CN102815892A - Anti-slide fog seal material and its construction method - Google Patents

Anti-slide fog seal material and its construction method Download PDF

Info

Publication number
CN102815892A
CN102815892A CN2012103053675A CN201210305367A CN102815892A CN 102815892 A CN102815892 A CN 102815892A CN 2012103053675 A CN2012103053675 A CN 2012103053675A CN 201210305367 A CN201210305367 A CN 201210305367A CN 102815892 A CN102815892 A CN 102815892A
Authority
CN
China
Prior art keywords
parts
antiskid
mist
sealing material
kaolin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012103053675A
Other languages
Chinese (zh)
Other versions
CN102815892B (en
Inventor
刘廷国
王力民
岳学军
侯曙光
阮旭东
刘玉恒
王凯宾
陈小雪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Gaoyuan Road Maintenance Equipment Co Ltd
Original Assignee
Henan Gaoyuan Road Maintenance Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Gaoyuan Road Maintenance Equipment Co Ltd filed Critical Henan Gaoyuan Road Maintenance Equipment Co Ltd
Priority to CN201210305367.5A priority Critical patent/CN102815892B/en
Publication of CN102815892A publication Critical patent/CN102815892A/en
Application granted granted Critical
Publication of CN102815892B publication Critical patent/CN102815892B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)
  • Road Paving Machines (AREA)

Abstract

The invention relates to an anti-slide fog seal material and its construction method. The anti-slide fog seal material is obtained by the following steps of: mixing 15-30 parts by weight of composite kaolin, 35-70 parts by weight of water and 1.2-2.0 parts by weight of an asphalt emulsifier, adjusting the pH value into a range required by the corresponding asphalt emulsifier with a pH value conditioning agent, then emulsifying 25-40 parts by weight of hot melt asphalt so as to obtain a stable mixed emulsion, and finally mixing the emulsion with 50-80 parts by weight of sand and conducting stirring. When the anti-slide fog seal material is sprayed on a road surface uniformly by a spraying vehicle, it can bond well with the road surface. Thus, the material not only seals original road surface micro-cracks and voids, plays a strong waterproof role, but also prolongs the road service life. And the sand in the anti-slide fog seal material can substantially improve the anti-slide performance of the road surface.

Description

Antiskid mist sealing material and constructional method thereof
Technical field
The present invention relates to technical field of highway maintenance technology, be specifically related to a kind of antiskid mist sealing material and constructional method thereof.
Background technology
Mist seal AEMA (Asphalt Emulsion Manufacturers Association) technology is a kind of have efficient maintenance performance, road preventive maintenance with low cost technology.It is directly to spray the mist sealing material at road surface, and the surface of a black promptly is provided for road; It can the shutoff fine cracks and the hole, hole, and stops moisture to get into the surface pore, improves the water resistance on surface; Ability renewal or reduction surfaces be aged pitch, prolongs the work-ing life on road surface; In addition, the aggregate that the firm road surface of mist seal is loose, further loose to prevent it, can protect or the bond of redeck because of wearing out and being lost, reduce aging and weathering road pavement Effect on Performance.
More mist sealing material is arranged at present both at home and abroad; Yet find in the practical engineering application; The defective of two broad aspect below they in use all exist: (1) construction initial stage cling property is not enough, can form one deck asphalt membrane, the asphalt film smooth surface that this layer is made up of free pitch on the road surface after the construction of mist seal; And the frictional force between the tire is little, has directly reduced the cling property on road surface.(2) wear resisting property and relatively poor with the adhesion property on road surface, i.e. poor durability, common mist seal is using one to after two months, and the mist sealing material on the building stones is ground off, takes away by driving mostly, and the road surface does not observe the vestige that carried out the construction of mist seal basically.
Summary of the invention
The technical problem that the present invention solved is to overcome the defective of former pavement skid resistance condition deficiency in mist seal construction back and poor durability, and a kind of antiskid, wear-resisting, persistent antiskid mist sealing material and constructional method thereof are provided.
In order to address the above problem, the technical scheme that the present invention adopts is:
The present invention provides a kind of antiskid mist sealing material, is made by the starting material of following weight part meter:
25~40 parts in petroleum pitch
15~30 parts of the compound kaolin of 200~500 orders
1.2~2.0 parts of asphalt emulsifiers
35~70 parts in water
0.2 ~ 1.0 part of pH value regulator
0.15mm 50~80 parts in the sand material of ~ 0.30mm particle diameter.
According to above-mentioned antiskid mist sealing material, preferably the starting material by following weight part meter make:
30 parts in petroleum pitch
25~27 parts of the compound kaolin of 200~500 orders
1.8 parts of asphalt emulsifiers
43~45 parts in water
0.2 ~ 1.0 part of pH value regulator
0.15mm 50~80 parts in the sand material of ~ 0.30mm particle diameter.
According to above-mentioned antiskid mist sealing material, make by the starting material of following weight part meter:
25 ~ 30 parts in petroleum pitch
15 ~ 20 parts of the compound kaolin of 200 ~ 500 orders
1.2 ~ 1.4 parts of asphalt emulsifiers
35 ~ 45 parts in water
0.2 ~ 0.5 part of pH value regulator
0.15mm 50 ~ 60 parts in the sand material of ~ 0.30mm particle diameter.
According to above-mentioned antiskid mist sealing material, make by the starting material of following weight part meter:
30 ~ 35 parts in petroleum pitch
20 ~ 25 parts of the compound kaolin of 200 ~ 500 orders
1.4 ~ 1.8 parts of asphalt emulsifiers
45 ~ 60 parts in water
0.5 ~ 0.8 part of pH value regulator
0.15mm 60 ~ 70 parts in the sand material of ~ 0.30mm particle diameter.
According to above-mentioned antiskid mist sealing material, make by the starting material of following weight part meter:
35 ~ 40 parts in petroleum pitch
25 ~ 30 parts of the compound kaolin of 200 ~ 500 orders
1.8 ~ 2.0 parts of asphalt emulsifiers
60 ~ 70 parts in water
0.8 ~ 1.0 part of pH value regulator
0.15mm 70 ~ 80 parts in the sand material of ~ 0.30mm particle diameter.
According to above-mentioned antiskid mist sealing material, said petroleum pitch is 70# or 90# bi tumenf orr oad; Said asphalt emulsifier is alkylammonium salt or quaternary ammonium salt emulsifying agent; PH value regulator is industrial concentrated hydrochloric acid, and its mass concentration is 30%~38%, mainly is for regulating the pH value of kaolin emulsified bitumen soap lye; The sand material is to choose any one kind of them or several kinds in natural silicon carbide, garnet, diamantine, silit, bottom sand, iron sand and the silica sand; The sand material does not contain ultra particle diameter particle; Do not contain harmful impurity; And surface irregularity is the main source of antiskid mist sealing material antiskid effect, and the used in amounts of actual use medium sand material combines the construction depth on former road surface to confirm; Water is tap water, does not contain harmful impurity or ion.
A kind of constructional method of utilizing above-mentioned antiskid mist sealing material making antiskid mist seal may further comprise the steps:
Step 1: be equipped with various raw materials according to above-mentioned antiskid mist sealing material proportioning;
Step 2: in the water with 50~80 ℃ of asphalt emulsifier addings; Regulate the pH value to the scope of corresponding emulsifying agent requirement with pH value regulator; Treat that fully the dissolving back adds compound kaolin and stirs; Thorough mixing is regulated in the scope of the extremely corresponding emulsifying agent requirement of pH value of mixing liquid with pH value regulator after evenly once more, makes kaolin emulsified bitumen soap lye;
Step 3: petroleum pitch is heated to 130~140 ℃, on go on foot the gained soap lye and be heated to 60~70 ℃, petroleum pitch and soap lye are added in the mulser; Emulsification 1~3 minute; The mulser rotating speed is 2900~3000 rpm, makes the kaolin emulsified bitumen, and gained kaolin emulsified bitumen should satisfy table 1;
The compound kaolin emulsified bitumen of table 1 index request
Test item Normal viscosity (C 25,3 Stability in storage (5d)
Requirement ≥25s ≤3%
Step 4: the adding of sand material is upward gone on foot in the gained kaolin emulsified bitumen, after brute force mixes, make antiskid mist sealing material, need to keep stirring after antiskid mist sealing material is processed, the time that stops to stir in use or the transportation is no more than 2 hours;
Step 5: punish former pavement disease, loose material, earth, weeds on the cleaning road surface are removed greasy dirt and other foreign material, mark wire along spraying direction;
Step 6: antiskid mist seal liquid distributor is opened to the construction starting point; Aim at wire; The height and the spray angle of adjustment flusher; Start flusher, antiskid mist sealing material is sprayed onto on the road surface, and spray pressure and the speed of a motor vehicle of in the liquid distributor traveling process, regulating flusher are until the cloth amount of the spilling 0.3kg/m that reaches expection 2~0.6kg/m 2, spill Bu Wendu during construction and should be controlled between 50~70 ℃, spray the back antiskid mist seal;
Step 7: health is open to traffic after 1~4 hour.
It is 0.3kg/m that antiskid mist sealing material of the present invention spills the cloth amount 2~0.6kg/m 2, antiskid mist sealing material film thickness is 0.2mm~0.5mm after the moulding fully, and its medium sand material fraction of coverage is not less than 60%, and the road surfaces coefficient of sliding resistance is not less than 50BPN during open to traffic.
Antiskid mist seal liquid distributor according to the invention is the conventional equipment that is exclusively used in the construction of antiskid mist seal, partly is made up of chassis, tank body, pump, power system and flusher etc., and its tank body has powerful whipping appts; Can be used for the processing and the storage of antiskid mist sealing material; Pipeline has anti-deposition design, and pump can be used for the pumping of solids-laden fluid material, has the big and big characteristics of pumpage of pressure; Flusher can spray the emulsion that contains solid particulate through particular design.
Positive beneficial effect of the present invention:
1. the construction back is detected to construction road section and with the adjacent highway section of common mist seal punishment; Detection method adopts " T 0964-2008 portable pendulum tester is measured the surface friction coefficient TP " in " highway subgrade road surface on-the-spot test rules " (JTG E60-2008); Detected result such as table 2
Seal highway section antiskid of table 2 antiskid mist and waterproof effect
Technology type Former road surface Tradition mist seal Antiskid mist seal
Frictional coefficient (BPN) 36 28 55
Infiltration coefficient (ml/min) 450 Do not seep water Do not seep water
Can know by last table:
(1) improved the cling property on former road surface after antiskid mist sealing material of the present invention is constructed; Effectively avoid traditional mist seal to use the insufficient problem of initial stage cling property, especially under the relatively poor situation of former pavement skid resistance condition, more can embody the function of antiskid mist seal of the present invention;
(2) antiskid mist sealing material of the present invention is reduced to 0 ml/min with the road surface infiltration coefficient from 450 ml/min, has improved the water resistance on road surface greatly, can effectively delay the aging of pavement structure.
2. the construction back is observed the road surface effect of construction section, is found out by Fig. 1, Fig. 2 contrast:
(1) antiskid mist sealing material bonding strength of the present invention, abrasion resisting ability are strong, are difficult for being ground off, taking away by wheel, the far ultra common mist sealing material of its weather resistance;
(2) be open to traffic after two months, taken away by driving, embed the inner sand grains bonding of oil film well, still have excellent anti-slide performance though part protrudes in the sand material of oil film and building stones end face.
3, antiskid mist seal of the present invention not only starting material be easy to get, construction process is simple, and reasonable in design, can in the maintenance project of each standard highway bituminous pavement, promote the use of.
Description of drawings
Fig. 1 is the embodiment of the invention 1 a construction back design sketch.
Fig. 2 is the embodiment of the invention 1 construction design sketch at wheel path place after two months that is open to traffic.
Embodiment
To further explain of the present invention, but the invention is not restricted to these embodiment below in conjunction with specific embodiment, in following examples raw materials used be commercially available.
Embodiment 1:
Adopt antiskid mist sealing material of the present invention that bituminous pavement is carried out the construction of antiskid mist seal and be example, antiskid mist sealing material is made by the starting material of following weight part meter:
25.0 parts of great achievement 70# bi tumenf orr oads
15.0 parts of the compound kaolin of 200 ~ 500 orders
1.2 parts of asphalt emulsifier MK-06
35.0 parts in tap water
0.2 part of 37% concentrated hydrochloric acid
0.15mm 50.0 parts in the natural silicon carbide of ~ 0.30mm particle diameter
The practical implementation process may further comprise the steps:
Step 1: be equipped with various raw materials according to above-mentioned antiskid mist sealing material proportioning;
Step 2: in the water with 50 ℃ of asphalt emulsifier MK-06 addings; With salt acid for adjusting pH value to 2.0~3.0; Treat fully to dissolve the back compound kaolin of adding and stir, regulate pH value to 2.0~3.0 of mixing liquid after thorough mixing is even once more with hydrochloric acid, make kaolin emulsified bitumen soap lye;
Step 3: great achievement 70# bi tumenf orr oad is heated to 130 ℃, and soap lye is heated to 60 ℃, bi tumenf orr oad and soap lye added in the mulser, and emulsification 1 ~ 3 minute, the mulser rotating speed is 2900~3000 rpm, makes the kaolin emulsified bitumen;
Step 4: the kaolin emulsified bitumen is added in the antiskid mist seal liquid distributor, open the whipping appts of antiskid mist seal liquid distributor, add natural silicon carbide again and continue and stir, thorough mixing evenly back antiskid mist seal liquid distributor goes to the job location;
Step 5: choose the bituminous pavement 150m of amorphousness disease, earth and other foreign material of cleaning on the road surface, with lane line as the direction wire;
Step 6: antiskid mist seal liquid distributor is opened to the construction starting point; Aim at traffic lane line; The height and the spray angle of adjustment flusher; Start flusher, antiskid mist sealing material is sprayed onto on the road surface, and spray pressure and the speed of a motor vehicle of in the liquid distributor traveling process, regulating flusher are until spilling the cloth amount near 0.3kg/m 2, the construction spray temperature is 50 ℃;
Step 7: health is open to traffic after 1 ~ 3 hour.
Embodiment 2:
Antiskid mist sealing material adopts the starting material of following weight part meter to make:
25.1 parts of great achievement 70# bi tumenf orr oads
15.1 parts of the compound kaolin of 200 ~ 500 orders
1.21 parts of asphalt emulsifier MK-06
35.1 parts in tap water
0.21 part of 37% concentrated hydrochloric acid
0.15mm 50.1 parts in the natural silicon carbide of ~ 0.30mm particle diameter
The practical implementation process is identical with embodiment 1.
Embodiment 3:
Antiskid mist sealing material adopts the starting material of following weight part meter to make:
32.5 parts of great achievement 70# bi tumenf orr oads
22.5 parts of the compound kaolin of 200 ~ 500 orders
1.6 parts of asphalt emulsifier MK-06
52.5 parts in tap water
0.6 part of 37% concentrated hydrochloric acid
0.15mm 65.0 parts in the natural silicon carbide of ~ 0.30mm particle diameter
Practical implementation process and embodiment 1 are basic identical, and difference is: in the water with 65 ℃ of asphalt emulsifier addings in the step 2; In the step 3 petroleum pitch is heated to 135 ℃, soap lye is heated to 65 ℃; Spill the cloth amount in the step 6 near 0.45kg/m 2, the construction spray temperature is 60 ℃.
Embodiment 4:
Antiskid mist sealing material adopts the starting material of following weight part meter to make:
39.9 parts of Kelamayi 70# bi tumenf orr oads
29.9 parts of the compound kaolin of 200 ~ 500 orders
1.99 parts of asphalt emulsifier MK-06
0.99 part of 37% concentrated hydrochloric acid
69.9 parts in tap water
0.15mm 79.9 parts of the black corundums of ~ 0.30mm particle diameter
Practical implementation process and embodiment 1 are basic identical, and difference is: in the water with 80 ℃ of asphalt emulsifier addings in the step 2; In the step 3 petroleum pitch is heated to 140 ℃, soap lye is heated to 70 ℃; Spill the cloth amount in the step 6 near 0.6kg/m 2, the construction spray temperature is 70 ℃.
Embodiment 5:
Antiskid mist sealing material adopts the starting material of following weight part meter to make:
40 parts of Kelamayi 70# bi tumenf orr oads
30 parts of the compound kaolin of 200 ~ 500 orders
2 parts of asphalt emulsifier MK-06
70 parts in tap water
1 part of 37% concentrated hydrochloric acid
0.15mm 80 parts of the black corundums of ~ 0.30mm particle diameter
The practical implementation process is identical with embodiment 4.
Embodiment 6:
Antiskid mist sealing material adopts the starting material of following weight part meter to make:
30.0 parts of great achievement 70# bi tumenf orr oads
26.0 parts of the compound kaolin of 200 ~ 500 orders
1.8 parts of asphalt emulsifier MK-06
44.0 parts in tap water
0.5 part of 37% concentrated hydrochloric acid
0.15mm 65.0 parts in the natural silicon carbide of ~ 0.30mm particle diameter
The practical implementation process is identical with embodiment 3.
Embodiment 7:
Antiskid mist sealing material adopts the starting material of following weight part meter to make:
27.5 parts of great achievement 70# bi tumenf orr oads
17.5 parts of the compound kaolin of 200 ~ 500 orders
1.3 parts of asphalt emulsifier MK-06
40.0 parts in tap water
0.4 part of 37% concentrated hydrochloric acid
0.15mm 55.0 parts in the natural silicon carbide of ~ 0.30mm particle diameter
Practical implementation process and embodiment 1 are basic identical, and difference is: in the water with 55 ℃ of asphalt emulsifier addings in the step 2; In the step 3 petroleum pitch is heated to 135 ℃, soap lye is heated to 65 ℃; Spill the cloth amount in the step 6 near 0.4kg/m 2, the construction spray temperature is 55 ℃.
Embodiment 8:
Antiskid mist sealing material adopts the starting material of following weight part meter to make:
29.9 parts of great achievement 70# bi tumenf orr oads
19.9 parts of the compound kaolin of 200 ~ 500 orders
1.39 parts of asphalt emulsifier MK-06
44.9 parts in tap water
0.49 part of 37% concentrated hydrochloric acid
0.15mm 59.9 parts in the natural silicon carbide of ~ 0.30mm particle diameter
Practical implementation process and embodiment 1 are basic identical, and difference is: in the water with 60 ℃ of asphalt emulsifier addings in the step 2; In the step 3 petroleum pitch is heated to 135 ℃, soap lye is heated to 65 ℃; Spill the cloth amount in the step 6 near 0.4kg/m 2, the construction spray temperature is 65 ℃.
Embodiment 9:
Antiskid mist sealing material adopts the starting material of following weight part meter to make:
30.0 parts of great achievement 70# bi tumenf orr oads
20.0 parts of the compound kaolin of 200 ~ 500 orders
1.4 parts of asphalt emulsifier MK-06
45.0 parts in tap water
0.5 part of 37% concentrated hydrochloric acid
0.15mm 60.0 parts in the natural silicon carbide of ~ 0.30mm particle diameter
The practical implementation process is identical with embodiment 8.
Embodiment 10:
Antiskid mist sealing material adopts the starting material of following weight part meter to make:
30.1 parts of great achievement 70# bi tumenf orr oads
20.1 parts of the compound kaolin of 200 ~ 500 orders
1.41 parts of asphalt emulsifier MK-06
45.1 parts in tap water
0.51 part of 37% concentrated hydrochloric acid
0.15mm 60.1 parts of the bottom sands of ~ 0.30mm particle diameter
The practical implementation process is identical with embodiment 8.
Embodiment 11:
Antiskid mist sealing material adopts the starting material of following weight part meter to make:
34.9 parts of great achievement 70# bi tumenf orr oads
24.9 parts of the compound kaolin of 200 ~ 500 orders
1.79 parts of asphalt emulsifier MK-06
59.9 parts in tap water
0.79 part of 37% concentrated hydrochloric acid
0.15mm 69.9 parts of the bottom sands of ~ 0.30mm particle diameter
Practical implementation process and embodiment 1 are basic identical, and difference is: in the water with 70 ℃ of asphalt emulsifier addings in the step 2; In the step 3 petroleum pitch is heated to 135 ℃, soap lye is heated to 65 ℃; Spill the cloth amount in the step 6 near 0.5kg/m 2, the construction spray temperature is 65 ℃.
Embodiment 12:
Antiskid mist sealing material adopts the starting material of following weight part meter to make:
35.0 parts of Kelamayi 70# bi tumenf orr oads
25.0 parts of the compound kaolin of 200 ~ 500 orders
1.8 parts of asphalt emulsifier MK-06
60.0 parts in tap water
0.8 part of 37% concentrated hydrochloric acid
0.15mm 50.0 parts of the bottom sands of ~ 0.30mm particle diameter
0.15mm 20.0 parts of the black corundums of ~ 0.30mm particle diameter
The practical implementation process is identical with embodiment 11.
Embodiment 13:
Antiskid mist sealing material adopts the starting material of following weight part meter to make:
35.1 parts of Kelamayi 70# bi tumenf orr oads
25.1 parts of the compound kaolin of 200 ~ 500 orders
1.81 parts of asphalt emulsifier MK-06
60.1 parts in tap water
0.81 part of 37% concentrated hydrochloric acid
0.15mm 50.1 parts of the bottom sands of ~ 0.30mm particle diameter
0.15mm 20.1 parts of the black corundums of ~ 0.30mm particle diameter
The practical implementation process is identical with embodiment 11.
Embodiment 14:
Antiskid mist sealing material adopts the starting material of following weight part meter to make:
37.5 parts of Kelamayi 70# bi tumenf orr oads
27.5 parts of the compound kaolin of 200 ~ 500 orders
1.9 parts of asphalt emulsifier MK-06
65.0 parts in tap water
0.9 part of 37% concentrated hydrochloric acid
0.15mm 52.5 parts of the bottom sands of ~ 0.30mm particle diameter
0.15mm 22.5 parts of the black corundums of ~ 0.30mm particle diameter
Practical implementation process and embodiment 1 are basic identical, and difference is: in the water with 75 ℃ of asphalt emulsifier addings in the step 2; In the step 3 petroleum pitch is heated to 140 ℃, soap lye is heated to 65 ℃; Spill the cloth amount in the step 6 near 0.55kg/m 2, the construction spray temperature is 65 ℃.

Claims (8)

1. an antiskid mist sealing material is characterized in that, is made by the starting material of following weight part meter:
25 ~ 40 parts in petroleum pitch
15 ~ 30 parts of the compound kaolin of 200 ~ 500 orders
1.2 ~ 2.0 parts of asphalt emulsifiers
35 ~ 70 parts in water
0.2 ~ 1.0 part of pH value regulator
0.15mm 50 ~ 80 parts in the sand material of ~ 0.30mm particle diameter.
2. antiskid mist sealing material according to claim 1 is characterized in that, is made by the starting material of following weight part meter:
30 parts in petroleum pitch
25 ~ 27 parts of the compound kaolin of 200 ~ 500 orders
1.8 parts of asphalt emulsifiers
43 ~ 45 parts in water
0.2 ~ 1 part of pH value regulator
0.15mm 0 ~ 80 part in the sand material of ~ 0.30mm particle diameter.
3. antiskid mist sealing material according to claim 1 is characterized in that, is made by the starting material of following weight part meter:
25 ~ 30 parts in petroleum pitch
15 ~ 20 parts of the compound kaolin of 200 ~ 500 orders
1.2 ~ 1.4 parts of asphalt emulsifiers
35 ~ 45 parts in water
0.2 ~ 0.5 part of pH value regulator
0.15mm 50 ~ 60 parts in the sand material of ~ 0.30mm particle diameter.
4. antiskid mist sealing material according to claim 1 is characterized in that, is made by the starting material of following weight part meter:
30 ~ 35 parts in petroleum pitch
20 ~ 25 parts of the compound kaolin of 200 ~ 500 orders
1.4 ~ 1.8 parts of asphalt emulsifiers
45 ~ 60 parts in water
0.5 ~ 0.8 part of pH value regulator
0.15mm 60 ~ 70 parts in the sand material of ~ 0.30mm particle diameter.
5. antiskid mist sealing material according to claim 1 is characterized in that, is made by the starting material of following weight part meter:
35 ~ 40 parts in petroleum pitch
25 ~ 30 parts of the compound kaolin of 200 ~ 500 orders
1.8 ~ 2.0 parts of asphalt emulsifiers
60 ~ 70 parts in water
0.8 ~ 1.0 part of pH value regulator
0.15mm 70 ~ 80 parts in the sand material of ~ 0.30mm particle diameter.
6. according to each described antiskid mist sealing material of claim 1 ~ 6, it is characterized in that: said petroleum pitch is 70# or 90# bi tumenf orr oad; Said asphalt emulsifier is alkylammonium salt or quaternary ammonium salt emulsifying agent; Said pH value regulator is that mass concentration is 30% ~ 38% concentrated hydrochloric acid; Said sand material is choosing any one kind of them or several kinds in natural silicon carbide, garnet, diamantine, silit, bottom sand, iron sand and the silica sand.
7. a constructional method of utilizing the said antiskid mist of claim 1 sealing material making antiskid mist seal is characterized in that, may further comprise the steps:
Step 1: be equipped with each raw material according to the said antiskid mist of claim 1 sealing material proportioning;
Step 2: in the water with 50~80 ℃ of said asphalt emulsifier addings; Regulate the pH value to the scope of corresponding emulsifying agent requirement with pH value regulator; Treat that fully the dissolving back adds compound kaolin and stirs; Thorough mixing is regulated in the scope of the extremely corresponding emulsifying agent requirement of pH value of mixing liquid with pH value regulator after evenly once more, makes kaolin emulsified bitumen soap lye;
Step 3: petroleum pitch is heated to 130~140 ℃; Last step gained kaolin emulsified bitumen soap lye is heated to 60~70 ℃, and petroleum pitch and said soap lye are added in the mulser emulsification 1~3 minute; The mulser rotating speed is 2900~3000 rpm, makes the kaolin emulsified bitumen;
Step 4: the adding of sand material is upward gone on foot in the gained kaolin emulsified bitumen, after brute force mixes, make antiskid mist sealing material, need to keep stirring after antiskid mist sealing material is processed, the time that stops to stir in use or the transportation is no more than 2 hours;
Step 5: loose material, earth, weeds on the cleaning road surface, remove greasy dirt and other foreign material, mark wire along construction direction;
Step 6: with antiskid mist seal liquid distributor antiskid mist sealing material is sprayed onto on the road surface, and spray pressure and the speed of a motor vehicle of in the liquid distributor traveling process, regulating flusher are until the cloth amount of the spilling 0.3kg/m that reaches expection 2~0.6kg/m 2, spray temperature is controlled between 50~70 ℃, spray the back antiskid mist seal;
Step 7: health is open to traffic after 1~4 hour.
8. according to the constructional method of the said antiskid mist of claim 7 seal, it is characterized in that thickness is 0.2mm~0.5mm after the moulding of antiskid mist seal.
CN201210305367.5A 2012-08-27 2012-08-27 Anti-slide fog seal material and its construction method Active CN102815892B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210305367.5A CN102815892B (en) 2012-08-27 2012-08-27 Anti-slide fog seal material and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210305367.5A CN102815892B (en) 2012-08-27 2012-08-27 Anti-slide fog seal material and its construction method

Publications (2)

Publication Number Publication Date
CN102815892A true CN102815892A (en) 2012-12-12
CN102815892B CN102815892B (en) 2014-03-05

Family

ID=47300398

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210305367.5A Active CN102815892B (en) 2012-08-27 2012-08-27 Anti-slide fog seal material and its construction method

Country Status (1)

Country Link
CN (1) CN102815892B (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104164818A (en) * 2014-08-22 2014-11-26 长安大学 Water-based reinforced type fog sealing layer material for asphalt pavement, and preparation method and construction method of water-based reinforced type fog sealing layer material for asphalt pavement
CN105541194A (en) * 2015-12-09 2016-05-04 长安大学 Fog seal material and preparation method thereof
CN105568833A (en) * 2015-12-16 2016-05-11 孙声亮 Diluting maintenance method for asphalt pavement
CN107938460A (en) * 2017-11-27 2018-04-20 中汽中心盐城汽车试验场有限公司 A kind of automobile test low attached bituminous paving and its laying method
CN108165176A (en) * 2017-12-28 2018-06-15 中公高科养护科技股份有限公司 A kind of anti-freezing ice sealing material of mist containing sand and preparation method thereof
CN108585621A (en) * 2018-04-17 2018-09-28 江苏西尔玛道路环保材料有限公司 A kind of asphaltic base concentration cover material and preparation method thereof and the sealing mixture of mist containing sand
CN108624069A (en) * 2018-05-16 2018-10-09 江苏西尔玛道路环保材料有限公司 Sand material is hanged in a kind of bituminous paving pitted skin patching material and preparation method thereof and the repairing of bituminous paving pitted skin
CN108842556A (en) * 2018-07-02 2018-11-20 绍兴市公路管理局 Tunnel cement concrete road surface oil resistant finishing coat and its overlay technique
CN108947455A (en) * 2018-08-18 2018-12-07 江苏顺晟新材料科技有限公司 A kind of color slurry sealing and preparation method thereof
CN109096991A (en) * 2018-08-14 2018-12-28 江苏增光复合材料科技有限公司 A kind of antiskid mist sealing material and its construction method
CN109627792A (en) * 2018-11-30 2019-04-16 湖南鑫长胜材料科技有限公司 A kind of mist sealing material, preparation method and application
CN109694482A (en) * 2017-10-23 2019-04-30 神华集团有限责任公司 Modified emulsifying asphalt and preparation method thereof and mist sealing material
CN109694583A (en) * 2017-10-23 2019-04-30 神华集团有限责任公司 Mist sealing maintenance material and its preparation method and application
CN111153633A (en) * 2020-01-09 2020-05-15 江苏中新苏通市政工程有限公司 Anti-cracking asphalt concrete and preparation process thereof
CN111410913A (en) * 2019-01-04 2020-07-14 中国石油化工股份有限公司 Modified sand-containing fog sealing layer material and preparation method thereof
CN112408860A (en) * 2020-11-04 2021-02-26 广东中和正通工程技术有限公司 Asphalt concrete and application thereof
CN116285687A (en) * 2023-03-15 2023-06-23 北京工业大学 Phase-change fog seal material containing phase-change material, and preparation method and application thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101475748A (en) * 2009-01-20 2009-07-08 钦兰成 High strength cold state asphalt fissure cementation water-proof glue and preparation thereof
CN102515669A (en) * 2011-12-19 2012-06-27 重庆市智翔铺道技术工程有限公司 Water-retaining and cooling material for road as well as preparation and construction methods for same

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101475748A (en) * 2009-01-20 2009-07-08 钦兰成 High strength cold state asphalt fissure cementation water-proof glue and preparation thereof
CN102515669A (en) * 2011-12-19 2012-06-27 重庆市智翔铺道技术工程有限公司 Water-retaining and cooling material for road as well as preparation and construction methods for same

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104164818B (en) * 2014-08-22 2016-03-23 长安大学 Flexible pavement use enhancement mode mist sealing material and preparation method and construction method
CN104164818A (en) * 2014-08-22 2014-11-26 长安大学 Water-based reinforced type fog sealing layer material for asphalt pavement, and preparation method and construction method of water-based reinforced type fog sealing layer material for asphalt pavement
CN105541194A (en) * 2015-12-09 2016-05-04 长安大学 Fog seal material and preparation method thereof
CN105568833A (en) * 2015-12-16 2016-05-11 孙声亮 Diluting maintenance method for asphalt pavement
CN109694482A (en) * 2017-10-23 2019-04-30 神华集团有限责任公司 Modified emulsifying asphalt and preparation method thereof and mist sealing material
CN109694482B (en) * 2017-10-23 2021-08-10 国家能源投资集团有限责任公司 Modified emulsified asphalt, preparation method thereof and fog sealing layer material
CN109694583B (en) * 2017-10-23 2021-04-06 神华集团有限责任公司 Fog sealing layer curing material and preparation method and application thereof
CN109694583A (en) * 2017-10-23 2019-04-30 神华集团有限责任公司 Mist sealing maintenance material and its preparation method and application
CN107938460A (en) * 2017-11-27 2018-04-20 中汽中心盐城汽车试验场有限公司 A kind of automobile test low attached bituminous paving and its laying method
CN108165176A (en) * 2017-12-28 2018-06-15 中公高科养护科技股份有限公司 A kind of anti-freezing ice sealing material of mist containing sand and preparation method thereof
CN108165176B (en) * 2017-12-28 2020-08-25 中公高科养护科技股份有限公司 Anti-freezing sand-containing fog sealing layer material and preparation method thereof
CN108585621A (en) * 2018-04-17 2018-09-28 江苏西尔玛道路环保材料有限公司 A kind of asphaltic base concentration cover material and preparation method thereof and the sealing mixture of mist containing sand
CN108624069A (en) * 2018-05-16 2018-10-09 江苏西尔玛道路环保材料有限公司 Sand material is hanged in a kind of bituminous paving pitted skin patching material and preparation method thereof and the repairing of bituminous paving pitted skin
CN108842556A (en) * 2018-07-02 2018-11-20 绍兴市公路管理局 Tunnel cement concrete road surface oil resistant finishing coat and its overlay technique
CN109096991A (en) * 2018-08-14 2018-12-28 江苏增光复合材料科技有限公司 A kind of antiskid mist sealing material and its construction method
CN109096991B (en) * 2018-08-14 2020-10-23 江苏增光复合材料科技有限公司 Anti-sliding fog seal material and construction method thereof
CN108947455A (en) * 2018-08-18 2018-12-07 江苏顺晟新材料科技有限公司 A kind of color slurry sealing and preparation method thereof
CN109627792A (en) * 2018-11-30 2019-04-16 湖南鑫长胜材料科技有限公司 A kind of mist sealing material, preparation method and application
CN109627792B (en) * 2018-11-30 2021-06-08 湖南鑫长胜材料科技有限公司 Fog sealing layer material, preparation method and application
CN111410913A (en) * 2019-01-04 2020-07-14 中国石油化工股份有限公司 Modified sand-containing fog sealing layer material and preparation method thereof
CN111410913B (en) * 2019-01-04 2022-08-12 中国石油化工股份有限公司 Modified sand-containing fog sealing layer material and preparation method thereof
CN111153633A (en) * 2020-01-09 2020-05-15 江苏中新苏通市政工程有限公司 Anti-cracking asphalt concrete and preparation process thereof
CN112408860A (en) * 2020-11-04 2021-02-26 广东中和正通工程技术有限公司 Asphalt concrete and application thereof
CN116285687A (en) * 2023-03-15 2023-06-23 北京工业大学 Phase-change fog seal material containing phase-change material, and preparation method and application thereof

Also Published As

Publication number Publication date
CN102815892B (en) 2014-03-05

Similar Documents

Publication Publication Date Title
CN102815892B (en) Anti-slide fog seal material and its construction method
US7714058B2 (en) Pavement life extension product and method
CN104446163B (en) A kind of mist sealing material and preparation method thereof
CN103114526B (en) Steel bridge deck pavement cold mixing maintenance material and manufacturing method thereof
CN105439496A (en) A water-borne epoxy resin-emulsified bitumen micro-surfacing mixture and a preparing method thereof
CN103232206B (en) Thin slurry mixture paved on thin-layer cover on ice and snow melting micro-surface and paving method
CN101476273A (en) Japanese epoxy asphalt pavement construction method for large-stride steel bridge deck
CN105088965A (en) Steel bridge deck pavement structure and method
CN107586459A (en) A kind of durability porous asphalt pavement anti-disperse material and its construction method
CN105113407B (en) Bridge deck pavement surface layer structure and maintenance construction method
CN109083024A (en) A kind of construction technology of the modification coating for highway bridge floor
CN102828454B (en) Resin asphalt concrete paving structure capable of being constructed at normal temperature, and paving method thereof
CN103924495A (en) Small and medium-sized steel bridge deck pavement system and implementation method
CN101319091A (en) Colorful asphalt emulsion, preparation, and application in colorful slurry sealing layer
CN109056525A (en) A kind of Steel Bridge Deck composite pavement structure and method for paving
CN114351529A (en) Pavement structure adopting warm-mix ultrathin layer overlay and construction method thereof
CN103232205B (en) Thin paste mixture for paving automobile-exhaust-absorptive micro-surfacing overlay and pavement method thereof
CN211340403U (en) Bridge deck asphalt pavement structure capable of actively resisting ice and snow
CN105803937B (en) A kind of AC and epoxy construction layer clad steel bridge floor pavement construction method
CN103880353B (en) The slurry mixture of response type rubber asphalt micro-surface area thin overlay and laying method
CN213448074U (en) Composite construction suitable for steel bridge deck drainage is mated formation
Bressette et al. Asphalt rubber and its potential use in China
US8080597B2 (en) Composition and a process thereof
CN104846715A (en) Method for cape seal of preventative-maintenance experimental road
Yao et al. Functional Layer Materials of and Preventive Maintenance Materials of Pavement

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant