CN102864920A - Planar tight abutted seam large-area aluminium plate ceiling construction method - Google Patents

Planar tight abutted seam large-area aluminium plate ceiling construction method Download PDF

Info

Publication number
CN102864920A
CN102864920A CN2011102439429A CN201110243942A CN102864920A CN 102864920 A CN102864920 A CN 102864920A CN 2011102439429 A CN2011102439429 A CN 2011102439429A CN 201110243942 A CN201110243942 A CN 201110243942A CN 102864920 A CN102864920 A CN 102864920A
Authority
CN
China
Prior art keywords
ceiling
construction method
plate
ceiling construction
plane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011102439429A
Other languages
Chinese (zh)
Inventor
曹沛君
魏无蓉
陈菊俊
朱建新
顾宇
周艺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Suming Decoration Co Ltd
Original Assignee
Suzhou Suming Decoration Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Suming Decoration Co Ltd filed Critical Suzhou Suming Decoration Co Ltd
Priority to CN2011102439429A priority Critical patent/CN102864920A/en
Publication of CN102864920A publication Critical patent/CN102864920A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention provides a planar tight abutted seam large-area aluminium plate ceiling construction method. The ceiling construction method comprises the following steps of: dividing a construction section; positioning and measuring; mounting primary and secondary keels; processing a ceiling plate; mounting connecting pieces; mounting the ceiling plate; and checking the ceiling plate. The ceiling construction method effectively solves the problems that several times of adjusting and checking are required to keep unification of gaps, waste is caused as a plate size has to be changed when an accumulated error is larger and the rate of the progress is slower in the traditional ceiling. The ceiling construction method is used for achieving the purposes of making sizes of plates uniform, shortening processing period, realizing one-time in-place mounting and saving labor cost.

Description

The large plate aluminium sheet of the close piece in a kind of plane large tracts of land ceiling construction method
Technical field
The present invention relates to the large plate aluminium sheet of the close piece large tracts of land in a kind of plane ceiling construction method.
Background technology
Gapless when " close piece " aluminium sheet ceiling construction is the aluminium sheet splicing.During the traditional handicraft furred ceiling, all leave the above flexible space of 10-20mm between plate and the plate, however the aluminium sheet of traditional handicraft lifting, flexible gap size is difficult to control, and cumulative errors are large.In the situation that the large whole impression of area requires, be difficult to reach the effect of design.Adopt large tracts of land aluminium sheet furred ceiling " close piece " job practices, effectively control cumulative errors, improve this engineering whole impression quality, increase work efficiency.Also reduced simultaneously mounting cost.
Summary of the invention
Provide following technical scheme in order to overcome the technical problem that exists in the prior art, to the invention provides:
The large plate aluminium sheet of the close piece large tracts of land in a kind of plane large tracts of land ceiling construction method is characterized in that described method step is:
A) construction section is divided: according to drawing, the ceiling construction work plane is divided, constuction joint is located at the structure junction, utilize structural joint that work plane is cut apart;
B) location survey: according to ready-portioned construction section, utilize transit with the control point pilot measurement of every shrinkage joint to the location keel of furred ceiling work plane, and carry out on the ground the unwrapping wire anchor point and carry out fender pile;
C) primary and secondary skeletal frame is installed: according to the form of structure that design drawing requires, and the zinc-plated square tube main joist of connected mode lifting 40*40;
D) ceiling board processing: determine the ceiling board size according to each section size, machining accuracy, materials arrival check;
E) installation of connector: select dissimilar connected modes according to the furred ceiling scheme, calculate the connection supporting capacity;
Whether F) the installation of ceiling board: the position line during according to measurement is hung two-way control line, and first examination is hung, and the plate sample is led the way, and presses again large tracts of land expansion of tab order, measure at any time installing plate simultaneously and conform to and the degree of deviation with setting-out point;
G) ceiling board check and correction.
As the preferred technical solution of the present invention, among the described step C, fastener or fastener mode are adopted in the connection of primary and secondary skeletal frame, work as after the keel lifting is finished and it are carried out strict check and correction, the absolute altitude planeness.
The beneficial effect that the present invention brings is: adopts this method to efficiently solve and had been the unification of maintenance slit in the furred ceiling in the past, and be through adjusting several times check and correction; The board dimension of having to change when cumulative errors are larger causes waste, the slower contradiction of progress simultaneously, and the size that is used for plate is unified, and the process-cycle shortens, and one-time-reach-place is installed, and has saved labour cost.
Description of drawings
Fig. 1 is furred ceiling aluminium sheet and keel connection diagram
Fig. 2 is the flexible schematic diagram of processing of aluminium sheet lap gap
The specific embodiment
Below in conjunction with accompanying drawing preferred embodiment of the present invention is elaborated, thereby so that advantages and features of the invention can be easier to be it will be appreciated by those skilled in the art that protection scope of the present invention is made more explicit defining.
The large plate aluminium sheet of the close piece in a kind of plane large tracts of land ceiling construction method, described method step is:
A) construction section is divided: according to drawing, the ceiling construction work plane is divided, constuction joint is located at the structure junction, utilize structural joint that work plane is cut apart;
B) location survey: according to ready-portioned construction section, utilize transit with the control point pilot measurement of every shrinkage joint to the location keel of furred ceiling work plane, and carry out on the ground the unwrapping wire anchor point and carry out fender pile;
C) primary and secondary skeletal frame is installed: according to the form of structure that design drawing requires, and the zinc-plated square tube main joist of connected mode lifting 40*40;
D) ceiling board processing: determine the ceiling board size according to each section size, machining accuracy, materials arrival check;
E) installation of connector: select dissimilar connected modes according to the furred ceiling scheme, calculate the connection supporting capacity; As depicted in figs. 1 and 2.
Whether F) the installation of ceiling board: the position line during according to measurement is hung two-way control line, and first examination is hung, and the plate sample is led the way, and presses again large tracts of land expansion of tab order, measure at any time installing plate simultaneously and conform to and the degree of deviation with setting-out point;
G) ceiling board check and correction.
Among the described step C, fastener or fastener mode are adopted in the connection of primary and secondary skeletal frame, work as after the keel lifting is finished and it are carried out strict check and correction, the absolute altitude planeness.
The above; it only is one of the specific embodiment of the present invention; but protection scope of the present invention is not limited to this; any those of ordinary skill in the art are in the disclosed technical scope of the present invention; variation or the replacement that can expect without creative work all should be encompassed within protection scope of the present invention.Therefore, protection scope of the present invention should be as the criterion with the protection domain that claims were limited.

Claims (2)

1. the large plate aluminium sheet of the close piece in plane large tracts of land ceiling construction method is characterized in that described method step is:
A) construction section is divided: according to drawing, the ceiling construction work plane is divided, constuction joint is located at the structure junction, utilize structural joint that work plane is cut apart;
B) location survey: according to ready-portioned construction section, utilize transit with the control point pilot measurement of every shrinkage joint to the location keel of furred ceiling work plane, and carry out on the ground the unwrapping wire anchor point and carry out fender pile;
C) primary and secondary skeletal frame is installed: according to the form of structure that design drawing requires, and the zinc-plated square tube main joist of connected mode lifting 40*40;
D) ceiling board processing: determine the ceiling board size according to each section size, machining accuracy, materials arrival check;
E) installation of connector: select dissimilar connected modes according to the furred ceiling scheme, calculate the connection supporting capacity;
Whether F) the installation of ceiling board: the position line during according to measurement is hung two-way control line, and first examination is hung, and plate is itched and led the way, and presses again large tracts of land expansion of tab order, measure at any time installing plate simultaneously and conform to and the degree of deviation with setting-out point;
G) ceiling board check and correction.
2. the large plate aluminium sheet of the close piece in a kind of plane according to claim 1 large tracts of land ceiling construction method, it is characterized in that among the described step C, fastener or fastener mode are adopted in the connection of primary and secondary skeletal frame, work as after the keel lifting is finished and it is carried out strict check and correction, the absolute altitude planeness.
CN2011102439429A 2011-08-24 2011-08-24 Planar tight abutted seam large-area aluminium plate ceiling construction method Pending CN102864920A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011102439429A CN102864920A (en) 2011-08-24 2011-08-24 Planar tight abutted seam large-area aluminium plate ceiling construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011102439429A CN102864920A (en) 2011-08-24 2011-08-24 Planar tight abutted seam large-area aluminium plate ceiling construction method

Publications (1)

Publication Number Publication Date
CN102864920A true CN102864920A (en) 2013-01-09

Family

ID=47444027

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011102439429A Pending CN102864920A (en) 2011-08-24 2011-08-24 Planar tight abutted seam large-area aluminium plate ceiling construction method

Country Status (1)

Country Link
CN (1) CN102864920A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111549967A (en) * 2020-04-23 2020-08-18 江苏兴业智慧建筑科技有限公司 Novel ceiling board connecting structure and construction process thereof
CN114086712A (en) * 2021-11-12 2022-02-25 中铁建设集团(杭州)建设有限公司 Alternate construction method for splicing aluminum veneers in high and large space

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4457249A (en) * 1980-07-11 1984-07-03 K B Weecan Marine Method of fabricating an integral shell formed body and the body formed thereby
CN101575892A (en) * 2009-03-26 2009-11-11 北京市建筑工程装饰有限公司 Large-area lower edge nested aluminum plate curved hung ceiling with high punching rate and construction method thereof

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4457249A (en) * 1980-07-11 1984-07-03 K B Weecan Marine Method of fabricating an integral shell formed body and the body formed thereby
CN101575892A (en) * 2009-03-26 2009-11-11 北京市建筑工程装饰有限公司 Large-area lower edge nested aluminum plate curved hung ceiling with high punching rate and construction method thereof

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
彭艳等: "大面积铝合金吊顶施工工法", 《建筑技术》 *
王长贵: "体育馆大面积铝扣板吊顶施工工艺", 《安徽建筑》 *
蹇强等: "铝板吊顶施工技术", 《中国新技术新产品》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111549967A (en) * 2020-04-23 2020-08-18 江苏兴业智慧建筑科技有限公司 Novel ceiling board connecting structure and construction process thereof
CN114086712A (en) * 2021-11-12 2022-02-25 中铁建设集团(杭州)建设有限公司 Alternate construction method for splicing aluminum veneers in high and large space

Similar Documents

Publication Publication Date Title
CN103774853A (en) Installation construction method for curtain wall with hyperbolic metal veneer
CN203640309U (en) Adjustable pipe carrier used on large-span steel structure roof primary truss general assembly jig frame
CN105019665A (en) Method for mounting long-span structure beam based on total station
CN103498523A (en) Floor system
CN102102444A (en) Assembling and positioning construction method of large steel casting members
CN104196231A (en) Concrete floor aluminum alloy template and construction method thereof
CN103088843B (en) Pipe gallery embedded iron parts construction method of installation
CN102864920A (en) Planar tight abutted seam large-area aluminium plate ceiling construction method
CN203213372U (en) F-shaped hanging piece and suspended ceiling system employing same
CN202299020U (en) A unit pottery pipe decoration curtain wall member
CN104060841B (en) Large-span steel girder construction method of installation
CN203701066U (en) Soil pressure meter position-adjustable fixed installation device
CN204024088U (en) The fast-positioning device of workshop steel column sectional lifting docking
CN111746753A (en) Method for mounting box leg web plate of container ship
CN104563525B (en) A kind of box steel arch beam Integral horizontal type group is to method
CN103184743B (en) Template flange
CN203113563U (en) Unit-typed curtain wall
CN203145274U (en) Purlin for steel-structure buildings
CN204435632U (en) A kind of double curved surface metal curtain wall
CN105064643B (en) The cladding accurate installation method of building stones hanging part for board of R types
CN211317106U (en) Add axillary plate template mounting detection ruler
CN104989015A (en) Heat insulation installation structure for novel stone curtain wall
CN210217179U (en) Steel skirting line decorated by exposed bolts
CN211597203U (en) Connection structure and precast concrete wallboard system
CN105421780A (en) Construction method of prefabricated concrete structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 215000 Xiangcheng District, Jiangsu Province, Yang Cheng Road, No. 98, No.

Applicant after: Suzhou Suming Decoration Co., Ltd.

Address before: 215000 Xiangcheng District, Jiangsu Province, Yang Cheng Road, No. 98, No.

Applicant before: Suzhou Suming Decoration Co.,Ltd.

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130109