CN102758458B - 地下连续墙修复方法 - Google Patents

地下连续墙修复方法 Download PDF

Info

Publication number
CN102758458B
CN102758458B CN201210269023.3A CN201210269023A CN102758458B CN 102758458 B CN102758458 B CN 102758458B CN 201210269023 A CN201210269023 A CN 201210269023A CN 102758458 B CN102758458 B CN 102758458B
Authority
CN
China
Prior art keywords
wall
construction
excavation
diaphragm wall
wall body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210269023.3A
Other languages
English (en)
Other versions
CN102758458A (zh
Inventor
黄德中
李林
刘宝文
何国军
徐辰春
周隽
李鸿
袁风波
于晓东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Tunnel Engineering Co Ltd
Original Assignee
Shanghai Tunnel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Tunnel Engineering Co Ltd filed Critical Shanghai Tunnel Engineering Co Ltd
Priority to CN201210269023.3A priority Critical patent/CN102758458B/zh
Publication of CN102758458A publication Critical patent/CN102758458A/zh
Application granted granted Critical
Publication of CN102758458B publication Critical patent/CN102758458B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

本发明的地下连续墙修复方法,包括如下步骤,制定方案,灌注桩施工,MJS加固,桩顶圈梁设计成U型与地下连续墙顶圈梁共同浇筑施工,两端支撑在墙顶圈梁上,基坑开挖,内部结构施工。

Description

地下连续墙修复方法
技术领域
本发明涉及一种工程修复方法,特别地,涉及一种地下连续墙修复方法。
背景技术
因各种因素(包括地质条件、施工条件和机械设备、工艺流程等)导致有些地下连续墙的墙身混凝土缺损,对工程造成两方面的不利影响:1、墙身强度和止水性能不能满足设计要求而严重威胁到基坑安全和稳定。2、地下连续墙在施工阶段作为支护结构,在正常使用阶段地下连续墙又作为结构外墙使用,承受永久水平和竖向荷载,称为“两墙合一”,墙身缺损直接影响工程质量和安全。现有的外贴新地下连续墙的施工工艺造价高,工期长,需要实施更为实用经济的地下连续墙修复方法。
发明内容
本发明的主要目的是提供一种地下连续墙修复方法,通过坑外钻孔灌注桩补强、MJS工法桩加强止水,在基坑封底后再结合内衬墙施工完成地下连续墙的墙身修复。
地下连续墙修复方法,包括如下步骤:
制定方案,通过掌握地下连续墙墙身缺损范围来制定方案;
灌注桩施工,须覆盖墙身缺损范围的迎土面;
MJS加固,MJS工法桩须覆盖墙身缺损范围,充填灌注桩桩间及桩墙间土体。
桩顶圈梁施工,圈梁两端支撑在地下连续墙墙顶圈梁上;
基坑开挖施工,基坑开挖应在钻孔灌注桩桩身强度达到70%以上方可进行。土方分层开挖应以设计支撑结构底面为界进行划分,每层土体开挖前,先对缺损地墙附近范围内的土体进行试探性开挖,对暴露出来的缺损墙身进行人工掏挖或者风镐凿除,沿地墙内侧线立模板浇筑微膨胀混凝土,完成墙身局部修复,待达到墙身设计强度后继续下层土方开挖,循环进行直至坑底;支撑地下连续墙的钢筋混凝土围檩施工时需预留其下内衬墙的浇捣孔和振捣孔,预留孔位置应在本层内衬墙浇筑范围外,在圈梁中斜向深入下一道内衬墙浇筑范围。
内部结构施工,混凝土底板浇筑完成后可进行内部结构施工。内衬墙施工应以混凝土围檩中心线为界,首先应完全清除中心线以下缺损地下连续墙混凝土,然后绑扎内衬墙钢筋,并完成混凝土浇筑。之后,按照相同步骤施工围檩中心线上部结构。
较佳地,基坑开挖前须布设灌注桩水平和竖向位移、地表沉降、坑外地下水位的监测点,加强在基坑开挖和墙身修复过程中的监测。
较佳地,基坑开挖中,以1m深度为单位分层,逐层放坡开挖,人工掏挖或者风镐凿除的深度为墙身厚度的40%但不超过40cm,凿除过程中不得损伤地下连续墙主筋。
较佳地,基坑开挖前须布设灌注桩水平和竖向位移、地表沉降、坑外地下水位的监测点,加强在基坑开挖和墙身修复过程中的监测。
较佳地,MJS工法桩施工过程中须严格控制地内压力,加强地下连续墙水平位移监测。
较佳地,可增加桩顶圈梁与其墙顶圈梁间的横撑,地下连续墙圈梁若提前完成,须在新老混凝土接头处凿毛植筋。
较佳地,通过钻芯取样掌握地下连续墙墙身缺损范围。
本发明的有益效果是:相对于外贴新地下连续墙的施工工艺而言,具有造价低、施工难度小、工期快等特点。
附图说明
图1是本发明地下连续墙修复方法的具体步骤流程图。
图2是本发明地下连续墙灌注桩和MJS工法桩平面示意图。
图3是本发明地下连续墙灌注桩和MJS工法桩立面示意图。
具体实施方式
以下参照附图详细描述本发明的技术方案。
如图1所示,地下连续墙墙身缺损修复技术的实施步骤主要包括制定方案、灌注桩施工、MJS加固、基坑开挖、内部结构施工,下面分步进行详细说明。
如图2所示,10为完整的地下连续墙,11为存在缺损的地下连续墙。制定方案步骤为通过钻芯取样掌握地下连续墙墙身缺损范围,来制定施工方案。
接下来进行灌注桩施工:经设计验算满足强度、刚度要求后实施钻孔灌注桩20,钻孔灌注桩20须覆盖墙身缺损范围11的迎土面,钻孔灌注桩20须达到70%强度以上方可进行基坑开挖。
如图2,3所示,40为MJS工法桩。加固步骤中,须覆盖墙身缺损范围11,加固对象为灌注桩20桩间及其与地下连续墙10间隙土体。MJS工法桩40施工过程中须严格控制地内压力,加强地下连续墙水平位移监测。桩顶圈梁30与地下连续墙顶圈梁共同浇筑施工,两端支撑在墙顶圈梁上,实现桩的共同受力,并将水平力向墙顶圈梁支撑体系扩散。如桩顶圈梁的长度过大可适当增加其与墙顶圈梁间的横撑。如地下连续墙圈梁已提前完成,须在新老混凝土接头处凿毛植筋,确保连接质量和强度。
基坑开挖步骤中,基坑开挖前应布设灌注桩水平和竖向位移、地表沉降、坑外地下水位的监测点,加强在基坑开挖和墙身修复过程中的监测。土方分层开挖以设计支撑结构底面为界进行划分,每层土体开挖宜再细分2-3个步骤进行。每层土体开挖前,先对墙身缺损地墙附近范围内的土体进行试探性开挖,以1m深度为单位分层,逐层放坡开挖。对暴露出来的缺损墙身进行人工掏挖或者风镐凿除。深度不应超过墙身厚度的40%且不超过40cm。凿除过程中不得损伤地下连续墙主筋。沿地墙内侧线立模板浇筑微膨胀混凝土,完成墙身局部修复。然后可以施工本层钢筋混凝土围檩及支撑体系51。支撑地下连续墙的钢筋混凝土围檩施工时需预留其下内衬墙的浇捣孔和振捣孔,预留孔位置应在本层内衬墙浇筑范围外,在圈梁中斜深入下一道内衬墙浇筑范围。
内部结构施工,混凝土底板浇筑完成后可进行内部结构施工。内衬墙施工应以混凝土围檩中心线为界,首先应完全清除中心线以下缺损地下连续墙混凝土,然后绑扎内衬墙钢筋,并完成混凝土浇筑。之后,按照相同步骤施工围檩中心线上部结构。内部结构施工过程中应确保混凝土围檩有足够的支撑点。墙身修复施工流程是:凿除开挖过程中浇筑的墙身混凝土→人工掏挖地下连续墙(至满足设计强度的混凝土面或者暴露地下连续墙迎土面主筋)→内衬墙钢筋绑扎→内衬墙立模→浇筑混凝土→养护。
虽然本发明的地下连续墙修复方法已参照当前的具体实例进行了描述,但是本技术领域的技术人员应该认识到,以上的实例仅是用来说明本发明,在没有脱离本发明精神的情况下还可做出各种等效的变化和修改都将落在本发明的权利要求书的范围内。

Claims (5)

1.地下连续墙修复方法,其特征在于,包括如下步骤:
制定方案,通过掌握地下连续墙墙身缺损范围来制定方案;
灌注桩施工,须覆盖墙身缺损范围的迎土面;桩顶圈梁两端应支撑在墙顶圈梁上;
MJS加固,MJS工法桩须覆盖墙身缺损范围;
基坑开挖,土方分层开挖以设计支撑结构底面为界进行划分,每层土体开挖前,先对墙身缺损地墙附近范围内的土体进行试探性开挖,对暴露出来的问题墙身进行人工掏挖或者风镐凿除,沿地墙内侧线立模板浇筑,微膨胀混凝土,完成墙身局部修复,待达到墙身设计强度后继续下层土方开挖,循环进行直至坑底;支撑地下连续墙的钢筋混凝土围檩施工时需预留其下内衬墙的浇捣孔和振捣孔,预留孔位置应在本层内衬墙浇筑范围外,在圈梁中斜深入下一道内衬墙浇筑范围;
内部结构施工,混凝土底板浇筑完成后进行内部结构施工;内衬墙施工应以混凝土围檩中心线为界,首先应完全清除中心线以下缺损地下连续墙混凝土,然后绑扎内衬墙钢筋,并完成混凝土浇筑;之后,按照相同步骤施工围檩中心线上部结构。
2.如权利要求1所述的地下连续墙修复方法,其特征在于,基坑开挖中,以1m深度为单位分层,逐层放坡开挖,人工掏挖或者风镐凿除的深度为墙身厚度的40%但不超过40cm,凿除过程中不得损伤地下连续墙主筋。
3.如权利要求1所述的地下连续墙修复方法,其特征在于,MJS工法桩施工过程中须严格控制地内压力,加强地下连续墙水平位移监测。
4.如权利要求1所述的地下连续墙修复方法,其特征在于,可增加桩顶圈梁与其墙顶圈梁间的横撑,地下连续墙圈梁若提前完成,须在新老混凝土接头处凿毛植筋。
5.如权利要求1所述的地下连续墙修复方法,其特征在于,内衬墙施工应以混凝土围檩中心线为界分段施工,确保混凝土围檩在地墙修复过程中有足够的支撑点。
CN201210269023.3A 2012-07-30 2012-07-30 地下连续墙修复方法 Active CN102758458B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210269023.3A CN102758458B (zh) 2012-07-30 2012-07-30 地下连续墙修复方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210269023.3A CN102758458B (zh) 2012-07-30 2012-07-30 地下连续墙修复方法

Publications (2)

Publication Number Publication Date
CN102758458A CN102758458A (zh) 2012-10-31
CN102758458B true CN102758458B (zh) 2014-10-01

Family

ID=47053091

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210269023.3A Active CN102758458B (zh) 2012-07-30 2012-07-30 地下连续墙修复方法

Country Status (1)

Country Link
CN (1) CN102758458B (zh)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103161178B (zh) * 2013-03-26 2016-12-28 中国葛洲坝集团基础工程有限公司 一种防渗墙成槽循环钻进施工方法
CN104674862B (zh) * 2015-01-28 2016-07-13 中铁十六局集团北京轨道交通工程建设有限公司 一种液压抓斗卡斗后地下连续墙修复方法
CN105274979A (zh) * 2015-10-12 2016-01-27 上海市基础工程集团有限公司 在既有结构上开孔对下部土体进行地基处理的施工方法
CN109137929A (zh) * 2018-08-29 2019-01-04 中铁上海工程局集团有限公司 一种混凝土环形支撑与围护桩之间连接的施工方法
CN110847155A (zh) * 2019-11-22 2020-02-28 中铁开发投资集团有限公司 一种地下连续墙施工过程中的接缝防水预处理方法
CN114293559A (zh) * 2021-12-23 2022-04-08 上海市机械施工集团有限公司 一种水平mjs施工方法
CN114837240A (zh) * 2022-05-10 2022-08-02 中交一公局集团有限公司 后钻孔桩提高单室闭合地下连续墙基础承载力的结构及方法
CN115341554A (zh) * 2022-08-30 2022-11-15 中建八局第三建设有限公司 一种富水粉砂地层下缺陷地连墙封堵及补强保护施工方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201424658Y (zh) * 2008-11-17 2010-03-17 天津三建建筑工程有限公司 地下连续墙槽段接缝处渗漏水检测及封堵修复装置
CN101429764B (zh) * 2008-11-17 2010-08-11 天津三建建筑工程有限公司 地下连续墙槽段接缝处渗漏水检测及封堵修复装置及其方法
CN102535518A (zh) * 2012-01-13 2012-07-04 同济大学 一种地下连续墙大接缝的封堵方法

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2004288174B2 (en) * 2003-10-28 2007-08-16 Warren Environmental & Coating, Llc Method for preparing in-ground tunnel structures

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201424658Y (zh) * 2008-11-17 2010-03-17 天津三建建筑工程有限公司 地下连续墙槽段接缝处渗漏水检测及封堵修复装置
CN101429764B (zh) * 2008-11-17 2010-08-11 天津三建建筑工程有限公司 地下连续墙槽段接缝处渗漏水检测及封堵修复装置及其方法
CN102535518A (zh) * 2012-01-13 2012-07-04 同济大学 一种地下连续墙大接缝的封堵方法

Also Published As

Publication number Publication date
CN102758458A (zh) 2012-10-31

Similar Documents

Publication Publication Date Title
CN102758458B (zh) 地下连续墙修复方法
CN107762535B (zh) 复杂地质环境下隧道明洞暗做施工工艺
CN108868778B (zh) 一种大型地下结构非开挖修建方法
CN111411993A (zh) 穿越巨型溶洞大厅的大断面隧道支护体系及施工方法
CN110093928A (zh) 一种基坑支护结构及土方开挖施工方法
CN204491626U (zh) 拉森钢板桩与预应力锚杆组合的基坑围护结构
CN102434717B (zh) 工字钢顶管工作坑的施工方法
CN106930321B (zh) 一种大直径顶管结合洞桩修建地下结构的施工方法
CN104264688A (zh) 人工挖孔变截面桩支护施工工艺
CN102505704A (zh) 软弱地质竖井中大型沉井施工方法
CN108842819A (zh) 一种城市轨道交通电缆线路隧道施工方法
CN104294769B (zh) 一种补桩与增大台帽组合加固已建桥台结构的施工方法
CN112575670B (zh) 一种适用于隧道穿越巨型溶洞的t形刚构桥及其施工技术
CN103696784A (zh) 一种浅埋大跨隧道下穿建构筑物的大直径长管幕施工方法
CN109630127A (zh) 一种富水软弱地层超深盾构竖井的施工方法
CN211340827U (zh) 地铁隧道穿越既有桥桩新建桥梁的构造
CN109610470A (zh) 一种采用三轴搅拌桩机的基坑支护施工方法
CN206070508U (zh) 一种加固地基基础的装置
CN108867692A (zh) 城市大断面明挖隧道临近建筑物保护及隧道基坑挖掘方法
CN211500658U (zh) 一种适用于砂土地基的浅埋近接隧道支护结构
CN107740446A (zh) 既有建筑物基础被动补充与洞内托换系统的联合施工方法
CN110306559A (zh) 一种地铁出入口支护桩的施工方法
CN110565686A (zh) 管廊下穿河道的施工方法
CN204097889U (zh) 一种补桩与增大台帽组合加固已建桥台结构
CN105735383A (zh) 一种保留结构体系的局部地下清障施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHANGHAI TUNNEL ENGINEERING CO., LTD.

Free format text: FORMER OWNER: SHANGHAI TUNNEL ENGINEERING CO LTD

Effective date: 20150119

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 200082 TO: 200232

TR01 Transfer of patent right

Effective date of registration: 20150119

Address after: 200232 Shanghai Wanping Road No. 1099

Patentee after: SHANGHAI TUNNEL ENGINEERING CO., LTD.

Address before: 200082 No. 118, Dalian Road, Shanghai, Yangpu District

Patentee before: Shanghai Tunnel Engineering Co., Ltd.