CN202727092U - Plugging device for position of straight rib of side mold of precast concrete component of wall - Google Patents

Plugging device for position of straight rib of side mold of precast concrete component of wall Download PDF

Info

Publication number
CN202727092U
CN202727092U CN 201220293257 CN201220293257U CN202727092U CN 202727092 U CN202727092 U CN 202727092U CN 201220293257 CN201220293257 CN 201220293257 CN 201220293257 U CN201220293257 U CN 201220293257U CN 202727092 U CN202727092 U CN 202727092U
Authority
CN
China
Prior art keywords
diameter
wall
boss
chassis
side mold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220293257
Other languages
Chinese (zh)
Inventor
霍晓光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
1 ST CONSTRUCTION CO Ltd OF 22 MCC GROUP
China 22MCC Group Corp Ltd
Original Assignee
1 ST CONSTRUCTION CO Ltd OF 22 MCC GROUP
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 1 ST CONSTRUCTION CO Ltd OF 22 MCC GROUP, China 22MCC Group Corp Ltd filed Critical 1 ST CONSTRUCTION CO Ltd OF 22 MCC GROUP
Priority to CN 201220293257 priority Critical patent/CN202727092U/en
Application granted granted Critical
Publication of CN202727092U publication Critical patent/CN202727092U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Moulds, Cores, Or Mandrels (AREA)

Abstract

A plugging device for the position of a straight rib of a side mold of a precast concrete component of a wall is composed of a circular stepped shaft which is composed of a chassis and a boss, wherein the diameter of the boss is matched with the diameter of an open hole of the side mold, and the diameter of the chassis is larger than that of the boss. The circular stepped shaft is provided with a central hole, the diameter of the chassis is 20mm larger than that of the boss, the thickness of the boss and the thickness of the chassis are respectively 10mm, and the diameter of the central hole is at least 1mm smaller than that of an extended rib of the wall. According to the plugging device for the position of the straight rib of the side mold of the precast concrete component of the wall, production modes can be standardized, construction operation is simplified, and labor efficiency is improved; the problem of slurry leakage of a reserved hole during wall production is solved; and continuous investment is reduced, cost is saved, and quality of the precast component is guaranteed.

Description

墙体混凝土预制构件边模直筋位置封堵装置The position sealing device of the side formwork straight reinforcement of the wall concrete prefabricated component

技术领域 technical field

本实用新型涉及一种建筑物施工机械设备,具体的说,是涉及一种墙体混凝土预制构件边模直筋位置封堵装置。  The utility model relates to a building construction machinery and equipment, in particular to a sealing device for the position of the straight reinforcement of the side mold of the wall concrete prefabricated component. the

背景技术 Background technique

在装配式混凝土结构中,要求墙体混凝土预制构件水平筋及竖向筋伸出构件,以作为预制构件安装时节点连接用。为此需要在墙体生产的模具上预留出筋孔洞,而为了拆模的方便预留钢筋与模具间必然会存在较大的缝隙,在混凝土浇筑作业时会由此部位漏浆。  In the prefabricated concrete structure, the horizontal reinforcement and vertical reinforcement of the concrete prefabricated component of the wall are required to protrude from the component, which is used for the node connection during the installation of the prefabricated component. For this reason, it is necessary to reserve a rib hole on the mold produced by the wall body, and there must be a large gap between the reserved steel bar and the mold for the convenience of form removal, and the grout will leak from this position during the concrete pouring operation. the

墙体混凝土预制构件在生产过程中,需要针对模具上预留出筋孔洞进行封堵,防止漏浆问题的发生。现有施工方式中,对预留孔进行封堵主要采用泡沫棒或钢板封堵,此两种封堵方式第一种封堵材料的周转次数有限,会增加封堵材料的投入费用;第二种方式不利于工人的安装及拆除操作,效率较低。  During the production process of wall concrete prefabricated components, it is necessary to seal the holes reserved on the mould, so as to prevent the occurrence of grout leakage. In the existing construction methods, foam rods or steel plates are mainly used to block the reserved holes. The first of these two plugging methods has a limited turnover of the plugging material, which will increase the input cost of the plugging material; the second This way is unfavorable for the installation and removal operation of workers, and the efficiency is low. the

实用新型内容 Utility model content

针对上述现有技术中的不足,本实用新型提供一种能够解决预留孔漏浆难题的墙体混凝土预制构件边模直筋位置封堵装置。  Aiming at the deficiencies in the above-mentioned prior art, the utility model provides a position sealing device for the straight reinforcement of the side form of the wall concrete prefabricated member which can solve the problem of grout leakage from the reserved hole. the

本实用新型所采取的技术方案是:  The technical scheme that the utility model takes is:

一种墙体混凝土预制构件边模直筋位置封堵装置,由圆形阶梯轴组成,所述圆形阶梯轴由底盘和凸台组成,所述凸台的直径与边模开孔直径相适配,所述底盘直径大于凸台直径;所述圆形阶梯轴设置有中心孔。 A device for blocking the position of the straight reinforcement of the side formwork of a prefabricated wall concrete component, which is composed of a circular stepped shaft, the circular stepped shaft is composed of a chassis and a boss, and the diameter of the boss is suitable for the diameter of the opening of the side formwork Matching, the diameter of the chassis is greater than the diameter of the boss; the circular stepped shaft is provided with a central hole.

所述底盘直径大于凸台直径20mm。  The diameter of the chassis is 20mm larger than the diameter of the boss. the

所述凸台与底盘的厚度均为10mm。  The thicknesses of the boss and the chassis are both 10mm. the

所述中心孔直径至少小于墙体出筋直径1mm。  The diameter of the central hole is at least 1 mm smaller than the diameter of the ribs on the wall. the

本实用新型相对现有技术的有益效果:  The utility model has the beneficial effects relative to the prior art:

本实用新型墙体混凝土预制构件边模直筋位置封堵装置,可以规范生产方式,简化施工操作,提高劳动效率;解决墙体生产时预留孔漏浆的问题;减少持续投入,节约制造成本,保证了预制构件的质量。 The utility model provides a plugging device for the position of the straight reinforcement of the side mold of the wall concrete prefabricated member, which can standardize the production mode, simplify the construction operation, and improve labor efficiency; solve the problem of grout leakage in the reserved holes during wall production; reduce continuous investment and save manufacturing costs , to ensure the quality of prefabricated components.

附图说明 Description of drawings

图1是本实用新型墙体混凝土预制构件边模直筋位置封堵装置主视结构示意图;  Fig. 1 is the front structural schematic diagram of the plugging device for the side formwork straight rib position of the concrete prefabricated member of the wall body of the utility model;

图2是本实用新型墙体混凝土预制构件边模直筋位置封堵装置侧视结构示意图。 Fig. 2 is a side view structural diagram of the sealing device for the position of the straight reinforcement of the side form of the wall concrete prefabricated member of the utility model.

附图中主要部件符号说明:  Explanation of symbols of main components in the drawings:

图中:  In the picture:

1、凸台         2、底盘 1. Boss 2. Chassis

3、中心孔  。 3. Center hole.

具体实施方式 Detailed ways

以下参照附图及实施例对本实用新型进行详细的说明:  The utility model is described in detail below with reference to accompanying drawing and embodiment:

附图1至2可知,一种墙体混凝土预制构件边模直筋位置封堵装置,由圆形阶梯轴组成,所述圆形阶梯轴由底盘和凸台组成,所述凸台的直径与边模开孔直径相适配,所述底盘直径大于凸台直径;所述圆形阶梯轴设置有中心孔;所述底盘直径大于凸台直径20mm;所述凸台与底盘的厚度均为10mm;所述中心孔直径至少小于墙体出筋直径1mm。 As can be seen from accompanying drawings 1 to 2, a kind of wall concrete prefabricated component side formwork straight reinforcement position sealing device is made up of circular stepped shaft, and described circular stepped shaft is made up of chassis and boss, and the diameter of described boss is the same as The opening diameter of the side mold is suitable, the diameter of the chassis is larger than the diameter of the boss; the circular stepped shaft is provided with a central hole; the diameter of the chassis is 20mm larger than the diameter of the boss; the thickness of the boss and the chassis are both 10mm ; The diameter of the central hole is at least 1 mm smaller than the diameter of the ribs exiting the wall.

本实用新型墙体混凝土预制构件边模直筋位置封堵装置,可以规范生产方式,简化施工操作,提高劳动效率;解决墙体生产时预留孔漏浆的问题;减少持续投入,节约成本,保证了预制构件的质量。  The utility model wall concrete prefabricated component side mold straight rib position sealing device can standardize the production mode, simplify the construction operation, improve labor efficiency; solve the problem of grout leakage in the reserved holes during wall production; reduce continuous investment, save costs, The quality of prefabricated components is guaranteed. the

本实用新型墙体混凝土预制构件边模直筋位置封堵装置由橡胶制成,外形尺寸可按照出筋直径的不同进行调整。  The utility model wall concrete prefabricated member side formwork straight rib position sealing device is made of rubber, and the external dimension can be adjusted according to the difference of the diameter of the rib. the

本实用新型墙体混凝土预制构件边模直筋位置封堵装置工作方式为:  The working mode of the sealing device for the position of the straight reinforcement of the side form of the wall concrete prefabricated member of the utility model is as follows:

在钢筋绑扎完毕边模固定后将伸出边模的钢筋穿入墙体混凝土预制构件边模直筋位置封堵装置的中心圆孔内,该装置沿钢筋向边模移近直到凸台顶进边模孔内,底盘边顶在边模上为止;混凝土预制构件成型后将本实用新型从预留孔拆卸下来即可。本实用新型墙体混凝土预制构件边模直筋位置封堵装置可以重复使用,因此提高劳动效率,节约制造成本。 After the steel bars are bound and the side formwork is fixed, the steel bars protruding from the side formwork are inserted into the central circular hole of the plugging device for the position of the straight bars of the side formwork of the prefabricated concrete component of the wall. In the side formwork hole, the chassis edge is pushed against the side formwork; after the concrete prefabricated component is formed, the utility model can be disassembled from the reserved hole. The utility model can repeatedly use the sealing device for the position of the straight reinforcement of the side form of the concrete prefabricated member of the wall body, so that the labor efficiency is improved and the manufacturing cost is saved.

Claims (4)

1.一种墙体混凝土预制构件边模直筋位置封堵装置,其特征在于:由圆形阶梯轴组成,所述圆形阶梯轴由底盘和凸台组成,所述凸台的直径与边模开孔直径相适配,所述底盘直径大于凸台直径;所述圆形阶梯轴设置有中心孔。 1. a kind of wall concrete prefabricated member side mold straight rib position sealing device is characterized in that: it is made up of circular stepped shaft, and described circular stepped shaft is made up of chassis and boss, and the diameter of described boss is in line with the edge The diameter of the mold opening is suitable, and the diameter of the chassis is larger than the diameter of the boss; the circular stepped shaft is provided with a central hole. 2.根据权利要求1所述墙体混凝土预制构件边模直筋位置封堵装置,其特征在于:所述底盘直径大于凸台直径20mm。 2. The device for sealing the position of the straight reinforcement of the side form of the prefabricated wall concrete member according to claim 1, wherein the diameter of the chassis is 20mm larger than the diameter of the boss. 3.根据权利要求1所述墙体混凝土预制构件边模直筋位置封堵装置,其特征在于:所述凸台与底盘的厚度均为10mm。 3. The device for sealing the position of the straight reinforcement of the side form of the prefabricated concrete member of the wall according to claim 1, wherein the thickness of the boss and the chassis are both 10 mm. 4.根据权利要求1所述墙体混凝土预制构件边模直筋位置封堵装置,其特征在于:所述中心孔直径至少小于墙体出筋直径1mm。 4. The device for sealing the position of the straight reinforcement of the side form of the prefabricated concrete member of the wall according to claim 1, wherein the diameter of the central hole is at least 1mm smaller than the diameter of the reinforcement of the wall.
CN 201220293257 2012-06-21 2012-06-21 Plugging device for position of straight rib of side mold of precast concrete component of wall Expired - Lifetime CN202727092U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220293257 CN202727092U (en) 2012-06-21 2012-06-21 Plugging device for position of straight rib of side mold of precast concrete component of wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220293257 CN202727092U (en) 2012-06-21 2012-06-21 Plugging device for position of straight rib of side mold of precast concrete component of wall

Publications (1)

Publication Number Publication Date
CN202727092U true CN202727092U (en) 2013-02-13

Family

ID=47652833

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220293257 Expired - Lifetime CN202727092U (en) 2012-06-21 2012-06-21 Plugging device for position of straight rib of side mold of precast concrete component of wall

Country Status (1)

Country Link
CN (1) CN202727092U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106042172A (en) * 2016-05-25 2016-10-26 中交第航务工程局有限公司 Rubber blanket slurry stopping process for position of prefabricated part protruding bars
CN110318526A (en) * 2018-03-31 2019-10-11 中国二十冶集团有限公司 Overhanging channel steel hole device and its application method for concrete prefabricated element
CN115534071A (en) * 2022-10-09 2022-12-30 金鹏装配式建筑有限公司 Mold plugging structure and laminated panel production line for prefabricated laminated panel production

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106042172A (en) * 2016-05-25 2016-10-26 中交第航务工程局有限公司 Rubber blanket slurry stopping process for position of prefabricated part protruding bars
CN110318526A (en) * 2018-03-31 2019-10-11 中国二十冶集团有限公司 Overhanging channel steel hole device and its application method for concrete prefabricated element
CN115534071A (en) * 2022-10-09 2022-12-30 金鹏装配式建筑有限公司 Mold plugging structure and laminated panel production line for prefabricated laminated panel production

Similar Documents

Publication Publication Date Title
CN202644997U (en) Simple plugging device for wall-penetrating holes of wall
CN103029204B (en) Modularized side form for prefabricating superimposed sheet
CN202727092U (en) Plugging device for position of straight rib of side mold of precast concrete component of wall
CN201376314Y (en) Prefabricated part forming die
CN202131618U (en) Seepage-prevention joint device for underground diaphragm wall
CN202164698U (en) Steel die for sewage inspection well
CN202622993U (en) Side mold plugging device at hoop position of wall concrete prefabricated member
CN204001723U (en) The detachable combined steel tool of a kind of shear wall reserved opening
CN203821456U (en) Outer side plugging structure of basement outer wall post-pouring joint
CN206769180U (en) A kind of shaped steel hole prefabricated section through walls
CN211775704U (en) building wood formwork
CN206201157U (en) A kind of prefab-form
CN105041340A (en) Structure and construction method for increasing arch crown concrete pouring speed in tunnel engineering
CN105569092B (en) Underground pipe gallery deformation joint water-stopping belt transmission rod position integrated template construction method
CN205244648U (en) Novel prestressing force steel cylinder concrete jack pipe
CN204748888U (en) Prefabricated coincide floor preparation leaking stoppage piece and have mould of this leaking stoppage piece for mould
CN204510810U (en) A kind of formwork structure for shutoff exterior wall reserved opening
CN204525753U (en) A kind of cement pipe molding mould
CN203188250U (en) Basement exterior wall post-cast strip construction structure
CN205976497U (en) Capillary groove design mould
CN211729620U (en) Precast concrete superimposed sheet mould
CN204590605U (en) Building steel door and window hole large form
CN207538061U (en) A kind of foundation forms for independent bearing platform construction
CN211397147U (en) Windowsill coping structure
CN203668962U (en) Bottom-section open caisson with waterproof structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20130213

CX01 Expiry of patent term