CN102817467B - 钢结构高空安装操作平台 - Google Patents

钢结构高空安装操作平台 Download PDF

Info

Publication number
CN102817467B
CN102817467B CN201210290248.7A CN201210290248A CN102817467B CN 102817467 B CN102817467 B CN 102817467B CN 201210290248 A CN201210290248 A CN 201210290248A CN 102817467 B CN102817467 B CN 102817467B
Authority
CN
China
Prior art keywords
shear wall
operating platform
cantilever beams
fitting
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210290248.7A
Other languages
English (en)
Other versions
CN102817467A (zh
Inventor
李毅
杨正军
吕黄兵
杜得强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Steel Structure Engineering Co Ltd
Original Assignee
China Construction Steel Structure Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Steel Structure Corp Ltd filed Critical China Construction Steel Structure Corp Ltd
Priority to CN201210290248.7A priority Critical patent/CN102817467B/zh
Publication of CN102817467A publication Critical patent/CN102817467A/zh
Application granted granted Critical
Publication of CN102817467B publication Critical patent/CN102817467B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明公开一种钢结构高空安装操作平台,包括悬挑梁,悬挑梁的内端设有内斜撑和内立柱,内斜撑和内立柱靠与预埋件连接;悬挑梁的外端设有多根外立柱,部分外立柱通过预埋件固定在剪力墙的外侧;外立柱的上端设有操作平台,操作平台与悬挑梁之间设有多根外斜撑,部分外斜撑通过预埋件固定在剪力墙的外侧。结构简单、制作和使用均很方便,有效提高了施工效率,可以通过控制墙体内的埋件而增大适用范围。并且,该操作平台可循环使用,不会造成材料浪费。

Description

钢结构高空安装操作平台
技术领域
本发明专利涉及一种钢结构施工中为钢结构施工提供操作空间的操作平台,尤其涉及一种钢结构高空安装操作平台。
背景技术
在钢结构安装的施工中,现场焊接是其中的重要环节。目前,在各种钢结构施工现场中,许多时候焊接等的操作空间非常小,或者布置不合理。即使有临时搭设的操作平台,往往无法循环利用,浪费材料又影响施工速度。针对这些问题,
目前,在各种钢结构施工现场中,无脚手架的情况下操作平台设计往往不合理,尤其是悬挑的。外伸操作平台多为临时制作,没有统一的类别、规格,往往使用一次报废,造成材料浪费。即使有些夹具可以多次使用,但往往设计不合理,使用中经常会出现各种问题,如造成多次焊接,破坏钢柱体表面,进而影响施工进度。
发明专利内容
本发明专利实施方式提供一种钢结构高空安装操作平台,可方便的固定安装在剪力墙上,与操作架配合,为钢结构工程中的焊接等提供工作空间,可循环使用,减少材料浪费,同时有助于提高施工进度。
本发明的目的是通过下述技术方案实现的:
本发明的钢结构高空安装操作平台,包括悬挑梁,所述悬挑梁的内端通过预埋件或膨胀螺栓固定在室内板上,所述悬挑梁的外端从剪力墙上的窗户伸出;
所述悬挑梁的内端设有内斜撑和内立柱,所述内斜撑的一端与所述悬挑梁的内端固定连接,另一端通过预埋件或膨胀螺栓固定在所述剪力墙的内侧,所述内立柱靠在所述剪力墙的内侧,并通过预埋件或膨胀螺栓固定在所述剪力墙的内侧,所述内立柱的下端与所述悬挑梁固定连接;
所述悬挑梁的外端设有多根外立柱,其中一部分外立柱靠在所述剪力墙的外侧,并通过预埋件或膨胀螺栓固定在所述剪力墙的外侧,所述外立柱的下端与所述悬挑梁固定连接;
所述外立柱的上端设有操作平台,所述操作平台与所述悬挑梁之间设有多根外斜撑,其中一部分外斜撑靠在所述剪力墙的外侧,并通过预埋件或膨胀螺栓固定在所述剪力墙的外侧。
由上述本发明提供的技术方案可以看出,本发明的钢结构高空安装操作平台,通过在剪力墙中设置埋件,固定悬挑梁、立柱和斜撑,并进一步焊接框架形成操作平台。结构简单、制作和使用均很方便,有效提高了施工效率,可以通过控制墙体内的埋件而增大适用范围。并且,该操作平台可循环使用,不会造成材料浪费。
附图说明
图1为本发明专利实施例提供的钢结构高空安装操作平台的侧面结构示意图;
图2为本发明专利实施例提供的钢结构高空安装操作平台的正面结构示意图。
图中:1、悬挑梁,2、内斜撑,3、内立柱,4、操作平台,5、外立柱,6、外斜撑。
具体实施方式
下面结合具体实施例对本发明专利作进一步说明。
本发明的钢结构高空安装操作平台,其较佳的具体实施方式如图1、图2所示:
包括悬挑梁,所述悬挑梁的内端通过预埋件或膨胀螺栓(图中未示出)固定在室内板上,所述悬挑梁的外端从剪力墙上的窗户伸出;
所述悬挑梁的内端设有内斜撑和内立柱,所述内斜撑的一端与所述悬挑梁的内端固定连接,另一端通过预埋件或膨胀螺栓固定在所述剪力墙的内侧,所述内立柱靠在所述剪力墙的内侧,并通过预埋件或膨胀螺栓固定在所述剪力墙的内侧,所述内立柱的下端与所述悬挑梁固定连接;
所述悬挑梁的外端设有多根外立柱,其中一部分外立柱靠在所述剪力墙的外侧,并通过预埋件或膨胀螺栓固定在所述剪力墙的外侧,所述外立柱的下端与所述悬挑梁固定连接;
所述外立柱的上端设有操作平台,所述操作平台与所述悬挑梁之间设有多根外斜撑,其中一部分外斜撑靠在所述剪力墙的外侧,并通过预埋件或膨胀螺栓固定在所述剪力墙的外侧。
操作平台上搭设有操作架(图中未示出)。
具体实施例中:
悬挑梁从窗户悬挑出去,定位后与混凝土楼面埋件固定在一起;操作平台受力构件立柱和斜撑安装在主体内,与预埋在砼剪力墙上的埋件固定;主要受力构件安装、焊接完成后,将平台整体安装、焊接在悬挑梁上;当需要凿建筑钢结构埋件时,搭设操作架,操作架步距为1.5m,纵横距均为1.5m,操作架搭设的过程中通过拉杆与混凝土结构和钢结构形成有效连接。
操作架搭设完毕之后,即可凿出建筑钢结构的预埋件,然后拆除合适位置的操作架,进行建筑结构的吊装和校正。之后重新搭设操作架,为刚刚吊装钢结构的焊接等提供操作空间。当焊接等安装操作完成之后,往往操作平台很难通过塔吊拆除,此时可以用卷扬机和倒链将平台散件进行拆除。
综上所述,本发明专利实施例提供的钢结构高空安装操作平台,结构简单、使用方便,方便了作业人员的使用,加快了施工速度;且可以循环使用,减少了材料浪费,降低施工成本。
以上所述,仅为本发明专利较佳的具体实施方式,但本发明专利的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明专利揭露的技术范围内,可轻易想到的变化或替换,都应涵盖在本发明专利的保护范围之内。因此,本发明专利的保护范围应该以权利要求书的保护范围为准。

Claims (2)

1.一种钢结构高空安装操作平台,其特征在于,包括悬挑梁,所述悬挑梁的内端通过预埋件或膨胀螺栓固定在室内板上,所述悬挑梁的外端从剪力墙上的窗户伸出;
所述悬挑梁的内端设有内斜撑和内立柱,所述内斜撑的一端与所述悬挑梁的内端固定连接,另一端通过预埋件或膨胀螺栓固定在所述剪力墙的内侧,所述内立柱靠在所述剪力墙的内侧,并通过预埋件或膨胀螺栓固定在所述剪力墙的内侧,所述内立柱的下端与所述悬挑梁固定连接;
所述悬挑梁的外端设有多根外立柱,其中一部分外立柱靠在所述剪力墙的外侧,并通过预埋件或膨胀螺栓固定在所述剪力墙的外侧,所述外立柱的下端与所述悬挑梁固定连接;
所述外立柱的上端设有操作平台,所述操作平台与所述悬挑梁之间设有多根外斜撑,其中一部分外斜撑靠在所述剪力墙的外侧,并通过预埋件或膨胀螺栓固定在所述剪力墙的外侧。
2.根据权利要求1所述的钢结构高空安装操作平台,其特征在于,操作平台上搭设有操作架。
CN201210290248.7A 2012-08-15 2012-08-15 钢结构高空安装操作平台 Active CN102817467B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210290248.7A CN102817467B (zh) 2012-08-15 2012-08-15 钢结构高空安装操作平台

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210290248.7A CN102817467B (zh) 2012-08-15 2012-08-15 钢结构高空安装操作平台

Publications (2)

Publication Number Publication Date
CN102817467A CN102817467A (zh) 2012-12-12
CN102817467B true CN102817467B (zh) 2015-05-13

Family

ID=47301878

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210290248.7A Active CN102817467B (zh) 2012-08-15 2012-08-15 钢结构高空安装操作平台

Country Status (1)

Country Link
CN (1) CN102817467B (zh)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105442628B (zh) * 2014-08-20 2017-04-19 五冶集团上海有限公司 悬挑基础侧壁重型埋件施工方法
CN108930399A (zh) * 2018-08-01 2018-12-04 四川兴昌建设工程有限公司 一种飘窗预制外挂墙板施工用防护架
CN114033156A (zh) * 2021-12-09 2022-02-11 中建八局第四建设有限公司 一种吊篮固定装置

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2093107A (en) * 1981-02-17 1982-08-25 Keyes John Joseph Window scaffolding
WO1996032553A1 (en) * 1995-04-13 1996-10-17 Joro Limited Working platform assembly
CN201236476Y (zh) * 2008-08-04 2009-05-13 南通英雄建筑安装工程有限公司 附着墙体窗口的脚手架
CN101736893A (zh) * 2009-12-16 2010-06-16 通广建工集团有限公司 悬挑式脚手架支撑系统
CN201802059U (zh) * 2010-09-17 2011-04-20 中建三局建设工程股份有限公司 悬挑下撑式脚手架
CN202139833U (zh) * 2011-06-26 2012-02-08 李庆文 一种用于在用房屋建筑施工的悬挑脚手架
CN202831594U (zh) * 2012-08-15 2013-03-27 中建钢构有限公司 钢结构高空安装操作平台

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2093107A (en) * 1981-02-17 1982-08-25 Keyes John Joseph Window scaffolding
WO1996032553A1 (en) * 1995-04-13 1996-10-17 Joro Limited Working platform assembly
CN201236476Y (zh) * 2008-08-04 2009-05-13 南通英雄建筑安装工程有限公司 附着墙体窗口的脚手架
CN101736893A (zh) * 2009-12-16 2010-06-16 通广建工集团有限公司 悬挑式脚手架支撑系统
CN201802059U (zh) * 2010-09-17 2011-04-20 中建三局建设工程股份有限公司 悬挑下撑式脚手架
CN202139833U (zh) * 2011-06-26 2012-02-08 李庆文 一种用于在用房屋建筑施工的悬挑脚手架
CN202831594U (zh) * 2012-08-15 2013-03-27 中建钢构有限公司 钢结构高空安装操作平台

Also Published As

Publication number Publication date
CN102817467A (zh) 2012-12-12

Similar Documents

Publication Publication Date Title
CN101265748B (zh) 工具式型钢扣件钢管外脚手架
CN203808484U (zh) 一种整体悬挑附着式外脚手架
CN205224567U (zh) 一种可收缩折叠式电梯井施工平台
CN207268073U (zh) 新型柔性支模承重架
CN102817467B (zh) 钢结构高空安装操作平台
CN103206075B (zh) 型钢混凝土悬挑结构施工用悬吊平台
CN103122691A (zh) 塔吊标准节支承高空支模钢平台结构及施工方法
CN205421880U (zh) 一种适用于装配整体式混凝土外墙板的工具式防护架
CN206289945U (zh) 一种装配式便捷安全操作架
CN101712436A (zh) 一种钢桁架吊装工具及其钢桁架吊装工艺
CN202945798U (zh) 一种悬挑式脚手架角部装置
CN107514145A (zh) 一种可移动钢屋面内衬安装施工装置及方法
CN104018680B (zh) 一种大跨度实腹式弧形梁的提升方法
CN201190408Y (zh) 工具式型钢扣件钢管外脚手架
CN202831594U (zh) 钢结构高空安装操作平台
CN103112766A (zh) 悬置于房屋建筑地下室顶板上方的施工电梯及其施工方法
CN201825672U (zh) 一种发电机定子吊装装置
CN206220461U (zh) 一种可移动式工字钢电梯井操作平台
CN204225503U (zh) 大跨度钢桁架高空散装转换梁胎架
CN204238443U (zh) 一种可拆卸柱脚固定装置
CN203320922U (zh) 电梯井模板定型支撑装置
CN209509453U (zh) 一种高层建筑现浇混凝土结构工具式悬挑脚手架
CN203222981U (zh) 型钢混凝土悬挑结构施工用悬吊平台
CN203067936U (zh) 高空管道安装安全提升支架
CN203361596U (zh) 一种集成式升降操作平台辅助支架

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Operating platform for high-altitude installation of steel structure

Effective date of registration: 20180129

Granted publication date: 20150513

Pledgee: Bank of Beijing Limited by Share Ltd. Shenzhen branch

Pledgor: China Construction Steel Structure Corp.,Ltd.

Registration number: 2018440020010

CP03 Change of name, title or address

Address after: 3801, 38 / F, Zhongjian science and engineering building, No. 3331, Weilan Coast Community Center Road, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee after: China Construction Science And Industry Co.,Ltd.

Address before: 518040 Guangdong city of Shenzhen province Futian District Che Kung Temple tipping building 17 layer

Patentee before: China Construction Steel Structure Corp.,Ltd.

CP03 Change of name, title or address
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20221207

Granted publication date: 20150513

Pledgee: Bank of Beijing Limited by Share Ltd. Shenzhen branch

Pledgor: China Construction Steel Structure Corp.,Ltd.

Registration number: 2018440020010

PC01 Cancellation of the registration of the contract for pledge of patent right
TR01 Transfer of patent right

Effective date of registration: 20221219

Address after: Room 1908, Chengtou Xin Times Building, No. 2009, Pingshan Avenue, Liulian Community, Pingshan Street, Pingshan District, Shenzhen 518000

Patentee after: China Construction Steel Engineering Co.,Ltd.

Address before: 3801, 38 / F, China Construction Science and engineering building, No. 3331, Weilan Coast Community Central Road, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee before: China Construction Science And Industry Co.,Ltd.

TR01 Transfer of patent right