CN102828470A - Method for locating main girder cable sleeve of cable-stayed bridge - Google Patents
Method for locating main girder cable sleeve of cable-stayed bridge Download PDFInfo
- Publication number
- CN102828470A CN102828470A CN2012103253972A CN201210325397A CN102828470A CN 102828470 A CN102828470 A CN 102828470A CN 2012103253972 A CN2012103253972 A CN 2012103253972A CN 201210325397 A CN201210325397 A CN 201210325397A CN 102828470 A CN102828470 A CN 102828470A
- Authority
- CN
- China
- Prior art keywords
- tooth block
- noose
- cable
- cable sleeve
- line
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 23
- 238000004873 anchoring Methods 0.000 claims abstract description 28
- 238000003466 welding Methods 0.000 claims abstract description 9
- 238000013461 design Methods 0.000 claims abstract description 5
- 230000004807 localization Effects 0.000 claims description 11
- 238000009415 formwork Methods 0.000 claims description 7
- 230000003014 reinforcing effect Effects 0.000 claims description 6
- 238000006073 displacement reaction Methods 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 4
- 238000004519 manufacturing process Methods 0.000 abstract description 4
- 238000009434 installation Methods 0.000 abstract 1
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 229910001374 Invar Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 150000001875 compounds Chemical class 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000012797 qualification Methods 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210325397.2A CN102828470B (en) | 2012-09-05 | 2012-09-05 | Method for locating main girder cable sleeve of cable-stayed bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210325397.2A CN102828470B (en) | 2012-09-05 | 2012-09-05 | Method for locating main girder cable sleeve of cable-stayed bridge |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102828470A true CN102828470A (en) | 2012-12-19 |
CN102828470B CN102828470B (en) | 2014-06-11 |
Family
ID=47331762
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210325397.2A Expired - Fee Related CN102828470B (en) | 2012-09-05 | 2012-09-05 | Method for locating main girder cable sleeve of cable-stayed bridge |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102828470B (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103114528A (en) * | 2013-02-04 | 2013-05-22 | 中天建设集团有限公司 | Viaduct inclined web positioning and formwork-supporting tool |
CN103132455A (en) * | 2013-03-12 | 2013-06-05 | 中铁四局集团第二工程有限公司 | Three-dimensional combined type cable-stayed bridge body cable duct accurate positioning device and positioning method |
CN106948272A (en) * | 2017-05-04 | 2017-07-14 | 吴思明 | A kind of Cable stayed Bridge Main Tower noose pipe installs surveying and locating locator |
CN109376391A (en) * | 2018-09-20 | 2019-02-22 | 中国铁路设计集团有限公司 | A kind of tooth block design method based on BIM |
CN106638318B (en) * | 2016-11-25 | 2019-03-15 | 中铁大桥局集团第五工程有限公司 | The localization method and cable guide pipe installation method of cable-stayed bridge beam-ends anchor point |
CN109505260A (en) * | 2018-12-25 | 2019-03-22 | 中铁大桥局第七工程有限公司 | A kind of positioning device and localization method of finished main cable shape of self-anchored suspension anchor tube |
CN109629395A (en) * | 2019-02-02 | 2019-04-16 | 中铁十五局集团第工程有限公司 | A kind of the limit V-type snap-gauge and application method of the positioning of concrete inclined cable conduit |
CN111663428A (en) * | 2020-06-24 | 2020-09-15 | 中铁二院工程集团有限责任公司 | Negative inhaul cable suspension bridge |
CN112069583A (en) * | 2020-09-08 | 2020-12-11 | 中国十七冶集团有限公司 | Oblique cantilever safe and intelligent construction system and method for finite element synchronous analysis |
CN112609576A (en) * | 2020-11-19 | 2021-04-06 | 中铁二局集团有限公司 | Method and device for positioning and installing spatial attitude of stay cable guide pipe |
CN112813833A (en) * | 2020-12-31 | 2021-05-18 | 中交路桥华南工程有限公司 | Installation method of cableway pipe |
CN113481868A (en) * | 2021-07-30 | 2021-10-08 | 中国建筑第八工程局有限公司 | Cableway positioning device and method with anchor point adjusting structure for cable-stayed bridge |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS56163175A (en) * | 1980-02-08 | 1981-12-15 | Poudres & Explosifs Ste Nale | Formation of temporary assembly of construction members |
CN201217781Y (en) * | 2008-06-20 | 2009-04-08 | 龙建路桥股份有限公司 | Positioning apparatus |
CN201228345Y (en) * | 2008-06-11 | 2009-04-29 | 中铁工程设计咨询集团有限公司 | Rotary spherical hinge positioning apparatus on top of bridge pier |
CN101446071A (en) * | 2008-12-30 | 2009-06-03 | 中铁二局股份有限公司 | Method of exactly adjusting and locating curve steel box beam |
-
2012
- 2012-09-05 CN CN201210325397.2A patent/CN102828470B/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS56163175A (en) * | 1980-02-08 | 1981-12-15 | Poudres & Explosifs Ste Nale | Formation of temporary assembly of construction members |
CN201228345Y (en) * | 2008-06-11 | 2009-04-29 | 中铁工程设计咨询集团有限公司 | Rotary spherical hinge positioning apparatus on top of bridge pier |
CN201217781Y (en) * | 2008-06-20 | 2009-04-08 | 龙建路桥股份有限公司 | Positioning apparatus |
CN101446071A (en) * | 2008-12-30 | 2009-06-03 | 中铁二局股份有限公司 | Method of exactly adjusting and locating curve steel box beam |
Non-Patent Citations (2)
Title |
---|
吴伟锋等: "李渡长江大桥主塔斜拉索套管测量定位技术", 《华南港工》, no. 108, 15 October 2007 (2007-10-15), pages 49 - 52 * |
孔遁: "高速公路下穿钢管施工技术", 《安徽建筑》, no. 06, 28 December 2005 (2005-12-28), pages 94 - 96 * |
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103114528A (en) * | 2013-02-04 | 2013-05-22 | 中天建设集团有限公司 | Viaduct inclined web positioning and formwork-supporting tool |
CN103132455A (en) * | 2013-03-12 | 2013-06-05 | 中铁四局集团第二工程有限公司 | Three-dimensional combined type cable-stayed bridge body cable duct accurate positioning device and positioning method |
CN103132455B (en) * | 2013-03-12 | 2015-06-10 | 中铁四局集团第二工程有限公司 | Three-dimensional combined type cable-stayed bridge body cable duct accurate positioning device and positioning method |
CN106638318B (en) * | 2016-11-25 | 2019-03-15 | 中铁大桥局集团第五工程有限公司 | The localization method and cable guide pipe installation method of cable-stayed bridge beam-ends anchor point |
CN106948272A (en) * | 2017-05-04 | 2017-07-14 | 吴思明 | A kind of Cable stayed Bridge Main Tower noose pipe installs surveying and locating locator |
CN109376391A (en) * | 2018-09-20 | 2019-02-22 | 中国铁路设计集团有限公司 | A kind of tooth block design method based on BIM |
CN109505260A (en) * | 2018-12-25 | 2019-03-22 | 中铁大桥局第七工程有限公司 | A kind of positioning device and localization method of finished main cable shape of self-anchored suspension anchor tube |
CN109629395B (en) * | 2019-02-02 | 2024-02-02 | 中铁十五局集团第一工程有限公司 | Limiting V-shaped clamping plate for positioning concrete stay cable guide pipe and use method |
CN109629395A (en) * | 2019-02-02 | 2019-04-16 | 中铁十五局集团第工程有限公司 | A kind of the limit V-type snap-gauge and application method of the positioning of concrete inclined cable conduit |
CN111663428A (en) * | 2020-06-24 | 2020-09-15 | 中铁二院工程集团有限责任公司 | Negative inhaul cable suspension bridge |
CN112069583B (en) * | 2020-09-08 | 2023-10-20 | 中国十七冶集团有限公司 | Finite element synchronous analysis inclined cantilever safe intelligent construction system and method |
CN112069583A (en) * | 2020-09-08 | 2020-12-11 | 中国十七冶集团有限公司 | Oblique cantilever safe and intelligent construction system and method for finite element synchronous analysis |
CN112609576A (en) * | 2020-11-19 | 2021-04-06 | 中铁二局集团有限公司 | Method and device for positioning and installing spatial attitude of stay cable guide pipe |
CN112813833A (en) * | 2020-12-31 | 2021-05-18 | 中交路桥华南工程有限公司 | Installation method of cableway pipe |
CN112813833B (en) * | 2020-12-31 | 2022-12-27 | 中交路桥华南工程有限公司 | Installation method of cableway pipe |
CN113481868A (en) * | 2021-07-30 | 2021-10-08 | 中国建筑第八工程局有限公司 | Cableway positioning device and method with anchor point adjusting structure for cable-stayed bridge |
CN113481868B (en) * | 2021-07-30 | 2022-07-26 | 中国建筑第八工程局有限公司 | Cableway positioning device and method with anchor point adjusting structure for cable-stayed bridge |
