CN102616652A - Front anchoring device for climbing crane - Google Patents
Front anchoring device for climbing crane Download PDFInfo
- Publication number
- CN102616652A CN102616652A CN2012100740312A CN201210074031A CN102616652A CN 102616652 A CN102616652 A CN 102616652A CN 2012100740312 A CN2012100740312 A CN 2012100740312A CN 201210074031 A CN201210074031 A CN 201210074031A CN 102616652 A CN102616652 A CN 102616652A
- Authority
- CN
- China
- Prior art keywords
- anchoring
- crane
- plates
- pulling
- sides
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Abstract
The invention discloses a front anchoring device for a climbing crane, which belongs to the field of cranes and particularly relates to a climbing crane for erecting steel-truss arch bridges. The front anchoring device comprises pre-mounted anchoring pulling plates, an anchoring box girder and pulling plate components, the two pre-mounted anchoring pulling plates are symmetrically arranged on two sides of a through shaft of a front walking and traction device, steel plates on two sides of the anchoring box girder are welded at corresponding positions of an arch bridge box girder when the climbing crane which climbs an arch reaches a working position, the pre-mounted anchoring pulling plates on the through shaft of the walking trolley are connected with the pulling plate components on the anchoring box girder by hinge pins in order to prevent the crane from downwards slipping along the arch after the crane stands, and the purposes of locking and anchoring are achieved. In addition, the stress condition of the through shaft of the walking trolley is fine, accordingly, the single-plate type pulling plates are only mounted on the two sides of the through shaft, a double-shearing structure is formed between each of two sides of the anchoring box girder and the corresponding pre-mounted anchoring pulling plate by the aid of the corresponding pulling plate component consisting of a pair of double plates, the hinge pins connected with the pulling plates are stressed well, and the front anchoring device is safer and more reliable.
Description
Technical field
A kind of anterior anchor fitting that is used for climbing crane of the present invention belongs to the hoisting crane field, and particularly steel truss arched bridge sets up and uses climbing crane.
Background technology
When steel truss arched bridge is set a roof beam in place and is set a roof beam in place on the steel braced arch with hoisting crane; For make hoisting crane on the ramp construction with the level land on the same convenient; Require the top bottom-disc of hoisting crane to keep horizontality with the vault slope change; And low bottom-disc and camber one sections level of incline, this structure can can't be carried out lifting operation like no failure-free anchor structure fixed crane because of overcoming sliding force when then the hoisting crane machine is worked.For making hoisting crane safe and reliable being fixed on the arched girder of when work, design a kind of simple in structurely, anchoring is convenient, and is safe, safeguards that simple anterior anchor fitting is just imperative.
Summary of the invention
Patent purpose of the present invention provides a kind of anterior anchor fitting that is used for climbing crane, safe and reliable being fixed on the arched girder in the time of can not only making hoisting crane work, and also this anterior anchor fitting is simple in structure, and anchoring is convenient.
Patented technology scheme of the present invention is following:
The anterior anchor fitting of the present invention; Form by prepackage anchoring arm-tie, anchoring case beam and arm-tie assembly; Pre-install anchoring arm-tie symmetric arrangement traveling forwardly and draw gear axis both sides for two; Anchoring case beam is fixed in the relevant position of arched girder case beam, and prepackage anchoring arm-tie connects with bearing pin through the arm-tie assembly with anchoring case beam.
Described arm-tie assembly is made up of a pair of pair of plate.
The anchoring that the anterior anchor fitting of patent of the present invention is used for climbing crane when on arched girder, working.Climb arch when reaching control position at climbing crane, anchoring case beam both sides steel plate is welded on the relevant position of arched girder case beam.For preventing to glide along arch behind the hoisting crane erect-position,, play the purpose of locking anchoring with linking up with bearing pin between the arm-tie assembly on arm-tie on the running truck axis and the anchoring case beam.Because running truck axis stressing conditions is good, so only the veneer arm-tie is installed in its both sides.The arm-tie assembly that adopts a pair of pair of plate to form between anchoring case beam both sides and the prepackage anchoring arm-tie forms the double shear structure, makes the bearing pin stressing conditions that connects arm-tie good, more safe and reliable.
Description of drawings
Fig. 1 climbing crane of the present invention is with anterior anchor fitting front view
Fig. 2 climbing crane of the present invention is with anterior anchor fitting birds-eye view
The specific embodiment
How combine accompanying drawing to further specify patent of the present invention implements at present:
The anchoring that the anterior anchor fitting of the present invention is used for climbing crane when on arched girder, working.Two prepackage anchoring arm-ties 3 are with the both sides of the axis 2 of the traveling forwardly of pivotally attached mode symmetric arrangement and draw gear 1, climb at climbing crane and encircle when reaching control position, anchoring case beam 5 both sides steel plates are welded on the relevant position of arched girder case beam 6.For preventing behind the hoisting crane erect-position along arch along gliding, the arm-tie assembly 4 usefulness bearing pins 7 that the arm-tie 3 and the steel plate on the anchoring case beam 5 of axis 2 both sides of anterior traveling and draw gear 1 are formed through a pair of pair of plate link up, and reach the purpose that locks anchoring.Implement relevant operation after the locking anchoring again.
Claims (2)
1. anterior anchor fitting that is used for climbing crane; Form by prepackage anchoring arm-tie, anchoring case beam and arm-tie assembly; It is characterized in that two prepackage anchoring arm-tie symmetric arrangement travelings forwardly and draw gear axis both sides; Anchoring case beam is fixed in the relevant position of arched girder case beam, and prepackage anchoring arm-tie connects with bearing pin through the arm-tie assembly with anchoring case beam.
2. a kind of anterior anchor fitting that is used for climbing crane according to claim 1 is characterized in that the arm-tie assembly is made up of a pair of pair of plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100740312A CN102616652A (en) | 2012-03-20 | 2012-03-20 | Front anchoring device for climbing crane |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100740312A CN102616652A (en) | 2012-03-20 | 2012-03-20 | Front anchoring device for climbing crane |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102616652A true CN102616652A (en) | 2012-08-01 |
Family
ID=46556943
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012100740312A Pending CN102616652A (en) | 2012-03-20 | 2012-03-20 | Front anchoring device for climbing crane |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102616652A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103145035A (en) * | 2013-03-27 | 2013-06-12 | 中联重科股份有限公司 | Walking trolley anchor device and tower crane with same |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001193005A (en) * | 2000-01-13 | 2001-07-17 | Shimizu Corp | Method and apparatus for erecting column member and beam member |
CN2712878Y (en) * | 2004-04-12 | 2005-07-27 | 中铁大桥局集团武汉桥机有限公司 | Crane capable of hoisting materials on the inclined ramp |
CN201485194U (en) * | 2009-07-22 | 2010-05-26 | 秦皇岛天业通联重工股份有限公司 | 60T walking type full-swing erecting crane |
CN201843081U (en) * | 2010-11-03 | 2011-05-25 | 中铁六局集团有限公司 | Flexible leg anchoring device of bridge girder erection machine with single nose girder |
CN202508770U (en) * | 2012-03-20 | 2012-10-31 | 武桥重工集团股份有限公司 | Front portion anchoring device used for climbing crane |
-
2012
- 2012-03-20 CN CN2012100740312A patent/CN102616652A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001193005A (en) * | 2000-01-13 | 2001-07-17 | Shimizu Corp | Method and apparatus for erecting column member and beam member |
CN2712878Y (en) * | 2004-04-12 | 2005-07-27 | 中铁大桥局集团武汉桥机有限公司 | Crane capable of hoisting materials on the inclined ramp |
CN201485194U (en) * | 2009-07-22 | 2010-05-26 | 秦皇岛天业通联重工股份有限公司 | 60T walking type full-swing erecting crane |
CN201843081U (en) * | 2010-11-03 | 2011-05-25 | 中铁六局集团有限公司 | Flexible leg anchoring device of bridge girder erection machine with single nose girder |
CN202508770U (en) * | 2012-03-20 | 2012-10-31 | 武桥重工集团股份有限公司 | Front portion anchoring device used for climbing crane |
Non-Patent Citations (3)
Title |
---|
徐孝有: "《BWQ-35型爬坡式架梁起重机》", 《起重运输机械》, no. 6, 30 June 2006 (2006-06-30), pages 31 - 33 * |
许俊: "《一种可以全回转工作的拱上架梁起重机》", 《科协论坛(下半月)》, no. 3, 31 March 2009 (2009-03-31), pages 57 - 58 * |
鄢怀斌: "《BWQ35型变坡式架梁起重机》", 《桥梁建设》, 31 December 2005 (2005-12-31), pages 124 - 126 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103145035A (en) * | 2013-03-27 | 2013-06-12 | 中联重科股份有限公司 | Walking trolley anchor device and tower crane with same |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202936736U (en) | Cable-stayed bridge composite beam construction bridge floor crane | |
EP2497740A1 (en) | Movable rear counterweight device for crawler crane | |
CN103381997A (en) | Tower crane | |
CN203255892U (en) | Heightened gantry type crane | |
CN103061521A (en) | Torque type mounting method for cantilever steel truss of large stadium | |
CN202508770U (en) | Front portion anchoring device used for climbing crane | |
CN103541300B (en) | Based on the construction method of the railway concrete continuous beam that flat stacking is implemented | |
CN204625045U (en) | A kind of steel structure hoisting door shaped stent formula hanging apparatus | |
CN106677378A (en) | Controllable slippage node for fabricated prefabricated externally-hung wall body | |
CN102616652A (en) | Front anchoring device for climbing crane | |
CN204385883U (en) | A kind of Fabricated balcony | |
CN203486756U (en) | Lifting tool suitable for I-shaped steel | |
CN104495653A (en) | Multifunctional large-tonnage beam erecting crane and beam erecting method | |
CN104109997B (en) | A kind of multi-state bridge inspection vehicle | |
CN201793332U (en) | Slope climbing machine used for steel truss arch bridge construction | |
CN105625198A (en) | Reinforced rigid-framed arch bridge | |
CN204917761U (en) | Just two -way climbing formula of purlin arched bridge hoist of setting a roof beam in place | |
CN204690594U (en) | A kind of simple and easy door frame of the Slidable for the installation of framing type steel box-girder crossbeam | |
CN203795885U (en) | Tower-type large-height-building demolition machine | |
CN103359634A (en) | Tower crane annular jacking crossbeam device | |
CN206553111U (en) | One kind balance arm brace installs auxiliary body | |
CN204728191U (en) | A kind of portable steel slab bridge | |
CN204728190U (en) | A kind of portable steel bridge | |
CN206267037U (en) | Reversely hung Yong is trapezoidal tiltedly to climb Hanging Basket | |
CN204959602U (en) | Bridge panel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |