CN102759713A - Battery energy efficiency testing device and testing method thereof - Google Patents
Battery energy efficiency testing device and testing method thereof Download PDFInfo
- Publication number
- CN102759713A CN102759713A CN2011101107708A CN201110110770A CN102759713A CN 102759713 A CN102759713 A CN 102759713A CN 2011101107708 A CN2011101107708 A CN 2011101107708A CN 201110110770 A CN201110110770 A CN 201110110770A CN 102759713 A CN102759713 A CN 102759713A
- Authority
- CN
- China
- Prior art keywords
- battery
- energy
- discharge
- edn
- time
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000012360 testing method Methods 0.000 title claims abstract description 21
- 238000000034 method Methods 0.000 claims abstract description 45
- 238000005259 measurement Methods 0.000 claims abstract description 13
- 238000007599 discharging Methods 0.000 claims abstract description 5
- 238000010998 test method Methods 0.000 claims description 19
- 238000009434 installation Methods 0.000 claims 1
- 238000004146 energy storage Methods 0.000 abstract 1
- 230000005611 electricity Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 240000004859 Gamochaeta purpurea Species 0.000 description 1
- 238000003556 assay Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000010287 polarization Effects 0.000 description 1
- 238000012797 qualification Methods 0.000 description 1
Images
Landscapes
- Secondary Cells (AREA)
Abstract
The invention provides a battery energy efficiency testing device and a testing method thereof. The testing method comprises the steps of charging and discharging a battery by using a constant current, determining the charging energy and the discharging energy of the battery under a state of charge (SOC) value and calculating the energy efficiency of the battery. Compared with the prior art, the testing method has the advantages that the measurement of an open-circuit voltage of the battery is neglected, and electric vehicles and energy storage power stations can be tested during running processes.
Description
Technical field
The present invention relates to a kind of energy content of battery efficiency test device and method of testing thereof.
Background technology
Electric battery is the key components of energy-accumulating power station and electric automobile, how rationally to use battery, and the energy efficiency that improves battery is the problem that energy-accumulating power station and electric automobile further develop the necessary solution of institute.
Battery is when carrying out the mensuration of energy efficiency; Need carry out discharging and recharging of big electric current, traditional energy content of battery assay method adopts the open-circuit voltage determination method, and the method need be measured the open-circuit voltage of battery; But need leaving standstill just for a long time, battery can obtain open-circuit voltage; Energy-accumulating power station and electric automobile can't leave standstill in the operational process of being everlasting for a long time, so this method can not satisfy actual request for utilization.
Summary of the invention
In operational process, can't obtain open-circuit voltage to present electric automobile and energy-accumulating power station; And then can't detect the situation of energy content of battery efficient, the present invention provide a kind of can be in electric automobile and energy-accumulating power station operational process the device and the method for testing thereof of test battery energy efficiency.
A kind of energy content of battery efficiency test device; Comprise constant flow module, acquisition module and control module; Said constant flow module and acquisition module are electrically connected with battery respectively; Said control module is electrically connected with acquisition module and constant flow module respectively; Said constant flow module is used for battery being discharged and recharged with constant electric current according to the order control of control module; Said acquisition module is used for measuring battery in the real-time voltage value and the current SOC value of charge and discharge process and send to said control module, and the real-time voltage value that said control module is used for sending according to acquisition module is calculated the energy efficiency η under rechargeable energy Ecn, discharge energy Edn and the current SOC value of charge and discharge process
n, wherein,
Further; Said constant flow module is used in time T n, battery being discharged and recharged with constant electric current I according to the order of control module; Said control module is used for real-time voltage Ucn and the Udn according to charge and discharge process; Utilize formula
to calculate rechargeable energy, utilize formula
to calculate discharge energy.
