CN102787844A - 用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法 - Google Patents

用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法 Download PDF

Info

Publication number
CN102787844A
CN102787844A CN2012102500281A CN201210250028A CN102787844A CN 102787844 A CN102787844 A CN 102787844A CN 2012102500281 A CN2012102500281 A CN 2012102500281A CN 201210250028 A CN201210250028 A CN 201210250028A CN 102787844 A CN102787844 A CN 102787844A
Authority
CN
China
Prior art keywords
tunnel
inclined shaft
development machine
super long
heading
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012102500281A
Other languages
English (en)
Inventor
柴永模
邹春华
毛东晖
刘树山
徐润泽
宋修元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 13th Bureau Group Co Ltd
Original Assignee
China Railway 13th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 13th Bureau Group Co Ltd filed Critical China Railway 13th Bureau Group Co Ltd
Priority to CN2012102500281A priority Critical patent/CN102787844A/zh
Publication of CN102787844A publication Critical patent/CN102787844A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

一种用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法,用一台小直径掘进机从隧道低端洞口上导坑位置,向隧道高端洞口掘进,至4-8km处的上导坑位置转向沿斜井掘出,实现特长隧道施工,同时形成斜井“高烟囱”自吸式通风。本发明可实现特长隧道多工作面钻眼爆破与机械破岩技术相结合的快速施工,具有安全、快速、掘进机费用较低、适合我国山区特长隧道修建的特点。

Description

用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法
技术领域:
本发明属于一种隧道施工方法,特别涉及一种用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法。
背景技术:
目前,特长隧道施工方法主要采用钻爆法和掘进法两种方法。这两种方法存在如下缺陷:
1、钻爆法:
(1)钻爆法为减少对围岩的挠动,虽然已实现光面爆破、预裂爆破等,但是,爆破对软弱围岩的扰动仍不能克服。
(2)长隧道施工中,设置多座斜井,将长隧道分割成几段施工是缩短工期的常用办法。但由于用钻爆法修建斜井速度很慢,需要增加斜井数量来加快进度、节省工期,因此增加了隧道施工的成本,破坏了隧道斜井周边植被及地下水环境。
(3)钻爆法施工无法将隧道开挖过程中的各工序连续起来,从而影响施工速度和施工的安全性。
2、掘进机(TBM)法:掘进机法属机械切割破岩,对围岩扰动小,开挖面平整圆顺,超欠挖少,可以有效降低施工地质灾害的发生风险。目前广泛应用于交通、水利、城建、等行业工程建设中。目前,我国在隧道施工中普遍采用直径大于10m的大直径掘进机,由于掘进机直径大,既增加了掘进机设备投入,又增加了在山区长隧道中使用和运输难度。
发明内容:
本发明的目的就在于提供一种用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法,该方法采用小直径掘进机首先掘进长隧道斜井和导坑,再采用多工作面钻爆法扩大、衬砌,实现特长隧道分段快速施工。
如上构思,本发明的技术方案是:一种用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法,其特征在于:用一台小直径掘进机从隧道低端洞口上导坑位置,向隧道高端洞口掘进,至4-8km处的上导坑位置转向沿斜井掘出,实现特长隧道快速施工,同时形成斜井“高烟囱”自吸式通风。
上述斜井长度≤1500m,坡度16°。
上述小直径掘进机的直径小于隧道的建筑限界及衬砌内轮廓,即隧限直径。
上述小直径掘进机掘进隧道的斜井和上导坑的具体方法是:采用双线合修的单洞形式,设置一座斜井,用一台小直径掘进机从隧道低端洞口上导坑位置,向隧道高端洞口掘进,至6km处的上导坑位置转向沿斜井掘出,实现特长隧道快速施工;同时,利用斜井井口与隧道底高差及洞内、外温度差的“高烟囱”效应,利用通风机和软管将新风从隧道低端洞口吸入,并送到掘进机工作面,形成巷道式节能通风。
本发明具有如下的优点和积极效果:
1、本发明采用掘进机施工导坑的掘进速度是钻爆法掘进斜井速度的3-5倍,从而使长隧道分段少,减少斜井数量,减少对植被和地下水环境破坏。
2、本发明采用掘进机快速施工上导坑、斜井,有利隧道组织多工作面扩挖,从而达到长隧快做的目的。
3、本发明采用掘进机快速施工上导坑、斜井,有利于提前探明地质、有利于排水、施工通风和运输组织。
4、本发明采用掘进机快速施工上导坑、斜井,作业环境好,施工安全。
5、本发明采用小直径掘进机先掘进长隧道斜井及导坑,能为长隧道的设计与施工带来以下优点:
可对隧道轴线范围的地层连续地地质调查;能对隧道支护系统作进一步精确的设计,利用掘进机对围岩扰动小,可使用最少数量的初期支护手段;易于大断面扩施工,建成软弱地带隧道;使岩体中的高地应力预先释放,减少岩爆风险;能规划和安排隧道多个工作面开挖、支护和衬砌作业,确保隧道规划的建设工期。
附图说明:
图1是本发明的施工示意图。
具体实施方式:
以长度10km高速铁路客专隧道,采用合修的单洞形式,拟设置1座斜井,用1台小直径掘进机从隧道低端洞口1的上导坑2位置,向隧道高端洞口3掘进,至6km处的上导坑位置转向沿斜井4掘出,实现特长隧道快速施工,见图1,斜井长度1500m以内,坡度16°为例,说明如下:
(1)根据特长隧道及其斜井位置的工程地质、水文地条件、斜井在施工中和在隧道营运中的功能要求、特长隧道的建设工期等,确定选用掘进机直径、功能及主参数后,即可进行该长隧道上导坑、斜井的施工组织设计,培训人员,组织实施。
(2)掘进机施工上导坑以800m/月速度向前方6km处掘进,同时开挖隧道低端上半断面作业面5、6和隧道低端下半断面作业面7,转向以450m/月速度上坡掘进斜井出洞,同时开挖斜井工区隧道上半断面扩挖面8、9和斜井工区隧道全断面扩挖面10,然后完成隧道高端全断或半断面11的作业,总历时约11个月形成斜井“高烟囱”自吸式通风条件。
(3)完善斜井供电、提升设备、轨道安装、大能力皮带运输机安装(带宽1400mm,能力1200t/h)、安装块石破碎站(600t/h或350t/h)、建斜井井底车场等,为多工作面钻爆法施工提供大能力排碴、进料条件。
(4)该隧道至少用4个工作面以150m/月速度,在第25个月内可完成隧道上半面扩挖、支护。
(5)再用23个月即总历时48个月,可完成10km隧道的施工任务。

Claims (4)

1.一种用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法,其特征在于:用一台小直径掘进机从隧道低端洞口上导坑位置,向隧道高端洞口掘进,至4-8km处的上导坑位置转向沿斜井掘出,实现特长隧道快速施工,同时形成斜井“高烟囱”自吸式通风。
2.根据权利要求1所述的用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法,其特征在于:上述斜井长度≤1500m,坡度16°。
3.根据权利要求1所述的用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法,其特征在于:上述小直径掘进机的直径小于隧道的建筑限界及衬砌内轮廓,即隧限直径。
4.根据权利要求1所述的用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法,其特征在于:上述小直径掘进机掘进隧道的斜井和上导坑的具体方法是:采用双线合修的单洞形式,设置一座斜井,用一台小直径掘进机从隧道低端洞口上导坑位置,向隧道高端洞口掘进,至6km处的上导坑位置转向沿斜井掘出,实现特长隧道快速施工;同时,利用斜井井口与隧道底高差及洞内、外温度差的“高烟囱”效应,利用通风机和软管将新风从隧道低端洞口吸入,并送到掘进机工作面,形成巷道式节能通风。
CN2012102500281A 2012-07-19 2012-07-19 用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法 Pending CN102787844A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012102500281A CN102787844A (zh) 2012-07-19 2012-07-19 用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012102500281A CN102787844A (zh) 2012-07-19 2012-07-19 用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法

Publications (1)

Publication Number Publication Date
CN102787844A true CN102787844A (zh) 2012-11-21

Family

ID=47153405

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012102500281A Pending CN102787844A (zh) 2012-07-19 2012-07-19 用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法

Country Status (1)

Country Link
CN (1) CN102787844A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110107310A (zh) * 2019-05-05 2019-08-09 中交第三航务工程局有限公司 一种隧道斜井洞口的施工方法
CN110159271A (zh) * 2019-05-22 2019-08-23 中国电建集团西北勘测设计研究院有限公司 基于小型tbm掘进机的拱形地勘平洞掘进方法
CN110173266A (zh) * 2019-05-22 2019-08-27 中国电建集团西北勘测设计研究院有限公司 基于微型tbm掘进机的对称轮形地勘平洞掘进方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101220746A (zh) * 2008-02-01 2008-07-16 中铁十三局集团有限公司 20km双线双洞特长隧道施工中采用TBM导洞扩挖法
JP2009013603A (ja) * 2007-07-02 2009-01-22 Shimizu Corp トンネル構築方法
CN202170803U (zh) * 2011-08-01 2012-03-21 湖南省交通规划勘察设计院 特长、深埋公路隧道平导通风运营系统

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009013603A (ja) * 2007-07-02 2009-01-22 Shimizu Corp トンネル構築方法
CN101220746A (zh) * 2008-02-01 2008-07-16 中铁十三局集团有限公司 20km双线双洞特长隧道施工中采用TBM导洞扩挖法
CN202170803U (zh) * 2011-08-01 2012-03-21 湖南省交通规划勘察设计院 特长、深埋公路隧道平导通风运营系统

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
殷怀连等: "小直径TBM导洞扩挖法在双线铁路隧道中的应用", 《铁道标准设计》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110107310A (zh) * 2019-05-05 2019-08-09 中交第三航务工程局有限公司 一种隧道斜井洞口的施工方法
CN110159271A (zh) * 2019-05-22 2019-08-23 中国电建集团西北勘测设计研究院有限公司 基于小型tbm掘进机的拱形地勘平洞掘进方法
CN110173266A (zh) * 2019-05-22 2019-08-27 中国电建集团西北勘测设计研究院有限公司 基于微型tbm掘进机的对称轮形地勘平洞掘进方法
CN110159271B (zh) * 2019-05-22 2020-09-29 中国电建集团西北勘测设计研究院有限公司 基于小型tbm掘进机的拱形地勘平洞掘进方法

Similar Documents

Publication Publication Date Title
CN102392650B (zh) 一种隧道非爆开挖施工方法
CN104695971B (zh) 一种环形顶管施工方法
CN109026019A (zh) 水磨钻非爆破石方洞挖施工的方法
CN109736827B (zh) 城市地铁硬岩地层联络通道高压气体膨胀致裂开挖的方法
CN104712339A (zh) 一种环形顶管机
CN104564085B (zh) 城市超浅埋条件下超大断面隧道开挖综合施工方法
CN102787844A (zh) 用小直径掘进机掘进特长隧道上导坑和斜井的隧道修建法
CN105649633A (zh) 一种定向钻孔劈岩成硐法
CN205135632U (zh) 近距离煤层群的下分层结构
CN110566271A (zh) 一种用于市政道路下伏富水采空区的加固施工方法
CN102787845A (zh) 特长隧道采用掘进机先施工斜井和导坑的分段修建方法
Moriya Special shield tunnelling methods in Japan
CN112727484A (zh) 一种先盾构后顶管上下平行叠交隧道构造及其施工方法
CN104500071A (zh) 煤层开采避开动压影响的沿空留巷方法
WO2021003771A1 (zh) 无煤柱留设无巷道掘进矿井设计方法
CN110836118A (zh) 一种在高地应力高地质危害下快速安全的隧洞施工的设备及方法
CN106089216A (zh) 岩石隧道破岩施工方法
CN106089210A (zh) 一种环保型矿山洞采方法
CN114233293B (zh) 煤矿无区段煤柱开采及固废充填方法
CN204457773U (zh) 一种用于开采石料的装置
CN207761645U (zh) 盾构管廊系统
CN102966353A (zh) 厚煤层桥拱式三下压煤全采方法
CN112901175A (zh) 一种应用tbm施工地下实验室螺旋向下斜坡道的方法
CN219316959U (zh) 一种基于tbm技术的抽水蓄能电站地下厂房开挖结构
CN1247285A (zh) 不开挖地表的地下管线安装工程施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20121121