- CN102733612A CN102733612A CN201210137943XA CN201210137943A CN102733612A CN 102733612 A CN102733612 A CN 102733612A CN 201210137943X A CN201210137943X A CN 201210137943XA CN 201210137943 A CN201210137943 A CN 201210137943A CN 102733612 A CN102733612 A CN 102733612A
- Authority
- CN
- China
- Prior art keywords
- electric block
- track
- concrete
- construction
- block track
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses a mounting method of an electric hoist orbit. The method comprises the following steps of: (1) building a full scaffolding; (2) hoisting an electric hoist orbit to the full scaffolding which is built completely by a tower; (3) hanging a chain block at a flying ring preserved on a concrete floor which is constructed completely, hoisting the electric hoist orbit to a designated position by using the chain block, and connecting a plurality of connection plates on a concrete beam by a tensile bolt and fixedly connecting the lower parts of the plurality of connection plates with the electric hoist orbit through sheared bolts. By utilizing the method, a good construction platform is provided, an I-shaped steel is hoisted onto the scaffolding, and the built full scaffolding is a good construction platform, so that construction members can splice the I-shaped steel on the platform according to a drawing paper; and moreover, the mounting position of the platform distance is less than 1m, so that the construction is very convenient.
Description
Technical field
The present invention relates to a kind of pwoer track installing method, relate in particular to the electric block pwoer track installing method.
Background technology
Electric block is called for short electric hoist, is a kind of small-sized crane gear.Most electric blocks use button to follow manipulation on ground by the people, or also can in drivers' cab, handle or adopt wired (wireless) far distance controlled.Electric block is used in the middle of industrial construction very widely.It also is unit in charge of construction's one of requisite construction content in construction that the electric block track is installed.At present after general mounting method in the middle of the industrial construction is earlier the concrete frame construction to be accomplished; Adopt mobile crane that " worker " word steel is winched on the concrete slab; On with concrete slab, set up scaffold, slinging " worker " word steel from concrete slab then, at last fixed installation.But there are a lot of drawbacks in the method, wastes very much such as the use of mobile crane, and the secondary of scaffold is set up and removed, and makes cost increase claim for eot." worker " word steel is sling from concrete slab, and slinging is excessive height, and safety factor is low.
Summary of the invention
The objective of the invention is to overcome the deficiency of prior art, a kind of cost that greatly reduces be provided, install very fast, the electric block pwoer track installing method very easily of constructing.
Electric block pwoer track installing method of the present invention, it may further comprise the steps:
(1) sets up full hall scaffold;
(2) will hang by the electric block track that i iron is processed on the full hall scaffold of setting up after the completion with tower crane; Assembly unit electric block track in advance on described full hall scaffold is put well below position to be installed then, waits for that laying template and the fluid concrete accomplishing concrete floor and is connected fixing concrete beam with the electric block track construct;
(3) the suspension ring place that on the concrete floor that construction is accomplished, reserves hangs up jack; Adopt jack that the electric block track is hung assigned address then, on concrete beam, connect a plurality of junction plates then through tension bolt and with the bottom of described a plurality of junction plates respectively through being cut bolt and the electric block track is fixedly linked.
The invention has the beneficial effects as follows: 1. good operation platform is arranged, and is that " worker " word steel is hung on the scaffold in this construction, and the full hall scaffold of setting up is a good operation platform, and the constructor can be according to drawing assembly unit on platform good " worker " word steel.Platform is apart from one meter of installation site less than, and it is very convenient to construct.2. need not secondary and set up cripple and mobile crane lifting, the scaffold when this method is directly utilized the reinforced concrete frame structure construction is platform, does not need secondary to set up cripple during installation; Directly utilize the tower crane in reinforced concrete frame when construction before topping out, to carry out slinger's word rail road, need not rental car and hang and wait other lifting devices, time saving and energy saving, safety factor is high.3. it is workable to construct, and does not need secondary to set up cripple and other equipment, can save that steel pipe uses and the expense of lifting machine, greatly reduces cost, installs very soon, guarantee is provided to the duration.In the middle of industrial construction, obtained using widely.
Description of drawings
Accompanying drawing is an electric block pwoer track installing method scheme of installation of the present invention.
The specific embodiment
Below in conjunction with accompanying drawing the present invention is specified:
Electric block pwoer track installing method shown in accompanying drawing, it may further comprise the steps: full hall scaffold is set up in (1); (2) will hang by the electric block track 2 that i iron is processed on the full hall scaffold of setting up after the completion 1 with tower crane; Assembly unit electric block track in advance on described full hall scaffold is put well below position to be installed then, waits for that laying template and the fluid concrete accomplishing concrete floor and is connected fixing concrete beam with the electric block track construct; (3) the suspension ring place that on the concrete floor that construction is accomplished, reserves hangs up jack; Adopt jack that the electric block track is hung assigned address then, on concrete beam, connect a plurality of junction plates 5 then and also the bottom of described a plurality of junction plates is fixedly linked with the electric block track through cutting bolt 4 respectively through tension bolt 3.
Preferably after accomplishing described step (3),, between described electric block track and junction plate, be connected with diagonal brace when the distance of electric block rail top face to concrete beam bottom surface during greater than 6000mm.Can guarantee like this that track does not produce and rock.
The installation of electric block track meets the examination of " code for acceptance of construction quality of steel structures ", " universal industrial mill construction component standard atlas " (ANALYSIS FOR STEEL CRANE GIRDERS) G-426 () check crane girder and each item regulation of design document.
Embodiment 1
(1) sets up full hall scaffold; (2) will hang by the electric block track that " worker " word steel is processed on the full hall scaffold of setting up after the completion with tower crane; Assembly unit electric block track in advance on described full hall scaffold is put well below position to be installed then, waits for that laying template and the fluid concrete accomplishing concrete floor and is connected fixing concrete beam with the electric block track construct; (3) the suspension ring place that on the concrete floor that construction is accomplished, reserves hangs up jack; Adopt jack that the electric block track is hung assigned address then, on concrete beam, connect a plurality of junction plates then through tension bolt and with the bottom of described a plurality of junction plates respectively through being cut bolt and the electric block track is fixedly linked.
Adopt this method easy construction, duration to compare with conventional method and accelerated the duration; Reduced operating expenses, and the installation of electric block track meets the examination of " code for acceptance of construction quality of steel structures ", " universal industrial mill construction component standard atlas " (ANALYSIS FOR STEEL CRANE GIRDERS) G-426 () check crane girder and each item regulation of design document.
(1) sets up full hall scaffold; (2) will hang by the electric block track that " worker " word steel is processed on the full hall scaffold of setting up after the completion with tower crane; Assembly unit electric block track in advance on described full hall scaffold is put well below position to be installed then, waits for that laying template and the fluid concrete accomplishing concrete floor and is connected fixing concrete beam with the electric block track construct; (3) the suspension ring place that on the concrete floor that construction is accomplished, reserves hangs up jack; Adopt jack that the electric block track is hung assigned address then, on concrete beam, connect a plurality of junction plates then through tension bolt and with the bottom of described a plurality of junction plates respectively through being cut bolt and the electric block track is fixedly linked.(4) electric block rail top face to the distance of concrete beam bottom surface connects diagonal brace greater than 6000mm4 between described electric block track and junction plate.
Adopt this method easy construction, duration to compare with conventional method and accelerated the duration; Reduced operating expenses, and the installation of electric block track meets the examination of " code for acceptance of construction quality of steel structures ", " universal industrial mill construction component standard atlas " (ANALYSIS FOR STEEL CRANE GIRDERS) G-426 () check crane girder and each item regulation of design document.
Claims (2)
1. electric block pwoer track installing method is characterized in that it may further comprise the steps:
(1) sets up full hall scaffold;
(2) will hang by the electric block track that i iron is processed on the full hall scaffold of setting up after the completion with tower crane; Assembly unit electric block track in advance on described full hall scaffold is put well below position to be installed then, waits for that laying template and the fluid concrete accomplishing concrete floor and is connected fixing concrete beam with the electric block track construct;
(3) the suspension ring place that on the concrete floor that construction is accomplished, reserves hangs up jack; Adopt jack that the electric block track is hung assigned address then, on concrete beam, connect a plurality of junction plates then through tension bolt and with the bottom of described a plurality of junction plates respectively through being cut bolt and the electric block track is fixedly linked.
2. electric block pwoer track installing method according to claim 1; It is characterized in that: after accomplishing described step (3); When the distance of electric block rail top face to concrete beam bottom surface during, between described electric block track and junction plate, be connected with diagonal brace greater than 6000mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210137943.XA CN102733612B (en) | 2012-05-04 | 2012-05-04 | Mounting method of electric hoist orbit |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210137943.XA CN102733612B (en) | 2012-05-04 | 2012-05-04 | Mounting method of electric hoist orbit |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102733612A true CN102733612A (en) | 2012-10-17 |
CN102733612B CN102733612B (en) | 2014-10-29 |
Family
ID=46989857
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210137943.XA Active CN102733612B (en) | 2012-05-04 | 2012-05-04 | Mounting method of electric hoist orbit |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102733612B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103821362A (en) * | 2014-03-07 | 2014-05-28 | 中化二建集团有限公司 | Synchronous construction method for constructing suspended rail beam and roof |
CN113062579A (en) * | 2021-03-05 | 2021-07-02 | 上海建工一建集团有限公司 | Construction method for reforming existing large-space structure |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1024574A1 (en) * | 1982-03-23 | 1983-06-23 | Проектный и научно-исследовательский институт "Донецкий ПромстройНИИпроект" | Horizontally sliding forms |
CN2248212Y (en) * | 1994-10-19 | 1997-02-26 | 万文革 | Rail-lifting scaffold |
JP2000274069A (en) * | 1999-03-26 | 2000-10-03 | Osamu Okuda | Lift for scaffold component member |
DE202008010192U1 (en) * | 2008-07-30 | 2009-03-12 | Innosteel Kytzia Gmbh | Storage device for heavy components |
CN201288019Y (en) * | 2008-09-20 | 2009-08-12 | 朱长安 | Double-track single-main girder of electric block type crane |
-
2012
- 2012-05-04 CN CN201210137943.XA patent/CN102733612B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1024574A1 (en) * | 1982-03-23 | 1983-06-23 | Проектный и научно-исследовательский институт "Донецкий ПромстройНИИпроект" | Horizontally sliding forms |
CN2248212Y (en) * | 1994-10-19 | 1997-02-26 | 万文革 | Rail-lifting scaffold |
JP2000274069A (en) * | 1999-03-26 | 2000-10-03 | Osamu Okuda | Lift for scaffold component member |
DE202008010192U1 (en) * | 2008-07-30 | 2009-03-12 | Innosteel Kytzia Gmbh | Storage device for heavy components |
CN201288019Y (en) * | 2008-09-20 | 2009-08-12 | 朱长安 | Double-track single-main girder of electric block type crane |
Non-Patent Citations (1)
Title |
---|
吴祥生等: "起重机轨道安装", 《起重运输机械》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103821362A (en) * | 2014-03-07 | 2014-05-28 | 中化二建集团有限公司 | Synchronous construction method for constructing suspended rail beam and roof |
CN103821362B (en) * | 2014-03-07 | 2015-10-28 | 中化二建集团有限公司 | Outstanding beam-and-rail and roofing construction method for synchronously constructing |
CN113062579A (en) * | 2021-03-05 | 2021-07-02 | 上海建工一建集团有限公司 | Construction method for reforming existing large-space structure |
Also Published As
Publication number | Publication date |
---|---|
CN102733612B (en) | 2014-10-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103711301A (en) | Construction method and device for two-track movable electric basket and lifting hoist | |
CN102251483B (en) | Construction method for hoisting concrete-filled steel tube lattice bridge pier through self-lifting attached crane | |
CN101284628B (en) | Hoisting method for framework of large tonnage pressing machine | |
CN106193618A (en) | A kind of Long span aerial steel structure truss construction | |
CN104477736A (en) | Shaft elevator installation method | |
CN205772984U (en) | A kind of hanging apparatus of monolithic steel truss | |
CN201417657Y (en) | Installation device of indoor transformer | |
CN103899093A (en) | Step-by-step hoisting construction method of mega-frame steel truss beam | |
CN203654702U (en) | Operating platform for construction of reinforced concrete chimney | |
CN102493666A (en) | High-altitude translation installation and construction method for super-large super-heavy member | |
CN105019664A (en) | High-altitude sliding installation method for box room type electric room | |
CN103912128A (en) | Construction method of high-altitude one-piece steel truss | |
CN202945798U (en) | Overhanging type scaffold corner device | |
CN104153586A (en) | Construction method for installing purline through suspension cable cranes | |
CN204626930U (en) | Integrated lifting frame operating platform | |
CN103061514A (en) | Long-span steel structure corridor construction method | |
CN102733612B (en) | Mounting method of electric hoist orbit | |
CN202482772U (en) | Collapse-proof stop block mounting system for railway bridge | |
CN104404888A (en) | Large hoisting system allowing gradient to be adjusted in air and application | |
CN102372228B (en) | Translational installation method for large-span crane beam | |
CN105040592B (en) | Horizontal pull rope bridge and erection method thereof | |
CN103982046A (en) | Lifting and installation method of buckling restrained braces | |
CN203794505U (en) | Internal climbing steel beam conveying device of internal climbing movable arm tower crane | |
CN203613464U (en) | Slip form construction cargo transportation device | |
CN105625732A (en) | Supporting-free construction method of ultrahigh overhung steel-structure truss |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee | ||
CP03 | Change of name, title or address |
Address after: 300301 Dongli District, flawless Street Jintang Highway Bridge No. ten Patentee after: MCC TIANGONG GROUP TIANJIN CO., LTD. Address before: 300301, No. ten bridge, Tianjin, Dongli Patentee before: Tianjin MCC20 Construction Co., Ltd. |