CN102750751A - 工矿企业铁路道口值班室交接班控制系统及控制方法 - Google Patents

工矿企业铁路道口值班室交接班控制系统及控制方法 Download PDF

Info

Publication number
CN102750751A
CN102750751A CN201210233943XA CN201210233943A CN102750751A CN 102750751 A CN102750751 A CN 102750751A CN 201210233943X A CN201210233943X A CN 201210233943XA CN 201210233943 A CN201210233943 A CN 201210233943A CN 102750751 A CN102750751 A CN 102750751A
Authority
CN
China
Prior art keywords
succeeding
person
next shift
bit digital
background server
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201210233943XA
Other languages
English (en)
Other versions
CN102750751B (zh
Inventor
金保柱
蒋秋林
李进才
李佳状
吴志刚
牛德雄
朱文胜
郑军平
李雅琴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Iron and Steel Co Ltd
Original Assignee
Wuhan Iron and Steel Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Iron and Steel Group Corp filed Critical Wuhan Iron and Steel Group Corp
Priority to CN201210233943.XA priority Critical patent/CN102750751B/zh
Publication of CN102750751A publication Critical patent/CN102750751A/zh
Application granted granted Critical
Publication of CN102750751B publication Critical patent/CN102750751B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Time Recorders, Dirve Recorders, Access Control (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明涉及工矿企业铁路道口值班室交接班控制系统及控制方法,控制系统包括前端控制台、通讯网络和后台服务器,所述前端控制台包括指纹传感器、信息处理器和显示器,所述指纹传感器的信号输出端与信息处理器的信号输入端连接,所述信息处理器的信号输出端与显示器的信号输入端连接,所述前端控制台与后台服务器之间通过通讯网络连接。采用本发明,只有当值的道口值班人员才能完成交接班,进而操纵道口栏杆,后台调度人员能实时掌控道口状态,从而保证道口安全。

Description

工矿企业铁路道口值班室交接班控制系统及控制方法
技术领域
本发明涉及交接班控制系统及控制方法,特别是工矿企业铁路道口值班室交接班控制系统及控制方法。
背景技术
工矿企业铁路道口的控制对于安全生产至关重要,而道口值班室的交接班则是其中的首要环节。目前,工矿企业铁路道口值班室的交接班通常采用人工方式,即接班人员在规定时间内到达值班室会同交班人员在交接班簿上签字完成交接班。此方式最大的问题在于,一些道口、特别是处于偏远地区的道口往往发生待交班人在接班人尚未到达时便独自签字后将道口栏杆放下先行离开而导致值班室无人的现象,在此空挡其他人员可以任意操作道口栏杆,道口处于危险状态而后方调度人员却毫不知情,极易酿成事故。因此,设计出一种能规范道口员工的交接班行为并且有利于后台调度人员实时掌控道口状态以保证道口安全的工矿企业铁路道口值班室交接班控制系统及控制方法十分必要。
发明内容
本发明的目的是提供一种能规范道口员工的交接班行为并且有利于后台调度人员实时掌控道口状态以保证道口安全的工矿企业铁路道口值班室交接班控制系统及控制方法。
为实现上述目的,本发明提供了一种工矿企业铁路道口值班室交接班控制系统,其特征在于,包括前端控制台、通讯网络和后台服务器,
所述前端控制台包括指纹传感器、信息处理器和显示器,所述指纹传感器的信号输出端与信息处理器的信号输入端连接,所述信息处理器的信号输出端与显示器的信号输入端连接;
所述前端控制台与后台服务器之间通过通讯网络连接。
本发明还提供了一种工矿企业铁路道口值班室交接班控制方法,其特征在于,是采用权利要求1所述的一种工矿企业铁路道口值班室交接班控制系统进行的,包括以下步骤:
S1.交班者按下交班按钮;
S2.交班者刷入指纹;
S3.前端控制台根据人员设备认证表、值班表、请假审批表和接班密钥申请表判断交班者身份,若交班者身份无误,系统通知接班者刷指纹,接班者在30秒之内刷入指纹;
S4.前端控制台根据人员设备认证表、值班表、请假审批表和接班密钥申请表判断接班者身份,若接班者身份无误,完成交接班;
S5.系统生成三位数字动态密钥,并在显示器上显示10秒钟;
S6.系统填写考勤表和密钥数据表,并回传后台服务器;
S31.若在所述步骤S3中交班者身份不符,系统通知后台服务器;
S32.后台服务器生成接班密钥申请表;
S33.系统比对信息,确认后生成接班三位数字动态密钥,并在显示器上显示30秒钟;
S34.交班者按下交班按钮;
S35.交班者输入上次接班时的三位数字动态密钥;
S36.接班者在30之秒内输入接班三位数字动态密钥,完成交接班,进入所述步骤S5;
S41.若在所述步骤S4中接班者身份不符,系统通知后台服务器;
S42.后台服务器生成接班密钥申请表;
S43.系统比对信息,确认后生成接班三位数字动态密钥,并在显示器上显示30秒钟;
S44.交班者按下交班按钮;
S45.交班者输入上次接班时的三位数字动态密钥;
S46.接班者在30之秒内输入接班三位数字动态密钥,完成交接班,进入所述步骤S5。
进一步地,若在所述步骤S43中系统比对信息不符,返回所述步骤S41。
进一步地,若在所述步骤S46中接班者未在30之秒内输入接班三位数字动态密钥,返回所述步骤S44。
采用本发明,只有当值的道口值班人员才能完成交接班,进而操纵道口栏杆,后台调度人员能实时掌控道口状态,从而保证道口安全。
附图说明
图1为本发明的控制系统结构示意图;
图2为本发明的控制方法流程图。
图中:1—指纹传感器;2—信息处理器;3—显示器;4—通讯网络;5—后台服务器。
具体实施方式
以下结合附图和具体实施例对本发明作进一步的详细描述,但该实施例不应理解为对本发明的限制。
一种工矿企业铁路道口值班室交接班控制系统,包括前端控制台、通讯网络和后台服务器,
所述前端控制台包括指纹传感器、信息处理器和显示器,所述指纹传感器的信号输出端与信息处理器的信号输入端连接,所述信息处理器的信号输出端与显示器的信号输入端连接;
所述前端控制台与后台服务器之间通过通讯网络连接。
采用上述工矿企业铁路道口值班室交接班控制系统,通过以下方法控制工矿企业铁路道口值班室的交接班,其步骤包括:
S1.交班者按下交班按钮;
S2.交班者刷入指纹;
S3.前端控制台根据人员设备认证表、值班表、请假审批表和接班密钥申请表判断交班者身份,若交班者身份无误,系统通知接班者刷指纹,接班者在30秒之内刷入指纹;
S4.前端控制台根据人员设备认证表、值班表、请假审批表和接班密钥申请表判断接班者身份,若接班者身份无误,完成交接班;
S5.系统生成三位数字动态密钥,并在显示器上显示10秒钟;
S6.系统填写考勤表和密钥数据表,并回传后台服务器;
S31.若在所述步骤S3中交班者身份不符,系统通知后台服务器;
S32.后台服务器生成接班密钥申请表;
S33.系统比对信息,确认后生成接班三位数字动态密钥,并在显示器上显示30秒钟;
S34.交班者按下交班按钮;
S35.交班者输入上次接班时的三位数字动态密钥;
S36.接班者在30之秒内输入接班三位数字动态密钥,完成交接班,进入所述步骤S5;
S41.若在所述步骤S4中接班者身份不符,系统通知后台服务器;
S42.后台服务器生成接班密钥申请表;
S43.系统比对信息,确认后生成接班三位数字动态密钥,并在显示器上显示30秒钟;
S44.交班者按下交班按钮;
S45.交班者输入上次接班时的三位数字动态密钥;
S46.接班者在30之秒内输入接班三位数字动态密钥,完成交接班,进入所述步骤S5。
优选的实施例是,在上述方案中,若在所述步骤S43中系统比对信息不符,返回所述步骤S41。
优选的实施例是,在上述方案中,若在所述步骤S46中接班者未在30之秒内输入接班三位数字动态密钥,返回所述步骤S44。
本说明书中未作详细描述的内容,属于本专业技术人员公知的现有技术。

Claims (4)

1.一种工矿企业铁路道口值班室交接班控制系统,其特征在于,包括前端控制台、通讯网络和后台服务器,
所述前端控制台包括指纹传感器、信息处理器和显示器,所述指纹传感器的信号输出端与信息处理器的信号输入端连接,所述信息处理器的信号输出端与显示器的信号输入端连接;
所述前端控制台与后台服务器之间通过通讯网络连接。
2.一种工矿企业铁路道口值班室交接班控制方法,其特征在于,是采用权利要求1所述的一种工矿企业铁路道口值班室交接班控制系统进行的,包括以下步骤:
S1.交班者按下交班按钮;
S2.交班者刷入指纹;
S3.前端控制台根据人员设备认证表、值班表、请假审批表和接班密钥申请表判断交班者身份,若交班者身份无误,系统通知接班者刷指纹,接班者在30秒之内刷入指纹;
S4.前端控制台根据人员设备认证表、值班表、请假审批表和接班密钥申请表判断接班者身份,若接班者身份无误,完成交接班;
S5.系统生成三位数字动态密钥,并在显示器上显示10秒钟;
S6.系统填写考勤表和密钥数据表,并回传后台服务器;
S31.若在所述步骤S3中交班者身份不符,系统通知后台服务器;
S32.后台服务器生成接班密钥申请表;
S33.系统比对信息,确认后生成接班三位数字动态密钥,并在显示器上显示30秒钟;
S34.交班者按下交班按钮;
S35.交班者输入上次接班时的三位数字动态密钥;
S36.接班者在30之秒内输入接班三位数字动态密钥,完成交接班,进入所述步骤S5;
S41.若在所述步骤S4中接班者身份不符,系统通知后台服务器;
S42.后台服务器生成接班密钥申请表;
S43.系统比对信息,确认后生成接班三位数字动态密钥,并在显示器上显示30秒钟;
S44.交班者按下交班按钮;
S45.交班者输入上次接班时的三位数字动态密钥;
S46.接班者在30之秒内输入接班三位数字动态密钥,完成交接班,进入所述步骤S5。
3.根据权利要求2所述的工矿企业铁路道口值班室交接班控制方法,其特征在于:若在所述步骤S43中系统比对信息不符,返回所述步骤S41。
4.根据权利要求2或3所述的工矿企业铁路道口值班室交接班控制方法,其特征在于:若在所述步骤S46中接班者未在30之秒内输入接班三位数字动态密钥,返回所述步骤S44。
CN201210233943.XA 2012-07-06 2012-07-06 工矿企业铁路道口值班室交接班控制方法 Expired - Fee Related CN102750751B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210233943.XA CN102750751B (zh) 2012-07-06 2012-07-06 工矿企业铁路道口值班室交接班控制方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210233943.XA CN102750751B (zh) 2012-07-06 2012-07-06 工矿企业铁路道口值班室交接班控制方法

Publications (2)

Publication Number Publication Date
CN102750751A true CN102750751A (zh) 2012-10-24
CN102750751B CN102750751B (zh) 2015-02-25

Family

ID=47030899

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210233943.XA Expired - Fee Related CN102750751B (zh) 2012-07-06 2012-07-06 工矿企业铁路道口值班室交接班控制方法

Country Status (1)

Country Link
CN (1) CN102750751B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107730195A (zh) * 2016-10-28 2018-02-23 西安艾润物联网技术服务有限责任公司 停车场的交接班方法及装置
CN108665577A (zh) * 2018-03-19 2018-10-16 西安艾润物联网技术服务有限责任公司 一种基于人脸识别的交接班方法、存储介质、装置及系统
CN109544107A (zh) * 2018-11-13 2019-03-29 上海互海信息科技有限公司 一种船员交接系统及其方法
CN111612932A (zh) * 2020-05-21 2020-09-01 浩云科技股份有限公司 一种信息监管中异常信息的监测方法及装置

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201111139Y (zh) * 2007-12-06 2008-09-03 天津五洲国际集装箱码头有限公司 集装箱码头生产资源配置优化系统
CN201156264Y (zh) * 2007-12-29 2008-11-26 彭铁明 Gps指纹巡检仪
CN101833704A (zh) * 2010-03-30 2010-09-15 上海强控设备工程有限公司 企业油料监控管理系统
CN102543233A (zh) * 2011-12-13 2012-07-04 中广核工程有限公司 一种核电站数字化运行规程交接班平稳切换的方法及系统

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201111139Y (zh) * 2007-12-06 2008-09-03 天津五洲国际集装箱码头有限公司 集装箱码头生产资源配置优化系统
CN201156264Y (zh) * 2007-12-29 2008-11-26 彭铁明 Gps指纹巡检仪
CN101833704A (zh) * 2010-03-30 2010-09-15 上海强控设备工程有限公司 企业油料监控管理系统
CN102543233A (zh) * 2011-12-13 2012-07-04 中广核工程有限公司 一种核电站数字化运行规程交接班平稳切换的方法及系统

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107730195A (zh) * 2016-10-28 2018-02-23 西安艾润物联网技术服务有限责任公司 停车场的交接班方法及装置
CN108665577A (zh) * 2018-03-19 2018-10-16 西安艾润物联网技术服务有限责任公司 一种基于人脸识别的交接班方法、存储介质、装置及系统
CN109544107A (zh) * 2018-11-13 2019-03-29 上海互海信息科技有限公司 一种船员交接系统及其方法
CN109544107B (zh) * 2018-11-13 2022-12-13 上海互海信息科技有限公司 一种船员交接系统及其方法
CN111612932A (zh) * 2020-05-21 2020-09-01 浩云科技股份有限公司 一种信息监管中异常信息的监测方法及装置

Also Published As

Publication number Publication date
CN102750751B (zh) 2015-02-25

Similar Documents

Publication Publication Date Title
Paraskevas et al. Crisis knowledge in tourism: Types, flows and governance
CN204778091U (zh) 一种智能电梯控制系统
CN104609270A (zh) 一种智能电梯控制系统及方法
CN102750751B (zh) 工矿企业铁路道口值班室交接班控制方法
Medhi et al. Combating rural child malnutrition through inexpensive mobile phones
CN204833337U (zh) 一种基于企业私网认证下的云模式无纸化会议管理系统
CN103020810A (zh) 一种日程计划共享系统及方法
CN103905637A (zh) 显示备忘事件的方法及装置
CN104573921A (zh) 基于群组的企业移动办公系统任务分配方法
CN104346839A (zh) 一种基于局域网的员工电子考勤系统
CN104112377A (zh) 一种列车调度仿真培训系统及培训方法
Horton et al. Rolling back from the power/interest matrix: a new approach for role based stakeholder engagement in projects
CN102821374B (zh) 一种基于网络电视对手机闹钟进行调整的方法及系统
CN104079973A (zh) 基于电视机实景网络逛街交互方法及其系统
CN108197888A (zh) 一种建筑行业征信招聘方法
Gurung Nepal health sector decentralization in limbo: what are the bottlenecks
CN103973814A (zh) 远程翻译及其计费系统
CN113705825A (zh) 适用于多方使用的数据模型共享方法
Vavoula et al. School Visits Post-lockdown II: The Role of Digital. A Follow-on Survey Report
Lundie et al. Wales
Broeckhoven Biodiversity loss and climate change: Gender issues in international law and policy
Höhenberger et al. The prevalence of IoT in the facility services industry
CN106302736A (zh) 一种基于互联网的学校管理系统
CN108616879A (zh) 一种基于手机移动端的安全双向操作方法
Chu Building the Urban Community Disaster Relief System in China

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20170714

Address after: 430083, Hubei Wuhan Qingshan District Factory No. 2 Gate joint stock company organs

Patentee after: Wuhan iron and Steel Company Limited

Address before: 430080 Wuchang, Hubei Friendship Road, No. A, block, floor 999, 15

Patentee before: Wuhan Iron & Steel (Group) Corp.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150225

Termination date: 20190706

CF01 Termination of patent right due to non-payment of annual fee