en) A kind of mould for producing pre-stressed concrete hollow support pile
CN215329983U (en) Prefabricated device of garden lawn landscape lamp installation basis
CN213563414U (en) Preparation mould of reinforced concrete drain pipe
CN202273251U (en) Water stop precast slab for soil covering slab culvert
CN207616875U (en) A kind of retaining wall prefabricated-member mould
CN211571233U (en) Concrete slab made of waste concrete

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130116