CN102864777A - Fast prestress anchor stock structure and construction method - Google Patents

Fast prestress anchor stock structure and construction method Download PDF

Info

Publication number
CN102864777A
CN102864777A CN2012103894524A CN201210389452A CN102864777A CN 102864777 A CN102864777 A CN 102864777A CN 2012103894524 A CN2012103894524 A CN 2012103894524A CN 201210389452 A CN201210389452 A CN 201210389452A CN 102864777 A CN102864777 A CN 102864777A
Authority
CN
China
Prior art keywords
anchor
boring
anchor bar
bar
waist rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012103894524A
Other languages
Chinese (zh)
Inventor
张诗悦
孟庆祥
赵志涵
顾建国
娄保东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hohai University HHU
Original Assignee
Hohai University HHU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hohai University HHU filed Critical Hohai University HHU
Priority to CN2012103894524A priority Critical patent/CN102864777A/en
Publication of CN102864777A publication Critical patent/CN102864777A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses a fast prestress anchor stock structure. The structure is characterized by comprising a pedestal (1) arranged on one lateral side of a waist rail (4); a drill (5) penetrates through the waist rail (4) and enters a supporting body on the other lateral side of the waist rail (4); an anchoring reinforcement (2) penetrates through the pedestal (1) and is arranged in the drill (5), and a plurality of barbs (6) are arranged at the inner section of the anchoring reinforcement (2); a bearing plate (3) is arranged at the outer end of the anchoring reinforcement (2), and grout (7) is arranged in the drill (5) and around the anchoring reinforcement (2). Additionally, the invention further provides a construction method for the prestress anchor stock structure. According to the structure and the method, the structural design is reasonable, the application range is wide, the contact area of the pile foundation with surrounding soil layers can be obviously increased on the premise that the pile length and the cross section area are not changed, a large prestress can be exerted, the construction time can be reduced greatly, and the construction period is shortened.

Description

A kind of quick prestressed anchor structure and job practices
Technical field
The present invention relates to a kind of concrete anchor rod that is widely used in the various basic loads such as construction work, bridge engineering, municipal engineering, hydraulic engineering, specifically relate to structure and the construction technology of novel anchor pole, be specially adapted to the unstable situation that needs reinforcement in a hurry and process of side slope.
Background technology
Prestress anchoraging is a kind of measure that increases retaining structure or stability of rock-soil body with anchoring process.Its method is that drilling passes the slide plane that might slide or slided, one end of reinforcing bar (or cable wire) is fixed in the stable Rock And Soil at the bottom of the hole, reinforcing bar (or cable wire) is strained so that can produce certain screen resilience (being prestressing force) again, then the other end with reinforcing bar (rope) is fixed in Rock And Soil or retaining structure surface, utilizing the screen resilience of reinforcing bar to compress can slidable Rock And Soil or retaining structure, with the shear strength on the increase slide plane, thereby reach the purpose that improves Rock And Soil or retaining structure stability.
In the process of prestressed anchor construction, because the adhesion stress between reinforcing bar and the grouting body just can be carried out stretch-draw when reaching certain value, need the time more than 7 days in the general process, the stand-by period is longer.
Summary of the invention
The objective of the invention is to have overcome the deficiencies such as prestressed anchor construction period length of the prior art, complex procedures, proposed that a kind of engineering time section, frictional resistance are large, structure and the job practices of the quick prestressed anchor of good stability, but in extensive use and the building hydraulic engineering.
The technical solution used in the present invention is as follows:
A kind of quick prestressed anchor structure, it is characterized in that it includes pedestal, anchor bar, bearing plate, waist rail and boring, described pedestal is installed on the side of waist rail, the supporter that waist rail enters into the another side of waist rail is passed in boring, anchor bar passes pedestal and is installed in the boring, inner section of anchor bar is provided with many hangnails, in the outer end of anchor bar bearing plate is installed, in the described boring anchor bar around be provided with the grouting body.
Described hangnail is for being welded on the anchor bar, and the hangnail structure is flakey, and direction is outside towards anchor pole.
The present invention also provides a kind of job practices that adopts above-mentioned quick prestressed anchor structure, it is characterized in that concrete steps are:
(1) at first needs to calculate the pre-fixed pile of stake, then adopt various suitable boring methods to get out the native hole of projected depth in predetermined stake position;
(2) boring complete after, anchor bar is squeezed in the boring;
(3) after anchor bar is got to the precalculated position, the stretch-draw anchor reinforcing bar embeds in the rock of the soil body hangnail on the anchor bar on every side;
(4) in boring, pour into mixed earth packing material, form the grouting body anchor bar (2) is more intactly bondd with surrounding soil by mixing earth;
(5) carry out the waist rail construction, according to designing requirement size excavation pedestal foundation trench, will reserve again the hole that pedestal is put in good anchor bar end, then load onto bearing plate in the anchor bar end;
(6) the stretch-draw anchor reinforcing bar reaches predetermined power, and the unnecessary exposed steel bar of pruning;
(7) sealing off and covering anchorage, construction finishes.
Compared with prior art, the invention has the beneficial effects as follows:
Reasonable in design, applied range, can be under the prerequisite that does not change pile length and section area, increase significantly pile foundation and the contact area between the soil layer on every side, can apply larger prestressing force, adopt rational technology and construction technology, can greatly reduce the engineering time, so just can make the speed of application of prestressed anchor obtain larger performance, reduce the duration.
Description of drawings
Fig. 1 is the overall structure schematic diagram of prestressed anchor structure of the present invention.
The specific embodiment
Below in conjunction with accompanying drawing with further specify embodiments of the present invention.
As shown in Figure 1, prestressed anchor structure of the present invention includes pedestal 1, anchor bar 2, bearing plate 3, waist rail 4 and holes 5, described pedestal 1 is installed on the side of waist rail 4, the supporter that waist rail 4 enters into the another side of waist rail 4 is passed in boring 5, and anchor bar 2 passes pedestal 1 and is installed in the boring 5.2 inner sections of anchor bars are provided with many hangnails 6, and hangnail 6 is to be welded on the anchor bar 2, and hangnail 6 structures can be flakey, and direction is outside towards anchor pole.In the outer end of anchor bar 2 bearing plate 3 is installed, the grouting body 7 that forms for concrete around the 5 interior anchor bars 2 of holing.
Step during Specific construction is as follows:
(1) at first needs to calculate the pre-fixed pile of stake, then adopt various suitable boring methods to get out the native hole of projected depth in predetermined stake position, as adopting augers, the first-class boring method of Churn drill;
(2) boring complete after, with anchor bar 2 squeeze into boring 5 in;
(3) after anchor bar 2 is got to the precalculated position, stretch-draw anchor reinforcing bar 2 embeds in the rock of the soil body hangnail 6 on the anchor bar 2 on every side;
(4) in boring 5, pour into mixed earth packing material, form grouting body 7 anchor bar 2 is more intactly bondd with surrounding soil by mixing earth;
(5) carry out waist rail 4 constructions, according to designing requirement size excavation pedestal foundation trench, will reserve again the hole that pedestal 1 is put in good anchor bar 2 ends, then load onto bearing plate 3 in anchor bar 2 ends; Fix the template concreting, vibration compacting.
(6) stretch-draw anchor reinforcing bar 2 reaches predetermined power, and the unnecessary exposed steel bar of pruning;
(7) sealing off and covering anchorage, construction finishes.
The undeclared part of other that the present invention relates to is same as the prior art.

Claims (4)

1. quick prestressed anchor structure, it is characterized in that it includes pedestal (1), anchor bar (2), bearing plate (3), waist rail (4) and boring (5), described pedestal (1) is installed on the side of waist rail (4), the supporter that waist rail (4) enters into the another side of waist rail (4) is passed in boring (5), anchor bar (2) passes pedestal (1) and is installed in the boring (5), inner section of anchor bar (2) is provided with many hangnails (6), in the outer end of anchor bar (2) bearing plate (3) is installed, is provided with grouting body (7) around the interior anchor bar of described boring (5) (2).
2. quick prestressed anchor structure according to claim 1 is characterized in that described hangnail (6) for being welded on the anchor bar (2), and hangnail (6) structure is flakey, and direction is outside towards anchor pole.
3. job practices that adopts the described quick prestressed anchor structure of claim 1 is characterized in that concrete steps are:
(1) at first needs to calculate the pre-fixed pile of stake, then adopt various suitable boring methods to get out the native hole of projected depth in predetermined stake position;
(2) boring complete after, anchor bar (2) is squeezed in the boring (5);
(3) after anchor bar (2) is got to the precalculated position, stretch-draw anchor reinforcing bar (2) embeds in the rock of the soil body hangnail (6) on the anchor bar (2) on every side;
(4) in boring (5), pour into mixed earth packing material, form grouting body (7) anchor bar (2) is more intactly bondd with surrounding soil by mixing earth;
(5) carry out waist rail (4) construction, according to designing requirement size excavation pedestal foundation trench, will reserve again the hole that pedestal (1) is put in good anchor bar (2) end, then load onto bearing plate (3) in anchor bar (2) end;
(6) stretch-draw anchor reinforcing bar (2) reaches predetermined power, and the unnecessary exposed steel bar of pruning;
(7) sealing off and covering anchorage, construction finishes.
4. job practices according to claim 3 is characterized in that described hangnail (6) for being welded on the anchor bar (2), and hangnail (6) structure is flakey, and direction is outside towards anchor pole.
CN2012103894524A 2012-10-15 2012-10-15 Fast prestress anchor stock structure and construction method Pending CN102864777A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012103894524A CN102864777A (en) 2012-10-15 2012-10-15 Fast prestress anchor stock structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012103894524A CN102864777A (en) 2012-10-15 2012-10-15 Fast prestress anchor stock structure and construction method

Publications (1)

Publication Number Publication Date
CN102864777A true CN102864777A (en) 2013-01-09

Family

ID=47443888

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012103894524A Pending CN102864777A (en) 2012-10-15 2012-10-15 Fast prestress anchor stock structure and construction method

Country Status (1)

Country Link
CN (1) CN102864777A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103114586A (en) * 2013-01-29 2013-05-22 合肥工业大学 Pressure bearing type soil slope anchor and construction method thereof
CN105297721A (en) * 2015-09-18 2016-02-03 中国科学院武汉岩土力学研究所 Limit shearing resistance superposition type anchor rope and method for grouting anchor hole
CN106703022A (en) * 2017-01-10 2017-05-24 广东水利电力职业技术学院(广东省水利电力技工学校) Uplift pile with surface elastic scales and construction method of uplift pile
CN106703029A (en) * 2016-11-29 2017-05-24 河南理工大学 Pressure-type pre-stressed anchor capable of reducing prestress loss
CN108589720A (en) * 2018-04-12 2018-09-28 河海大学 A kind of intersection squeezes out anchoring rod and its application method
CN109083668A (en) * 2018-08-20 2018-12-25 中钢集团马鞍山矿山研究院有限公司 A kind of grouting and reinforcing anchor pole suitable for high stress breaking surrounding rock supporting
CN113585306A (en) * 2021-09-02 2021-11-02 曹双利 Water conservancy project impermeable membrane cofferdam structure and construction method thereof
US11612929B2 (en) * 2017-01-30 2023-03-28 Gripmetal Limited Texture workpiece and method for texturing a workpiece

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0941372A (en) * 1995-07-27 1997-02-10 Kurosawa Kensetsu Kk U-turn type ground anchor structure and pc steel stranded wire used for anchor structure thereof
CN2284811Y (en) * 1996-05-03 1998-06-24 宣嘉伦 Assembling butterfly anchor bolt
KR200167806Y1 (en) * 1999-08-11 2000-02-15 이재갑 Ground anchor using a steel pipe
KR100446586B1 (en) * 2001-06-04 2004-09-07 심동수 Soil-Nail able to Withdraw Itself by Blasting
CN101619574A (en) * 2009-07-28 2010-01-06 朱奎 Prestress pulling resistant anchor pile and constructing method thereof
CN101768967A (en) * 2008-12-29 2010-07-07 郑鸿彰 Soil anchor quick construction method and anchor thereof
CN201826872U (en) * 2010-11-01 2011-05-11 中铁十三局集团第四工程有限公司 Anchor rod with rebar barbs

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0941372A (en) * 1995-07-27 1997-02-10 Kurosawa Kensetsu Kk U-turn type ground anchor structure and pc steel stranded wire used for anchor structure thereof
CN2284811Y (en) * 1996-05-03 1998-06-24 宣嘉伦 Assembling butterfly anchor bolt
KR200167806Y1 (en) * 1999-08-11 2000-02-15 이재갑 Ground anchor using a steel pipe
KR100446586B1 (en) * 2001-06-04 2004-09-07 심동수 Soil-Nail able to Withdraw Itself by Blasting
CN101768967A (en) * 2008-12-29 2010-07-07 郑鸿彰 Soil anchor quick construction method and anchor thereof
CN101619574A (en) * 2009-07-28 2010-01-06 朱奎 Prestress pulling resistant anchor pile and constructing method thereof
CN201826872U (en) * 2010-11-01 2011-05-11 中铁十三局集团第四工程有限公司 Anchor rod with rebar barbs

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103114586A (en) * 2013-01-29 2013-05-22 合肥工业大学 Pressure bearing type soil slope anchor and construction method thereof
CN103114586B (en) * 2013-01-29 2016-08-31 合肥工业大学 Holding type pressure slight slope anchor and construction method thereof
CN105297721A (en) * 2015-09-18 2016-02-03 中国科学院武汉岩土力学研究所 Limit shearing resistance superposition type anchor rope and method for grouting anchor hole
CN106703029A (en) * 2016-11-29 2017-05-24 河南理工大学 Pressure-type pre-stressed anchor capable of reducing prestress loss
CN106703022A (en) * 2017-01-10 2017-05-24 广东水利电力职业技术学院(广东省水利电力技工学校) Uplift pile with surface elastic scales and construction method of uplift pile
US11612929B2 (en) * 2017-01-30 2023-03-28 Gripmetal Limited Texture workpiece and method for texturing a workpiece
CN108589720A (en) * 2018-04-12 2018-09-28 河海大学 A kind of intersection squeezes out anchoring rod and its application method
CN109083668A (en) * 2018-08-20 2018-12-25 中钢集团马鞍山矿山研究院有限公司 A kind of grouting and reinforcing anchor pole suitable for high stress breaking surrounding rock supporting
CN109083668B (en) * 2018-08-20 2020-05-19 中钢集团马鞍山矿山研究院有限公司 Be suitable for slip casting reinforcing stock of high stress broken country rock support usefulness
CN113585306A (en) * 2021-09-02 2021-11-02 曹双利 Water conservancy project impermeable membrane cofferdam structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN102864777A (en) Fast prestress anchor stock structure and construction method
CN202559345U (en) Bottom-expanded pre-stress anti-floating anchor rod
CN201722685U (en) No-adhesive prestress and pile side rear grouting punching pile structure
CN104131560A (en) Anti-floating anchor and construction method thereof
CN103603379A (en) Anti-floating system combining anti-floating cement soil pile and anti-floating anchor rod and construction process of anti-floating system
CN106930436B (en) Reinforced concrete shear wall with built-in prestressed steel diagonal bracing
CN103410144B (en) Prestressed reinforcement piles set into rock and construction method
CN103924679B (en) Prestressed concrete beam and circular steel pipe concrete column combined joint connected with regular rebars
CN103924676B (en) Prestressing force connects beams of concrete concrete-filled circular steel tube column node
CN201943069U (en) Precast compacting-enlarging pile
CN102134861B (en) Method for testing precast pile in soil body
CN104452757A (en) Quick presressed anchor rod structure and construction method
CN203530974U (en) Anti-floating anchor rod
CN209211459U (en) Skirt piles are gone along with sb. to guard him in a kind of buried subway station PBA
CN102251533B (en) Spiral ribbed steel pipe concrete pre-pressed composite oblique pile foundation and construction method
CN108643215B (en) Construction method of anchor pier type foundation after rotary spraying and pressing into variable cross section
CN206693469U (en) A kind of precast floor slab connecting node
CN103938731B (en) Combination joint of prefabricated concrete beam and round concrete filled steel tubular column connected through pre-stressed steel bars and common steel bars
CN201857608U (en) Synthetic pile
CN103924685B (en) Prestress connected concrete beam round steel tube concrete column node
CN204080797U (en) The composite pile of a kind of PHC stake and YTSC stake
CN103938734B (en) Prestressing force is connected beams of concrete square steel tube concrete column combination node with regular reinforcement
CN102080376B (en) Built-in composite anchor rod construction method and composite anchor rod drilling tool used by same
CN201132956Y (en) Prestressing force connecting apparatus for rods for reinforcing concrete static pressure piles
RU85499U1 (en) STRENGTHENING STRENGTH PLATE BASE

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130109