CN102611036A - 间距可调式横担固定器 - Google Patents

间距可调式横担固定器 Download PDF

Info

Publication number
CN102611036A
CN102611036A CN2012100682745A CN201210068274A CN102611036A CN 102611036 A CN102611036 A CN 102611036A CN 2012100682745 A CN2012100682745 A CN 2012100682745A CN 201210068274 A CN201210068274 A CN 201210068274A CN 102611036 A CN102611036 A CN 102611036A
Authority
CN
China
Prior art keywords
risers
riser
spacing
vertical plates
length direction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012100682745A
Other languages
English (en)
Other versions
CN102611036B (zh
Inventor
邓善辉
康长波
吴燎原
黄元龙
刘松波
张大成
骆明章
陈慕福
谢伟峰
黄春林
蔡江河
李晓榕
裴光燚
吕云生
吴长翔
梁鑫海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Sanming Power Supply Co of State Grid Fujian Electric Power Co Ltd
Original Assignee
Sanming Power Supply Co of State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sanming Power Supply Co of State Grid Fujian Electric Power Co Ltd filed Critical Sanming Power Supply Co of State Grid Fujian Electric Power Co Ltd
Priority to CN201210068274.5A priority Critical patent/CN102611036B/zh
Publication of CN102611036A publication Critical patent/CN102611036A/zh
Application granted granted Critical
Publication of CN102611036B publication Critical patent/CN102611036B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)
  • Insulators (AREA)

Abstract

本发明公开了一种间距可调式横担固定器,包括有两条并列设置的立板,平面双轨滑板,平面双轨滑板为一种槽状体,其卡在两并列设置的两立板的上沿并可沿着横板的长度方向来回移动,在两立板的两端部设置有两限位装置,在两立板上还设置有两个定位凸台,两定位凸台支撑于两立板之间并可相对两立板的长度方向移动的固定于立板上,在两立板的中部还设置有中心点支撑件,该支撑件支撑于两立板之间并伸出于两立板的下沿,在中心点支撑件伸出于立板的下沿处设置有通孔。本发明的间距可调式新型横担固定器具有拆装简便、操作灵活、工作效率高且安全系数大的优点,实现了地电位带电更换220kVSZ型铁塔直线双串绝缘子的目的。

Description

间距可调式横担固定器
技术领域
               本发明涉及一种横担固定器,特别是一种间距可调式横担固定器。
 
背景技术
近年来,随着输电线路设计标准的进一步提高,输电线路杆塔结构形式更加多样化,由生产厂家定型生产的带电更换220kV直线绝缘子横担固定器无法适用于SZ型铁塔直线双串绝缘子的带电更换作业,从而影响输电设备的带电作业率及可靠性。
发明内容
本发明的目的在于克服现有技术的不足之处,而提供一种可适用于地电位带电更换SZ型铁塔直线双串绝缘子的间距可调式横担固定器。
一种间距可调式横担固定器,其结构要点在于:包括有两条并列设置的立板,两个用于固定承力丝杆装置的平面双轨滑板,所述的平面双轨滑板为一种槽状体,其卡在两并列设置的两立板的上沿并可沿着横板的长度方向来回移动,在平面双轨滑板的槽底面上设置有贯通槽底的以供承力丝杆装置中的丝杆穿过的通孔,在两立板的两端部设置有两限位装置以防止平面双轨滑板滑出立板,在两立板上还设置有两个用于将本间距可调式横担固定器在铁塔横担平面上定位的定位凸台,两定位凸台支撑于两立板之间并可相对两立板的长度方向移动的固定于立板上,两定位凸台凸出于立板的下沿,在两立板的中部还设置有中心点支撑件,该支撑件支撑于两立板之间并伸出于两立板的下沿,在中心点支撑件伸出于立板的下沿处设置有通孔,在通孔处设置有可将该间距可调式横担固定器固定于铁塔横担上的螺纹连接件。
这种结构的间距可调式横担固定器,利用可相对两立板的长度方向移动的定位凸台,就可根据铁塔横担平面宽度,任意调整两定位凸台之间的间距以适应铁塔横担平面。
在工作时,根据铁塔横担平面宽度,将两定位凸台组装在两立板之间,而后将组装好的间距可调式横担固定器安放在铁塔横担平面上,调整中心点支撑件通孔与铁塔横担角钢间隙处的螺栓孔洞对齐,并用螺纹连接件将间距可调式横担固定器固定在铁塔横担平面上;承力丝杆装置中的丝杆通过平面双轨滑板水平安放在间距可调式横担固定器两侧,根据受力情况调整平面双轨滑板,使承力丝杆受力均衡,通过收紧承力丝杆提升导线,达到使绝缘子松弛,从而实现地电位带电更换直线双串绝缘子的目的。
两定位凸台可相对两立板实现长度方向移动或为在立板上设置有沿着立板的长度方向延伸的长槽,而后将定位凸台通过螺纹连接件将其锁于长槽上。
两定位凸台可相对两立板实现长度方向移动或为在立板上设置有沿着立板长度方向排列的多个的通孔,而后将定位凸台通过螺纹连接件锁于不同的通孔上。
所述的立板两端部的限位装置为在立板的两端部设置有横穿两立板的限位螺杆。
综上所述的,本发明相比现有技术如下优点:
本发明的间距可调式新型横担固定器具有拆装简便、操作灵活、工作效率高且安全系数大的优点,实现了地电位带电更换220kV SZ型铁塔直线双串绝缘子的目的。 
 
附图说明
   图1是间距可调式新型横担固定器总装图。
图2是间距可调式新型横担固定器主视图。
图3是间距可调式新型横担固定器俯视图。
标号说明 1立板  2中心点支撑件  3定位凸台  4平面双轨滑板  5限位螺杆  6穿心螺栓 7固定螺栓 8承力丝杆  10角钢  11绝缘子串  12导线。
具体实施方式
下面结合实施例对本发明进行更详细的描述。
实施例1 
一种如图1-3所示的间距可调式横担固定器,包括有两条并列设置的立板1,两个用于固定承力丝杆装置的平面双轨滑板4,所述的平面双轨滑板为一种槽状体,其卡在两并列设置的两立板的上沿并可沿着立板的长度方向来回移动,在平面双轨滑板的槽底面上设置有贯通槽底的以供承力丝杆装置中的承力丝杆8穿过的通孔,在两立板的两端部设置有两限位装置以防止平面双轨滑板滑出立板,在两立板上还设置有两个用于将本间距可调式横担固定器在铁塔横担平面上定位的定位凸台3,两定位凸台支撑于两立板之间并可相对两立板的长度方向移动的固定于立板上,两定位凸台凸出于立板的下沿,在两立板的中部还设置有中心点支撑件2,该支撑件支撑于两立板之间并伸出于两立板的下沿,在中心点支撑件伸出于立板的下沿处设置有通孔,在通孔处设置有可将该间距可调式横担固定器固定于铁塔横担上的螺纹连接件—穿心螺栓6。两定位凸台可相对两立板实现长度方向移动或为在立板上设置有沿着立板的长度方向延伸的长槽,而后将定位凸台通过固定螺栓7将其锁于长槽上。所述的立板两端部的限位装置为在立板的两端部设置有横穿两立板的限位螺杆5。
在作业前,作业人员可根据铁塔横担平面宽度,将定位凸台3组装在立板1上,而后将组装好的间距可调式横担固定器安放在铁塔横担平面上,调整中心点支撑件3穿心螺栓孔洞与铁塔横担角钢10间隙处的螺栓孔洞对齐,并用螺栓将间距可调式横担固定器固定在铁塔横担平面上;承力丝杆8通过平面双轨滑板4水平安放在间距可调式横担固定器两侧立板上,根据受力情况调整平面双轨滑板,使承力丝杆受力均衡,实际操作中,作业人员收紧承力丝杆8提升导线12,使绝缘子串11松弛,实现地电位带电更换220kVSZ型铁塔双串直线绝缘子11的目的。
本实施例未述部分与现有技术相同。

Claims (4)

1.一种间距可调式横担固定器,其特征在于:包括有两条并列设置的立板,两个用于固定承力丝杆装置的平面双轨滑板,所述的平面双轨滑板为一种槽状体,其卡在两并列设置的两立板的上沿并可沿着横板的长度方向来回移动,在平面双轨滑板的槽底面上设置有贯通槽底的以供承力丝杆装置中的丝杆穿过的通孔,在两立板的两端部设置有两限位装置以防止平面双轨滑板滑出立板,在两立板上还设置有两个用于将本间距可调式横担固定器在铁塔横担平面上定位的定位凸台,两定位凸台支撑于两立板之间并可相对两立板的长度方向移动的固定于立板上,两定位凸台凸出于立板的下沿,在两立板的中部还设置有中心点支撑件,该支撑件支撑于两立板之间并伸出于两立板的下沿,在中心点支撑件伸出于立板的下沿处设置有通孔,在通孔处设置有可将该间距可调式横担固定器固定于铁塔横担上的螺纹连接件。
2.根据权利要求1所述的间距可调式横担固定器,其特征在于:两定位凸台可相对两立板实现长度方向移动或为在立板上设置有沿着立板的长度方向延伸的长槽,而后将定位凸台通过螺纹连接件将其锁于长槽上。
3.根据权利要求2所述的间距可调式横担固定器,其特征在于:两定位凸台可相对两立板实现长度方向移动或为在立板上设置有沿着立板长度方向排列的多个的通孔,而后将定位凸台通过螺纹连接件锁于不同的通孔上。
4.根据权利要求2或3所述的间距可调式横担固定器,其特征在于:所述的立板两端部的限位装置为在立板的两端部设置有横穿两立板的限位螺杆。
CN201210068274.5A 2012-03-15 2012-03-15 间距可调式横担固定器 Active CN102611036B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210068274.5A CN102611036B (zh) 2012-03-15 2012-03-15 间距可调式横担固定器

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210068274.5A CN102611036B (zh) 2012-03-15 2012-03-15 间距可调式横担固定器

Publications (2)

Publication Number Publication Date
CN102611036A true CN102611036A (zh) 2012-07-25
CN102611036B CN102611036B (zh) 2016-08-24

Family

ID=46528262

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210068274.5A Active CN102611036B (zh) 2012-03-15 2012-03-15 间距可调式横担固定器

Country Status (1)

Country Link
CN (1) CN102611036B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103928867A (zh) * 2014-04-24 2014-07-16 国家电网公司 220kV线路钢管杆带电更换直线绝缘子所用双吊点杆头卡具
CN106495060A (zh) * 2016-10-21 2017-03-15 广东电网有限责任公司珠海供电局 辅助更换器具
CN109596946A (zh) * 2018-12-04 2019-04-09 国网天津市电力公司电力科学研究院 一种500kV普通型复合绝缘子双串悬挂方式试验方法
CN109787134A (zh) * 2018-11-26 2019-05-21 许继集团有限公司 移动式变电站及其进线装置

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201435594Y (zh) * 2009-05-12 2010-03-31 聂新华 避雷线提升器
CN201584671U (zh) * 2009-12-03 2010-09-15 保定供电公司 花梁架构用防坠器固定支架
CN201834664U (zh) * 2010-10-18 2011-05-18 广西玉柴机器股份有限公司 一种可调吊距横担发动机吊具
CN102097763A (zh) * 2009-12-14 2011-06-15 山西省电力公司晋中供电分公司 架空地线提线器
CN102231492A (zh) * 2011-04-20 2011-11-02 福建省电力有限公司福州电业局 多功能悬垂绝缘子串横担侧金具更换卡具
CN102237655A (zh) * 2011-07-05 2011-11-09 河南省电力公司洛阳供电公司 一种架空地线的提线方法及提线工具
CN202121254U (zh) * 2011-05-24 2012-01-18 福建省电力有限公司漳州电业局 双分裂双悬垂绝缘子串架设杆塔的横担侧边卡具
CN202550397U (zh) * 2012-03-15 2012-11-21 福建省电力有限公司三明电业局 间距可调式横担固定器
US8662550B2 (en) * 2007-12-24 2014-03-04 Haverfield International Incorporated Method of replacing insulators on a tower and insulator support and transport assembly therefor

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8662550B2 (en) * 2007-12-24 2014-03-04 Haverfield International Incorporated Method of replacing insulators on a tower and insulator support and transport assembly therefor
CN201435594Y (zh) * 2009-05-12 2010-03-31 聂新华 避雷线提升器
CN201584671U (zh) * 2009-12-03 2010-09-15 保定供电公司 花梁架构用防坠器固定支架
CN102097763A (zh) * 2009-12-14 2011-06-15 山西省电力公司晋中供电分公司 架空地线提线器
CN201834664U (zh) * 2010-10-18 2011-05-18 广西玉柴机器股份有限公司 一种可调吊距横担发动机吊具
CN102231492A (zh) * 2011-04-20 2011-11-02 福建省电力有限公司福州电业局 多功能悬垂绝缘子串横担侧金具更换卡具
CN202121254U (zh) * 2011-05-24 2012-01-18 福建省电力有限公司漳州电业局 双分裂双悬垂绝缘子串架设杆塔的横担侧边卡具
CN102237655A (zh) * 2011-07-05 2011-11-09 河南省电力公司洛阳供电公司 一种架空地线的提线方法及提线工具
CN202550397U (zh) * 2012-03-15 2012-11-21 福建省电力有限公司三明电业局 间距可调式横担固定器

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103928867A (zh) * 2014-04-24 2014-07-16 国家电网公司 220kV线路钢管杆带电更换直线绝缘子所用双吊点杆头卡具
CN106495060A (zh) * 2016-10-21 2017-03-15 广东电网有限责任公司珠海供电局 辅助更换器具
CN109787134A (zh) * 2018-11-26 2019-05-21 许继集团有限公司 移动式变电站及其进线装置
CN109787134B (zh) * 2018-11-26 2024-01-09 许继集团有限公司 移动式变电站及其进线装置
CN109596946A (zh) * 2018-12-04 2019-04-09 国网天津市电力公司电力科学研究院 一种500kV普通型复合绝缘子双串悬挂方式试验方法
CN109596946B (zh) * 2018-12-04 2021-01-19 国网天津市电力公司电力科学研究院 一种500kV普通型复合绝缘子双串悬挂方式试验方法

Also Published As

Publication number Publication date
CN102611036B (zh) 2016-08-24

Similar Documents

Publication Publication Date Title
CN102611036A (zh) 间距可调式横担固定器
CN204167789U (zh) 一种特高压输电线路的多联耐张绝缘子串检修用平梯
CN104201613B (zh) 远端操作更换直线单串绝缘子的装置及其应用方法
CN202268671U (zh) 一种架空电力输电线路可位移悬垂串
CN102944408B (zh) 锚链拉力试验机推链装置
CN202550397U (zh) 间距可调式横担固定器
CN102163824B (zh) 带电更换t型挂点悬垂绝缘子作业工具及其作业方法
CN102227062B (zh) 带电更换吊环式挂点悬垂式绝缘子串作业工具及其作业方法
CN203398639U (zh) 架空地线防振锤跑位追回器
CN103996469A (zh) 一种复合绝缘子一次成型压接装置
CN204558683U (zh) 一种并沟线夹
CN203967645U (zh) 并沟线夹装卸器
CN103272882B (zh) 用于工字轮收线机的滑道组件
CN103500961B (zh) 一种带电更换耐张绝缘子串专用工具
CN102623927B (zh) 带电更换220kV线路多回路双分裂导线绝缘子工具和方法
CN104624750A (zh) 钢管折弯机
CN205159906U (zh) 特高压输电线路耐张串绝缘出线伸缩平梯
CN204144792U (zh) 远端操作更换直线单串绝缘子的装置
CN103606846B (zh) 一种带电更换绝缘子串作业用高强度绝缘绳支撑组件
CN202543737U (zh) 轨道安装定位调节装置
CN104078895A (zh) 并沟线夹装卸器
CN202217989U (zh) 安装杆塔可控避雷针底座连接支架装置
CN205123125U (zh) 一种双分裂导线固定平台
CN105257966A (zh) 输配电设备台架
CN203445517U (zh) 空气动力型盘型悬式玻璃绝缘子更换卡具

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
ASS Succession or assignment of patent right

Owner name: FUJIAN ELECTRIC POWER CO., LTD. FUJIAN PROVINCE EL

Effective date: 20121206

Owner name: STATE GRID CORPORATION OF CHINA

Free format text: FORMER OWNER: FUJIAN PROVINCE ELETRIC POWER CO., LTD. SANMING POWER SUPPLY BUREAU

Effective date: 20121206

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 365000 SANMING, FUJIAN PROVINCE TO: 100031 XICHENG, BEIJING

TA01 Transfer of patent application right

Effective date of registration: 20121206

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant after: State Grid Corporation of China

Applicant after: Fujian Electric Power Co., Ltd.

Applicant after: Sanming Electricity Bureau of Fujian Electric Power Co., Ltd.

Address before: Fujian 365000 Sanming City province Meliet District listed Street No. 1032

Applicant before: Sanming Electricity Bureau of Fujian Electric Power Co., Ltd.

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant