CN102744784A - 重载铁路预制t梁整体绑扎胎具及其施工方法 - Google Patents

重载铁路预制t梁整体绑扎胎具及其施工方法 Download PDF

Info

Publication number
CN102744784A
CN102744784A CN2012102425562A CN201210242556A CN102744784A CN 102744784 A CN102744784 A CN 102744784A CN 2012102425562 A CN2012102425562 A CN 2012102425562A CN 201210242556 A CN201210242556 A CN 201210242556A CN 102744784 A CN102744784 A CN 102744784A
Authority
CN
China
Prior art keywords
moulding bed
backform
bed
welded
overall binding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012102425562A
Other languages
English (en)
Other versions
CN102744784B (zh
Inventor
李照中
俞剑
赵造来
孙东瑞
侯占武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningyang Beam Manufacturing of China Railway 16th Bureau Group Railway Transportation Engineering Co Ltd
Original Assignee
Ningyang Beam Manufacturing of China Railway 16th Bureau Group Railway Transportation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningyang Beam Manufacturing of China Railway 16th Bureau Group Railway Transportation Engineering Co Ltd filed Critical Ningyang Beam Manufacturing of China Railway 16th Bureau Group Railway Transportation Engineering Co Ltd
Priority to CN201210242556.2A priority Critical patent/CN102744784B/zh
Publication of CN102744784A publication Critical patent/CN102744784A/zh
Application granted granted Critical
Publication of CN102744784B publication Critical patent/CN102744784B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明涉及重载铁路预制T梁整体绑扎胎具及其施工方法,包括内胎架和外胎架,所述的内胎架包括底模、腹模和顶模,所述的底模与焊混凝土底台的预埋件焊接连接,所述的顶模与外胎架的顶部焊接在一起。本发明由于采用内胎架和外胎架焊接连接,具有节约占地面积、节约龙门吊的使用,提高工效的效果,本发明在吊装时由于采用整体吊具,能够保证钢筋骨架在吊装时整体变形和局部变形达到最小,保证了整体钢筋骨架的稳定性。

Description

重载铁路预制T梁整体绑扎胎具及其施工方法
一、     技术领域
本发明涉及一种绑扎胎具,具体为重载铁路预制T梁整体绑扎胎具及其施工方法。
二、背景技术
目前,在重载铁路梁场预制T梁中,钢筋绑扎大多采用底板和腹板钢筋与顶板钢筋分开绑扎,待分别吊入模板内再连接成整体,其缺点是:增加了钢筋绑扎工序在预制台座上的占用时间,又很难满足施工规范对梁体钢筋结构的整体性和定位准确性的要求。
三、     发明内容
为了解决以上缺陷,本发明提供一种能够既能够满足骨架结构的整体性和定位控制的准确性,又能提高钢筋骨架绑扎的效率,且整体骨架不易变形的铁路预制T梁整体绑扎胎具。
本发明采取的技术方案是:铁路预制T梁整体绑扎胎具,包括内胎架和外胎架,其特征在于:所述的内胎架包括底模、腹模和顶模,所述的底模与焊混凝土底台的预埋件焊接连接,所述的顶模与外胎架的顶部焊接在一起。
本发明所述的内胎架上间距开半圆形的槽口,使钢筋能够快速、准确定位。
本发明所述的内胎架和外胎架均为钢管结构,所述的外胎架的钢管臂内胎架的钢管大一个规格。
本发明重载铁路预制T梁整体绑扎胎具的施工方法,包括如下步骤:
一、安装混凝土底台,在混凝土底台上利用角钢设置预埋件,将内胎架的底模与预埋件焊接连接,然后依次安装腹模和顶模,构成内胎架;
二、将外胎架固定在混凝土底台的上方,将外胎架的顶部与顶模焊接连接;
三、进行绑扎制作钢筋笼,完成后,整体吊具钢丝绳从钢筋笼中垂直穿过,钢筋笼底部用钢筋平托,与钢丝绳套牢,将整个钢筋骨架吊起。
本发明还包括在步骤一中,安装混凝土底台,在混凝土底台上利用角钢设置预埋件,按照T梁模板图纸在底模、腹模和顶模上依次割半圆形槽口,将内胎架的底模与预埋件焊接连接,然后依次安装腹模和顶模,构成内胎架。
本发明在步骤一中,安装完腹模和顶模后,将底模、腹模和顶模连接成一个整体,然后将底模与预埋件焊接连接。
本发明的有益效果是:1、本发明采用整体绑扎胎具后,钢筋笼一次绑扎成型,一次吊装到位,即可合模,既能够保证钢筋骨架结构的整体性,又能节约钢筋绑扎工序的时间,且操作方便、快捷。
2、本发明由于采用内胎架和外胎架焊接连接,具有节约占地面积、节约龙门吊的使用,提高工效的效果。
3、本发明在吊装时利用整体吊具钢丝绳从钢筋笼中垂直穿过,钢筋笼底部用钢筋平托,与钢丝绳套牢,将整个钢筋骨架吊起,保证了整体钢筋骨架的稳定性。
四、附图说明
图1为本发明铁路预制T梁整体绑扎胎具整体结构示意图。
五、具体实施方式
重载铁路预制T梁整体绑扎胎具,包括内胎架1和外胎架2,所述的内胎架1包括底模3、腹模4和顶模5,所述的底模3与混凝土底台7的预埋件焊接连接,所述的顶模5与外胎架2的顶部焊接在一起。
本发明所述的内胎架2上间距开半圆形的槽口6。
本发明所述的内胎架1和外胎架2均为钢管结构,所述的外胎架2的钢管比内胎架1的钢管大一个规格。
本发明包括如下步骤:
一、安装混凝土底台7,在混凝土底台7上利用角钢设置预埋件,将内胎架的底模3与预埋件焊接连接,然后依次安装腹模4和顶模5,构成内胎架1;
二、将外胎架2固定在混凝土底台7的上方,将外胎架2的顶部与顶模5焊接连接;
三、进行绑扎制作钢筋笼,完成后,整体吊具钢丝绳从钢筋笼中垂直穿过,钢筋笼底部用钢筋平托,与钢丝绳套牢,将整个钢筋骨架吊起。
本发明还包括在步骤一中,安装混凝土底台7,在混凝土底台7上利用角钢设置预埋件,按照T梁模板图纸在底模3、腹模4和顶模5上依次割半圆形槽口6,将内胎架1的底模3与预埋件焊接连接,然后依次安装腹模4和顶模5,构成内胎架1。
本发明在步骤一中,安装完腹模4和顶模5后,将底模3、腹模4和顶模5连接成一个整体,然后将底模3与预埋件焊接连接。
本发明顶模5上利用型钢焊有起吊扁担,起吊系统采用长短拉索配合的钢丝绳结构,每根拉索下端部做成环扣,钢筋起吊前,在底模3和腹模4的空隙中穿入预应力橡胶棒,利用长、短拉索固定住顶模5,将整个钢筋骨架吊起。
实施例:本发明整体绑扎胎具高于底面10cm,通过预埋件将内胎架1和底面连接为一体,直接在地面上进行操作,本发明所述的外胎架2由对称设置的防护栏组成,所述的护栏为高度可调,所述的内胎架1为左右对称布置,安装时,严格按照半圆形槽口6的位置进行精确定位,本发明半圆形槽口6位置处固定L55×5mm的角钢,预埋件处利用L80×10mm的角钢进行固定。

Claims (6)

1.重载铁路预制T梁整体绑扎胎具,包括内胎架(1)和外胎架(2),所述的内胎架(1)包括底模(3)、腹模(4)和顶模(5),其特征在于:所述的底模(3)与混凝土底台(7)的预埋件焊接连接,所述的顶模(5)与外胎架(2)的顶部焊接在一起。
2.根据权利要求1所述的重载铁路预制T梁整体绑扎胎具,其特征在于:所述的内胎架(2)上间距开半圆形的槽口(6)。
3.根据权利要求1或2所述的重载铁路预制T梁整体绑扎胎具,其特征在于:所述的内胎架(1)和外胎架(2)均为钢管结构,所述的外胎架(2)的钢管比内胎架(1)的钢管大一个规格。
4.重载铁路预制T梁整体绑扎胎具的施工方法,其特征在于:包括如下步骤:
一、安装混凝土底台(7),在混凝土底台(7)上利用角钢设置预埋件,将内胎架的底模(3)与预埋件焊接连接,然后依次安装腹模(4)和顶模(5),构成内胎架(1);
二、将外胎架(2)固定在混凝土底台(7)的上方,将外胎架(2)的顶部与顶模(5)焊接连接;
三、进行绑扎制作钢筋笼,完成后,整体吊具钢丝绳从钢筋笼中垂直穿过,钢筋笼底部用钢筋平托,与钢丝绳套牢,将整个钢筋骨架吊起。
5.根据权利要求4所述的重载铁路预制T梁整体绑扎胎具的施工方法,其特征在于:还包括在步骤一中,安装混凝土底台(7),在混凝土底台(7)上利用角钢设置预埋件,按照T梁模板图纸在底模(3)、腹模(4)和顶模(5)上依次割半圆形槽口(6),将内胎架(1)的底模(3)与预埋件焊接连接,然后依次安装腹模(4)和顶模(5),构成内胎架(1)。
6.根据权利要求4或5所述的重载铁路预制T梁整体绑扎胎具的施工方法,其特征在于:在步骤一中,安装完腹模(4)和顶模(5)后,将底模(3)、腹模(4)和顶模(5)连接成一个整体,然后将底模(3)与预埋件焊接连接。
CN201210242556.2A 2012-07-13 2012-07-13 重载铁路预制t梁整体绑扎胎具及其施工方法 Active CN102744784B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210242556.2A CN102744784B (zh) 2012-07-13 2012-07-13 重载铁路预制t梁整体绑扎胎具及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210242556.2A CN102744784B (zh) 2012-07-13 2012-07-13 重载铁路预制t梁整体绑扎胎具及其施工方法

Publications (2)

Publication Number Publication Date
CN102744784A true CN102744784A (zh) 2012-10-24
CN102744784B CN102744784B (zh) 2014-08-06

Family

ID=47025453

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210242556.2A Active CN102744784B (zh) 2012-07-13 2012-07-13 重载铁路预制t梁整体绑扎胎具及其施工方法

Country Status (1)

Country Link
CN (1) CN102744784B (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106042173A (zh) * 2016-06-02 2016-10-26 中铁十六局集团铁运工程有限公司 桥梁生产系统
CN110405938A (zh) * 2019-07-30 2019-11-05 云南省建设投资控股集团有限公司 预制t梁腹板钢筋绑扎辅助胎架施工工法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101492907A (zh) * 2008-12-08 2009-07-29 中铁十五局集团有限公司 一种t型桥梁翼缘板现浇施工工法
CN201433342Y (zh) * 2009-07-01 2010-03-31 中铁十三局集团第三工程有限公司 一种t梁底腹板钢筋绑扎胎具

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101492907A (zh) * 2008-12-08 2009-07-29 中铁十五局集团有限公司 一种t型桥梁翼缘板现浇施工工法
CN201433342Y (zh) * 2009-07-01 2010-03-31 中铁十三局集团第三工程有限公司 一种t梁底腹板钢筋绑扎胎具

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106042173A (zh) * 2016-06-02 2016-10-26 中铁十六局集团铁运工程有限公司 桥梁生产系统
CN106042173B (zh) * 2016-06-02 2018-08-31 中铁十六局集团铁运工程有限公司 桥梁生产系统
CN110405938A (zh) * 2019-07-30 2019-11-05 云南省建设投资控股集团有限公司 预制t梁腹板钢筋绑扎辅助胎架施工工法
CN110405938B (zh) * 2019-07-30 2021-03-23 云南省建设投资控股集团有限公司 预制t梁腹板钢筋绑扎辅助胎架施工工法

Also Published As

Publication number Publication date
CN102744784B (zh) 2014-08-06

Similar Documents

Publication Publication Date Title
CN103088844A (zh) 钢筋混凝土检查井整体预制吊装施工方法
CN102900024B (zh) 大型混凝土结构翻升模板的使用方法
CN102080384B (zh) 地下车库顶板上安装升降机施工方法
CN108867384B (zh) 基于整体式吊模现浇混凝土墙式防撞护栏的施工方法
CN101659082A (zh) 箱梁钢筋骨架整体绑扎、整体吊装系统及其施工方法
CN103243649B (zh) 一种索鞍快速安装、定位的系统及方法
CN204384698U (zh) 板坯连铸机设备安装吊具
CN105220619A (zh) 一种快速制造双线圆端实体墩的方法
CN102744784B (zh) 重载铁路预制t梁整体绑扎胎具及其施工方法
CN201786010U (zh) 一种施工用升降平台
CN203795311U (zh) 多肢高墩同滑施工装置
CN202164030U (zh) 整体式箱梁吊架
CN201511439U (zh) 箱梁钢筋骨架整体绑扎、整体吊装系统
CN105951683A (zh) 闸墩牛腿钢筋施工方法
CN202967862U (zh) 一种槽形梁钢筋骨架吊具
CN204057696U (zh) 一种门式起重机门架
CN102777036A (zh) 一种超长竖向钢筋笼空中反向机械连接施工方法
CN103321405A (zh) 剪力墙、筒体混凝土结构大模板提升式施工方法
CN207760728U (zh) 一种便于预制t梁或箱梁纵向湿接缝模板安拆的装置
CN202718385U (zh) 顶升模板机构
CN116101892A (zh) 一种立式预制箱涵起吊翻转系统及其施工方法
CN202878484U (zh) 重载铁路预制t梁整体绑扎胎具
CN201620602U (zh) 一种预埋套管
CN205296213U (zh) 一种地下综合管廊衬砌台车
CN205224073U (zh) 一种接触网固定胎具

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20121024

Assignee: Railway transportation Engineering Co., Ltd of middle Tie Shiliuju group

Assignor: Railway Transport Engineering Co., Ltd. Ningyang Bridge Manufacturing Field of China Railway 16th Bureau Group Co., Ltd.

Contract record no.: 2015990000019

Denomination of invention: Heavy-load railway pre-cast T beam overall binding carcass and construction method thereof

Granted publication date: 20140806

License type: Exclusive License

Record date: 20150109

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model