CN101619574A - Prestress pulling resistant anchor pile and constructing method thereof - Google Patents

Prestress pulling resistant anchor pile and constructing method thereof Download PDF

Info

Publication number
CN101619574A
CN101619574A CN200910161845A CN200910161845A CN101619574A CN 101619574 A CN101619574 A CN 101619574A CN 200910161845 A CN200910161845 A CN 200910161845A CN 200910161845 A CN200910161845 A CN 200910161845A CN 101619574 A CN101619574 A CN 101619574A
Authority
CN
China
Prior art keywords
anchor
hole
steel strand
cement
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200910161845A
Other languages
Chinese (zh)
Other versions
CN101619574B (en
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2009101618458A priority Critical patent/CN101619574B/en
Publication of CN101619574A publication Critical patent/CN101619574A/en
Application granted granted Critical
Publication of CN101619574B publication Critical patent/CN101619574B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a prestress pulling resistant anchor pile and a constructing method thereof. The constructing method is characterized by comprising the following steps: (1) constructing a cement stirring pile; (2) pre-drilling: after cement stirring pile construction is finished, a small-bore diameter driller is immediately taken to pre-drill, and the driller jets slurry and fully stirs in the center of the stirring pile; (3) drilling an anchor hole: an anchor rod driller drills after 12 hours to 14 hours of the cement stirring pile construction finishing, and the drilling speed is 200 mm/min; (4) milling a hole; (5) leading an anchor rod to penetrate through the hole; (6) grouting: the first grouting amount is based on filing up the hole, and the fullness coefficient reaches more than 1.2; after the initial setting strength of first slurry reaches 5.0MPa, the secondary high-pressure grouting can be carried out by a high-pressure grouting pipe; (7) locking stretching by a secondary stretching method; (8) leading an anchor to penetrate; (9) sealing the anchor; and (10) carrying out anticorrosive processing. The invention has high practicability and favorable social benefits.

Description

Prestress pulling resistant anchor pile and job practices
Technical field
The present invention relates to building field, particularly prestress pulling resistant anchor pile and job practices.
Background technology
In the rich groundwater area, when lower or structure base absolute altitude was low when building basement basis absolute altitude, sole plate can be subjected to bigger buoyancy.In order to prevent the sole plate come-up, to adopt pulling resistant anchor pile usually.The tradition pulling resistant anchor pile is stressed to be transmitted at the bottom of stake from the stake top, and anchoring pile is stressed to be changed with underground SEA LEVEL VARIATION, is unfavorable for the long-term resistance to plucking of anchoring pile.Can adopt prestressing technique, in advance required maximum uplift resistance be put on anchoring pile, make that anchoring pile is stressed to be transmitted to the stake top at the bottom of the stake.In this case, the stressed groundwater table that is subjected to of anchoring pile influences not quite, helps the long-term resistance to plucking of anchoring pile.
Summary of the invention
Technical problem to be solved by this invention provides a kind of prestress pulling resistant anchor pile and job practices, solves the not good problem of traditional pulling resistant anchor pile stress performance.
For this reason, the present invention has adopted the prestress pulling resistant anchor pile technology, bond the special anchoring body of formation mutually by cement mixing pile, high strength cement slurry, steel strand, the suffered pulling force of anchoring body is delivered in the stable stratum by the frictional resistance on peripheral stratum, pulling resistant anchor pile unifies through prestressed stretch-draw and sole plate, has improved anchoring pile resistance to plucking ability.
In addition, the present invention also adopts the concentricity problem that has solved anchor hole and cement mixing pile at cement mixing pile prebored hole spray mud.The cement mixing pile construction back that finishes is adopted small-bore drilling tool preboring and is sprayed for a short time of weighted mud, makes mud and cement grout mix at agitation pile, is formed centrally heavy gluey cylinder in agitation pile.Because gluey cylinder and cement mixing pile intensity differ bigger, when boring anchor hole, the relatively stable of hole wall can be guaranteed, and the concentricity of anchor hole and cement mixing pile can be guaranteed, improved brill anchor hole efficiency of construction.
Construction sequence comprises:
(1) cement mixing pile construction
Cement mixing pile construction technology program is as follows: rig is in place → and bores whitewashing → liftings down to stir → repeat down to bore to whitewash → repeat to promote and stir → repeat down 1/3 long whitewashing of brill → repeat lifting stirring → rig to be shifted.
(2) prebored hole
Transfer the small-bore drilling tool immediately after the cement mixing pile construction finishes and carry out preboring, drilling tool sprays mud, mud balance is 1.05~1.1, drilling tool fully stirs at the agitation pile center, make mud and cement grout mix, in agitation pile, be formed centrally the gluey cylinder of proportion big (1.30~1.40), when boring anchor hole, can guarantee the relatively stable of hole wall on the one hand, help anchor hole on the other hand and keep concentric with cement mixing pile.
(3) anchor hole creeps into
Jumbolter creeps into behind cement mixing pile construction finishing 12~14h, and rate of penetration is 200mm/min.
(4) hole flushing
At the bottom of the pipe patchhole with the connection air compressor machine, flushing repeatedly from lower to upper.Replenish simultaneously constantly clear water, make that the mud relative density is less than 1.05 in the hole, inner hole deposition slag thickness is less than 300mm.
(5) hole under the anchor pole
The anchor pole bottom is the break adrift form, and anchor pole is installed a fixed center support by spacing 2m, and firm with the iron wire colligation.Steel strand adopt and manually lay, and transfer by bottle gouard moved by hands in case of necessity.
(6) slip casting
First pumping clear water returns water with the mediation pipeline before the slip casting to the aperture, and the slip casting of normal pressure pumping method is adopted in the back, must not extract Grouting Pipe before the slip casting, enriches to guarantee anchor pole bottom slip casting.Grouting amount is as the criterion to fill with the hole for the first time, and fullness coefficient reaches more than 1.2.After treating that the injecting cement paste initial setting strength reaches 5.0MPa for the first time, promptly available high-pressure slip-casting pipe carries out the high-pressure slip-casting second time.Anchoring section slip casting is returned the slurry method at the bottom of adopting the hole, and Grouting Pipe is inserted into 500mm place at the bottom of the hole, with mudjack cement paste is fed the Grouting Pipe injection hole at the bottom of, cement paste outwards is full of and with air extrusion in the hole successively from boring end mouth.
(7) tensioning fixation
Tensioning fixation should carry out after cement paste intensity reaches 100%.Adopt the two times tensioning method, the controlling value of stretch-draw for the first time is 10%~20%, with the stretch-draw of single windlass symmetry, presses steady anchoring part, bearing plate, the tension steel strand.Treat that every steel strand tension is after the intact first time, carry out the stretch-draw second time again, each stretch-draw answers classification to carry out, each load is respectively 0.25,0.5,0.75,1.0,1.1 times of steel strand design pulling force, must stablize 10~20min except that afterbody, all the other every grade needs are stablized 5min, and write down the elongation of each grade steel strand respectively, in stabilization time each time, must measure anchor head displacement three times, treat to lock again when steel strand prestress is not obviously decayed.The stretch-draw principle adopts as follows: rise lotus speed per minute and should not surpass 10% of design stress, off-load speed per minute should not surpass 20% of design stress.
(8) wear anchor
The PVC overcoat of the outer steel strand of anchor pier is peeled off, the butter on the steel strand is wiped clean with cotton yarn.Steel strand are managed out by peripheral preface and center preface, penetrated anchor slab, the cover upper clip, steel strand are answered symmetry or are evenly distributed on the anchor slab.
(9) sealing off and covering anchorage
Use the unnecessary steel strand of Abrasive cutting off machine excision, ground tackle is retained 100mm outward.Adding butter with protective sleeve protects and exposes steel strand.Seal anchor head with the C40 concrete, thickness of concrete cover is not less than 100mm.
(10) preservative treatment
The anchor pole head exposes steel strand and seals with anti-corrosion resin, and bearing plate carries out antirust, preservative treatment with rustproof paint and bituminous material brushing.To be coated with rustproof paint outward to center fixture, locating rack etc. in fixed.
The present invention is applicable to building basement basis pulling resistant anchor pile, the structure base pulling resistant anchor pile that buoyancy is bigger.
Compare with traditional pulling resistant anchor pile, anchor pole is applied prestressing force can make cement mixing pile, high strength cement slurry, steel strand acting in conjunction better, thereby improved the stress performance of pulling resistant anchor pile.Employing helps anchor hole at cement mixing pile prebored hole spray mud and keeps concentric with cement mixing pile, and the anchor bolt construction quality is guaranteed, and the present invention is practical, and social benefit is good.
Description of drawings
The technological process of Fig. 1 prestress pulling resistant anchor pile
The specific embodiment
Describe in detail below in conjunction with accompanying drawing.
Certain water factory's boiler room Foundation Design, north and south is wide to be 18m, the long 21.6m of thing, all place underground, totally 2 layers.Structure types is a frame construction, basic thickness of slab 800mm, embedded depth of foundation absolute altitude-9.6m.Consider this area's underground water height, underground boiler room own wt descends buoyancy of water irresistibly.Be to solve the resistance to plucking problem of building, adopt prestress pulling resistant anchor pile, make cement mixing pile, high strength cement slurry, steel strand integral body stressed, improved the stress performance of pulling resistant anchor pile, to reach the purpose of whole building resistance to plucking.
Adopt the cement mixer rig to form cement mixing pile, after the cement mixing pile construction finishes, transfer the small-bore drilling tool immediately and carry out preboring, drilling tool sprays the little weighted mud that compares, fully stir at the agitation pile center, make mud and cement grout mix, in agitation pile, be formed centrally heavy gluey cylinder, guarantee the concentricity of anchor hole and cement mixing pile.Treat behind the drilling tool preboring of small-bore to bore anchor hole again after agitation pile reaches certain intensity, be lowered to steel wire bundle in the anchor hole after, pressure injection high-strength cement slurries.After treating that the high-strength cement slurry intensity reaches requirement, every steel strand are applied prestressing force respectively, and be locked on the sole plate and with airtight steel cap the pulling resistant anchor pile top sealed and inject butter, thereby form prestress pulling resistant anchor pile.
Construction sequence comprises:
(1) cement mixing pile construction
Cement mixing pile construction slurry water gray scale adopts 0.5, mixes 1.5% early strength admixture gypsum and 0.15% water reducing agent wood calcium.
Cement mixing pile construction technology program is as follows: rig is in place → and bores whitewashing → liftings down to stir → repeat down to bore to whitewash → repeat to promote and stir → repeat down 1/3 long whitewashing of brill → repeat lifting stirring → rig to be shifted.
Cement mixing pile rig rate of penetration is 0.8~1.0m/min, and spray pressure is controlled at 0.4~0.6MPa, creep at the bottom of the stake behind the absolute altitude, and original place whitewashing 0.5min, counter-rotating at the uniform velocity promotes again.Hoisting velocity is 0.8~1.0m/min, at the uniform velocity is promoted to overhead 0.5m place, and the stirring several seconds makes pile crown evenly closely knit.
(2) prebored hole
Transfer the small-bore drilling tool immediately after the cement mixing pile construction finishes and carry out preboring, drilling tool sprays mud, mud balance is 1.05~1.1, drilling tool fully stirs at the agitation pile center, make mud and cement grout mix, in agitation pile, be formed centrally the gluey cylinder of proportion big (1.30~1.40), when boring anchor hole, can guarantee the relatively stable of hole wall on the one hand, help anchor hole on the other hand and keep concentric with cement mixing pile.
(3) anchor hole creeps into
After the jumbolter leveling in place, conduction three-wing bit (band centralizer) direct circulation clear water creeps at the bottom of the cement mixing pile stake before adopting.
Jumbolter creeps into behind cement mixing pile construction finishing 12~14h, and rate of penetration is 200mm/min.
Keep concentric with cement mixing pile as far as possible, the deviation at anchor hole center and cement mixing pile center is no more than 10mm, with the cement mixing pile perpendicularity deviation should be less than 8%.In a single day deflection takes place in anchor hole, the pore-forming again of taking measures.
(4) hole flushing
At the bottom of the pipe patchhole with the connection air compressor machine, flushing repeatedly from lower to upper.Replenish simultaneously constantly clear water, make that the mud relative density is less than 1.05 in the hole, inner hole deposition slag thickness is less than 300mm.Carry out the aperture and safeguard, prevent in the slurry flows hand-hole.
(5) hole under the anchor pole
The anchor pole bottom is the break adrift form, and anchor pole is installed a fixed center support by spacing 2m, and firm with the iron wire colligation.Anchor pole bottom dress taper protector, protection anchor pole bottom and hole wall are not destroyed.Grouting Pipe is installed with steel strand and is carried out synchronously, is arranged on steel wire bundle central authorities, and length exceeds steel strand 2m.Steel strand adopt and manually lay, and transfer by bottle gouard moved by hands in case of necessity; Before casting anchor, steel strand quality and length need can descend in the hand-hole after related personnel's acceptance(check).
(6) slip casting
Anchor pole slurry water gray scale adopts 0.4~0.45, and the proportioning of cement grout is a cement: water: early strength admixture: expansion agent=1: (0.45~0.5): (0.007~0.01): 0.07.Require during preparation to fill up the water yield in the mixer, add cement and Admixture then while stirring, mixing time is no less than 10min.
First pumping clear water returns water with the mediation pipeline before the slip casting to the aperture, and the slip casting of normal pressure pumping method is adopted in the back, must not extract Grouting Pipe before the slip casting, enriches to guarantee anchor pole bottom slip casting.Grouting amount is as the criterion to fill with the hole for the first time, and fullness coefficient reaches more than 1.2.The slip casting operation is continuous, and Grouting Pipe wants the marginal not limit to pull out, and the tube drawing height does not exceed hole entoplasm liquid level.After treating that the injecting cement paste initial setting strength reaches 5.0MPa for the first time, promptly available high-pressure slip-casting pipe carries out the high-pressure slip-casting second time.Anchoring section slip casting is returned the slurry method at the bottom of adopting the hole, and Grouting Pipe is inserted into 500mm place at the bottom of the hole, with mudjack cement paste is fed the Grouting Pipe injection hole at the bottom of, cement paste outwards is full of and with air extrusion in the hole successively from boring end mouth.
(7) tensioning fixation
Tensioning fixation should carry out after cement paste intensity reaches 100%.Adopt the two times tensioning method, the controlling value of stretch-draw for the first time is 10%~20%, with the stretch-draw of single windlass symmetry, presses steady anchoring part, bearing plate, tension steel strand.Treat that every steel strand tension is after the intact first time, carry out the stretch-draw second time again, each stretch-draw answers classification to carry out, each load is respectively 0.25,0.5,0.75,1.0,1.1 times of steel strand design pulling force, must stablize 10~20min except that afterbody, all the other every grade needs are stablized 5min, and write down the elongation of each grade steel strand respectively, in stabilization time each time, must measure anchor head displacement three times, treat to lock again when steel strand prestress is not obviously decayed.The stretch-draw principle adopts as follows: rise lotus speed per minute and should not surpass 10% of design stress, off-load speed per minute should not surpass 20% of design stress.
(8) wear anchor
The PVC overcoat of the outer steel strand of anchor pier is peeled off, the butter on the steel strand is wiped clean with cotton yarn.Steel strand are managed out by peripheral preface and center preface, penetrated anchor slab, the cover upper clip, steel strand are answered symmetry or are evenly distributed on the anchor slab.
(9) sealing off and covering anchorage
Use the unnecessary steel strand of Abrasive cutting off machine excision, ground tackle is retained 100mm outward.Adding butter with protective sleeve protects and exposes steel strand.Seal anchor head with the C40 concrete, thickness of concrete cover is not less than 100mm.
(10) preservative treatment
The anchor pole head exposes steel strand and seals with anti-corrosion resin, and bearing plate carries out antirust, preservative treatment with rustproof paint and bituminous material brushing.For preventing that the corrosion of anchor pole structure from taking place, and will be coated with rustproof paint outward to center fixture, locating rack etc. in fixed.
After this engineering construction finished, the pulling resistant anchor pile result of use was good.

Claims (10)

1, a kind of prestress pulling resistant anchor pile and job practices is characterized in that may further comprise the steps:
(1) cement mixing pile construction
Cement mixing pile construction technology program is as follows: rig is in place → and bores whitewashing → liftings down to stir → repeat down to bore to whitewash → repeat to promote and stir → repeat down 1/3 long whitewashing of brill → repeat lifting stirring → rig to be shifted.
(2) prebored hole
Transfer the small-bore drilling tool immediately after the cement mixing pile construction finishes and carry out preboring, drilling tool sprays mud, and drilling tool fully stirs at the agitation pile center.
(3) anchor hole creeps into
Jumbolter creeps into behind cement mixing pile construction finishing 12~14h, and rate of penetration is 200mm/min.
(4) hole flushing
At the bottom of the pipe patchhole with the connection air compressor machine, flushing repeatedly from lower to upper.Replenish simultaneously constantly clear water, make that the mud relative density is less than 1.05 in the hole, inner hole deposition slag thickness is less than 300mm.
(5) hole under the anchor pole
The anchor pole bottom is the break adrift form, and anchor pole is installed a fixed center support by spacing 2m, and firm with the iron wire colligation.Steel strand adopt and manually lay, and transfer by bottle gouard moved by hands in case of necessity.
(6) slip casting
Grouting amount is as the criterion to fill with the hole for the first time, and fullness coefficient reaches more than 1.2.After treating that the injecting cement paste initial setting strength reaches 5.0MPa for the first time, promptly available high-pressure slip-casting pipe carries out the high-pressure slip-casting second time.Anchoring section slip casting is returned the slurry method at the bottom of adopting the hole, and Grouting Pipe is inserted into 500mm place at the bottom of the hole, with mudjack cement paste is fed the Grouting Pipe injection hole at the bottom of, cement paste outwards is full of and with air extrusion in the hole successively from boring end mouth.
(7) tensioning fixation
Adopt the two times tensioning method, the controlling value of stretch-draw for the first time is 10%~20%, with the stretch-draw of single windlass symmetry, presses steady anchoring part, bearing plate, tension steel strand.Treat that every steel strand tension is after the intact first time, carry out the stretch-draw second time again, each stretch-draw answers classification to carry out, each load is respectively 0.25,0.5,0.75,1.0,1.1 times of steel strand design pulling force, must stablize 10~20min except that afterbody, all the other every grade needs are stablized 5min, and write down the elongation of each grade steel strand respectively, in stabilization time each time, must measure anchor head displacement three times, treat to lock again when steel strand prestress is not obviously decayed.
(8) wear anchor
The PVC overcoat of the outer steel strand of anchor pier is peeled off, the butter on the steel strand is wiped clean with cotton yarn.Steel strand are managed out by peripheral preface and center preface, penetrated anchor slab, the cover upper clip, steel strand are answered symmetry or are evenly distributed on the anchor slab.
(9) sealing off and covering anchorage
Use the unnecessary steel strand of Abrasive cutting off machine excision, ground tackle is retained 100mm outward.Adding butter with protective sleeve protects and exposes steel strand.
(10) preservative treatment
The anchor pole head exposes steel strand and seals with anti-corrosion resin, and bearing plate carries out antirust, preservative treatment with rustproof paint and bituminous material brushing.To be coated with rustproof paint outward to center fixture, locating rack etc. in fixed.
2, prestress pulling resistant anchor pile according to claim 1 and job practices, it is characterized in that having adopted the prestress pulling resistant anchor pile technology, bond the special anchoring body of formation mutually by cement mixing pile, high strength cement slurry, steel strand, the suffered pulling force of anchoring body is delivered in the stable stratum by the frictional resistance on peripheral stratum, and pulling resistant anchor pile unifies through prestressed stretch-draw and sole plate.
3, prestress pulling resistant anchor pile according to claim 1 and 2 and job practices is characterized in that: drilling tool injection mud balance is 1.05~1.1 in step (2) the prebored hole construction.
4, prestress pulling resistant anchor pile according to claim 1 and 2 and job practices, it is characterized in that: anchor pole slurry water gray scale adopts 0.4~0.45, and the proportioning of cement grout is a cement: water: early strength admixture: expansion agent=1: (0.45~0.5): (0.007~0.01): 0.07.
5, prestress pulling resistant anchor pile according to claim 3 and job practices, it is characterized in that: anchor pole slurry water gray scale adopts 0.4~0.45, and the proportioning of cement grout is a cement: water: early strength admixture: expansion agent=1: (0.45~0.5): (0.007~0.01): 0.07.
6, prestress pulling resistant anchor pile according to claim 1 and 2 and job practices, it is characterized in that: the stretch-draw principle adopts as follows in the construction of step (7) tensioning fixation: rise lotus speed per minute and should not surpass 10% of design stress, off-load speed per minute should not surpass 20% of design stress.
7, prestress pulling resistant anchor pile according to claim 3 and job practices, it is characterized in that: the stretch-draw principle adopts as follows in the construction of step (7) tensioning fixation: rise lotus speed per minute and should not surpass 10% of design stress, off-load speed per minute should not surpass 20% of design stress.
8, prestress pulling resistant anchor pile according to claim 4 and job practices, it is characterized in that: the stretch-draw principle adopts as follows in the construction of step (7) tensioning fixation: rise lotus speed per minute and should not surpass 10% of design stress, off-load speed per minute should not surpass 20% of design stress.
9, prestress pulling resistant anchor pile according to claim 1 and 2 and job practices is characterized in that: seal anchor head with the C40 concrete in the construction of (9) sealing off and covering anchorage, thickness of concrete cover is not less than 100mm.
10, prestress pulling resistant anchor pile according to claim 3 and job practices is characterized in that: seal anchor head with the C40 concrete in the construction of (9) sealing off and covering anchorage, thickness of concrete cover is not less than 100mm.
CN2009101618458A 2009-07-28 2009-07-28 Prestress pulling resistant anchor pile and constructing method thereof Expired - Fee Related CN101619574B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009101618458A CN101619574B (en) 2009-07-28 2009-07-28 Prestress pulling resistant anchor pile and constructing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009101618458A CN101619574B (en) 2009-07-28 2009-07-28 Prestress pulling resistant anchor pile and constructing method thereof

Publications (2)

Publication Number Publication Date
CN101619574A true CN101619574A (en) 2010-01-06
CN101619574B CN101619574B (en) 2011-04-13

Family

ID=41512970

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009101618458A Expired - Fee Related CN101619574B (en) 2009-07-28 2009-07-28 Prestress pulling resistant anchor pile and constructing method thereof

Country Status (1)

Country Link
CN (1) CN101619574B (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101851925A (en) * 2010-06-03 2010-10-06 中冶集团武汉勘察研究院有限公司 Deep mixing pile-micro pre-stressed steel pipe concrete pile-vertical anchor rod composite foundation pit support method
CN101886393A (en) * 2010-07-03 2010-11-17 朱奎 Construction method of combined foundation ditch support
CN102704478A (en) * 2012-06-08 2012-10-03 黄水森 Building anchor rod construction technology
CN102864777A (en) * 2012-10-15 2013-01-09 河海大学 Fast prestress anchor stock structure and construction method
CN103422501A (en) * 2013-03-13 2013-12-04 中国建筑第四工程局有限公司 Anti-floating anchor structure in sand layer geology and construction method thereof
CN106703065A (en) * 2016-11-17 2017-05-24 中国电建集团贵州工程公司 Underwater construction method for rock anchor rod draught fan foundation
CN106948347A (en) * 2017-04-01 2017-07-14 南京瑞迪建设科技有限公司 Pile extracting method and pile pulling system
CN107059872A (en) * 2017-04-01 2017-08-18 南京瑞迪建设科技有限公司 Oblique cord pile extracting method and oblique cord pile pulling system
CN111851525A (en) * 2020-08-31 2020-10-30 中建八局第二建设有限公司 Construction method of deep foundation pit support anchor rod under complex geological condition
CN111894045A (en) * 2020-08-17 2020-11-06 广州市设计院 Anti-floating anchoring structure and anti-floating anchoring construction method for basement bottom plate
CN112709225A (en) * 2020-12-28 2021-04-27 云南建投第二水利水电建设有限公司 Quick construction method for shell-expanding type prestressed anchor rod
CN112900459A (en) * 2021-01-27 2021-06-04 洛阳理工学院 Composite reinforcement method for soft clay side slope
CN115637739A (en) * 2022-10-08 2023-01-24 浙江东南网架股份有限公司 Prestress anti-floating anchor rod construction method based on digital simulation
CN115839083A (en) * 2022-12-05 2023-03-24 中建八局第二建设有限公司 Construction method for reinforcing single prestressed anchor rod combined foundation

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101851925A (en) * 2010-06-03 2010-10-06 中冶集团武汉勘察研究院有限公司 Deep mixing pile-micro pre-stressed steel pipe concrete pile-vertical anchor rod composite foundation pit support method
CN101886393A (en) * 2010-07-03 2010-11-17 朱奎 Construction method of combined foundation ditch support
CN102704478A (en) * 2012-06-08 2012-10-03 黄水森 Building anchor rod construction technology
CN102704478B (en) * 2012-06-08 2015-04-22 黄水森 Building anchor rod construction technology
CN102864777A (en) * 2012-10-15 2013-01-09 河海大学 Fast prestress anchor stock structure and construction method
CN103422501A (en) * 2013-03-13 2013-12-04 中国建筑第四工程局有限公司 Anti-floating anchor structure in sand layer geology and construction method thereof
CN103422501B (en) * 2013-03-13 2016-01-13 中国建筑第四工程局有限公司 Anti-floating anchor rod structure in sand seam geology and construction method thereof
CN106703065B (en) * 2016-11-17 2019-02-12 中国电建集团贵州工程公司 Rock-bolt blower foundation underwater construction engineering method
CN106703065A (en) * 2016-11-17 2017-05-24 中国电建集团贵州工程公司 Underwater construction method for rock anchor rod draught fan foundation
CN106948347A (en) * 2017-04-01 2017-07-14 南京瑞迪建设科技有限公司 Pile extracting method and pile pulling system
CN107059872A (en) * 2017-04-01 2017-08-18 南京瑞迪建设科技有限公司 Oblique cord pile extracting method and oblique cord pile pulling system
CN107059872B (en) * 2017-04-01 2022-06-07 南京瑞迪建设科技有限公司 Inclined cable pile pulling method and inclined cable pile pulling system
CN111894045A (en) * 2020-08-17 2020-11-06 广州市设计院 Anti-floating anchoring structure and anti-floating anchoring construction method for basement bottom plate
CN111851525A (en) * 2020-08-31 2020-10-30 中建八局第二建设有限公司 Construction method of deep foundation pit support anchor rod under complex geological condition
CN112709225A (en) * 2020-12-28 2021-04-27 云南建投第二水利水电建设有限公司 Quick construction method for shell-expanding type prestressed anchor rod
CN112900459A (en) * 2021-01-27 2021-06-04 洛阳理工学院 Composite reinforcement method for soft clay side slope
CN115637739A (en) * 2022-10-08 2023-01-24 浙江东南网架股份有限公司 Prestress anti-floating anchor rod construction method based on digital simulation
CN115839083A (en) * 2022-12-05 2023-03-24 中建八局第二建设有限公司 Construction method for reinforcing single prestressed anchor rod combined foundation

Also Published As

Publication number Publication date
CN101619574B (en) 2011-04-13

Similar Documents

Publication Publication Date Title
CN101619574B (en) Prestress pulling resistant anchor pile and constructing method thereof
CN104032737B (en) Construction method and the structure of pressure dispersing type enlarged footing anchor pole
CN101634149B (en) Prestressed anchor foundation pit support and construction method
CN102518135B (en) Horizontal jet grouting soil anchor and castinplace pile Composite Foundation Pit supporting construction engineering method
CN106498943B (en) Disposable high-pressure rotary-spray type enlarged footing Prestressed Soil anchor pole construction method
CN101748728B (en) Soil cement expanding uplift pile
US11840820B2 (en) Method for strengthening and lifting high-rise building having raft foundation
CN103088819A (en) Pre-stressed anchor cable construction method
CN101285309A (en) Compound support method for deep foundation pit of tall buildings
CN101886393B (en) Construction method of combined foundation ditch support
CN109208631A (en) A kind of gravity retaining wall inclination deviation rectification and reinforcement means
CN101560775A (en) Composite soil nailing wall structure
CN113668525A (en) Construction method of anti-floating anchor rod with water-drop-shaped enlarged head based on PSB finish-rolled deformed steel bar
CN100595397C (en) Anti-floating construction method by combination of bar-planting and anchoring-bolt
CN104372793A (en) Anti-floating method used for existing basement by adopting pre-stressed anchor cables in jet grouting pile method
CN108301428A (en) The pre- tensioning post-tensioning pile foundation of stake top and construction technology
CN105970955A (en) Self-drilling type nail and pipe combined double-liquid grouting soil nail construction process
CN214784243U (en) Back-inserted unbonded steel strand U-shaped pipe pressure-bearing uplift pile
CN209652927U (en) A prestressed rock-soil bolt
CN114293552A (en) High-pressure injection bag type expanded body pressure-bearing type anchor rod and construction method thereof
CN113982033B (en) Method for repairing hydraulic retaining wall with inclination trend by using water in post-construction structure without damage to wall
CN203716145U (en) Orientation steel pipe locking prestress multiple anchor rope
CN214401751U (en) Pore-forming type rotary spraying anti-floating anchor rod
CN205530218U (en) Slip casting composite foundation suitable for high -rise building structural strengthening is rectified
CN203866824U (en) Pressure-dispersing type expansion anchor rod structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110413

Termination date: 20110728