Also Published As
Publication number | Publication date |
---|---|
CN102828470B (en) | 2014-06-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102828470B (en) | Method for locating main girder cable sleeve of cable-stayed bridge | |
CN106638318B (en) | The localization method and cable guide pipe installation method of cable-stayed bridge beam-ends anchor point | |
CN104328799B (en) | A kind of sheltered reverse excavation subway station steel pipe column accurate positioning method | |
CN104120656A (en) | Method for automatically controlling bridge high pier construction perpendicularity | |
CN107090775B (en) | A kind of full framing space beam-ends cable guide pipe construction localization method | |
CN109878380B (en) | Subway vehicle section flexible contact net track-free construction method | |
CN101440667A (en) | Mounting method for wide span single layer rain shed reticulated shell structure | |
CN102828469B (en) | Positioning mounting construction method for triangular steel constructed pillar of inclined-leg steel box | |
CN109443327A (en) | A kind of distribution method of SURVEYING CONTROL NETWORK | |
CN106223623A (en) | Steel construction box arched roof truss installation method | |
CN109898871B (en) | Bidirectional inclined steel column mounting and positioning device and positioning method | |
CN202787088U (en) | Embedded template structure for cable sleeve of main beam of stayed-cable bridge | |
CN210507148U (en) | Positioning and adjusting device for main tower cable guide pipe of cable-stayed bridge | |
CN204059200U (en) | Bridge High-pier construction verticality automatic control structure | |
CN110241735B (en) | Positioning and adjusting device and method for main tower cable guide pipe of cable-stayed bridge | |
CN204370314U (en) | A kind of lower hanging steel bridge erects suspension rod | |
CN104060838B (en) | A kind of vestibule divides into groups aerial group to Method for Installation | |
CN108179749B (en) | Lattice column positioner and positioning method thereof | |
CN104006798B (en) | Pier stud verticality measuring instrument | |
CN103174155A (en) | Reverse construction method and construction steel support of erecting steel column and pouring concrete foundation in sequential mode | |
CN212477455U (en) | Pre-buried positioner of bridge suspension cable anchor cylinder | |
CN202255403U (en) | Upper centering bracket for gyroscopic total station | |
CN107841949B (en) | A kind of building technology of inverted trapezoidal Bridge beam assembly moulding bed | |
CN206815191U (en) | A kind of full framing space beam-ends cable guide pipe positioner | |
CN105064643A (en) | Method for precisely installing R-shaped dry hanging stone plate hanging element |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C53 | Correction of patent of invention or patent application | ||
C56 | Change in the name or address of the patentee | ||
CB03 | Change of inventor or designer information |
Inventor after: Su He Inventor after: Wang Haiyu Inventor after: Wu Jianying Inventor after: He Kaiwei Inventor after: Zhang Qingbin Inventor before: Wang Haiyu Inventor before: Su He Inventor before: He Kaiwei |
|
COR | Change of bibliographic data |
Free format text: CORRECT: INVENTOR; FROM: WANG HAIYU SU HE HE KAIWEI TO: SU HE WANG HAIYU WU JIANYING HE KAIWEI ZHANG QINGBIN |
|
CP02 | Change in the address of a patent holder |
Address after: Yaohai District of Hefei City, the 230011 major channels of Anhui province No. 51 days of International Building building 22-24 Patentee after: China Construction Seventh Engineering Bureau The Second Co.,Ltd. Address before: 230011, 5 floor, business center, Dongfang shopping mall, 48 Mingguang Road, Anhui, Hefei Patentee before: China Construction Seventh Engineering Bureau The Second Co.,Ltd. |
|
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140611 Termination date: 20210905 |
|
CF01 | Termination of patent right due to non-payment of annual fee |