CN102868323A - 一种光伏电站发电预测控制方法 - Google Patents
一种光伏电站发电预测控制方法 Download PDFInfo
- Publication number
- CN102868323A CN102868323A CN2012103094872A CN201210309487A CN102868323A CN 102868323 A CN102868323 A CN 102868323A CN 2012103094872 A CN2012103094872 A CN 2012103094872A CN 201210309487 A CN201210309487 A CN 201210309487A CN 102868323 A CN102868323 A CN 102868323A
- Authority
- CN
- China
- Prior art keywords
- generating
- data
- power generation
- photovoltaic
- time period
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/50—Photovoltaic [PV] energy
Landscapes
- Photovoltaic Devices (AREA)
Abstract
Description
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012103094872A CN102868323A (zh) | 2012-08-28 | 2012-08-28 | 一种光伏电站发电预测控制方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012103094872A CN102868323A (zh) | 2012-08-28 | 2012-08-28 | 一种光伏电站发电预测控制方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102868323A true CN102868323A (zh) | 2013-01-09 |
Family
ID=47446979
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012103094872A Pending CN102868323A (zh) | 2012-08-28 | 2012-08-28 | 一种光伏电站发电预测控制方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102868323A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104361406A (zh) * | 2014-10-31 | 2015-02-18 | 许继集团有限公司 | 一种光伏电站可利用太阳能发电量预测方法 |
CN105894128A (zh) * | 2016-04-26 | 2016-08-24 | 佛山电力设计院有限公司 | 一种区域太阳能预测及预测结果实时发布方法及系统 |
CN107092994A (zh) * | 2017-06-21 | 2017-08-25 | 苏州协鑫新能源运营科技有限公司 | 一种预测供电量的方法 |
CN108985625A (zh) * | 2018-07-16 | 2018-12-11 | 浙江电腾云光伏科技有限公司 | 一种光伏设备运行分析方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201540488U (zh) * | 2009-11-24 | 2010-08-04 | 中环光伏系统有限公司 | 一种全天候自适应单轴太阳能跟踪系统 |
CN101969207A (zh) * | 2010-09-16 | 2011-02-09 | 国网电力科学研究院 | 结合卫星遥感与气象遥测技术的光伏超短期功率预测方法 |
CN102163853A (zh) * | 2010-02-15 | 2011-08-24 | 株式会社电装 | 用于插入式车辆的充电控制器和导航设备 |
CN102522917A (zh) * | 2011-11-18 | 2012-06-27 | 中国电力科学研究院 | 光伏电站发电输出功率预测方法 |
-
2012
- 2012-08-28 CN CN2012103094872A patent/CN102868323A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201540488U (zh) * | 2009-11-24 | 2010-08-04 | 中环光伏系统有限公司 | 一种全天候自适应单轴太阳能跟踪系统 |
CN102163853A (zh) * | 2010-02-15 | 2011-08-24 | 株式会社电装 | 用于插入式车辆的充电控制器和导航设备 |
CN101969207A (zh) * | 2010-09-16 | 2011-02-09 | 国网电力科学研究院 | 结合卫星遥感与气象遥测技术的光伏超短期功率预测方法 |
CN102522917A (zh) * | 2011-11-18 | 2012-06-27 | 中国电力科学研究院 | 光伏电站发电输出功率预测方法 |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104361406A (zh) * | 2014-10-31 | 2015-02-18 | 许继集团有限公司 | 一种光伏电站可利用太阳能发电量预测方法 |
CN104361406B (zh) * | 2014-10-31 | 2017-11-21 | 许继集团有限公司 | 一种光伏电站可利用太阳能发电量预测方法 |
CN105894128A (zh) * | 2016-04-26 | 2016-08-24 | 佛山电力设计院有限公司 | 一种区域太阳能预测及预测结果实时发布方法及系统 |
CN107092994A (zh) * | 2017-06-21 | 2017-08-25 | 苏州协鑫新能源运营科技有限公司 | 一种预测供电量的方法 |
CN108985625A (zh) * | 2018-07-16 | 2018-12-11 | 浙江电腾云光伏科技有限公司 | 一种光伏设备运行分析方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Washom et al. | Ivory tower of power: Microgrid implementation at the University of California, San Diego | |
Rahman et al. | Advances in solar photovoltaic power plants | |
Jin et al. | Multicriteria planning for distributed wind generation under strategic maintenance | |
CN104715340A (zh) | 一种基于绿色能源的云计算能源管理系统及方法 | |
Sanduleac et al. | Integrating the electrical vehicles in the smart grid through unbundled smart metering and multi-objective virtual power plants | |
CN105634139A (zh) | 一种智能微网控制和电能质量监控一体化设备 | |
Zeng et al. | Notice of Retraction: Research of the Problems of Renewable Energy Orderly Combined to the Grid in Smart Grid | |
CN102868323A (zh) | 一种光伏电站发电预测控制方法 | |
Meng et al. | Degradation model of the orbiting current for GaInP/GaAs/Ge triple-junction solar cells used on satellite | |
Kanwal et al. | Gaussian process regression based inertia emulation and reserve estimation for grid interfaced photovoltaic system | |
Hasan et al. | The impact of temperature on battery degradation for large-scale bess in pv plant | |
Karoui et al. | Diagnosis and prognosis of complex energy storage systems: tools development and feedback on four installed systems | |
Andrae et al. | Comparative screening life cycle impact assessment of renewable and fossil power supply for a radio base station site | |
CN106356906A (zh) | 一种基于微电网的节能控制方法及系统 | |
CN107612022B (zh) | 含岸电的微电网系统及其电能调控方法 | |
Alsharif et al. | Applications of Solar Energy Technologies in North Africa: Current Practices and Future Prospects | |
CN203233179U (zh) | 风电功率预测系统 | |
Li et al. | A chance-constrained programming based energy storage system sizing model considering uncertainty of wind power | |
CN104978614A (zh) | 一种光伏发电预测系统 | |
CN115081735A (zh) | 一种基于小波神经网络的光伏功率预测方法及系统 | |
Singh | The role of hosting capacity study in power system advancements: a review | |
CN107276073A (zh) | 一种基于负荷‑风光等效负荷的母线负荷预测方法 | |
Mladenov et al. | Forecasting and risk assessment in MV grids | |
Dunlop et al. | Standards for the assessment of the environmental performance of photovoltaic modules, power conditioning components and photovoltaic systems | |
Atmaja et al. | Component degradation and system deterioration: An overview of early termination of PV-DG microgrid system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C53 | Correction of patent of invention or patent application | ||
CB02 | Change of applicant information |
Address after: Xinghua Road 518067 Guangdong city of Shenzhen Province, No. 6, building 6, 406-408 Library of the South China Sea Applicant after: CHINA SUSTAINABLE CONSTRUCTION GROUP CO., LTD. Address before: Xinghua Road 518067 Guangdong city of Shenzhen Province, No. 6, building 6, 406-408 Library of the South China Sea Applicant before: China South Curtain Wall Co., Ltd. |
|
COR | Change of bibliographic data |
Free format text: CORRECT: APPLICANT; FROM: CHINA SOUTH CURTAIN WALL CO., LTD. TO: SHENZHEN LANBO LVJIAN GROUP CO., LTD. |
|
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20130109 |