A kind of energy content of battery efficiency test method, said energy content of battery efficiency test method comprises:
Steps A, under initial SOC value, in time T n, battery is carried out charge or discharge with steady current I;
Step B, the current SOC value of mensuration;
Rechargeable energy Ecn in step C, the described charging process of determination step A or the discharge energy Edn in the discharge process;
Step D, battery is discharged in identical time T n with steady current I again or charge;
Discharge energy Edn in step e, the described discharge process of determination step D or the rechargeable energy Ecn in the charging process;
Step F, the energy efficiency η that utilizes formula 1 counting cell under current SOC value, to discharge and recharge
n:
Further, the method for said mensuration battery charge energy E cn comprises:
Step a, the real-time voltage Ucn of measurement battery in charging process;
Step b, utilize formula 2 to calculate rechargeable energy Ecn:
Further, the method for said mensuration battery discharging energy Edn comprises:
Step (1), the real-time voltage Udn of measurement battery in discharge process;
Step (2), utilize formula 3 to calculate discharge energy Edn:
Further, said test is to carry out under 13 ℃ of-38 ℃ of environment in temperature.
Further; Said SOC value discharges and recharges battery with electric weight Q1 in the 0%-30% interval, and wherein Q1=5% * nominal capacity discharges and recharges battery with electric weight Q2 in the 30%-70% interval; Q2=40% * nominal capacity wherein; Discharge and recharge with electric weight Q3 in the 70%-100% interval, wherein, Q3=5% * nominal capacity.
Further, the said time T 1=Qc1/I that battery is discharged and recharged with electric weight Q1, the time T 2=Qc2/I that battery is discharged and recharged with electric weight Q2, the time T 3=Qc3/I that battery is discharged and recharged with electric weight Q3.
Further, said energy content of battery efficiency test method also comprises step G: with the SOC value is horizontal ordinate, and the energy efficiency value is the corresponding relation curve that ordinate is set up SOC and energy efficiency.
The present invention discharges and recharges battery with steady current; Detect rechargeable energy and discharge energy in the charge and discharge process; The energy efficiency of counting cell has been saved the measurement to battery open circuit voltage, in the process of electric motor car and energy-accumulating power station operation, also can test energy content of battery efficient.
Description of drawings
Accompanying drawing 1 is the synoptic diagram of energy content of battery efficiency test device of the present invention.
Accompanying drawing 2 is process flow diagrams of energy content of battery efficiency test method of the present invention.
Accompanying drawing 3 is the SOC of a kind of embodiment of providing of energy content of battery efficiency test method of the present invention and the corresponding relation curve map of energy efficiency.
Embodiment
Clearer for technical matters, technical scheme and beneficial effect that the present invention is solved, below in conjunction with accompanying drawing and embodiment, the present invention is further elaborated.Should be appreciated that specific embodiment described herein only in order to explanation the present invention, and be not used in qualification the present invention.
Shown in accompanying drawing 1; The present invention provides a kind of energy content of battery efficiency test device; Comprise constant flow module 1, acquisition module 2 and control module 3; Said constant flow module 1 is electrically connected with battery respectively with acquisition module 2; Said control module 3 is electrically connected with acquisition module 2 and constant flow module 1 respectively,, said constant flow module 1 is used for battery being discharged and recharged with constant electric current according to the order control of control module 3; Said acquisition module 2 is used for measuring battery in the real-time voltage value and the current SOC value of charge and discharge process and send to said control module 3, and said control module 3 is used for calculating the energy efficiency η under rechargeable energy Ecn, discharge energy Edn and the current SOC value of charge and discharge process according to the real-time voltage value that acquisition module 2 sends
n, wherein,
Constant flow module 1 is used in time T n, battery being discharged and recharged with constant electric current I according to the order of control module 3; Said control module 3 is used for real-time voltage Ucn and the Udn according to charge and discharge process; Utilize formula
to calculate rechargeable energy, utilize formula
to calculate discharge energy.
The constant flow module 1 main constant-current circuit control steady current that adopts, the acquisition module 2 main voltage collection circuits that adopt are realized the collection to real-time voltage, control module is mainly through the single-chip microcomputer energy efficiency.
