CN102704468A - Construction method for immersed pipe cast-in-place pile - Google Patents

Construction method for immersed pipe cast-in-place pile Download PDF

Info

Publication number
CN102704468A
CN102704468A CN201210192809XA CN201210192809A CN102704468A CN 102704468 A CN102704468 A CN 102704468A CN 201210192809X A CN201210192809X A CN 201210192809XA CN 201210192809 A CN201210192809 A CN 201210192809A CN 102704468 A CN102704468 A CN 102704468A
Authority
CN
China
Prior art keywords
pile
immersed pipe
cast
construction method
immersed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201210192809XA
Other languages
Chinese (zh)
Other versions
CN102704468B (en
Inventor
宫能和
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201210192809.XA priority Critical patent/CN102704468B/en
Publication of CN102704468A publication Critical patent/CN102704468A/en
Application granted granted Critical
Publication of CN102704468B publication Critical patent/CN102704468B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a construction method for an immersed pipe cast-in-place pile. The construction method adopts the technical scheme that an immersed pipe pile is piled into a foundation at first, a mixing pile machine is mounted in the position of the immersed pipe pile for piling when the immersed pipe pile is not solidified and formed after a steel pipe is pulled out, and then a mixing pile is withdrawn so as to form the immersed pipe cast-in-place pile. The construction method overcomes the disadvantages in an immersed pipe pile and a cast-in-place pile, and obtains a brand new pile. The construction method achieves the effects as follows: the advantages of the immersed pipe pile and the cast-in-place pile are exerted, the immersed pipe pile and the cast-in-place pile can achieve the synergy, and the pile with high strength is obtained; cost is saved, the method is simple and is easy to popularize and apply; and meanwhile, construction wastes can be utilized, so that better environmental protection can be achieved.

Description

Immersed tube adds the job practices of castinplace pile
Technical field
The present invention relates to a kind of job practices, particularly a kind of immersed tube adds the job practices of castinplace pile.
Background technology
Before the present invention, basis piling has many kinds, and is wherein commonly used like Submersed type stake and agitation pile (claiming castinplace pile again).Pipeline sinking pile is exactly that stake point bottom contact connects a steel pipe, and steel pipe is normally circular, and the centre is empty; The steel pipe top connects power set, starts power set, and the stake point is squeezed into ground; Steel pipe is just imbedded in the ground with the stake point, and steel pipe top one side connects hopper then, in steel pipe, drops into building stones, sandstone, cement etc. through hopper; Then steel pipe is extracted, the stake point is stayed in the ground, and back to be formed has just formed stake.The advantage of pipeline sinking pile is can accomplish homogeneous and controllable on vertically; Can also accomplish to drop at diverse location as required the cementing material of different proportion or different moisture content, intensity is also than higher, but shortcoming also is tangible; Be that diameter is too little; Need in ground, squeeze into many stakes, long in time limit, cost is high.Agitation pile is that power set drive driving shaft, by with driving shaft on blade agitate soil in ground of being fixedly connected, feed cement while stirring, utilize cement and earth to mix, form.The advantage of agitation pile is that diameter is big, though the intensity of the mixing of cement and earth own is not high, major diameter can reach more than 1 meter usually can bring quite high intensity; Pile-forming speed is fast; In same area ground, its quantity can be less than pipeline sinking pile, can only be cement but its defective is the cementing material of agitation pile; Can't add building stones, sandstone etc., intensity can't improve naturally.
Summary of the invention
The object of the invention just is to overcome above-mentioned defective, develops the job practices that a kind of immersed tube adds castinplace pile.
Technical scheme of the present invention is:
Immersed tube adds the job practices of castinplace pile, and its major technique step is:
(1) in ground, squeezes into earlier pipeline sinking pile;
(2) after extracting steel pipe, during the not fixed moulding of pipeline sinking pile, set up mixing pile machine piling in the pipeline sinking pile position;
(3) agitation pile is withdrawed from back formation immersed tube and add castinplace pile.
Advantage of the present invention and effect have been to combine pipeline sinking pile and agitation pile advantage separately, have cast out the two defective separately, make to have produced synergy between the two, have formed a kind of brand-new bore forming method.Be easy to apply, environmental protection, cost is low, and method of operating is simple.
Other advantages of the present invention and effect will continue to describe below.
Description of drawings
Fig. 1---process sketch map of the present invention.
Each label corresponding component is represented as follows among the figure:
Ground 1, stake point 2, steel pipe 3, hopper 4, power set 5, driving shaft 6, drive unit 7, blade 8.
The specific embodiment
As shown in Figure 1:
Earlier on ground 1, select to beat the position of pipeline sinking pile, steel pipe 3 bottoms are stuck in that contact connects on the step on sharp 2 tops of stake, and power set 5 contact with steel pipe 3 tops and are connected; Start power set 5 and constantly hit steel pipe 3 tops; Steel pipe 3 bottoms head on stake point 2 and get in the ground, until arriving preposition fully, from hopper 4, in steel pipe 3, drop into building stones, sandstone, cement etc. then; Then steel pipe 3 is extracted, stake point 2 is stayed in the ground; Also not during fixed moulding, the agitation pile frame is set up in the position of original pipeline sinking pile and is started working in pipeline sinking pile, and drive unit 7 connects driving shafts 6; Start drive unit 7; The blade 8 that is fixedly connected on the driving shaft 6 of agitation pile blends unconsolidated pipeline sinking pile, and the earth with periphery stirs again, when agitation pile is stirred to the precalculated position; Agitation pile withdraws from ground 1 from ground, thereby forms agitation pile; Owing in the original pipeline sinking pile stone etc. is arranged, the intensity of mixing the big agitation pile of the formed diameter in back with peripheral earth strengthens greatly, and promptly diameter has stone etc. greatly again; Therefore, pipeline sinking pile and agitation pile are combined the defective of having avoided them to exist separately, kept their unborn separately advantages again simultaneously, more produced their that all do not have separately, beyond thought effects, promptly produced synergy.
Secondly, just because of the present invention the two is combined, thereby can formerly beat pipeline sinking pile the time, to steel pipe 3 in, drop into building waste etc. through hopper 4, this is compliance with environmental protection requirements both, the intensity that has guaranteed again, and this is unaccommodated when independent pipeline sinking pile; Simultaneously; When beating pipeline sinking pile, owing to must not beat agitation pile during moulding in pipeline sinking pile, also owing to also need drop into cement in the process that agitation pile is beaten; Thereby when beating pipeline sinking pile, can reduce the cement input amount or even not drop into cement; Many input building wastes, thus under guaranteed strength and pile quality prerequisite, reduce cost, and this is huge cost savings for a work items.
In the very big mucky soil of water content, drive piles; Then can when beating pipeline sinking pile, mix a certain proportion of coarse aggregate material (aggregate chips earlier; Flyash, slag powders, building waste of pulverizing or the like); Under the situation of identical cement mixed weight, consolidation strength can be improved greatly, under same soil cement intensity requires, cement consumption can be saved greatly simultaneously.
Also have; For driving piles on the ground of filling in the sea to grow grain; Make full use of the pipeline sinking pile characteristics in the time of can formerly beating pipeline sinking pile, put into different coarse aggregate materials according to different depth, like this when beating agitation pile; Blade 8 can be put into different coarse aggregate materials with different depth and be mixed together stirring at the cement of different depth place and peripheral earth and feeding, makes stake demonstrate corresponding intensity at different depth.
Through a large amount of indoor Mix Ratio Test result, the high-moisture mucky soil after adding certain coarse aggregate cement as the cementing material situation under consolidation strength improve greatly.

Claims (3)

1. immersed tube adds the job practices of castinplace pile, and its step is:
(1) in ground, squeezes into earlier pipeline sinking pile;
(2) after extracting steel pipe, during the not fixed moulding of pipeline sinking pile, set up mixing pile machine piling in the pipeline sinking pile position;
(3) agitation pile is withdrawed from back formation immersed tube and add castinplace pile.
2. immersed tube according to claim 1 adds the job practices of castinplace pile, it is characterized in that reducing the cement input in the step (1) or not dropping into cement.
3. immersed tube according to claim 1 adds the job practices of castinplace pile, it is characterized in that adding in the step (1) building waste.
CN201210192809.XA 2012-06-11 2012-06-11 Construction method for immersed pipe cast-in-place pile Active CN102704468B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210192809.XA CN102704468B (en) 2012-06-11 2012-06-11 Construction method for immersed pipe cast-in-place pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210192809.XA CN102704468B (en) 2012-06-11 2012-06-11 Construction method for immersed pipe cast-in-place pile

Publications (2)

Publication Number Publication Date
CN102704468A true CN102704468A (en) 2012-10-03
CN102704468B CN102704468B (en) 2015-05-20

Family

ID=46897500

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210192809.XA Active CN102704468B (en) 2012-06-11 2012-06-11 Construction method for immersed pipe cast-in-place pile

Country Status (1)

Country Link
CN (1) CN102704468B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1050421A (en) * 1990-11-12 1991-04-03 中国建筑科学研究院珠海科研设计部 The piling method of casting prefabricated composite pile
JPH06136745A (en) * 1992-04-28 1994-05-17 J D F:Kk Construction method for hollow widened bottom cast-in-place concrete pile
CN1272574A (en) * 2000-04-03 2000-11-08 王光明 Immersed tube bored concrete composite pile construction method
CN1305040A (en) * 2001-02-28 2001-07-25 邓亚光 Method for building compound pile
CN2915942Y (en) * 2006-01-04 2007-06-27 邓亚光 Combined piling machine

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1050421A (en) * 1990-11-12 1991-04-03 中国建筑科学研究院珠海科研设计部 The piling method of casting prefabricated composite pile
JPH06136745A (en) * 1992-04-28 1994-05-17 J D F:Kk Construction method for hollow widened bottom cast-in-place concrete pile
CN1272574A (en) * 2000-04-03 2000-11-08 王光明 Immersed tube bored concrete composite pile construction method
CN1305040A (en) * 2001-02-28 2001-07-25 邓亚光 Method for building compound pile
CN2915942Y (en) * 2006-01-04 2007-06-27 邓亚光 Combined piling machine

Also Published As

Publication number Publication date
CN102704468B (en) 2015-05-20

Similar Documents

Publication Publication Date Title
CN203174589U (en) Deep layer cement mixing pile machine drill bit blade device
CN105714773B (en) A kind of method for processing foundation
CN205969508U (en) Building type material mixing device
CN205521946U (en) Concrete mixer
CN105297710A (en) High-pressure-jetting cement soil twist drill and reamed reinforced concrete grouting combined pile and manufacturing method
CN105040683A (en) Informatization construction method for cement mixing piles
CN204940261U (en) A kind of geotechnical engineering agitation pile
CN101831890B (en) Blending construction method of blended gravelly soil for dam watertight core
CN110185025A (en) A kind of mobile closed formula solidification soil vibration mixing apparatus
CN203818328U (en) Automatic-charging movable concrete agitator
CN202123569U (en) Device for recycling residual slurry of pretensioning prestressed concrete pipe piles
CN102704468B (en) Construction method for immersed pipe cast-in-place pile
CN103174130B (en) A kind of layer of sand anti-collapse method of Punching Borehole Cast-in-place Concrete Pile
JP5507591B2 (en) Excavation stirring method for hard ground
CN207484464U (en) A kind of landslide control deep-mixing pile driver
CN208514730U (en) Dry-mixed mortar process units
CN101408089B (en) Construction method of buried depth monitoring instrument poreforming and anchorage cable poreforming under unfavorable geological condition
CN102605775B (en) Combination pile of flexible pile and rigid pile concentrically arranged at upper end and lower end and pile forming method
CN206812212U (en) A kind of construction concreting agitator
CN101487251A (en) Construction method of premixing pouring soil cement pile used for strengthening ground and pile produced thereby
CN210282725U (en) Lime stabilized soil mixture device
CN108086915A (en) A kind of major diameter jet mixing drill bit
CN205100208U (en) Crowded, reaming reinforced concrete bored concrete pile composite pile of high water spray earth anger
JP2015105522A (en) Ground improvement method
CN103306278A (en) Method for processing soft soil foundation with environment-friendly light pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant