CN102808599B - Drilling line stringing-up safety method - Google Patents
Drilling line stringing-up safety method Download PDFInfo
- Publication number
- CN102808599B CN102808599B CN201210231993.4A CN201210231993A CN102808599B CN 102808599 B CN102808599 B CN 102808599B CN 201210231993 A CN201210231993 A CN 201210231993A CN 102808599 B CN102808599 B CN 102808599B
- Authority
- CN
- China
- Prior art keywords
- old
- hook
- new
- rope
- line
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Emergency Lowering Means (AREA)
Abstract
The invention relates to the technical field of well repair operation of an oilfield, in particular to a drilling line stringing-up safety method. The method comprises the following steps of: 1, untwisting a new steel wire line before a drilling line is stringed up; 2, fixing a new hook and an old hook of a derrick at positions on two sides of the derrick, which are 2 to 2.5 m above the ground, by using a steel wire line sleeve, and opening protection plates on both sides of the new hook and the old hook; and 3, disassembling all line clips at old dead line ends of the derrick, cutting off an old drilling line at a position which is 0.5 to 1.0 m above the upper parts of the dead line clips, splitting the old drilling line at the position of 1.0 m to 1.2 m, connecting a split part of the old drilling line and the split part of a new drilling line at the position of 1.0 m to 1.2 m, and fixing the top of a joint by using a thin steel wire or a thin hemp line. By adoption of the drilling line stringing-up safety method, the drilling line can be stringed up on the ground, the hooks can be replaced, the operation process is safe, and working efficiency is high, and the defects that an operator needs to work at high altitude during the conventional drilling line stringing-up and hook replacement operation, the operation process is dangerous and the working efficiency is low are overcome.
Description
Technical field:
The present invention relates to a kind of oil well repairing operation technical field, particularly a kind of cable-feeding safety method.
Background technology:
Spring, winter Hetao area wind-force stronger, large rop exercise is changed in work high above the ground, and to make risk larger, when carrying out cable-feeding to scene, oil recovery factory, changing hook operation, old large rope must be first extracted out with chain rail working rig (certainly carrying on the back handcart, electric car), high-altitude application personnel carry messenger (coir rope) in sky roof, utilize messenger carry out drawing wear newly restrict greatly, change hook operation.Such personal height operation easier risk increases, and work limitation is lower, in case of strong wind, bad weather easily cause personal height falling accident.
Summary of the invention:
The technical problem to be solved in the present invention is to provide a kind of cable-feeding safety method, the method achieves to carry out cable-feeding on ground, change hook operation, safe operation process, and operating efficiency is high.Overcome existing cable-feeding, change hook operation and need operating personnel's work high above the ground, operating process is dangerous, ineffective deficiency.
The technical solution used in the present invention is: a kind of cable-feeding safety method, and the method step is as follows:
Steel wire rope broken strength before cable-feeding of one, will newly enable;
Two, new hook and the old derrick both sides that are hooked in greatly of derrick are fixed far from 2-2.5 rice, ground steel wire loop, open new hook and old hook two side guard plate simultaneously;
Three, old for derrick dead line end rope clip is all laid down, after cutting off old large rope apart from 0.5-1.0 rice, dead line clamp top, split stock at old large rope 1.0-1.2 rice and split a burst place with new 1.0-1.2 rice of restricting greatly and be connected, and top, junction finer wire or fine cordage are fixed;
Four, working rig slowly on carry large rope, remove junction rapidly when large rope fast line junction enters old hook first pulley 1-2 rice; The new large rope of drawing is being entered new hook first pulley with old large rope on the homonymy direction in the direction of old hook first pulley, after old large rope is extracted out from old hook block, be connected and fixed along new hook first pulley opposite side direction and new rope greatly, continue to carry large rope slowly;
Five, wear that 50 tons, the 80 tons large ropes of hook enter second and third, four road pulleys all operate according to the 4th step by that analogy, guarantee cable-feeding, change hook and accurately complete;
Six, last new large rope end becomes derrick dead line end, has blocked tensiometer, has adopted the fixing clamping of six road rope clips.
The invention has the beneficial effects as follows: the present invention can carry out cable-feeding, change hook operation on ground, avoid operating personnel to carry out work high above the ground, safe operation process is reliable, and operating efficiency is high.
Detailed description of the invention:
A kind of cable-feeding safety method, the method step is as follows:
Steel wire rope broken strength before cable-feeding of one, will newly enable;
Two, new hook and the old derrick both sides that are hooked in greatly of derrick are fixed far from 2-2.5 rice, ground steel wire loop, open new hook and old hook two side guard plate simultaneously;
Three, old for derrick dead line end rope clip is all laid down, after cutting off old large rope apart from 0.5-1.0 rice, dead line clamp top, split stock at old large rope 1.0-1.2 rice and split a burst place with new 1.0-1.2 rice of restricting greatly and be connected, and top, junction finer wire or fine cordage are fixed;
Four, working rig slowly on carry large rope, remove junction rapidly when large rope fast line junction enters old hook first pulley 1-2 rice; The new large rope of drawing is being entered new hook first pulley with old large rope on the homonymy direction in the direction of old hook first pulley, after old large rope is extracted out from old hook block, be connected and fixed along new hook first pulley opposite side direction and new rope greatly, continue to carry large rope slowly;
Five, wear that 50 tons, the 80 tons large ropes of hook enter second and third, four road pulleys all operate according to the 4th step by that analogy, guarantee cable-feeding, change hook and accurately complete;
Six, last new large rope end becomes derrick dead line end, has blocked tensiometer, has adopted the fixing clamping of six road rope clips.
Be understandable that, above about specific descriptions of the present invention, the technical scheme described by the embodiment of the present invention is only not limited to for illustration of the present invention, those of ordinary skill in the art is to be understood that, still can modify to the present invention or equivalent replacement, to reach identical technique effect; Needs are used, all within protection scope of the present invention as long as meet.
Claims (1)
1. a cable-feeding safety method, is characterized in that: the method step is as follows:
Steel wire rope broken strength before cable-feeding of one, will newly enable;
Two, new hook and the old derrick both sides that are hooked in greatly of derrick are fixed far from 2-2.5 rice, ground steel wire loop, open new hook and old hook two side guard plate simultaneously;
Three, old for derrick dead line end rope clip is all laid down, after cutting off old large rope apart from 0.5-1.0 rice, dead line clamp top, split stock at old large rope 1.0-1.2 rice and split a burst place with new 1.0-1.2 rice of restricting greatly and be connected, and top, junction finer wire or fine cordage are fixed;
Four, working rig slowly on carry large rope, remove junction rapidly when large rope fast line junction enters old hook first pulley 1-2 rice; The new large rope of drawing is being entered new hook first pulley with old large rope on the homonymy direction in the direction of old hook first pulley, after old large rope is extracted out from old hook block, be connected and fixed along new hook first pulley opposite side direction and new rope greatly, continue to carry large rope slowly;
Five, wear that 50 tons, the 80 tons large ropes of hook enter second and third, four road pulleys all operate according to the 4th step by that analogy, guarantee cable-feeding, change hook and accurately complete;
Six, last new large rope end becomes derrick dead line end, has blocked tensiometer, has adopted the fixing clamping of six road rope clips.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210231993.4A CN102808599B (en) | 2012-07-05 | 2012-07-05 | Drilling line stringing-up safety method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210231993.4A CN102808599B (en) | 2012-07-05 | 2012-07-05 | Drilling line stringing-up safety method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102808599A CN102808599A (en) | 2012-12-05 |
CN102808599B true CN102808599B (en) | 2015-03-25 |
Family
ID=47232450
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210231993.4A Expired - Fee Related CN102808599B (en) | 2012-07-05 | 2012-07-05 | Drilling line stringing-up safety method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102808599B (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4789136A (en) * | 1986-10-30 | 1988-12-06 | Quadco, Inc. | Method and cable anchor assembly for anchoring plastic coated rope |
CN2660089Y (en) * | 2003-08-22 | 2004-12-01 | 宝鸡石油机械有限责任公司 | Spirally lifting headframe basement having lifting system and wire threading way |
CN2825918Y (en) * | 2005-04-13 | 2006-10-11 | 中国石化集团江汉石油管理局第四机械厂 | Improved traveling block for self-lifting type upright derrick |
CN201236640Y (en) * | 2008-07-25 | 2009-05-13 | 宝鸡石油机械有限责任公司 | Novel travelling hoist compensating system |
CN101712443A (en) * | 2009-12-22 | 2010-05-26 | 舞阳钢铁有限责任公司 | Quick replacement method of steel cables of crane |
CN201530668U (en) * | 2009-05-15 | 2010-07-21 | 中国十七冶建设有限公司 | Protection device for hook of hoist |
CN201567979U (en) * | 2009-12-16 | 2010-09-01 | 中国石油天然气集团公司 | Drilling-assisted pressurizing device for extraction of petroleum and CBM (coal bed methane) |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20080277364A1 (en) * | 2006-06-30 | 2008-11-13 | Mcguffin Martin H | Multi-reeve handling and hoisting system |
-
2012
- 2012-07-05 CN CN201210231993.4A patent/CN102808599B/en not_active Expired - Fee Related
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4789136A (en) * | 1986-10-30 | 1988-12-06 | Quadco, Inc. | Method and cable anchor assembly for anchoring plastic coated rope |
CN2660089Y (en) * | 2003-08-22 | 2004-12-01 | 宝鸡石油机械有限责任公司 | Spirally lifting headframe basement having lifting system and wire threading way |
CN2825918Y (en) * | 2005-04-13 | 2006-10-11 | 中国石化集团江汉石油管理局第四机械厂 | Improved traveling block for self-lifting type upright derrick |
CN201236640Y (en) * | 2008-07-25 | 2009-05-13 | 宝鸡石油机械有限责任公司 | Novel travelling hoist compensating system |
CN201530668U (en) * | 2009-05-15 | 2010-07-21 | 中国十七冶建设有限公司 | Protection device for hook of hoist |
CN201567979U (en) * | 2009-12-16 | 2010-09-01 | 中国石油天然气集团公司 | Drilling-assisted pressurizing device for extraction of petroleum and CBM (coal bed methane) |
CN101712443A (en) * | 2009-12-22 | 2010-05-26 | 舞阳钢铁有限责任公司 | Quick replacement method of steel cables of crane |
Non-Patent Citations (2)
Title |
---|
更换千米深井提升钢丝绳的施工工艺;邢德喜等;《煤矿机电》;20081231(第5期);95-96 * |
陈锋等.浅析煤矿立井多绳摩擦式提升机的换绳方法.《能源技术与管理》.2009,(第4期),98-99. * |
Also Published As
Publication number | Publication date |
---|---|
CN102808599A (en) | 2012-12-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105888262B (en) | A kind of construction method of large span piping lane pipeline | |
CN102030270B (en) | Auxiliary tool and method for replacing wire rope of bridge crane | |
CN102808599B (en) | Drilling line stringing-up safety method | |
CN105932601A (en) | Method for repairing break strand of overhead ground wire | |
CN102237654B (en) | Method for replacing jumper string using tool at double angle hanging point | |
CN202197048U (en) | Double angle steel hanging point lifting and connecting tool for tower use | |
CN201332236Y (en) | Transmission line lead repairing manned tackle | |
CN109768502A (en) | A kind of transmission line of electricity not overboard lead over strait puts Di Nima construction method | |
CN202917897U (en) | Cable hoisting horizontal pulley | |
CN102561207A (en) | Construction method for vertically rotating arch rib | |
CN103373664B (en) | Self-tightening lifting appliance | |
CN104058349B (en) | A kind of steel strand hoisting clamping device and method for improving | |
CN203923102U (en) | The transmission system with lineoutofservice signal pull detection for a kind of hydraulic decoking equipment | |
CN203081312U (en) | Drilling rig derrick racking platform escape device | |
CN105162043A (en) | Line suspension device for spanning line change of distribution aerial circuit, and application thereof | |
CN101797969B (en) | Method for releasing and recovering underwater equipment with high wind wave resistance | |
CN206338037U (en) | A kind of well workover self-balancing derrick | |
CN206332388U (en) | Ocean bottom cable repairing device | |
CN102361273B (en) | Cable-stayed suspension combined suspending method for cable protection in gallery inspection | |
CN109205469A (en) | A kind of split type structure of electric block and its electric control system | |
CN103601065B (en) | A kind of steel wire coil hoisting clamp | |
CN203755166U (en) | Simple lifting device for constructors to go up and down | |
CN204569099U (en) | A kind of steel wire rope for elevator lift instrument | |
CN204150923U (en) | A kind of track lifting appliance | |
CN216109859U (en) | Safety net hanging device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150325 Termination date: 20150705 |
|
EXPY | Termination of patent right or utility model |