CN102732874A - Surface treatment production line of copper products - Google Patents

Surface treatment production line of copper products Download PDF

Info

Publication number
CN102732874A
CN102732874A CN2012102263731A CN201210226373A CN102732874A CN 102732874 A CN102732874 A CN 102732874A CN 2012102263731 A CN2012102263731 A CN 2012102263731A CN 201210226373 A CN201210226373 A CN 201210226373A CN 102732874 A CN102732874 A CN 102732874A
Authority
CN
China
Prior art keywords
mentioned
surface treatment
washing bath
slot
tank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012102263731A
Other languages
Chinese (zh)
Other versions
CN102732874B (en
Inventor
蔡吉林
洪煌耀
郑孟照
侯军海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JOYOU KITCHEN AND BATHROOM Co.,Ltd.
Original Assignee
Joyou Building Materials Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Joyou Building Materials Group Co Ltd filed Critical Joyou Building Materials Group Co Ltd
Priority to CN201210226373.1A priority Critical patent/CN102732874B/en
Publication of CN102732874A publication Critical patent/CN102732874A/en
Application granted granted Critical
Publication of CN102732874B publication Critical patent/CN102732874B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Cleaning And De-Greasing Of Metallic Materials By Chemical Methods (AREA)

Abstract

The invention discloses a surface treatment production line of copper products. The surface treatment production line comprises a conveying rail which is arranged along a straight line, wherein a processing slot group distributed along the straight line is arranged below the conveying rail; the processing slot group comprises a hot dipping oil removing slot, a first rinsing slot, a pickling slot, a second rinsing slot, a passivation slot, a third rinsing slot, a lead washing slot and a fourth rinsing slot which are sequentially and adjacently arranged; an electrical conveying mechanism which can reciprocate along the conveying rail and is provided with a lifting rack is matched and arranged on the conveying rail; and the electrical conveying mechanism is controlled by an electrical control system. By adopting the scheme, when the surface treatment production line of the copper product works, the electrical conveying mechanism sequentially lifts or moves a turnover basket filled with the copper products, so that the turnover basket sequentially dips into each corresponding processing slot to perform corresponding surface treatment on the copper products according to the surface treatment requirements of the copper products. Compared with the prior art, the surface treatment production line has the advantages of lower labor intensity of a worker, and high production efficiency.

Description

Brass work surface treatment flow line
Technical field
The present invention relates to the surface treatment of brass work, specifically is brass work surface treatment flow line.
Background technology
In order to prevent that brass work is corroded or variable color in production, storing and use; Improve the corrosion resisting property of brass work in atmosphere; People need carry out surface treatment to brass work, and the surface treatment of brass work generally includes degreasing, pickling, passivation, washes operations such as lead.
In the existing copper product surface treatment process; Degreasing, pickling, passivation, to wash operations such as lead generally be in different workshops, to accomplish; Each workshop is provided with corresponding treatment trough; Brass work is accomplished corresponding the processing in the treatment trough in a workshop after, forward in the workshop of subsequent processing by Turnround basket again and handle accordingly.This process of surface treatment, because each operation is in different workshops, to accomplish, brass work is moved pretty troublesome between each workshop; Labor strength is bigger, and, for dripping, the brass work that prevents just to go out treatment trough spills treatment solution on the way in circular flow; After accomplishing an operation, brass work generally will leave standstill certain hour, and week forwards the workshop of subsequent processing to again; Thereby cause the processing cycle longer, production efficiency is lower.
Summary of the invention
The purpose of this invention is to provide a kind of brass work surface treatment flow line, it need not can reduce labor strength, and enhance productivity at each workshop turnover brass work.
To achieve these goals, the technical scheme of the present invention's employing is following:
Brass work surface treatment flow line; Has the delivery track that is provided with along straight line; The below of this delivery track is provided with the treatment trough group of arranging along straight line; This treatment trough group comprise adjacent setting in regular turn hot dipping degreasing tank, first washing bath, pickling tank, second washing bath, deactivation slot, the 3rd washing bath, wash lead bath and the 4th washing bath; The supporting power-driven conveyors structure that can move back and forth along delivery track that is provided with on the above-mentioned delivery track, this power-driven conveyors structure has liftable hanger, and this power-driven conveyors structure is through its work of electric control system control.
Above-mentioned power-driven conveyors structure is an electric hoist.
Also comprise the smog gathering system; This smog gathering system comprises smoke collector, pipeline and sprinkling system; Above-mentioned smoke collector corresponds respectively to above-mentioned pickling tank and above-mentioned deactivation slot is provided with, and above-mentioned each smoke collector is connected to treatment tank through above-mentioned pipeline respectively, and above-mentioned sprinkling system is arranged in the above-mentioned pipeline; In order to the smog that passes through is sprayed, make the smog drop that congeals into flow into treatment tank.
One side of above-mentioned treatment trough group is provided with the manway that supplies operator's walking, is the outside with this side, and above-mentioned smoke collector is arranged at the inboard of above-mentioned pickling tank and deactivation slot respectively.
Above-mentioned pipeline comprises arm, gathers pipe and return line; The above-mentioned pipe that gathers is horizontally placed on the top that flow line belongs to the workshop; One end of above-mentioned arm connects corresponding above-mentioned smoke collector respectively, and the other end of above-mentioned arm extends upward respectively and is connected to the above-mentioned pipe that gathers, and an above-mentioned end that gathers pipe connects an end of above-mentioned return line; The other end of above-mentioned return line extends downward above-mentioned treatment tank, and above-mentioned sprinkling system is arranged at the above-mentioned intersection that gathers pipe and above-mentioned return line.
The top of above-mentioned sprinkling system is provided with venting port, and above-mentioned return line is connected with the gas blower that waste gas is blowed to above-mentioned venting port.
Above-mentioned first washing bath, second washing bath, the 3rd washing bath and the 4th washing bath have twice respectively, and the back of above-mentioned the 4th washing bath is hot water tank together.
Above-mentioned pickling tank comprises nitric acid groove and the salt acid tank that is provided with in regular turn, and above-mentioned deactivation slot comprises the twice junket acid anhydride acid tank that is provided with in regular turn.
After adopting such scheme, brass work surface treatment flow line of the present invention will be set together along straight line is adjacent in regular turn with each operation corresponding processing groove group of brass work surface-treated; And be furnished with delivery track and power-driven conveyors structure, during work, brass work is positioned over Turnround basket; Turnround basket hangs on the hanger of power-driven conveyors structure; Under the control of electric control system, the power-driven conveyors structure goes up and down to Turnround basket successively or moves, and makes Turnround basket according to the requirement of brass work surface-treated; Immerse each corresponding treatment trough successively, brass work is carried out corresponding surface treatment.Compared with prior art, brass work surface treatment flow line of the present invention has that labor strength is lower, the production efficiency advantage of higher.
Description of drawings
Fig. 1 is the structural representation of facing of the present invention;
Fig. 2 is plan structure synoptic diagram of the present invention (omitting delivery track, smog gathering system and treatment tank etc.).
Embodiment
Brass work surface treatment flow line of the present invention like Fig. 1, shown in 2, comprises delivery track 1, treatment trough group 2, manway 3 and smog gathering system 4.
Delivery track 1 is set up in the top in workshop through support 10, along the straight line setting, and the supporting electric hoist 11 that is provided with on the delivery track 1, electric hoist 11 is through its work of electric control system control.
Treatment trough group 2 is positioned at the below of delivery track 1 and arranges along straight line; Treatment trough group 2 comprise adjacent setting in regular turn hot dipping degreasing tank 21, first washing bath 22, pickling tank 23, second washing bath 24, deactivation slot 25, the 3rd washing bath 26, wash lead bath 27 and the 4th washing bath 28; Above-mentioned each treatment trough of treatment trough group 2 is respectively equipped with leakage fluid dram, and each leakage fluid dram passes through pipe connection respectively to purification tank for liquid waste.Pickling tank 23 comprises the nitric acid groove 231 and salt acid tank 232 that is provided with in regular turn, and deactivation slot 25 comprises the twice junket acid anhydride acid tank 251,252 that is provided with in regular turn.First washing bath 22, second washing bath 24 and the 3rd washing bath 26 have twice respectively; The 4th washing bath 28 also has twice, and first road 281 is the cold rinse bank identical with the 3rd washing bath 26 with first washing bath 22, second washing bath 24, and the back 282 is a hot water tank together.
It is that the commonly used of 20-25 grams per liter removes oil solution that concentration is housed in the hot dipping degreasing tank 21, and is furnished with 6 Ultrasonic Cleanerss, and the temperature of removing oil solution is about 65 ℃.The salpeter solution that mass percent concentration is 10-15% is housed in the nitric acid groove 231.The hydrochloric acid soln that mass percent concentration is 10-20% is housed in the salt acid tank 232.It is the junket acid anhydride acid solution of 180-200 grams per liter that concentration all is housed in the junket acid anhydride acid tank 251,252.Wash the lead solution of washing commonly used is housed in the lead bath 27, this is commonly used washes lead solution and can wash plumbous liquid and water mixes by 1:4.5-5 commonly used.In the first road 281 of first washing bath 22, second washing bath 24, the 3rd washing bath 26 and the 4th washing bath clean cold water is housed all, the back of the 4th washing bath 28 282 is equipped with 80 ℃ hot water together.
Manway 3 is arranged at a side of treatment trough group 2, is the outside with this side, and treatment trough group 2 relative opposite sides are inboard, through being arranged at the manway 3 in treatment trough group 2 outsides, supplies operator to walk, operate above that.
Smog gathering system 4 comprises smoke collector 41, pipeline 42, sprinkling system 43 and gas blower 44.
Smoke collector 41 is located at the inboard of nitric acid groove 231, salt acid tank 232, junket acid anhydride acid tank 251 and junket acid anhydride acid tank 252 respectively; Smoke collector 41 comprises housing and is located at the intravital suction fan of shell; This housing is provided with latticed blast inlet, and the smog that will be volatilized by nitric acid groove 231, salt acid tank 232, junket acid anhydride acid tank 251 and junket acid anhydride acid tank 252 through this suction fan is along in the latticed blast inlet upstream line 42.The suction fan of smoke collector 41 is through its work of electric control system control.
Pipeline 42 comprises arm 421, gathers pipe 422 and return line 423; Gather pipe 422 and be horizontally placed on the top that flow line belongs to the workshop; One end of arm 421 connects the air outlet of the suction fan of corresponding smoke collector 41 respectively; The other end of arm 421 extends upward respectively to be connected to and gathers pipe 422, and an end that gathers pipe 422 connects an end of return line 423, and the other end of return line 423 extends downward treatment tank 5.
Sprinkling system 43 is arranged at the intersection's (water source of sprinkling system 43 is inserted by the external world) that gathers pipe 422 and return line 423; Gas through this intersection is behind sprinkling system 43 sprays, and the contained smoke-like objectionable impurities drop that congeals into flows into treatment tanks 5 along return line 423.The top of sprinkling system 43 offers venting port 424, and gas blower 44 is connected on the return line 423 and (is positioned at the below of sprinkling system 43), in order to waste gas up to standard is blowed to venting port 424, is discharged by the chimney that is connected with venting port 424.Gas blower 44 is through its work of electric control system control.
Brass work surface treatment flow line of the present invention, during work, operator stand on the manway 3; The Turnround basket that brass work is housed is hung on the hook of electric hoist 11; Under the control of electric control system, electric hoist 11 goes up and down to Turnround basket (brass work is housed) successively or moves, and makes Turnround basket (brass work is housed) according to the requirement of brass work surface-treated operation; Immerse each corresponding treatment trough successively, brass work is carried out corresponding surface treatment.
Particularly, each treatment process is following:
1, through electric hoist 11 Turnround basket (brass work is housed) is descended, immerse removing in the oil solution in the hot dipping degreasing tank 21 and carry out ultrasonic cleaning about 3 minutes;
2, through electric hoist 11 Turnround basket (brass work is housed) is risen and advance to the top in the first road of first washing bath 22 along delivery track 1; Through electric hoist 11 Turnround basket (brass work is housed) is descended again, immerse in the first road cold water of first washing bath 22 and wash;
3, through electric hoist 11 Turnround basket (brass work is housed) is risen and advance to the back top together of first washing bath 22 along delivery track 1; Through electric hoist 11 Turnround basket (brass work is housed) is descended again, immerse in back one cold water of first washing bath 22 and wash;
4, through electric hoist 11 Turnround basket (brass work is housed) is risen and advance to the top of nitric acid groove 231, through electric hoist 11 Turnround basket (brass work is housed) is descended again, immerse pickling 10-20 second in the salpeter solution in the nitric acid groove 231 along delivery track 1;
5, through electric hoist 11 Turnround basket (brass work is housed) is risen and advance to the top of salt acid tank 232, through electric hoist 11 Turnround basket (brass work is housed) is descended again, immerse pickling 10-20 second in the hydrochloric acid soln in the salt acid tank 232 along delivery track 1;
6, through electric hoist 11 Turnround basket (brass work is housed) is risen and advance to the top in the first road of second washing bath 24 along delivery track 1; Through electric hoist 11 Turnround basket (brass work is housed) is descended again, immerse in the first road cold water of second washing bath 24 and wash;
7, through electric hoist 11 Turnround basket (brass work is housed) is risen and advance to the back top together of second washing bath 24 along delivery track 1; Through electric hoist 11 Turnround basket (brass work is housed) is descended again, immerse in back one cold water of second washing bath 24 and wash;
8, through electric hoist 11 Turnround basket (brass work is housed) is risen and advance to the top of junket acid anhydride acid tank 251 along delivery track 1; Through electric hoist 11 Turnround basket (brass work is housed) is descended again, immerse passivation 10-15 second in the junket acid anhydride acid solution in the junket acid anhydride acid tank 251;
9, through electric hoist 11 Turnround basket (brass work is housed) is risen and advance to the top of junket acid anhydride acid tank 252 along delivery track 1; Through electric hoist 11 Turnround basket (brass work is housed) is descended again, immerse passivation 10-15 second in the junket acid anhydride acid solution in the junket acid anhydride acid tank 252;
10, through electric hoist 11 Turnround basket (brass work is housed) is risen and advance to the top in the first road of the 3rd washing bath 26 along delivery track 1; Through electric hoist 11 Turnround basket (brass work is housed) is descended again, immerse in the first road cold water of the 3rd washing bath 26 and wash;
11, through electric hoist 11 Turnround basket (brass work is housed) is risen and advance to the back top together of the 3rd washing bath 26 along delivery track 1; Through electric hoist 11 Turnround basket (brass work is housed) is descended again, immerse in back one cold water of the 3rd washing bath 26 and wash;
12, through electric hoist 11 Turnround basket (brass work is housed) is risen and advance to the top of washing lead bath 27 along delivery track 1; Through electric hoist 11 Turnround basket (brass work is housed) is descended again; Immersion is washed washing in the lead bath 27 and is carried out heat in the lead solution earlier and wash 1-2 hour (control is washed the temperature of lead solution at 47-50 ℃, carries out soak at room temperature (cold wash) again more than 8 hours;
13, through electric hoist 11 Turnround basket (brass work is housed) is risen and advance to the top in the first road 281 of the 4th washing bath 28 along delivery track 1; Through electric hoist 11 Turnround basket (brass work is housed) is descended again, immerse in first road 281 cold water of the 4th washing bath 28 and wash;
14, through electric hoist 11 Turnround basket (brass work is housed) is risen and advance to back 282 the top together of the 4th washing bath 28 along delivery track 1; Through electric hoist 11 Turnround basket (brass work is housed) is descended again, immerse in back 282 hot water together of the 4th washing bath 28 and carry out the hot water washing.
In above-mentioned each operation, groove (the changing treatment solution) condition of changing of each treatment trough is:
A, hot dipping degreasing tank 21: remove change of oil solution look or supernatant and increase;
B, nitric acid groove 231: during the blackening of salpeter solution color;
C, salt acid tank 232: the hydrochloric acid soln color is changeed when deceiving indigo plant;
D, junket acid anhydride acid tank 251,252: junket acid anhydride acid solution is by Huang, when red stain is black;
E, wash lead bath 27: washing lead solution with 175 kilograms of every grooves is example, when the brass work of being washed reaches 16 ton hours;
Back together 282 of F, the 4th washing bath 28: when supernatant increases.

Claims (8)

1. brass work surface treatment flow line; It is characterized in that: have the delivery track that is provided with along straight line; The below of this delivery track is provided with the treatment trough group of arranging along straight line; This treatment trough group comprise adjacent setting in regular turn hot dipping degreasing tank, first washing bath, pickling tank, second washing bath, deactivation slot, the 3rd washing bath, wash lead bath and the 4th washing bath; The supporting power-driven conveyors structure that can move back and forth along delivery track that is provided with on the above-mentioned delivery track, this power-driven conveyors structure has liftable hanger, and this power-driven conveyors structure is through its work of electric control system control.
2. brass work surface treatment flow line according to claim 1 is characterized in that: above-mentioned power-driven conveyors structure is an electric hoist.
3. brass work surface treatment flow line according to claim 1; It is characterized in that: also comprise the smog gathering system; This smog gathering system comprises smoke collector, pipeline and sprinkling system; Above-mentioned smoke collector corresponds respectively to above-mentioned pickling tank and above-mentioned deactivation slot is provided with, and above-mentioned each smoke collector is connected to treatment tank through above-mentioned pipeline respectively, and above-mentioned sprinkling system is arranged in the above-mentioned pipeline; In order to the smog that passes through is sprayed, make the smog drop that congeals into flow into treatment tank.
4. brass work surface treatment flow line according to claim 3; It is characterized in that: a side of above-mentioned treatment trough group is provided with the manway that supplies operator's walking; With this side is the outside, and above-mentioned smoke collector is arranged at the inboard of above-mentioned pickling tank and deactivation slot respectively.
5. brass work surface treatment flow line according to claim 3; It is characterized in that: above-mentioned pipeline comprises arm, gathers pipe and return line; The above-mentioned pipe that gathers is horizontally placed on the top that flow line belongs to the workshop; One end of above-mentioned arm connects corresponding above-mentioned smoke collector respectively, and the other end of above-mentioned arm extends upward respectively and is connected to the above-mentioned pipe that gathers, and an above-mentioned end that gathers pipe connects an end of above-mentioned return line; The other end of above-mentioned return line extends downward above-mentioned treatment tank, and above-mentioned sprinkling system is arranged at the above-mentioned intersection that gathers pipe and above-mentioned return line.
6. brass work surface treatment flow line according to claim 5, it is characterized in that: the top of above-mentioned sprinkling system is provided with venting port, and above-mentioned return line is connected with the gas blower that waste gas is blowed to above-mentioned venting port.
7. brass work surface treatment flow line according to claim 1 is characterized in that: above-mentioned first washing bath, second washing bath, the 3rd washing bath and the 4th washing bath have twice respectively, and the back of above-mentioned the 4th washing bath is hot water tank together.
8. according to claim 1 or 4 described brass work surface treatment flow lines, it is characterized in that: above-mentioned pickling tank comprises nitric acid groove and the salt acid tank that is provided with in regular turn, and above-mentioned deactivation slot comprises the twice junket acid anhydride acid tank that is provided with in regular turn.
CN201210226373.1A 2012-06-28 2012-06-28 Surface treatment production line of copper products Active CN102732874B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210226373.1A CN102732874B (en) 2012-06-28 2012-06-28 Surface treatment production line of copper products

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210226373.1A CN102732874B (en) 2012-06-28 2012-06-28 Surface treatment production line of copper products

Publications (2)

Publication Number Publication Date
CN102732874A true CN102732874A (en) 2012-10-17
CN102732874B CN102732874B (en) 2014-04-16

Family

ID=46989155

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210226373.1A Active CN102732874B (en) 2012-06-28 2012-06-28 Surface treatment production line of copper products

Country Status (1)

Country Link
CN (1) CN102732874B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109136878A (en) * 2018-08-07 2019-01-04 无锡职业技术学院 A kind of diamond-coated tools soda acid automation pretreatment unit
WO2021103509A1 (en) * 2020-06-18 2021-06-03 江苏徐工工程机械研究院有限公司 Workpiece cleaning apparatus and cleaning method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05295571A (en) * 1992-04-20 1993-11-09 Japan Energy Corp Surface treatment of copper and copper alloy
CN2793030Y (en) * 2005-03-31 2006-07-05 阎丽辉 Electric calabash hung conveying rope
US20070032080A1 (en) * 2005-08-03 2007-02-08 Korea Institute Of Industrial Technology System and method for manufacturing flexible copper clad laminate film
CN101676439A (en) * 2008-09-18 2010-03-24 浙江帝龙新材料股份有限公司 Aluminum strip continuous anodic oxidation automatic production line
CN202730230U (en) * 2012-06-28 2013-02-13 中宇建材集团有限公司 Production line for treating surface of copper product

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05295571A (en) * 1992-04-20 1993-11-09 Japan Energy Corp Surface treatment of copper and copper alloy
CN2793030Y (en) * 2005-03-31 2006-07-05 阎丽辉 Electric calabash hung conveying rope
US20070032080A1 (en) * 2005-08-03 2007-02-08 Korea Institute Of Industrial Technology System and method for manufacturing flexible copper clad laminate film
CN101676439A (en) * 2008-09-18 2010-03-24 浙江帝龙新材料股份有限公司 Aluminum strip continuous anodic oxidation automatic production line
CN202730230U (en) * 2012-06-28 2013-02-13 中宇建材集团有限公司 Production line for treating surface of copper product

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109136878A (en) * 2018-08-07 2019-01-04 无锡职业技术学院 A kind of diamond-coated tools soda acid automation pretreatment unit
WO2021103509A1 (en) * 2020-06-18 2021-06-03 江苏徐工工程机械研究院有限公司 Workpiece cleaning apparatus and cleaning method
US20230002912A1 (en) * 2020-06-18 2023-01-05 Jiangsu Xcmg Construction Machinery Research Institute Ltd. Workpiece cleaning apparatus and cleaning method

Also Published As

Publication number Publication date
CN102732874B (en) 2014-04-16

Similar Documents

Publication Publication Date Title
CN103372548B (en) Large aluminum fin automatic cleaning device and method
CN110158103B (en) Steel pipe pickling production line
CN203530431U (en) Intelligent phosphating processing system for metal surface
CN103302047A (en) Automatic cleaning machine for workpieces
CN101775607A (en) Forced circulation pickling method of copper and copper alloy tubes, rods and wires
CN201454911U (en) High-pressure cleaning flow line
CN201912034U (en) Multilayer automatic dish-washing machine
CN102732874B (en) Surface treatment production line of copper products
CN202730230U (en) Production line for treating surface of copper product
CN209363125U (en) The cleaning device of high-speed steel hard alloy tool
CN205056523U (en) Full -automatic cleaning machine
CN207413879U (en) A kind of stainless steel electric kettle body automatic Cleaning Line
CN203380142U (en) Automatic cleaning machine for workpieces
CN105648452B (en) Steel pipe degreasing process
CN202610339U (en) Self-cleaning electrochemical treatment system for aluminum alloy workpiece of electric cooker
CN204338499U (en) Self-purging washing flow line
CN203991432U (en) Steel wire rope automatic cleaning equipment
CN102978643A (en) Online rod pickling device
CN113751421A (en) Ultrasonic cleaning machine for piston and cleaning method
CN203560012U (en) Automatic phosphating treatment mechanism of filter housing
CN211914736U (en) Cleaning device for finished product after processing of bus turbine
CN202037138U (en) Coating washing spray device
CN204816966U (en) Electrostatic spraying pretreatment equipment
CN208617988U (en) A kind of screw acid dip pickle
CN208466779U (en) A kind of automatic flushing device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
PP01 Preservation of patent right

Effective date of registration: 20150706

Granted publication date: 20140416

RINS Preservation of patent right or utility model and its discharge
PD01 Discharge of preservation of patent
PD01 Discharge of preservation of patent

Date of cancellation: 20170706

Granted publication date: 20140416

PP01 Preservation of patent right
PP01 Preservation of patent right

Effective date of registration: 20170706

Granted publication date: 20140416

PD01 Discharge of preservation of patent
PD01 Discharge of preservation of patent

Date of cancellation: 20190106

Granted publication date: 20140416

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200806

Address after: 362000 Quanzhou City, Fujian Province, Nanan Lun Cang town JOYOU Industrial Park

Patentee after: JOYOU KITCHEN AND BATHROOM Co.,Ltd.

Address before: 362300 Quanzhou, Fujian City, Nanan Province Cang town

Patentee before: Zhongyu Building Materials Group Co.,Ltd.