CN102733511A CN2011100871418A CN201110087141A CN102733511A CN 102733511 A CN102733511 A CN 102733511A CN 2011100871418 A CN2011100871418 A CN 2011100871418A CN 201110087141 A CN201110087141 A CN 201110087141A CN 102733511 A CN102733511 A CN 102733511A
Authority
CN
China
Prior art keywords
plastic wall
wood plastic
wood
column
junction plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011100871418A
Other languages
Chinese (zh)
Inventor
王广武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2011100871418A priority Critical patent/CN102733511A/en
Publication of CN102733511A publication Critical patent/CN102733511A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses an overall filling wood plastic wall body. The overall filling wood plastic wall body comprises a thermal insulation material, a wood plastic wall plate, a wood plastic upright post, a metal profile, an adhesive material and a wall surface coating layer, wherein a connection plate or a U-shaped connection plate is arranged at the bottom of the wood plastic wall plate; the lower part of the connection plate or the U-shaped connection plate is connected with a foundation or a building ring beam; a connection rib is arranged on the upper part of the connection plate and is inserted into a cavity of the wood plastic wall plate or the wood plastic wall plate is inserted into a groove of the U-shaped connection plate. Thermal insulation materials are filled in the cavity of the wood plastic wall plate or the adhesive material is filled in the lower part inside the cavity of the wood plastic wall plate, and the thermal insulation materials are filled in the upper part inside the cavity of the wood plastic wall plate.

Description

Overall perfusion wood plastic wall and manufacturing approach thereof
Technical field:
The present invention relates to mould the body of wall of hollow wall panel and heat insulating material combination manufacturing with wood.
Background technology:
Do not retrieve as yet on the junction plate that is fixed on basis or the building collar tie beam dowel is set, dowel injects in the wood plastic wall cavity, the report of perfusion heat insulating material in the wood plastic wall cavity.
Summary of the invention:
The objective of the invention is: 1, perfusion heat insulating material or adhesives in the Wood plastic wall board, make heat insulating material or adhesives and junction plate and wallboard integrated, improve the bond strength of wood plastic wall and junction plate.2, wood is moulded and is established shape in the stand column cavity; Wood is moulded perfusion heat insulating material or adhesives in the cavity between column and the embedded with metal section bar; Heat insulating material improves the heat-insulating property of column; Shape improves the shock resistance of column, and adhesives improves the bond strength that wood is moulded column and junction plate.3, under-filled adhesives in Wood plastic wall board or the wall column cavity, the top fill insulant material is filled the bond strength that adhesives improves wood plastic wall or wall column and junction plate, and fill insulant material improves the heat-insulating property of Wood plastic wall board or wall column.4, perfusion self-hardening resin heat insulating material in Wood plastic wall board or the wall column solves wall board material quick-hardening problem, improves the speed of application of Wood plastic wall board or wall column, solves wallboard or wall column bottom pressure bulging problem.5, wood is moulded perfusion heat insulating material in the cavity between column and the embedded with metal section bar, improves wall column compressive property and shock resistance.
6, joint tongue and dovetail holddown groove are established in wallboard or wall column one side end face; Wallboard or wall column opposite side end face are established link slot and dovetail holddown groove; Fill glue in the dovetail holddown groove; Glue improves between adjacent Wood plastic wall board and moulds column seam crossing bonding strength and sealing performance with Wood plastic wall board and wood moulding the sealing of column seam crossing with Wood plastic wall board and wood between adjacent Wood plastic wall board.
The overall perfusion wood plastic wall that the present invention proposes comprises: heat insulating material, and Wood plastic wall board, wood is moulded column; Shape, adhesives, wall surface coating; Wood plastic wall board side plug tenon injects adjacent wood and moulds in the stud sides slot or the Wood plastic wall board side slot injects adjacent wood and moulds in the stud sides plug tenon; Wood plastic wall board side plug tenon injects in the adjacent Wood plastic wall board side slot, and junction plate or U-shaped junction plate are established in the Wood plastic wall board bottom, and junction plate or U-shaped junction plate bottom link with basis or building collar tie beam; Dowel is established on junction plate top; Dowel injects in the Wood plastic wall board cavity or Wood plastic wall board injects in the U-shaped junction plate groove, under-filled adhesives in fill insulant material or the Wood plastic wall board cavity in the Wood plastic wall board cavity, top fill insulant material; Heat insulating material or adhesives and junction plate and wallboard are integrated, improve the bond strength of wood plastic wall and junction plate and basis or building collar tie beam.
Wood is moulded being connected of column and junction plate and basis or building collar tie beam; Wood is moulded the column bottom and is set up the post junction plate; Column junction plate and basis link; Connection shaped steel is established on column junction plate top, connects shaped steel and inserts wood and mould in the column shape cavity, and coupling bar will connect shaped steel and wood and mould the column shape and link together; Interior fill insulant material of cavity or wood that wood is moulded between column and the embedded with metal section bar are moulded under-filled adhesives in the cavity between column and the embedded with metal section bar; The top fill insulant material, heat insulating material or adhesives and column junction plate and wall column are integrated, improve the bond strength that wood is moulded wall column and junction plate and basis or building collar tie beam.
For solving between adjacent Wood plastic wall board and Wood plastic wall board and wooden sealing performance and the bonding strength of moulding the column seam crossing; Joint tongue and dovetail holddown groove are established in wallboard or wall column one side end face; The dovetail holddown groove is located on joint tongue end or joint tongue two side planes, and wallboard or wall column opposite side end face are established link slot and dovetail holddown groove, and the dovetail holddown groove is located at link slot end or plug tenon end, link slot both sides; Fill glue in the dovetail holddown groove; Wallboard or wall column joint tongue insert in adjacent wall board or the wall column link slot, fill in the joint tongue dovetail holddown groove and fill gluing being connected together in glue and the adjacent link slot dovetail holddown groove, with moulding the sealing of column seam crossing with Wood plastic wall board and wood between adjacent Wood plastic wall board; Improve bonding strength, prevent that the slit from appearring in seam crossing.
For solving sealing performance and the bonding strength that connects adjacent Wood plastic wall board seam crossing up and down; Connect up and down and establish the interlayer junction plate between Wood plastic wall board; Dowel is established on junction plate top and dowel is established in the bottom; Junction plate bottom dowel injects down in the Wood plastic wall board heat insulating material, and junction plate top dowel injects to be gone up in the Wood plastic wall board cavity, in heat insulating material or adhesives pour into into the Wood plastic wall board cavity from last Wood plastic wall board opening; Heat insulating material or adhesives are wrapped in around the dowel of top and around the dowel of bottom, heat insulating material or adhesives are combined into one interlayer junction plate and last Wood plastic wall board with following Wood plastic wall board.
Mould the bonding strength that column and following wood are moulded column for solving overwood; Wood is moulded the column inner core and is inserted overwood respectively and mould column and connect in the shaped steel and to mould column with wood up and down and be connected in the shaped steel; Wood is moulded perfusion heat insulating material or infusion and binding material in the cavity between column and the embedded with metal section bar, and connector or perfusion wood are moulded in the cavity between column and the embedded with metal section bar binding material or heat insulating material and overwood is moulded column and following wood moulded column and wood and mould the column inner core and be combined into one.
Be to improve the shock resistance and the heat-insulating property of Wood plastic wall board or wall column external surface, wallboard or wall column external surface adopt thickening wood to mould shingle nail or by wallboard or wall column external surface co-extrusion insulation layer
For improving the shock resistance of Wood plastic wall board, place shape in the wallboard cavity, the heat insulating material or the adhesives that are filled in the wallboard cavity are wrapped in around the shape.
Heat insulating material comprises: self-hardening resin and expanded perlite thermal-nsulation material, self-hardening resin and vermiculite heat insulating material, self-hardening resin and coal ash heat-preservation material, self-hardening resin and pozzolan heat insulating material; The polyurethane heat insulating material, expanded perlite, vermiculite; Flyash, pozzolan, phase-change energy-storing thermal insulation material.
Adhesives comprises: cement, clay, polyurethane grouting material, water glass grout material, epoxy resin grouting material, acrylic acid grouting material.
The wallboard that Wood plastic wall board is extruded manufacturing after with inorganic material particle and organic plastics blend substitutes; As: the glass plastic wall board that glass microballoon or glass fiber and organic plastics are formed; The coal plastic wall board that flyash and organic plastics are formed, the stone flour wallboard that CHARACTERISTICS OF TAILINGS SAND or stone flour and organic plastics are formed.Organic plastics comprises: PVC, PP, PE, ABS and alloy thereof.
Overall perfusion wood plastic wall manufacturing approach: junction plate is established in the Wood plastic wall board bottom, and the junction plate bottom links with basis or building collar tie beam, and dowel is established on junction plate top, and dowel injects in the Wood plastic wall board cavity; Wood is moulded column bottom junction plate and the basis links, and connection shaped steel is established on column junction plate top, connects shaped steel insertion wood and moulds in the column shape cavity, and wood is moulded column to connector and the column junction plate is combined into one; Wood plastic wall board side plug tenon injects adjacent wood and moulds in the stud sides slot or the Wood plastic wall board side slot injects adjacent wood and moulds in the stud sides plug tenon, and Wood plastic wall board side plug tenon injects in the adjacent Wood plastic wall board side slot; Fill insulant material or the under-filled adhesives of Wood plastic wall board cavity in the Wood plastic wall board cavity, the top fill insulant material, heat insulating material or adhesives are wrapped in around the dowel, and junction plate and Wood plastic wall board are combined into one; Wood moulds that column and shape are formed in the cavity fill insulant material or wood is moulded column and the under-filled adhesives of shape composition cavity, the top fill insulant material, and heat insulating material or adhesives are moulded column with column junction plate and wood and are combined into one.
Overall perfusion wood plastic wall manufacturing approach: the U-shaped junction plate is established in the Wood plastic wall board bottom, and U-shaped junction plate bottom links with basis or building collar tie beam; Insert in the U-shaped junction plate Wood plastic wall board bottom; Wood plastic wall board side plug tenon injects adjacent wood and moulds in the stud sides slot or the Wood plastic wall board side slot injects adjacent wood and moulds in the stud sides plug tenon, and Wood plastic wall board side plug tenon injects in the adjacent Wood plastic wall board side slot; Fill insulant material or the under-filled adhesives of Wood plastic wall board cavity in the Wood plastic wall board cavity, the top fill insulant material, heat insulating material or adhesives are combined into one U-shaped junction plate and Wood plastic wall board.
Description of drawings:
Below in conjunction with accompanying drawing and embodiment the present invention is further described.
Fig. 1 has the fixedly interior fill insulant material Wood plastic wall board structure chart of tongue-and-groove connection of characteristic side dovetail groove of the present invention.
Fig. 2 is that the horizontal connection horizontal of Fig. 1 is to the package assembly sectional drawing.
Fig. 3 is that fill insulant material and rectangular metal Guan Mu mould pillar construction figure in having a characteristic side dovetail groove of the present invention fixedly tongue-and-groove connecting.
Fig. 4 be Fig. 1 side dovetail groove in fixedly tongue-and-groove connects fill insulant material Wood plastic wall board and Fig. 3 side dovetail groove fixedly tongue-and-groove be connected interior fill insulant material and rectangular metal Guan Mu moulds the horizontal connection horizontal of column to assembling assumption diagram.
Fig. 5 is that Fig. 1 Wood plastic wall board bottom vertically is connected sectional structure chart with lower connecting plate with heat insulating material.
Fig. 6 is that Fig. 1 Wood plastic wall board bottom vertically is connected the side sectional structure chart with lower connecting plate with heat insulating material.
Fig. 7 is that Fig. 1 Wood plastic wall board bottom vertically is connected the side sectional structure chart with following U-shaped steel tank junction plate with heat insulating material.
Fig. 8 is that Fig. 1 Wood plastic wall board bottom vertically is connected sectional structure chart with heat insulating material with adhesives with lower connecting plate.
Fig. 9 is that Fig. 1 Wood plastic wall board bottom vertically is connected side sectional structure chart with heat insulating material with adhesives with lower connecting plate.
Figure 10 is that Fig. 1 Wood plastic wall board bottom vertically is connected side sectional structure chart with heat insulating material with adhesives with following U-shaped steel tank junction plate.
Figure 11 is that Fig. 1 connects the Wood plastic wall board sectional structure chart up and down.
Figure 12 inlays rectangular metal Guan Mu to mould column bottom and vertically be connected sectional structure chart with lower connecting plate with heat insulating material in Fig. 3.
Figure 13 inlays rectangular metal Guan Mu to mould column bottom and vertically be connected sectional structure chart with heat insulating material with adhesives with lower connecting plate in Fig. 3.
Inlaying rectangular metal Guan Mu in Figure 14 Fig. 3 in the fill insulant material moulds upper pillar stand and vertically is connected sectional structure chart with lower pillar stand.
Inlaying rectangular metal Guan Mu in Figure 15 Fig. 3 in fill insulant material and the adhesives moulds upper pillar stand and vertically is connected sectional structure chart with lower pillar stand.
The specific embodiment:
Embodiment 1:
Fixedly the interior fill insulant material Wood plastic wall board structure chart of tongue-and-groove connection is as shown in Figure 1 for a kind of side dovetail groove, and the horizontal connection horizontal of Fig. 1 is as shown in Figure 2 to the package assembly sectional drawing, wherein: the 1st, Wood plastic wall board, the 2nd, wallboard joint tongue; The 3rd, tenon seal groove, the 4th, sealing platform, the 5th, sealing platform dovetail groove, the 6th, wallboard link slot; The 7th, groove seal groove, the 8th, wallboard link slot side boss, the 9th, side boss dovetail groove, the 10th, self-hardening resin heat insulating material; The 11st, structure glue, the 12nd, sealing joint strip, the 13rd, connected nail.
During assembling; Structure glue 11 is filled in the sealing platform dovetail groove 5 respectively and is filled in the adjacent wall board side boss dovetail groove 9; Wallboard joint tongue 2 injects in the wallboard link slot 6; Sealing joint strip 12 is inlayed into tenon seal groove 3 and the 7 interior sealings of groove seal groove; Be filled into sealing platform dovetail groove 5 inner structure glue 11 and be filled into adjacent wall board side boss dovetail groove 9 inner structure glue 11 mutual extrusion and be combined into one; Connected nail 13 passes wallboard link slot 6 and with wallboard joint tongue 2 adjacent wall board 1 is fixed together, and structure glue 11 solidifies the back and connected nail 13 is fixed adjacent Wood plastic wall board 1 and the sealing that bonds together jointly, and self-hardening resin heat insulating material 10 is filled into respectively in the cavity of adjacent Wood plastic wall board.
Embodiment 2:
A kind of side dovetail groove in fixedly tongue-and-groove connects fill insulant material and rectangular metal Guan Mu to mould pillar construction figure as shown in Figure 3, Fig. 1 side dovetail groove fixedly tongue-and-groove connect interior fill insulant material Wood plastic wall board and Fig. 3 side dovetail groove fixedly tongue-and-groove be connected interior fill insulant material and rectangular metal Guan Mu to mould the horizontal connection horizontal of column as shown in Figure 4 to assembling assumption diagram, wherein: the 10th, the self-hardening resin heat insulating material; The 11st, structure glue, the 12nd, sealing joint strip, the 13rd, connected nail; The 14th, wood is moulded wall column, and the 15th, wall column joint tongue, the 16th, wall column joint tongue seal groove; The 17th, sealing platform, the 18th, sealing platform dovetail groove, the 19th, wall column link slot; The 20th, groove seal groove, the 21st, wall column band chamber link slot side boss, the 22nd, side boss dovetail groove; The 23rd, stud, the 24th, interior embedded with metal section bar.
During assembling; Structure glue 11 is filled into respectively in the sealing platform dovetail groove 5 and in the wall column side boss dovetail groove 22; Wallboard joint tongue 2 injects in the wall column link slot 19; Sealing joint strip 12 is inlayed into wallboard tenon seal groove 3 and the 20 interior sealings of wall column groove seal groove; Be filled in the sealing platform dovetail groove 5 and be combined into one with wall column side boss dovetail groove 18 inner structure glue 11 mutual extrusion, connected nail 13 passes wall column link slot 19 and with wallboard joint tongue 2 wallboard 1 and wall column 14 is fixed together, and structure glue 11 is solidified back and connected nail 13 and jointly Wood plastic wall board 1 and adjacent wood moulded wall column 14 sealing that bonds together.Structure glue 11 is filled into wood respectively and moulds in the wall column 14 sealing platform dovetail grooves 18 and in the Wood plastic wall board 1 side boss dovetail groove 9; Wallboard link slot 6 inserts in the wall column joint tongue 15; Sealing joint strip 12 is inlayed into wall column tenon seal groove 16 and the 7 interior sealings of wallboard groove seal groove; Be filled in the wall column sealing platform dovetail groove 18 and be combined into one with Wood plastic wall board 1 side boss dovetail groove 9 inner structure glue 11 mutual extrusion; Connected nail 13 passes wallboard link slot 6 and with wall column joint tongue 15 wallboard 1 and wall column 14 is fixed together; Structure glue 11 is solidified back and connected nail 13 and jointly Wood plastic wall board 1 and adjacent wood is moulded wall column 14 sealing that bonds together, and self-hardening resin heat insulating material 10 is filled into respectively in the cavity of Wood plastic wall board 1 and moulds in the cavity of wall column 14 and interior embedded with metal section bar 24 compositions with adjacent wood.
Embodiment 3:
It is as shown in Figure 5 that Fig. 1 Wood plastic wall board bottom and lower connecting plate and heat insulating material vertically are connected sectional structure chart, and vertically to be connected the side sectional structure chart as shown in Figure 6 with lower connecting plate and heat insulating material bottom Fig. 1 Wood plastic wall board, wherein: the 1st, Wood plastic wall board; The 10th, the self-hardening resin heat insulating material; The 25th, ground or building collar tie beam, the 26th, ground or building collar tie beam junction plate, the 27th, dowel under the junction plate; The 28th, wallboard lower connecting plate, the 29th, dowel on the wallboard lower connecting plate.
During assembling; Dowel 27 is embedded in ground or the building collar tie beam 25 under ground or building collar tie beam junction plate 26 and the junction plate; Wallboard lower connecting plate 28 is welded on ground or the building collar tie beam junction plate 26 fixing; Dowel 29 inserts in Wood plastic wall board 1 cavity on the wallboard lower connecting plate, and self-hardening resin heat insulating material 10 pours in Wood plastic wall board 1 cavity from Wood plastic wall board 1 upper shed, after self-hardening resin heat insulating material 10 solidifies ground or building collar tie beam junction plate 26 is combined with Wood plastic wall board 1.
Embodiment 4:
It is as shown in Figure 5 that Fig. 1 Wood plastic wall board bottom and lower connecting plate and heat insulating material vertically are connected sectional structure chart, and vertically to be connected the side sectional structure chart as shown in Figure 7 with following U-shaped steel tank junction plate and heat insulating material bottom Fig. 1 Wood plastic wall board, wherein: the 1st, Wood plastic wall board; The 10th, heat insulating material; The 25th, ground or building collar tie beam, the 26th, ground or building collar tie beam junction plate, the 27th, junction plate dowel; The 30th, wallboard U-shaped lower connecting plate, the 31st, wallboard connected nail.
During assembling; Dowel 27 is embedded in ground or the building collar tie beam 25 under ground or building collar tie beam junction plate 26 and the junction plate; Wallboard U-shaped lower connecting plate 30 is welded on ground or the building collar tie beam junction plate 26 fixing; Wood plastic wall board 1 inserts in the Wood plastic wall board U-shaped lower connecting plate 30, and heat insulating material 10 pours in Wood plastic wall board 1 cavity from Wood plastic wall board 1 upper shed, after self-hardening resin heat insulating material 10 solidifies ground or building collar tie beam junction plate 26 is combined with Wood plastic wall board U-shaped lower connecting plate 30.
Embodiment 3:
It is as shown in Figure 8 that Fig. 1 Wood plastic wall board bottom and lower connecting plate and heat insulating material and adhesives vertically are connected sectional structure chart; It is as shown in Figure 9 that Fig. 1 Wood plastic wall board bottom and lower connecting plate and heat insulating material and adhesives vertically are connected the side sectional structure chart, wherein: the 1st, Wood plastic wall board, the 10th, self-hardening resin heat insulating material; The 25th, ground or building collar tie beam; The 26th, ground or building collar tie beam junction plate, the 27th, dowel under the junction plate, the 28th, wallboard lower connecting plate; The 29th, dowel on the wallboard lower connecting plate, the 32nd, self-hardening resin clay or sulphate aluminium cement mixture.
During assembling; Dowel 27 is embedded in ground or the building collar tie beam 25 under ground or building collar tie beam junction plate 26 and the junction plate; Wallboard lower connecting plate 28 is welded on ground or the building collar tie beam junction plate 26 fixing; Dowel 29 inserts in Wood plastic wall board 1 cavity on the wallboard lower connecting plate, and self-hardening resin clay or sulphate aluminium cement mixture 32 pour in Wood plastic wall board 1 cavity, then from Wood plastic wall board 1 upper shed; Self-hardening resin heat insulating material 10 pours in Wood plastic wall board 1 cavity from Wood plastic wall board 1 upper shed, and self-hardening resin clay or sulphate aluminium cement mixture 32 combine ground or building collar tie beam junction plate 26 with self-hardening resin heat insulating material 10 with Wood plastic wall board 1.
Embodiment 4:
It is as shown in Figure 9 that Fig. 1 Wood plastic wall board bottom and lower connecting plate and heat insulating material and adhesives vertically are connected sectional structure chart; It is shown in figure 10 that Fig. 1 Wood plastic wall board bottom and following U-shaped steel tank junction plate and heat insulating material and adhesives vertically are connected the side sectional structure chart, wherein: the 1st, Wood plastic wall board, the 10th, self-hardening resin heat insulating material; The 25th, ground or building collar tie beam; The 26th, ground or building collar tie beam junction plate, the 27th, dowel under the junction plate, the 30th, wallboard U-shaped lower connecting plate; The 31st, wallboard connected nail, the 32nd, self-hardening resin clay or sulphate aluminium cement mixture.
During assembling; Dowel 27 is embedded in ground or the building collar tie beam 25 under ground or building collar tie beam junction plate 26 and the junction plate; Wallboard U-shaped lower connecting plate 30 is welded on ground or the building collar tie beam junction plate 26 fixing; Wood plastic wall board 1 inserts in the Wood plastic wall board U-shaped lower connecting plate 30; Self-hardening resin clay or sulphate aluminium cement mixture 32 pour in Wood plastic wall board 1 cavity from Wood plastic wall board 1 upper shed; Then, self-hardening resin heat insulating material 10 pours in Wood plastic wall board 1 cavity from Wood plastic wall board 1 upper shed, and self-hardening resin clay or sulphate aluminium cement mixture 32 combine ground or building collar tie beam junction plate 26 with self-hardening resin heat insulating material 10 with Wood plastic wall board U-shaped lower connecting plate 30.
Embodiment 5:
It is shown in figure 11 that Fig. 1 connects the Wood plastic wall board sectional structure chart up and down, wherein: the 1st, Wood plastic wall board, the 10th, self-hardening resin heat insulating material; The 33rd, joint bar under the interlayer junction plate, the 34th, interlayer junction plate, the 35th, joint bar hole under the interlayer junction plate; The 36th, joint bar on the interlayer junction plate, the 37th, overstory plastic wall board.
During assembling; Joint bar 36 inserts in the Wood plastic wall board 1 self-hardening resin heat insulating material under the interlayer junction plate; Joint bar hole 35 passes that joint bar 36 is placed on the Wood plastic wall board 1 interlayer junction plate 34 under the interlayer junction plate under the interlayer junction plate; Overstory plastic wall board 37 is placed on the interlayer junction plate 34; On the interlayer junction plate between joint bar 33 and part layer under the junction plate joint bar 36 get in overstory plastic wall boards 37 cavitys; Self-hardening resin heat insulating material 10 pours in overstory plastic wall board 37 cavitys from 37 upper sheds of overstory plastic wall board, under interlayer junction plate 34 and the interlayer junction plate on joint bar 33 and the interlayer junction plate joint bar 36 with self-hardening resin heat insulating material 10 overstory plastic wall board 37 and Wood plastic wall board 10 are linked together.
Embodiment 6:
Inlay rectangular metal Guan Mu in Fig. 3 and mould column bottom and lower connecting plate and heat insulating material vertically to be connected sectional structure chart shown in figure 12, wherein: the 10th, the self-hardening resin heat insulating material, the 14th, wood is moulded wall column; The 24th, interior embedded with metal section bar, the 25th, cement ground, the 26th, ground junction plate; The 27th, dowel under the junction plate; The 38th, the column junction plate, the 39th, the column junction plate connects shaped steel, the 40th, coupling bar.
During assembling; Ground junction plate 26 is embedded in the cement ground 25 with junction plate dowel 27; Column junction plate 38 is welded on the ground junction plate 26 fixing; Connecting shaped steel 39 insertion wood moulds in wall column 14 interior embedded with metal section bar 24 cavitys; Coupling bar 40 connects shaped steel 38 with the column junction plate and links together with interior embedded with metal section bar 24, and wood is moulded wall column 14 and the interior self-hardening resin heat insulating material 10 that pours into of the cavity of interior embedded with metal section bar 24, and self-hardening resin heat insulating material 10 is moulded wall column 14 with interior embedded with metal section bar 24 and wood and is combined into one with column junction plate 38.
Embodiment 7:
Inlay rectangular metal Guan Mu in Fig. 3 and mould column bottom and lower connecting plate and heat insulating material and adhesives vertically to be connected sectional structure chart shown in figure 13, wherein: the 10th, the self-hardening resin heat insulating material, the 14th, wood is moulded wall column; The 24th, interior embedded with metal section bar, the 25th, cement ground, the 26th, ground junction plate; The 27th, dowel under the junction plate, the 38th, the column junction plate, the 39th, the column junction plate connects shaped steel; The 40th, coupling bar, the 41st, self-hardening resin clay or sulphate aluminium cement mixture.
During assembling; Dowel 27 is embedded in the cement ground 25 under ground junction plate 26 and the junction plate; Column junction plate 38 is welded on the ground junction plate 26 fixing; Connecting shaped steel 39 insertion wood moulds in wall column 14 interior embedded with metal section bar 24 cavitys; Coupling bar 40 connects shaped steel 38 with the column junction plate and links together with interior embedded with metal section bar 24; Wood is moulded wall column 14 and the cavity of interior embedded with metal section bar 24 interior bottom perfusion self-hardening resin clay or sulphate aluminium cement mixture 41, self-hardening resin clay or sulphate aluminium cement mixture 41 tops perfusion self-hardening resin heat insulating material 10, and self-hardening resin clay or cement 41 with self-hardening resin heat insulating material 10 interior embedded with metal section bar 24 and wood are moulded wall column 14 and column junction plate 38 is combined into one.
Embodiment 8:
In Fig. 3 fill insulant material in inlay rectangular metal Guan Mu and mould upper pillar stand and lower pillar stand vertically to be connected sectional structure chart shown in figure 14, wherein: the 10th, the self-hardening resin heat insulating material, the 14th, wood is moulded wall column; The 24th, interior embedded with metal section bar, the 42nd, column connects inner core, and the 43rd, column connects inserting column on the inner core; The 44th, column connects the inner core median septum, and the 45th, column connects inserting column under the inner core, the 46th, coupling bar; The 47th, wood is moulded wall column, and the 48th, seam seal gum.
During assembling; Column connects the wood of inserting column 45 reeve filling self-hardening resin heat insulating materials 10 under the inner core and moulds in lower pillar stand 14 embedded with metal section bars 24 cavitys; Embedded with metal section bar 24 was connected under the inner core inserting column 45 and column is connected inner core 42 and wood moulds lower pillar stand 14 and link together in coupling bar 46 passed with column; Wood is moulded interior embedded with metal section bars 24 in the wall column 47 and is inserted columns and connect on the inner cores in the inserting column 43; Embedded with metal section bar 24 was connected on the inner core inserting column 43 and column is connected inner core 42 moulds wall column 47 with wood and link together in coupling bar 46 passed with column, and wood is moulded the interior filling of the cavity self-hardening resin heat insulating material 10 of wall column 47 and interior embedded with metal section bar 24 compositions.
Embodiment 9:
Inlay rectangular metal Guan Mu in Figure 33 in fill insulant material and the adhesives and mould upper pillar stand and lower pillar stand vertically to be connected sectional structure chart shown in figure 15, wherein: the 10th, the self-hardening resin heat insulating material, the 14th, wood is moulded wall column; The 24th, interior embedded with metal section bar, the 42nd, column connects inner core, and the 43rd, column connects inserting column on the inner core; The 44th, column connects the inner core median septum; The 45th, column connects inserting column under the inner core, and the 46th, coupling bar, the 47th, wood is moulded wall column; The 48th, seam seal gum, the 49th, self-hardening resin clay or sulphate aluminium cement mixture.
During assembling; Inserting column 45 reeve filling self-hardening resin heat insulating materials 10 are moulded in lower pillar stand 14 embedded with metal section bars 24 cavitys with the wood of self-hardening resin clay or sulphate aluminium cement mixture 49 under the column connection inner core; Embedded with metal section bar 24 was connected under the inner core inserting column 45 and column is connected inner core 42 and wood moulds lower pillar stand 14 and link together in coupling bar 46 passed with column; Wood is moulded interior embedded with metal section bars 24 in the wall column 47 and is inserted columns and connect on the inner cores in the inserting column 43; Embedded with metal section bar 24 was connected on the inner core inserting column 43 and column is connected inner core 42 and wood moulds wall column 47 and link together in coupling bar 46 passed with column; Wood is moulded under-filled self-hardening resin clay or sulphate aluminium cement mixture 49 in the cavity that wall column 47 and interior embedded with metal section bar 24 form, and self-hardening resin heat insulating material 10 is filled on top.

Claims (10)

1. the overall perfusion wood plastic wall comprises: heat insulating material, and Wood plastic wall board, wood is moulded column; Shape, adhesives, wall surface coating; It is characterized in that: junction plate or U-shaped junction plate are established in the Wood plastic wall board bottom; Junction plate or U-shaped junction plate bottom link with basis or building collar tie beam, and dowel is established on junction plate top, and dowel injects in the Wood plastic wall board cavity or Wood plastic wall board injects in the U-shaped junction plate groove; Under-filled adhesives in fill insulant material or the Wood plastic wall board cavity in the Wood plastic wall board cavity, the top fill insulant material.
2. overall perfusion wood plastic wall according to claim 1; It is characterized in that: wood is moulded the column bottom and is set up the post junction plate, and column junction plate and basis link, and connection shaped steel is established on column junction plate top; Connecting shaped steel insertion wood moulds in the column shape cavity; Wood is moulded in the cavity between column and embedded with metal section bar fill insulant material or wood and is moulded between column and the embedded with metal section bar in the cavity, under-filled adhesives, top fill insulant material.
3. overall perfusion wood plastic wall according to claim 1; It is characterized in that: connect up and down and establish the interlayer junction plate between Wood plastic wall board; Dowel is established on interlayer junction plate top; Dowel is established in interlayer junction plate bottom, and in the Wood plastic wall board heat insulating material, interlayer junction plate top dowel injects to be gone up in the Wood plastic wall board cavity under interlayer junction plate bottom dowel injected; Heat insulating material or adhesives are wrapped in around the dowel of interlayer junction plate top and around the dowel of interlayer junction plate bottom, heat insulating material or adhesives are combined into one interlayer junction plate and last Wood plastic wall board with following Wood plastic wall board.
4. overall perfusion wood plastic wall according to claim 1; It is characterized in that: wood is moulded the column inner core and is inserted overwood respectively and mould column and connect and to mould column with following wood in the shaped steel and be connected in the shaped steel, and connector or infusion and binding material are moulded column and following wood with overwood and moulded column and wood and mould the column inner core and be combined into one.
5. overall perfusion wood plastic wall according to claim 1; It is characterized in that: joint tongue and dovetail holddown groove are established in wallboard or wall column one side end face; The dovetail holddown groove is located on joint tongue end or joint tongue two side planes; Wallboard or wall column opposite side end face are established link slot and dovetail holddown groove, and the dovetail holddown groove is located at link slot end or plug tenon end, link slot both sides, fill glue in the dovetail holddown groove; Wallboard or wall column joint tongue insert in adjacent wall board or the wall column link slot, fill in the joint tongue dovetail holddown groove and fill gluing being connected together in glue and the adjacent link slot dovetail holddown groove.
6. overall perfusion wood plastic wall according to claim 1, it is characterized in that: place shape in the wallboard cavity, the heat insulating material or the adhesives that are filled in the wallboard cavity are wrapped in around the shape.
7. overall perfusion wood plastic wall according to claim 1, it is characterized in that: heat insulating material comprises: self-hardening resin and expanded perlite thermal-nsulation material, self-hardening resin and vermiculite heat insulating material; Self-hardening resin and coal ash heat-preservation material, self-hardening resin and pozzolan heat insulating material, polyurethane heat insulating material; Expanded perlite, vermiculite, flyash; Pozzolan, phase-change energy-storing thermal insulation material.
8. overall perfusion wood plastic wall according to claim 1, it is characterized in that: adhesives comprises: cement, clay, polyurethane grouting material, water glass grout material, epoxy resin grouting material, acrylic acid grouting material.
9. overall perfusion wood plastic wall manufacturing approach: junction plate is established in the Wood plastic wall board bottom, and the junction plate bottom links with basis or building collar tie beam, and dowel is established on junction plate top, and dowel injects in the Wood plastic wall board cavity; Wood is moulded column bottom junction plate and the basis links, and connection shaped steel is established on column junction plate top, connects shaped steel insertion wood and moulds in the column shape cavity, and wood is moulded column to connector and the column junction plate is combined into one; Wood plastic wall board side plug tenon injects adjacent wood and moulds in the stud sides slot, and the Wood plastic wall board side slot injects adjacent wood and moulds in the stud sides plug tenon, and Wood plastic wall board side plug tenon injects in the adjacent Wood plastic wall board side slot; Fill insulant material or the under-filled adhesives of Wood plastic wall board cavity in the Wood plastic wall board cavity, the top fill insulant material, heat insulating material or adhesives are wrapped in around the dowel, and junction plate and Wood plastic wall board are combined into one; Wood moulds that column and shape are formed in the cavity fill insulant material or wood is moulded column and the under-filled adhesives of shape composition cavity, the top fill insulant material, and heat insulating material or adhesives are moulded column with column junction plate and wood and are combined into one.
10. overall perfusion wood plastic wall manufacturing approach: the U-shaped junction plate is established in the Wood plastic wall board bottom, and U-shaped junction plate bottom links with basis or building collar tie beam; Insert in the U-shaped junction plate Wood plastic wall board bottom; Wood plastic wall board side plug tenon injects adjacent wood and moulds in the stud sides slot or the Wood plastic wall board side slot injects adjacent wood and moulds in the stud sides plug tenon, and Wood plastic wall board side plug tenon injects in the adjacent Wood plastic wall board side slot; Fill insulant material or the under-filled adhesives of Wood plastic wall board cavity in the Wood plastic wall board cavity, the top fill insulant material, heat insulating material or adhesives are combined into one U-shaped junction plate and Wood plastic wall board.
CN2011100871418A 2011-04-08 2011-04-08 Overall filling wood plastic wall body and manufacturing method thereof Pending CN102733511A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011100871418A CN102733511A (en) 2011-04-08 2011-04-08 Overall filling wood plastic wall body and manufacturing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011100871418A CN102733511A (en) 2011-04-08 2011-04-08 Overall filling wood plastic wall body and manufacturing method thereof

Publications (1)

Publication Number Publication Date
CN102733511A true CN102733511A (en) 2012-10-17

Family

ID=46989760

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011100871418A Pending CN102733511A (en) 2011-04-08 2011-04-08 Overall filling wood plastic wall body and manufacturing method thereof

Country Status (1)

Country Link
CN (1) CN102733511A (en)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103912078A (en) * 2014-04-25 2014-07-09 河南德霖集成房屋有限公司 Connecting structure of composite wallboard and foundation ground
CN104060685A (en) * 2013-03-20 2014-09-24 北京恒通创新赛木科技股份有限公司 House structure
CN105484423A (en) * 2014-09-17 2016-04-13 北新集团建材股份有限公司 Metal sectional material and wood-plastic co-extrusion moulded composite plate as well as preparation method thereof
CN105793498A (en) * 2014-08-30 2016-07-20 创新建筑科技公司 Prefabricated demising and end walls
US10041289B2 (en) 2014-08-30 2018-08-07 Innovative Building Technologies, Llc Interface between a floor panel and a panel track
US10145103B2 (en) 2010-06-08 2018-12-04 Innovative Building Technologies, Llc Premanufactured structures for constructing buildings
CN108951404A (en) * 2018-08-10 2018-12-07 苏交科集团股份有限公司 Precast segment pier stud cross connecting structure and connection method
US10190309B2 (en) 2010-06-08 2019-01-29 Innovative Building Technologies, Llc Slab construction system and method for constructing multi-story buildings using pre-manufactured structures
US10260250B2 (en) 2014-08-30 2019-04-16 Innovative Building Technologies, Llc Diaphragm to lateral support coupling in a structure
US10323428B2 (en) 2017-05-12 2019-06-18 Innovative Building Technologies, Llc Sequence for constructing a building from prefabricated components
US10364572B2 (en) 2014-08-30 2019-07-30 Innovative Building Technologies, Llc Prefabricated wall panel for utility installation
US10487493B2 (en) 2017-05-12 2019-11-26 Innovative Building Technologies, Llc Building design and construction using prefabricated components
US10508442B2 (en) 2016-03-07 2019-12-17 Innovative Building Technologies, Llc Floor and ceiling panel for slab-free floor system of a building
US10676923B2 (en) 2016-03-07 2020-06-09 Innovative Building Technologies, Llc Waterproofing assemblies and prefabricated wall panels including the same
US10724228B2 (en) 2017-05-12 2020-07-28 Innovative Building Technologies, Llc Building assemblies and methods for constructing a building using pre-assembled floor-ceiling panels and walls
US10900224B2 (en) 2016-03-07 2021-01-26 Innovative Building Technologies, Llc Prefabricated demising wall with external conduit engagement features
US10961710B2 (en) 2016-03-07 2021-03-30 Innovative Building Technologies, Llc Pre-assembled wall panel for utility installation
US11054148B2 (en) 2014-08-30 2021-07-06 Innovative Building Technologies, Llc Heated floor and ceiling panel with a corrugated layer for modular use in buildings
US11098475B2 (en) 2017-05-12 2021-08-24 Innovative Building Technologies, Llc Building system with a diaphragm provided by pre-fabricated floor panels

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10145103B2 (en) 2010-06-08 2018-12-04 Innovative Building Technologies, Llc Premanufactured structures for constructing buildings
US10190309B2 (en) 2010-06-08 2019-01-29 Innovative Building Technologies, Llc Slab construction system and method for constructing multi-story buildings using pre-manufactured structures
CN104060685A (en) * 2013-03-20 2014-09-24 北京恒通创新赛木科技股份有限公司 House structure
CN103912078A (en) * 2014-04-25 2014-07-09 河南德霖集成房屋有限公司 Connecting structure of composite wallboard and foundation ground
CN105793498A (en) * 2014-08-30 2016-07-20 创新建筑科技公司 Prefabricated demising and end walls
CN105793498B (en) * 2014-08-30 2018-09-18 创新建筑科技公司 Prefabricated demising wall and headwall
US10041289B2 (en) 2014-08-30 2018-08-07 Innovative Building Technologies, Llc Interface between a floor panel and a panel track
US11054148B2 (en) 2014-08-30 2021-07-06 Innovative Building Technologies, Llc Heated floor and ceiling panel with a corrugated layer for modular use in buildings
US10364572B2 (en) 2014-08-30 2019-07-30 Innovative Building Technologies, Llc Prefabricated wall panel for utility installation
US10260250B2 (en) 2014-08-30 2019-04-16 Innovative Building Technologies, Llc Diaphragm to lateral support coupling in a structure
US10975590B2 (en) 2014-08-30 2021-04-13 Innovative Building Technologies, Llc Diaphragm to lateral support coupling in a structure
US10329764B2 (en) 2014-08-30 2019-06-25 Innovative Building Technologies, Llc Prefabricated demising and end walls
US11060286B2 (en) 2014-08-30 2021-07-13 Innovative Building Technologies, Llc Prefabricated wall panel for utility installation
CN105484423B (en) * 2014-09-17 2019-07-02 北新集团建材股份有限公司 A kind of mental section and the molding composite board of wood-plastic co-extrusion and preparation method thereof
CN105484423A (en) * 2014-09-17 2016-04-13 北新集团建材股份有限公司 Metal sectional material and wood-plastic co-extrusion moulded composite plate as well as preparation method thereof
US10508442B2 (en) 2016-03-07 2019-12-17 Innovative Building Technologies, Llc Floor and ceiling panel for slab-free floor system of a building
US10676923B2 (en) 2016-03-07 2020-06-09 Innovative Building Technologies, Llc Waterproofing assemblies and prefabricated wall panels including the same
US10900224B2 (en) 2016-03-07 2021-01-26 Innovative Building Technologies, Llc Prefabricated demising wall with external conduit engagement features
US10961710B2 (en) 2016-03-07 2021-03-30 Innovative Building Technologies, Llc Pre-assembled wall panel for utility installation
US10487493B2 (en) 2017-05-12 2019-11-26 Innovative Building Technologies, Llc Building design and construction using prefabricated components
US10724228B2 (en) 2017-05-12 2020-07-28 Innovative Building Technologies, Llc Building assemblies and methods for constructing a building using pre-assembled floor-ceiling panels and walls
US10323428B2 (en) 2017-05-12 2019-06-18 Innovative Building Technologies, Llc Sequence for constructing a building from prefabricated components
US11098475B2 (en) 2017-05-12 2021-08-24 Innovative Building Technologies, Llc Building system with a diaphragm provided by pre-fabricated floor panels
CN108951404A (en) * 2018-08-10 2018-12-07 苏交科集团股份有限公司 Precast segment pier stud cross connecting structure and connection method

Similar Documents

Publication Publication Date Title
CN102733511A (en) Overall filling wood plastic wall body and manufacturing method thereof
CN102677780A (en) Tongue and groove connecting structure filled with supporting material
CN201443174U (en) Wood-plastic composite plate with external filled decorative surface
CN205557921U (en) Wallboard and prefabricated constructional column integrated structure of light partition wall
CN102677781A (en) Dovetail fixing tongue-and-groove connection wall plate or wall pillar
CN101929217A (en) Dovetailing cold-rolled steel composite plate
CN102251605A (en) Ceramic plate, pottery clay plate, stone plate or solar plate and wood and plastic composite plate
CN201502269U (en) Door and window formed by corner combining and glue connecting
CN102691356A (en) Hole wallboard internally filled with thermal insulation materials
CN104863305B (en) The preparation method of green assembled architecture wallboard
CN102691355A (en) An inner-filling thermal insulation wallboard
CN104989010B (en) A kind of connection method for bamboo and wood prefabricated panel
CN210827824U (en) Connecting structure of prefabricated wall
CN204983396U (en) Bamboo - aerated concrete combination beam
CN206636053U (en) Built-in profile steel steel tubes concrete column structure
CN207211388U (en) The vertical connection structure of precast shear wall
CN201502129U (en) Wood plastic heat insulating wallboard
CN105544745B (en) Assembled sandwich keeps the temperature close rib compound external wall panel partitioning slot device and construction method
CN203769178U (en) Combined thermal insulation building block with steps
CN206625453U (en) A kind of autoclaved aerated concrete slab structure
CN106906954A (en) A kind of built-in profile steel steel tubes concrete column structure and preparation method thereof
CN101481976A (en) U-shaped inlaid heat-insulating composite section bar
CN109318363B (en) The preparation method and external wall self-insulation system assembly method of assembled architecture outer wall plate
CN206971465U (en) The prefabricated integration assembling wall of insulation construction and house
CN207567989U (en) Component is stitched in prefabricated reinforced concrete wall panel horizontal connection

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication