CN102691507B - Integrated fast construction method for shield machine - Google Patents

Integrated fast construction method for shield machine Download PDF

Info

Publication number
CN102691507B
CN102691507B CN201210170508.7A CN201210170508A CN102691507B CN 102691507 B CN102691507 B CN 102691507B CN 201210170508 A CN201210170508 A CN 201210170508A CN 102691507 B CN102691507 B CN 102691507B
Authority
CN
China
Prior art keywords
construction
shield machine
jurisdiction
construction place
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210170508.7A
Other languages
Chinese (zh)
Other versions
CN102691507A (en
Inventor
赖伟文
钟志全
黄壮鹏
郭清华
黎向平
刘糖果
王家星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Hua Qiao construction group Limited by Share Ltd
Original Assignee
China Tunnel Construction Co ltd Guangdong
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tunnel Construction Co ltd Guangdong filed Critical China Tunnel Construction Co ltd Guangdong
Priority to CN201210170508.7A priority Critical patent/CN102691507B/en
Publication of CN102691507A publication Critical patent/CN102691507A/en
Application granted granted Critical
Publication of CN102691507B publication Critical patent/CN102691507B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses an integrated fast construction method for a shield machine. According to the method, plain concrete is laid between a target construction position and a start construction position, so that after construction reaches the target construction position, the shield machine can conduct continuous excavation on the plain concrete till arriving the start construction position at the other end. The method has the advantages that the transit construction period of the shield machine can be shortened effectively; and the construction risk can be reduced. The method is applied to the field of building construction.

Description

A kind of method of shield machine integration rapid construction
Technical field
The present invention relates to a kind of construction techniques, particularly relate to a kind of rapid constructing method of shield machine.
Background technology
Because transit tunnel in subway work circuit and station can alternately occur at interval, or centre, tunnel is provided with ventilating shaft, electric power well etc., therefore during shield-tunneling construction, often has shield structure to miss the stop this link of constructing.And technique on shield machine's station-crossing execute man-hour requirement experience get to the station, by station and the operations such as driving that again start.Arrive in traditional shield construction method, three operation continuitys of missing the stop and start are not strong, namely need behind arrival station first shield body and chassis to be decomposed, then translation or handling, to originating terminal, are again started after then re-assemblying and constructed respectively.
Above traditional construction method has following shortcoming: (1), shield machine must be disassembled, re-assembly, and shield driving can be made to interrupt, have impact on the continuity of construction, drag the slow duration simultaneously; (2), need to employ large-scale facility such as reception bracket, reaction frame etc. in the process disassembling, re-assembly shield machine, its construction cost is high; (3), many, the complex process of the operation disassembling assembling process of shield machine, security risk is higher; (4), shield machine arrive time, owing to lacking counter-force, pipe sheet assembling is second-rate, often have percolating water phenomenon occur.
Summary of the invention
For solving the problem, the invention provides a kind of rapid constructing method that effectively can shorten the technique on shield machine's station-crossing construction period.
The technical solution adopted for the present invention to solve the technical problems is:
A method for shield machine integration rapid construction, is characterized in that, comprise the following steps:
1) in arrival construction place and construction place of starting, portal curtain plate is installed respectively;
2) between the portal curtain plate arriving construction place and construction place of starting, plain concrete is laid;
3) shield machine is through the portal arriving construction place, cuts described plain concrete, until shield machine arrives construction place of starting;
4) in arrival construction place and the laying section of jurisdiction, plain concrete place of having carried out between construction place cutting of starting, and carry out section of jurisdiction at section of jurisdiction underfill slurries and fix.
Be further used as the improvement of technical solution of the present invention, the route advanced along shield machine in section of jurisdiction is laid.
Be further used as the improvement of technical solution of the present invention, the route advanced along described shield machine is equipped with domain section of jurisdiction and semi-ring section of jurisdiction, is equipped with five semi-ring sections of jurisdiction between two adjacent domain sections of jurisdiction.
Be further used as the improvement of technical solution of the present invention, after section of jurisdiction has been laid, carry out section of jurisdiction at section of jurisdiction underfill slurries and fix.
Beneficial effect of the present invention: the method for this rapid construction is in arrival construction place and start between construction place and be equipped with plain concrete, thus can directly tunnel continuously on plain concrete after arriving construction place at shield machine construction, until arrive construction place of starting of the other end, this construction method effectively can shorten the duration of technique on shield machine's station-crossing construction, and reduces construction risk.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, the invention will be further described:
Fig. 1 is shield machine Construction State schematic diagram on plain concrete in the embodiment of the present invention.
Detailed description of the invention
With reference to Fig. 1, the present invention is the method for a kind of shield machine integration rapid construction, it is characterized in that, comprises the following steps:
1) in arrival construction place and construction place of starting, portal curtain plate is installed respectively;
2) between the portal curtain plate arriving construction place and construction place of starting, plain concrete is laid;
3) shield machine is through the portal arriving construction place, cuts described plain concrete, until shield machine arrives construction place of starting;
4) in arrival construction place and the laying section of jurisdiction, plain concrete place of having carried out between construction place cutting of starting, and carry out section of jurisdiction in section of jurisdiction underfill dual slurry and fix.
The method of this rapid construction is in arrival construction place and start between construction place and be equipped with plain concrete, thus can directly tunnel continuously on plain concrete after arriving construction place at shield machine construction, until arrive construction place of starting of the other end, this construction method effectively can shorten the duration of technique on shield machine's station-crossing construction, this construction method not only reduces the input to auxiliary equipment and material, simultaneously it is simple to operate and construction cost is low, also can better ensure construction safety, and reduce construction risk.
As the preferred embodiment of the present invention, the intensity of the plain concrete laid within the scope of cutter head of shield machine cutting between the portal curtain plate arriving construction place and construction place of starting is C15.
Concordant with railway roadbed design height at the height arriving the plain concrete laid between the portal curtain plate of construction place and construction place of starting, driving counter-force can be provided to the bottom of shield machine in shield machine progradation, follow-up construction of laying a railway track can be facilitated again.
The intensity of the plain concrete within the scope of cutter head of shield machine cutting is C15, can the cutter of available protecting shield machine, in case concrete strength is too large, causes damaging cutter in shield machine tunneling process.
As the preferred embodiment of the present invention, the route advanced along shield machine in section of jurisdiction is laid.
As the preferred embodiment of the present invention, after section of jurisdiction has been laid, carry out section of jurisdiction at section of jurisdiction underfill slurries and fix.
As the preferred embodiment of the present invention, the route advanced along described shield machine is equipped with domain section of jurisdiction and semi-ring section of jurisdiction, is equipped with five semi-ring sections of jurisdiction between two adjacent domain sections of jurisdiction.
Certainly, the invention is not limited to above-mentioned embodiment, those of ordinary skill in the art also can make equivalent variations or replacement under the prerequisite without prejudice to spirit of the present invention, and these equivalent modification or replacement are all included in the application's claim limited range.

Claims (1)

1. a method for shield machine integration rapid construction, is characterized in that, comprise the following steps:
1), in arrival construction place and construction place of starting, portal curtain plate is installed respectively;
2), between the portal curtain plate arriving construction place and construction place of starting, plain concrete is laid;
3), shield machine through arriving the portal of construction place, cut described plain concrete, until shield machine arrives construction place of starting;
4), in described arrival construction place and the laying section of jurisdiction, plain concrete place of having carried out between construction place cutting of starting, the route advanced along shield machine in described section of jurisdiction is laid, the route advanced along described shield machine is equipped with domain section of jurisdiction and semi-ring section of jurisdiction, be equipped with five semi-ring sections of jurisdiction between two adjacent domain sections of jurisdiction, and carry out section of jurisdiction at section of jurisdiction underfill slurries and fix.
CN201210170508.7A 2012-05-28 2012-05-28 Integrated fast construction method for shield machine Active CN102691507B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210170508.7A CN102691507B (en) 2012-05-28 2012-05-28 Integrated fast construction method for shield machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210170508.7A CN102691507B (en) 2012-05-28 2012-05-28 Integrated fast construction method for shield machine

Publications (2)

Publication Number Publication Date
CN102691507A CN102691507A (en) 2012-09-26
CN102691507B true CN102691507B (en) 2015-02-04

Family

ID=46857225

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210170508.7A Active CN102691507B (en) 2012-05-28 2012-05-28 Integrated fast construction method for shield machine

Country Status (1)

Country Link
CN (1) CN102691507B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104088646B (en) * 2014-04-11 2016-02-24 中国水利水电第十一工程局有限公司 A kind of construction method of shape of a hoof open type shield machine
CN108756903A (en) * 2018-06-01 2018-11-06 中铁二局集团有限公司 A kind of shield machine crosses the construction method of well

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2794797B1 (en) * 1999-06-09 2001-09-07 Entpr Quillery & Cie METHOD OF IMPLEMENTING A TUNNEL
CN101603426A (en) * 2009-07-08 2009-12-16 广东华隧建设股份有限公司 The job practices that soft stratum is reinforced in a kind of shield-tunneling construction
CN101608551A (en) * 2009-06-15 2009-12-23 广东华隧建设股份有限公司 The job practices of a kind of shield machine closed origin and arrival
CN102022119A (en) * 2010-12-15 2011-04-20 广东华隧建设股份有限公司 Shield machine balance originating method
CN102425427A (en) * 2011-12-30 2012-04-25 中铁二局股份有限公司 Method for constructing tunnel by utilizing shield empty-pushing crossing mine method
CN102425433A (en) * 2011-12-30 2012-04-25 中铁一局集团有限公司 Minus-ring-free originating construction method for constructing sectional shield tunnel

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2794797B1 (en) * 1999-06-09 2001-09-07 Entpr Quillery & Cie METHOD OF IMPLEMENTING A TUNNEL
CN101608551A (en) * 2009-06-15 2009-12-23 广东华隧建设股份有限公司 The job practices of a kind of shield machine closed origin and arrival
CN101603426A (en) * 2009-07-08 2009-12-16 广东华隧建设股份有限公司 The job practices that soft stratum is reinforced in a kind of shield-tunneling construction
CN102022119A (en) * 2010-12-15 2011-04-20 广东华隧建设股份有限公司 Shield machine balance originating method
CN102425427A (en) * 2011-12-30 2012-04-25 中铁二局股份有限公司 Method for constructing tunnel by utilizing shield empty-pushing crossing mine method
CN102425433A (en) * 2011-12-30 2012-04-25 中铁一局集团有限公司 Minus-ring-free originating construction method for constructing sectional shield tunnel

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
盾构过站施工新技术;李奕等;《建筑机械化》;20070530;第32-34页 *
盾构隧道底部注浆加固技术;朱相乾等;《建筑机械化》;20080530;第53-55页 *

Also Published As

Publication number Publication date
CN102691507A (en) 2012-09-26

Similar Documents

Publication Publication Date Title
CN104821531B (en) Deicing apparatus of power transmission line
CN204419190U (en) A kind of shield machine of variable diameter
CN102691507B (en) Integrated fast construction method for shield machine
CN205990920U (en) A kind of tunnel inverted arch self-propelled trestle
CN104314577B (en) Shield machine assembly and disassembly methods in tunnel
CN106321142A (en) Rock cross-cut coal uncovering method combining microwave-assisted extraction with grouting reinforcement
CN103982194A (en) Method for barrier-free starting of shield tunneling machine
CN104141497B (en) A kind of shield machine translation tune reaction frame installation method that starts
CN202428560U (en) Infrared full-automatic type edge trimming machine
CN204352421U (en) Portable fire prevention sandbox
CN103032072A (en) Method for disassembling, lifting and transferring closed type station shield to transferring line to be hoisted out
CN203655316U (en) Top isolating device for coal mine filling bracket
CN105569328A (en) Concealed tie member for external scaffold of curtain wall engineering and construction technology of concealed tie member
CN201599041U (en) Synchronous slip casting device for shielding machine
CN204457797U (en) A kind of top longitudinal beam structure of subway station
CN103693360B (en) A kind of fortune brick device
CN103899312A (en) Right angle turn construction method of underwell T-shaped roadway
CN204156119U (en) A kind of novel grounded electrode structure
CN203866653U (en) Iron tapping flatcar rail intersection rail changing device
CN103317244B (en) Automatic gantry type reinforcing rib welding machine
CN103879411B (en) A kind of insulation system for screen door in rail transit and construction method thereof
CN203891893U (en) Barrier-free originating hole structure of shield machine
CN205452985U (en) Novel cable bearer
CN205856937U (en) A kind of translation turnout
CN205572736U (en) Can fixed marble cutter

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 510220 Guangdong city of Guangzhou province Haizhuqu District Yue Xuan Street No. 81 (G-3) 1501-1512, 1604-1607 room

Patentee after: Guangdong Hua Qiao construction group Limited by Share Ltd

Address before: 9, building 510620, industrial building, 101 Tianhe Road, Guangzhou, Guangdong, Tianhe District

Patentee before: China Tunnel Construction Co., Ltd. Guangdong

CP03 Change of name, title or address