Shown in accompanying drawing 2, the present invention also provides a kind of energy content of battery efficiency test method, and said energy content of battery efficiency test method comprises:
Steps A, under initial SOC value, in time T n, battery is carried out charge or discharge with steady current I;
Step B, the current SOC value of mensuration;
Rechargeable energy Ecn in step C, the described charging process of determination step A or the discharge energy Edn in the discharge process;
Step D, battery is discharged in identical time T n with steady current I again or charge;
Discharge energy Edn in step e, the described discharge process of determination step D or the rechargeable energy Ecn in the charging process;
Step F, the energy efficiency η that utilizes formula 1 counting cell under current SOC value, to discharge and recharge
n:
Among a kind of embodiment provided by the invention, with constant electric current I battery is discharged and recharged, the value of electric current I was confirmed by the whole charging and discharging process of the nominal capacity of battery and setting required time that finishes; The nominal capacity of battery is the capacity of battery, nominal capacity (Ah)=electric current (A) * time (h), and this is as well known to those skilled in the art; For example, nominal capacity is the battery of 50Ah, is set in to discharge and recharge in 1 hour to finish; Then charging and discharging currents is 50A, and promptly constant electric current I is 50A.
At SOC is that 0%-30% is interval; Q1 charges to battery with electric weight; Q1=5% * nominal capacity wherein; Duration of charging T1=Qc1/I, the polarization resistance of battery changes not quite in this scope, and the electric weight of the nominal capacity of employing 5% charges to battery and can make the energy error that tests out less.Serves as that zero battery charges with steady current I to initial SOC value; Every warp is T1 after a while; The SOC value of battery just increases by 5%; Measure each 5% interval interior rechargeable energy Ecn, reach 30% up to battery SOC, the method that is determined at SOC rechargeable energy Ecn (n=1,2,3,4,5,6) in each 5% interval comprises:
Step a, measurement battery real-time voltage Ucn (n=1,2,3,4,5,6) in charging process;
Step b, utilize formula 2 to calculate charge capacity Ecn:
In SOC was the 30%-70% interval, Qc2 charged to battery with electric weight, wherein Q2=40% * nominal capacity; Duration of charging T2=Qc2/I; Elapsed time T2, battery SOC are 30% to increase to 70% by initial value, and the method for measuring the rechargeable energy Ec7 of battery in this SOC interval comprises:
Step a, measurement battery real-time voltage Uc7 in charging process;
Step b, utilize formula 3 to calculate charge capacity Ec7:
At SOC is that 70%-100% is interval, and Q3 charges to battery with electric weight, wherein Q3=5% * nominal capacity; Duration of charging T3=Qc3/I; Every warp is T3 after a while, and the SOC value of battery just increases by 5%, measures each 5% interval interior rechargeable energy Ecn; Reach 100% up to battery SOC, the method that is determined at SOC rechargeable energy Ecn (n=8,9,10,11,12,13) in each 5% interval comprises:
Step a, measurement battery real-time voltage Ucn (n=8,9,10,11,12,13) in charging process;
Step b, utilize formula 4 to calculate charge capacity Ecn:
Charging is discharged to battery with constant electric current I after accomplishing again; At battery electric quantity is that 70%-100% is interval, and Q3 discharges to battery with electric weight, and be T3 discharge time; To decide electric current I be that 100% battery discharges to initial SOC value with constant; Every warp is T3 after a while, and the SOC value of battery just descends 5%, measures each 5% interval interior discharge energy Edn; Reach 70% up to battery SOC, the method that is determined at SOC discharge energy Edn (n=13,12,11,10,9,8) in each 5% interval comprises:
Step a, measurement battery real-time voltage Udn (n=13,12,11,10,9,8) in discharge process;
Step b, utilize formula 5 to calculate charge capacity Edn:
At SOC is that 30%-70% is interval, and Q2 discharges to battery with electric weight, and be T2 discharge time, and elapsed time T2, battery SOC are 70% to drop to 30% by initial value, and the method for measuring battery discharge energy Ed7 in this SOC interval comprises:
Step a, measurement battery real-time voltage Ud7 in discharge process;
Step b, utilize formula 6 to calculate charge capacity Ed7:
At SOC is that 0%-30% is interval; Q1 discharges to battery with electric weight, and be T1 discharge time, and every warp is T1 after a while; The SOC value of battery just descends 5%; Measure each 5% interval interior discharge energy Edn, reach 0% up to battery SOC, the method that is determined at SOC discharge energy Edn (n=6,5,4,3,2,1) in each 5% interval comprises:
Step a, measurement battery real-time voltage Udn (n=6,5,4,3,2,1) in discharge process;
Step b, utilize formula 7 to calculate charge capacity Edn:
Calculate battery at the interval charge-discharge energy of each SOC, the energy content of battery efficient of utilizing formula 1 to calculate under the current SOC value:
The interval value of battery SOC is 0-30% in the present embodiment, 30%-70%, 70%-100%; Charge/discharge electricity amount is made as 5% nominal capacity and 40% nominal capacity, just as a preferred version, in actual test process, can select other interval value; Also can set charge/discharge electricity amount according to actual needs, for example, can select 0%-20%; 20%-80%; 80%-100% is interval, and charge/discharge electricity amount discharges and recharges at 0%-20% and the interval electric weight of 2% * nominal capacity that adopts of 80%-100%, discharges and recharges at the interval electric weight of 30% * nominal capacity that adopts of 20%-80%.
The energy content of battery method of testing that present embodiment is described is to carry out under 13 ℃ of-38 ℃ of environment in temperature.
Shown in accompanying drawing 3, set up SOC-energy efficiency plane coordinate system, with SOC horizontal ordinate, energy efficiency is an ordinate, with the energy content of battery efficiency eta that tests out
n(n=1,2,3 ... 13) point under the SOC of correspondence value, be painted into this planimetric coordinates and fasten; With level and smooth curve point is coupled together again; Promptly obtain SOC-energy efficiency corresponding relation curve; Can draw the situation of change of battery according to this curve, better understand battery performance in each SOC value corresponding energy efficient and the interval self-energy efficient of each SOC.
Through above embodiment; With steady current battery is discharged and recharged, calculate rechargeable energy and discharge energy, draw the energy efficiency of battery; Saved measurement, in the process of electric motor car and energy-accumulating power station operation, also can test energy content of battery efficient to battery open circuit voltage.
The above is merely preferred embodiment of the present invention, not in order to restriction the present invention, all any modifications of within spirit of the present invention and principle, being done, is equal to and replaces and improvement etc., all should be included within protection scope of the present invention.
Claims (9)
1. energy content of battery efficiency test device; Comprise constant flow module, acquisition module and control module; Said constant flow module and acquisition module are electrically connected with battery respectively; Said control module is electrically connected with acquisition module and constant flow module respectively; It is characterized in that; Said constant flow module is used for battery being discharged and recharged with constant electric current according to the order of control module control, and said acquisition module is used for measuring battery in the real-time voltage value and the current SOC value of charge and discharge process and send to said control module, the energy efficiency η under rechargeable energy Ecn, discharge energy Edn and the current SOC value of the real-time voltage value calculating charge and discharge process that said control module is used for sending according to acquisition module
n, wherein,
2. energy content of battery proving installation according to claim 1; It is characterized in that; Said constant flow module is used in time T n, battery being discharged and recharged with constant electric current I according to the order of control module; Said control module is used for real-time voltage Ucn and the Udn according to charge and discharge process; Utilize formula
to calculate rechargeable energy, utilize formula
to calculate discharge energy.
3. an energy content of battery efficiency test method is characterized in that, said energy content of battery efficiency test method comprises:
Steps A, under initial SOC value, in time T n, battery is carried out charge or discharge with steady current I;
Step B, the current SOC value of mensuration;
Rechargeable energy Ecn in step C, the described charging process of determination step A or the discharge energy Edn in the discharge process;
Step D, battery is discharged in identical time T n with steady current I again or charge;
Discharge energy Edn in step e, the described discharge process of determination step D or the rechargeable energy Ecn in the charging process;
Step F, the energy efficiency η that utilizes formula 1 counting cell under current SOC value, to discharge and recharge
n:
4. energy content of battery efficiency test method according to claim 3 is characterized in that, the method for said mensuration battery charge energy E cn comprises:
Step a, the real-time voltage Ucn of measurement battery in charging process;
Step b, utilize formula 2 to calculate rechargeable energy Ecn:
5. energy content of battery efficiency test method according to claim 3 is characterized in that, the method for said mensuration battery discharging energy Edn comprises:
Step (1), the real-time voltage Udn of measurement battery in discharge process;
Step (2), utilize formula 3 to calculate discharge energy Edn:
6. energy content of battery efficiency test method according to claim 3 is characterized in that, said test is to carry out under 13 ℃ of-38 ℃ of environment in temperature.
7. energy content of battery efficiency test method according to claim 3 is characterized in that said SOC value discharges and recharges battery with electric weight Q1 in the 0%-30% interval; Q1=5% * nominal capacity wherein; Battery is discharged and recharged with electric weight Q2 in the 30%-70% interval, wherein Q2=40% * nominal capacity discharges and recharges with electric weight Q3 in the 70%-100% interval; Wherein, Q3=5% * nominal capacity.
8. energy content of battery efficiency test method according to claim 7; It is characterized in that; The said time T 1=Qc1/I that battery is discharged and recharged with electric weight Q1, the time T 2=Qc2/I that battery is discharged and recharged with electric weight Q2, the time T 3=Qc3/I that battery is discharged and recharged with electric weight Q3.
9. energy content of battery efficiency test method according to claim 2 is characterized in that, said energy content of battery efficiency test method also comprises step G: with the SOC value is horizontal ordinate, and the energy efficiency value is the corresponding relation curve that ordinate is set up SOC and energy efficiency.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110110770.8A CN102759713B (en) | 2011-04-29 | 2011-04-29 | A kind of energy content of battery efficiency test device and method of testing thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110110770.8A CN102759713B (en) | 2011-04-29 | 2011-04-29 | A kind of energy content of battery efficiency test device and method of testing thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102759713A true CN102759713A (en) | 2012-10-31 |
CN102759713B CN102759713B (en) | 2015-08-26 |
Family
ID=47054224
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201110110770.8A Active CN102759713B (en) | 2011-04-29 | 2011-04-29 | A kind of energy content of battery efficiency test device and method of testing thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102759713B (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103884989A (en) * | 2012-12-20 | 2014-06-25 | 北汽福田汽车股份有限公司 | Coulombic-efficiency detection method used for SOC estimation of power cell |
CN103941190A (en) * | 2014-02-26 | 2014-07-23 | 陕西科技大学 | Storage battery energy efficiency testing device |
CN104569847A (en) * | 2015-01-28 | 2015-04-29 | 国网冀北电力有限公司电力科学研究院 | Lithium battery performance evaluation method and device |
CN105244559A (en) * | 2015-11-12 | 2016-01-13 | 中国检验检疫科学研究院 | Comprehensive performance detection method for lithium ion battery temperature |
CN105324676A (en) * | 2013-02-21 | 2016-02-10 | 雷诺两合公司 | Detection device and biological-sample analysis device |
CN105676131A (en) * | 2015-12-31 | 2016-06-15 | 王金全 | Vanadium cell dynamic state of charge (SOC<d>)estimation method based on charging/discharging energy efficiency |
CN105866692A (en) * | 2016-03-30 | 2016-08-17 | 上海中科深江电动车辆有限公司 | Battery energy efficiency test device and test method |
CN107290678A (en) * | 2017-07-03 | 2017-10-24 | 北京理工大学 | A kind of electrokinetic cell health status on-line monitoring method |
CN107741566A (en) * | 2017-09-21 | 2018-02-27 | 晶晨半导体(上海)股份有限公司 | A kind of battery detection method |
CN111912772A (en) * | 2020-07-08 | 2020-11-10 | 肇庆理士电源技术有限公司 | Test method for thermoelectric electrochemical performance of plate anode based on new material PPTC |
CN112213649A (en) * | 2019-10-31 | 2021-01-12 | 蜂巢能源科技有限公司 | Method and system for constructing open-circuit voltage curve |
WO2024103213A1 (en) * | 2022-11-14 | 2024-05-23 | 宁德时代新能源科技股份有限公司 | Energy efficiency monitoring method and apparatus, and computer device and storage medium |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6289430A (en) * | 1985-08-23 | 1987-04-23 | ジヤツク アビバン | Charge controller of battery |
JPH07236203A (en) * | 1994-02-23 | 1995-09-05 | Mitsubishi Electric Corp | Controller for electric automobile |
JPH08275403A (en) * | 1995-03-31 | 1996-10-18 | Kansai Electric Power Co Inc:The | Charging equipment for battery |
CN101308196A (en) * | 2008-06-13 | 2008-11-19 | 中国科学院电工研究所 | Measurement circuit for current integration |
CN201229395Y (en) * | 2008-06-25 | 2009-04-29 | 河北工业大学 | Lithium ion battery set residual electric energy computation device |
-
2011
- 2011-04-29 CN CN201110110770.8A patent/CN102759713B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6289430A (en) * | 1985-08-23 | 1987-04-23 | ジヤツク アビバン | Charge controller of battery |
JPH07236203A (en) * | 1994-02-23 | 1995-09-05 | Mitsubishi Electric Corp | Controller for electric automobile |
JPH08275403A (en) * | 1995-03-31 | 1996-10-18 | Kansai Electric Power Co Inc:The | Charging equipment for battery |
CN101308196A (en) * | 2008-06-13 | 2008-11-19 | 中国科学院电工研究所 | Measurement circuit for current integration |
CN201229395Y (en) * | 2008-06-25 | 2009-04-29 | 河北工业大学 | Lithium ion battery set residual electric energy computation device |
Non-Patent Citations (1)
Title |
---|
胡建军等: "混合动力电动汽车MH/Ni电池放电性能实验分析", 《重庆大学学报(自然科学版)》, vol. 30, no. 10, 31 October 2007 (2007-10-31) * |
Cited By (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103884989B (en) * | 2012-12-20 | 2016-12-28 | 北汽福田汽车股份有限公司 | A kind of coulombic efficiency detection method for electrokinetic cell SOC estimation |
CN103884989A (en) * | 2012-12-20 | 2014-06-25 | 北汽福田汽车股份有限公司 | Coulombic-efficiency detection method used for SOC estimation of power cell |
CN105324676A (en) * | 2013-02-21 | 2016-02-10 | 雷诺两合公司 | Detection device and biological-sample analysis device |
CN105324676B (en) * | 2013-02-21 | 2018-03-30 | 雷诺两合公司 | To the assessment for the energy that can be extracted from motor vehicle battery |
CN103941190A (en) * | 2014-02-26 | 2014-07-23 | 陕西科技大学 | Storage battery energy efficiency testing device |
CN104569847A (en) * | 2015-01-28 | 2015-04-29 | 国网冀北电力有限公司电力科学研究院 | Lithium battery performance evaluation method and device |
CN105244559B (en) * | 2015-11-12 | 2019-12-10 | 中国检验检疫科学研究院 | Method for detecting comprehensive temperature performance of lithium ion battery |
CN105244559A (en) * | 2015-11-12 | 2016-01-13 | 中国检验检疫科学研究院 | Comprehensive performance detection method for lithium ion battery temperature |
CN105676131A (en) * | 2015-12-31 | 2016-06-15 | 王金全 | Vanadium cell dynamic state of charge (SOC<d>)estimation method based on charging/discharging energy efficiency |
CN105676131B (en) * | 2015-12-31 | 2019-03-29 | 王金全 | A kind of vanadium cell dynamic battery charge state estimation method based on charge-discharge energy efficiency |
CN105866692A (en) * | 2016-03-30 | 2016-08-17 | 上海中科深江电动车辆有限公司 | Battery energy efficiency test device and test method |
CN107290678A (en) * | 2017-07-03 | 2017-10-24 | 北京理工大学 | A kind of electrokinetic cell health status on-line monitoring method |
CN107290678B (en) * | 2017-07-03 | 2019-12-10 | 北京理工大学 | A method for online monitoring of power battery health status |
CN107741566A (en) * | 2017-09-21 | 2018-02-27 | 晶晨半导体(上海)股份有限公司 | A kind of battery detection method |
CN112213649A (en) * | 2019-10-31 | 2021-01-12 | 蜂巢能源科技有限公司 | Method and system for constructing open-circuit voltage curve |
CN112213649B (en) * | 2019-10-31 | 2023-05-23 | 蜂巢能源科技有限公司 | Method and system for constructing open-circuit voltage curve |
CN111912772A (en) * | 2020-07-08 | 2020-11-10 | 肇庆理士电源技术有限公司 | Test method for thermoelectric electrochemical performance of plate anode based on new material PPTC |
CN111912772B (en) * | 2020-07-08 | 2023-06-20 | 肇庆理士电源技术有限公司 | Method for testing thermoelectric electrochemical performance of anode plate based on novel material PPTC |
WO2024103213A1 (en) * | 2022-11-14 | 2024-05-23 | 宁德时代新能源科技股份有限公司 | Energy efficiency monitoring method and apparatus, and computer device and storage medium |
Also Published As
Publication number | Publication date |
---|---|
CN102759713B (en) | 2015-08-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102759713A (en) | Battery energy efficiency testing device and testing method thereof | |
CN102121973B (en) | Method for testing net energy of electrical vehicle power battery | |
CN102756661B (en) | Determination method and device for state of charge of vehicular battery | |
CN102355031B (en) | Active equalizing charging method and device for LiFePO4 power battery packs | |
CN101468610B (en) | Battery charge controller for mixed power vehicle and method thereof | |
CN104977537B (en) | The determination method of battery SOC and the battery management system for using this method | |
CN102608540A (en) | Coulomb efficiency measuring method used for SOC (system-on-chip) evaluation of power battery | |
CN102854470A (en) | Measurement method for estimating actual available capacity by SOC (state of charge) of power battery set | |
CN111886752A (en) | Battery control device, battery control method, uninterruptible power supply device, power system, and electric vehicle | |
CN104166102B (en) | Judgment method for SOC use interval of automotive power battery pack | |
CN102124360A (en) | Storage battery device, battery state evaluation device and method for storage battery | |
CN103995232B (en) | A kind of detection method of lithium iron phosphate dynamic battery group peak value charge-discharge performance | |
CN101860056A (en) | Power lithium battery pack balancing and managing system based on Map model | |
CN104101838A (en) | Power cell system, and charge state and maximum charging and discharging power estimation methods thereof | |
CN101783518A (en) | Battery manager and application method thereof | |
CN105738815A (en) | Method for detecting state of health of lithium ion battery online | |
CN102445663A (en) | A method for estimating the state of health of an electric vehicle battery | |
CN103797683A (en) | Secondary battery charging device, method of charging in secondary battery charging device, photovoltaic generator, method of power generation in photovoltaic generator, photovoltaic-charged secondary battery system, electronic device, and electrical vehicle | |
CN103675698A (en) | Power battery charge state estimating device and method | |
CN102169002A (en) | Method for measuring fuel consumption and discharge of hybrid electromobile | |
CN102520367A (en) | Method for evaluating life of space hydrogen-nickel storage batteries | |
CN102331560A (en) | A method for estimating state of charge of Ni-MH battery | |
CN104485474A (en) | Electric vehicle battery pack matching method based on coincidence indicator | |
CN102540081A (en) | Method for determining charge state of vehicle-mounted storage battery | |
CN105607011A (en) | Method and device for estimating state of health (SOH) of battery |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |