CN102828472B - Method for cutting off temporary support of continuous girder bridge by wire saw - Google Patents

Method for cutting off temporary support of continuous girder bridge by wire saw Download PDF

Info

Publication number
CN102828472B
CN102828472B CN201210351989.1A CN201210351989A CN102828472B CN 102828472 B CN102828472 B CN 102828472B CN 201210351989 A CN201210351989 A CN 201210351989A CN 102828472 B CN102828472 B CN 102828472B
Authority
CN
China
Prior art keywords
temporary support
rope
saw equipment
cut
rope saw
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210351989.1A
Other languages
Chinese (zh)
Other versions
CN102828472A (en
Inventor
涂千强
梁江涛
姜建国
唐涛
张恒
邓浩宇
况永辉
刘玉芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd filed Critical First Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority to CN201210351989.1A priority Critical patent/CN102828472B/en
Publication of CN102828472A publication Critical patent/CN102828472A/en
Application granted granted Critical
Publication of CN102828472B publication Critical patent/CN102828472B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a method for cutting off a temporary support of a continuous girder bridge by a wire saw. The method comprises the following steps of: 1, chiseling a first groove at each of four corners of the lower part of the temporary support; 2, mounting wire saw equipment and a cutting wire; 3, cutting off the section of the lower part of the temporary support to perforate; 4, stuffing a disc steel bar into a gap at the section of the cut-off lower part of the temporary support; 5, chiseling a second groove at each of four corners of the upper part of the temporary support; 6, mounting the wire saw equipment and the cutting wire; 7, cutting the section of the upper part of the temporary support to perforate; 8, dismantling the wire saw equipment and the cutting wire; 9, pushing out the whole separated temporary support by a jack; and 10, symmetrically cutting off the residual temporary supports according to the modes from the step 1 to the step 9. According to the invention, in a process of dismantling the temporary supports of the continuous girder bridge, an accident can be effectively avoided, and the dismantling speed of the temporary supports can be quickened.

Description

Method with rope sawing except continuous girder bridge temporary support
Technical field
The present invention relates to a kind of method of removing continuous girder bridge temporary support, be specifically related to a kind of method of removing continuous girder bridge temporary support with rope sawing.
Background technology
In the continuous beam bridge construction, after the closure of beam body, must remove temporary support and become continuous system conversion to reach firm structure.At present, conventionally adopt artificial hand-held air rock drill to cut the temporary support of continuous girder bridge.During construction, first temporary support surrounding reinforcement cover concrete is divested, then with gas cutting, cut off anchor bar, finally cut again residue concrete.This method is when implementing, and because temporary support is between beam body and pier shaft top cap, construction space is narrower, is not easy to artificial chisel except construction, and belongs to work high above the ground, and personal safety has a big risk; In addition, temporary support concrete design strength is high, and reinforcing bar is intensive, and artificial chisel is except very difficult, causes removing efficiency low, directly affects follow-up work, makes all can not better realize in the management objectives such as safety, cost, progress.Therefore, for the dismounting of continuous girder bridge temporary support, need to develop a kind of new construction method.
Summary of the invention
The object of this invention is to provide a kind of method of using rope sawing to remove continuous girder bridge temporary support, adopt the method construction, can effectively avoid the generation of security incident and the dismounting speed of quickening temporary support.
The method of removing continuous girder bridge temporary support with rope sawing of the present invention, its step is as follows:
Step 1, on four corner angle of temporary support bottom, cut a hole respectively first groove, and near two first grooves in pier shaft outside lower than two the first grooves near permanent bearing one side, in order to facilitate ejecting of follow-up temporary support;
Step 2, in temporary support bottom one side installing rope saw equipment, and this rope saw equipment is fixed on the bridge pier of continuous beam, then by rope saw equipment cut rope sling on temporary support, and by cut rope put in four the first grooves of temporary support bottom, start rope saw equipment starts to cut off;
Step 3, the cross section of being cut off when temporary support bottom are greater than two of temporary support cross section/for the moment, rope saw equipment is installed to the opposite side of temporary support bottom, retighten rope saw equipment and install and cut rope, start rope saw equipment cuts off perforation by temporary support lower section;
In step 4, the lower section gap of having been cut off at temporary support, fill at least two steel-bars, as roller bearing, use;
Step 5, on four corner angle on temporary support top, cut a hole respectively second groove, and near two second grooves in pier shaft outside higher than two the second grooves near permanent bearing one side, in order to facilitate ejecting of follow-up temporary support;
Step 6, on temporary support top one side installing rope saw equipment, and this rope saw equipment is fixed on the surface of temporary support, then by rope saw equipment cut rope sling on temporary support, and by cut rope put in four second grooves on temporary support top, start rope saw equipment starts to cut off;
Step 7, the cross section of being cut off when temporary support top are greater than two of temporary support cross section/for the moment, rope saw equipment is installed to the opposite side on temporary support top, retighten rope saw equipment and install and cut rope, start rope saw equipment cuts off perforation by cross section, temporary support top;
Step 8, remove rope saw equipment and cut rope;
Step 9, use jack, eject as roller bearing the temporary support integral body of having separated by steel-bar;
Step 10, the mode according to step 1 to step 9, symmetry is cut off on bridge pier other temporary support.
Beneficial effect of the present invention: adopt the method to remove continuous girder bridge temporary support, can guarantee constructor's safety, greatly improve the efficiency of removing temporary support, and the effectively lower cost of construction.
Accompanying drawing explanation
Fig. 1 removes one of construction schematic diagram of continuous girder bridge temporary support with rope sawing;
Fig. 2 is except two of the construction schematic diagram of continuous girder bridge temporary support with rope sawing;
Fig. 3 is except three of the construction schematic diagram of continuous girder bridge temporary support with rope sawing;
Fig. 4 is except four of the construction schematic diagram of continuous girder bridge temporary support with rope sawing;
Fig. 5 is except five of the construction schematic diagram of continuous girder bridge temporary support with rope sawing.
The specific embodiment
Now by reference to the accompanying drawings the present invention is described in further detail:
The method except continuous girder bridge temporary support with rope sawing as shown in Figures 1 to 5,
Step 1, as shown in Figure 1 is manually cut a hole respectively first groove 2 on four corner angle of temporary support 1 bottom, and near two first grooves 2 in pier shaft outside lower than two the first grooves 2 near permanent bearing one side;
Step 2, as shown in Figure 2, at temporary support 1 bottom one side installing rope saw equipment 3, and this rope saw equipment 3 is fixed on the surface of temporary support 1, then the rope 4 that cuts of rope saw equipment 3 is enclosed within on temporary support 1, and put in four the first grooves 2 of temporary support 1 bottom cutting rope 1, start rope saw equipment 3 starts to cut off;
Step 3, as shown in Figure 3, the cross section of being cut off when temporary support 1 bottom is greater than two of temporary support 1 cross section/for the moment, rope saw equipment 3 is installed to the opposite side of temporary support 1 bottom, this rope saw equipment 3 is fixed on the surface of temporary support 1, then the rope 4 that cuts of rope saw equipment 3 is enclosed within on temporary support 1, and put in four the first grooves 2 of temporary support 1 bottom cutting rope 1, start rope saw equipment 3 cuts off perforation by temporary support 1 lower section;
Step 4, as shown in Figure 4, fills at least two steel-bars 6 in the lower section gap of having been cut off at temporary support 1 and uses as roller bearing, and the quantity of steel-bar 6 is determined according to the size of temporary support 1;
Step 5, on four corner angle on temporary support 1 top, cut a hole respectively second groove 5, and near two second grooves 5 in pier shaft outside higher than two the second grooves 5 near permanent bearing 1 one sides;
Step 6, at temporary support 1 top one side installing rope saw equipment 3, and this rope saw equipment 3 is fixed on the surface of temporary support 1, then the rope 4 that cuts of rope saw equipment 3 is enclosed within on temporary support 1, and put in four second grooves 5 on temporary support 1 top cutting rope 1, start rope saw equipment 3 starts to cut off;
Step 7, the cross section of being cut off when temporary support 1 top are greater than two of temporary support 1 cross section/for the moment, rope saw equipment 3 is installed to the opposite side on temporary support 1 top, this rope saw equipment 3 is fixed on the surface of temporary support 1, then the rope 4 that cuts of rope saw equipment 3 is enclosed within on temporary support 1, and put in four second grooves 5 on temporary support 1 top cutting rope 1, start rope saw equipment 3 cuts off perforation by temporary support 1 cross section, top;
Step 8, remove rope saw equipment 3 and cut rope 4;
Step 9, as shown in Figure 5, the base of jack 7 utilizes permanent bearing for fulcrum, by steel-bar 6, as roller bearing, the temporary support of having separated 1 integral body is ejected.
Step 10, the mode according to step 1 to step 9, symmetry is cut off remaining temporary support 1.

Claims (1)

1. with rope sawing, remove a method for continuous girder bridge temporary support, its step is as follows:
Step 1, on four corner angle of temporary support (1) bottom, cut a hole respectively first groove (2), and near two first grooves in pier shaft outside lower than two the first grooves near permanent bearing one side;
Step 2, at temporary support (1) bottom one side installing rope saw equipment (3), and this rope saw equipment is fixed on the surface of temporary support, then the rope (4) that cuts of rope saw equipment is enclosed within on temporary support, and put in four first grooves (2) of temporary support bottom cutting rope, start rope saw equipment starts to cut off;
Step 3, the cross section of being cut off when temporary support (1) bottom are greater than two of temporary support cross section/for the moment, the saw equipment (3) of restricting is installed to the opposite side of temporary support bottom, retighten rope saw equipment and install and cut rope, start rope saw equipment cuts off perforation by temporary support lower section;
In step 4, the lower section gap of having been cut off at temporary support (1), fill at least two steel-bars (6);
Step 5, on four corner angle on temporary support (1) top, cut a hole respectively second groove (5), and near two second grooves in pier shaft outside higher than two the second grooves near permanent bearing one side;
Step 6, at temporary support (1) top one side installing rope saw equipment (3), and this rope saw equipment is fixed on the surface of temporary support, then the rope (4) that cuts of rope saw equipment is enclosed within on temporary support, and put in four second grooves (5) on temporary support top cutting rope, start rope saw equipment starts to cut off;
Step 7, the cross section of being cut off when temporary support (1) top are greater than two of temporary support cross section/for the moment, the saw equipment (3) of restricting is installed the opposite side on temporary support top, retighten rope saw equipment and install and cut rope, start rope saw equipment cuts off perforation by cross section, temporary support top;
Step 8, remove rope saw equipment (3) and cut rope (4);
Step 9, with jack (7), release the temporary support of having separated (1) is whole;
Step 10, the mode according to step 1 to step 9, symmetry is cut off remaining temporary support (1).
CN201210351989.1A 2012-09-20 2012-09-20 Method for cutting off temporary support of continuous girder bridge by wire saw Expired - Fee Related CN102828472B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210351989.1A CN102828472B (en) 2012-09-20 2012-09-20 Method for cutting off temporary support of continuous girder bridge by wire saw

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210351989.1A CN102828472B (en) 2012-09-20 2012-09-20 Method for cutting off temporary support of continuous girder bridge by wire saw

Publications (2)

Publication Number Publication Date
CN102828472A CN102828472A (en) 2012-12-19
CN102828472B true CN102828472B (en) 2014-04-02

Family

ID=47331764

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210351989.1A Expired - Fee Related CN102828472B (en) 2012-09-20 2012-09-20 Method for cutting off temporary support of continuous girder bridge by wire saw

Country Status (1)

Country Link
CN (1) CN102828472B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108386007B (en) * 2018-03-28 2021-04-23 深圳市工勘岩土集团有限公司 Construction method for directionally dismantling large-volume reinforced concrete by using wire saw
CN108453908B (en) * 2018-04-30 2023-09-26 安徽省公路桥梁工程有限公司 Temporary consolidation cutting system and method for cantilever casting box girder
CN110939064A (en) * 2019-11-19 2020-03-31 中国铁建大桥工程局集团有限公司 Method for quickly removing continuous beam pier and beam consolidation

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05256031A (en) * 1992-12-15 1993-10-05 Daimoshiya:Kk Cutting and demolishing device for reinforced concrete structure
JPH10249847A (en) * 1997-03-11 1998-09-22 Concrete Kooring Kk Horizontally cutting method for concrete structure
JP2002327543A (en) * 2001-05-02 2002-11-15 Nippon Concrete Cutting Kogyo Osaka:Kk Horizontal cutting construction method for columnar concrete structure
KR20030096204A (en) * 2003-12-02 2003-12-24 한용철 Repair method for bridge shoe
CN101768926A (en) * 2009-12-29 2010-07-07 中铁隧道集团有限公司 Diamond rope saw static force cutting method
CN101892636A (en) * 2010-08-12 2010-11-24 上海先为土木工程有限公司 Integral lifting reconstruction method for high-span overweight continuous box girder

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05256031A (en) * 1992-12-15 1993-10-05 Daimoshiya:Kk Cutting and demolishing device for reinforced concrete structure
JPH10249847A (en) * 1997-03-11 1998-09-22 Concrete Kooring Kk Horizontally cutting method for concrete structure
JP2002327543A (en) * 2001-05-02 2002-11-15 Nippon Concrete Cutting Kogyo Osaka:Kk Horizontal cutting construction method for columnar concrete structure
KR20030096204A (en) * 2003-12-02 2003-12-24 한용철 Repair method for bridge shoe
CN101768926A (en) * 2009-12-29 2010-07-07 中铁隧道集团有限公司 Diamond rope saw static force cutting method
CN101892636A (en) * 2010-08-12 2010-11-24 上海先为土木工程有限公司 Integral lifting reconstruction method for high-span overweight continuous box girder

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
刚构桥盆式支座更换技术;高文波;《广东建材》;20090313(第1期);第40-42页 *
吴淞路闸桥切割拆除施工流程;罗志军;《中国市政工程》;20120420(第6期);第54-57页 *
罗志军.吴淞路闸桥切割拆除施工流程.《中国市政工程》.2012,(第6期),第54-57页.
高文波.刚构桥盆式支座更换技术.《广东建材》.2009,(第1期),第40-42页.

Also Published As

Publication number Publication date
CN102828472A (en) 2012-12-19

Similar Documents

Publication Publication Date Title
CN103470068B (en) A kind of method for dismounting of existing roll line underground space concrete structure
CN102828472B (en) Method for cutting off temporary support of continuous girder bridge by wire saw
CN107604941A (en) A kind of new and old subway station connectivity part diaphragm wall and side wall restructuring bankrupt
CN108612109A (en) The carrierless method for dismounting of concrete support beam
CN106192781A (en) The method for dismounting of prestressing force list case three Room plate-girder
JP5794941B2 (en) How to remove concrete slab
CN113774822B (en) Dismantling method of old reinforced concrete bridge
CN103205923A (en) Bridge deck pavement concrete rapid and microquake explosion method
CN202520316U (en) Suspended safety isolator used in construction of tunnel shaft
CN103790398A (en) Large concrete structural body pre-supporting-free demolition method
CN103362078A (en) Old frame bridge dismantling method in new-old frame bridge replacing process
CN103628898B (en) A kind of for preventing the diaphragm wall supporting method of Floor Heave in Roadway
CN101403257B (en) Nondestructive demounting method for prefabricated part of IMS system Dai nationality folk house major structure
CN107905127B (en) A kind of low vibration global orientation method for dismounting suitable for bridge pier column
CN102677680A (en) Dismantling method for concrete waist beam
CN201810324U (en) Steel frame for supporting and protecting lower part of middle separation wall in early tunnel period
CN108005083A (en) Anchor cable processing method in the range of a kind of foundation pit enclosure structure
CN113356215A (en) Cutting construction method and cutting device for rock platform of underground factory building rock wall crane beam
CN102535347A (en) Continuous beam falling system and continuous beam falling method
CN206279537U (en) For the pre-groove of deep foundation pit reinforced concrete support beam demolition blasting
CN101832141A (en) Method for connecting temporary supports of tunnel
CN204551472U (en) Square pile head cuts stopping means
CN204676863U (en) elevator shaft operating platform
CN204919380U (en) A hanging flower basket that is used for blasting of large -scale bridge to demolish
CN203308115U (en) Combined steel pipe support

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140402

Termination date: 20140920

EXPY Termination of patent right or utility model