CN102561688A - 台风地区高、大跨度异形拉索幕墙的施工方法 - Google Patents

台风地区高、大跨度异形拉索幕墙的施工方法 Download PDF

Info

Publication number
CN102561688A
CN102561688A CN2010106235040A CN201010623504A CN102561688A CN 102561688 A CN102561688 A CN 102561688A CN 2010106235040 A CN2010106235040 A CN 2010106235040A CN 201010623504 A CN201010623504 A CN 201010623504A CN 102561688 A CN102561688 A CN 102561688A
Authority
CN
China
Prior art keywords
curtain wall
drag
installing
large span
line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2010106235040A
Other languages
English (en)
Other versions
CN102561688B (zh
Inventor
吴耀勇
刘剑斌
董兆昆
陈自力
叶雄
谢庆
谭晓春
李科
刘斌
黄杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 2 Engineering Group Co Ltd
Decoration Engineering Co Ltd of China Railway No 2 Engineering Group Co Ltd
Original Assignee
China Railway Erju Co Ltd
Decoration Engineering Co Ltd of China Railway No 2 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Erju Co Ltd, Decoration Engineering Co Ltd of China Railway No 2 Engineering Group Co Ltd filed Critical China Railway Erju Co Ltd
Priority to CN201010623504.0A priority Critical patent/CN102561688B/zh
Publication of CN102561688A publication Critical patent/CN102561688A/zh
Application granted granted Critical
Publication of CN102561688B publication Critical patent/CN102561688B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

本发明公开了一种台风地区高、大跨度异形拉索幕墙的施工方法,按如下步骤进行:1)、测量放线;2)、钢桁架柱基座焊接;3)、钢桁架柱安装;4)、三角型桁架梁安装;5)、耳板安装;6)、拉索的安装;7)、拉索张拉;8)、夹具安装;9)、玻璃安装;10)、打胶;11)、清洗验收。本发明施工后的幕墙具有柔性结构体系、索网结构的特性,它主要适合台风、地震多发地区的建筑施工中。

Description

台风地区高、大跨度异形拉索幕墙的施工方法
技术领域
本发明涉及公共、民用建筑施工领域,特别涉及一种台风地区高、大跨度异形拉索幕墙的施工方法。
背景技术
随着国民经济和科学技术的迅速发展,人们对建筑物的艺术审美要求越来越高,建筑物功能更日趋完善,玻璃幕墙作为建筑物的时装,其类型和形式也不断创新,单层索网结构幕墙、单向拉索结构幕墙、双层呼吸式幕墙、光电幕墙等新型幕墙在工程上的应用便是例证。其中尤以单层索网结构幕墙、单向拉索结构幕墙以其高通透性更受建筑师和业主的青睐,目前,在国内和国外的一些建筑中得到应用,有些建筑也因为单索点支玻璃幕墙的存在使其成为一个经典。正在逐步在大型公共建筑、高档写字楼中广泛应用。
发明内容
本发明的主要目的是针对上述问题,提供一种柔性结构体系、索网结构的台风地区高、大跨度异形拉索幕墙的施工方法。
为了实现上述发明目的,本发明采用的技术方案如下:一种台风地区高、大跨度异形拉索幕墙的施工方法,按如下步骤进行:
1)、测量放线;
2)、钢桁架柱基座焊接;
3)、钢桁架柱安装;
4)、三角型桁架梁安装;
5)、耳板安装;
6)、拉索的安装;
7)、拉索张拉;
8)、夹具安装;
9)、玻璃安装;
10)、打胶;
11)、清洗验收。
所述步骤7的拉索张拉中,拉索预应力的施加应按照分级施加的原则进行:
第一次施加至目标力的50%,整体均化;
第二次施加至目标力的75%,整体均化;
第三次施加至目标力的100%,整体均化。
本发明是结合高跨度异形拉索幕墙体系施工,深入研究异型结构拉索的预应力张拉控制技术、拉索幕墙安装施工技术,确保施工的异形空间索网结构达到设计标准,满足建筑整体效果。
本发明的有益效果是:
(1)、本施工方法构建柔性结构体系(采用正交不锈钢拉索形成的受力体系),特别适合台风、地震多发地区,可以适应建筑立面丰富多彩的空间变化。
(2)、本施工方法构建索网结构(采用不锈钢拉索形成的受力结构,仿佛象一张正交的大方格网状结构),使建筑立面更通透、采光、节能。
附图说明
图1是本发明的施工流程图;
图2是本发明高跨度异形拉索幕墙轴测示意图;
图3是幕墙柱连接铰和支撑点示意图;
图2中,1为南立面单索点式玻璃幕墙,2为东立面单索点式玻璃幕墙,3为北立面单索点式玻璃幕墙,4为西立面单索点式玻璃幕墙;图3中,5为柱连接铰2,6为柱间支撑点1,7为柱间支撑点2,8为柱间支撑点3。
具体实施方式
下面结合具体实施方式对本发明的上述发明内容作进一步的详细描述。
但不应将此理解为本发明上述主题的范围仅限于下述实施例。在不脱离本发明上述技术思想情况下,根据本领域普通技术知识和惯用手段,做出各种替换和变更,均应包括在本发明的范围内。
如深圳北站作为深圳市交通建设的一项标志性工程,其中双向单索点式玻璃幕墙用于站房外围周圈,最大分格水平宽约27m、纵高约24m、幕墙总面积19000m2,是整个建筑的点睛之笔。无论是规模还是技术难度,在国内都尚属首例。
见图2、图3所示,高、大跨度异形拉索幕墙,主要由钢桁架柱、三角型桁架梁、钢桁架柱基座、耳板、不锈钢索具(拉索和不锈钢夹具)、Low-e10+12A+10钢化中空玻璃组成,由钢桁架柱、三角型桁架梁、钢桁架柱基座、耳板、不锈钢索具组合成索网结构,从外面几乎看不到索的存在,具有明快、简洁、轻巧、美观、通透、节能环保等特点。
见图1所示,一种台风地区高、大跨度异形拉索幕墙的施工方法,按如下步骤进行:
1)、测量放线,全站仪在9米层上定出钢桁架基座及上部屋盖下悬杆接口位置;
2)、钢桁架柱基座焊接,钢桁架柱基座直接焊接在H型钢梁上;
3)、钢桁架柱安装,钢桁架在工厂加工好后,在现场采取汽车吊分二段拼接安装在钢桁架柱基座上;
4)、三角型桁架梁安装,三角型桁架梁在工厂加工好后,采取汽车吊,分段焊接,三角型桁架梁安装在钢桁架柱上,三角型桁架梁下基座与钢桁架柱顶基座连接;
5)、耳板安装,耳板主要是焊接在钢桁架柱、三角型桁架梁、H型钢上用于挂拉索的受力结构;
6)、拉索的安装,根据每跨拉索的长度,在工厂定尺加工好,采用汽车吊安装;
7)、拉索张拉,拉索挂好后,根据设计值先竖后横的顺序,采用多组液压千斤顶原理的张拉工具,分三次张拉,张拉力在设计值5%正偏差范围内;
8)、夹具安装,张拉完后,在十字正交横竖索安装不锈钢夹具;
9)、玻璃安装,先在玻璃厂根据提供的尺寸下料单生产出不同规格的LOW-E中空玻璃,铺装安装通道,将玻璃用平板推车运至安装位置点,然后用采用电动葫芦吊装,将玻璃安装在预安装的位置;
10)、打胶;
11)、清洗验收。
高跨度异形拉索幕墙的张拉技术(关键工序):
1、拉索预应力的施加应按照分级施加的原则进行:
●第一次施加至目标力的50%,整体均化;
●第二次施加至目标力的75%,整体均化;
●第三次施加至目标力的100%,整体均化;
●均化的目的是保证各规格拉索力值符合设计要求、保证桁架柱两端的拉索力平衡;
索力加到目标力后再安装连接夹具、考虑到玻璃安装过程中拉索有沉降,夹具的调平过程应对照各节点玻璃重量加载进行。
2、任何情况下,后续施工的拉索作用力不可传递到已经安装的玻璃板块上。

Claims (2)

1.一种台风地区高、大跨度异形拉索幕墙的施工方法,其特征在于:按如下步骤进行:
1)、测量放线;
2)、钢桁架柱基座焊接;
3)、钢桁架柱安装;
4)、三角型桁架梁安装;
5)、耳板安装;
6)、拉索的安装;
7)、拉索张拉;
8)、夹具安装;
9)、玻璃安装;
10)、打胶;
11)、清洗验收。
2.根据权利要求1所述的台风地区高、大跨度异形拉索幕墙的施工方法,其特征在于:所述步骤7的拉索张拉中,拉索预应力的施加应按照分级施加的原则进行:
第一次施加至目标力的50%,整体均化;
第二次施加至目标力的75%,整体均化;
第三次施加至目标力的100%,整体均化。
CN201010623504.0A 2010-12-31 2010-12-31 台风地区高、大跨度异形拉索幕墙的施工方法 Active CN102561688B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010623504.0A CN102561688B (zh) 2010-12-31 2010-12-31 台风地区高、大跨度异形拉索幕墙的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010623504.0A CN102561688B (zh) 2010-12-31 2010-12-31 台风地区高、大跨度异形拉索幕墙的施工方法

Publications (2)

Publication Number Publication Date
CN102561688A true CN102561688A (zh) 2012-07-11
CN102561688B CN102561688B (zh) 2014-09-03

Family

ID=46408155

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010623504.0A Active CN102561688B (zh) 2010-12-31 2010-12-31 台风地区高、大跨度异形拉索幕墙的施工方法

Country Status (1)

Country Link
CN (1) CN102561688B (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103216105A (zh) * 2013-04-18 2013-07-24 成军 悬挑拉索式双曲玻璃幕墙施工方法
CN110158493A (zh) * 2019-06-26 2019-08-23 兰州有色冶金设计研究院有限公司 组合式抗风天幕及方法

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
俞建国等: "拉索点式幕墙的施工技术与质量控制", 《浙江建筑》 *
原波等: "河南艺术中心工程超高超大艺术墙玻璃幕墙施工技术应用", 《精品工程》 *
吉明军: "南京火车站点式玻璃幕墙拉索体系安装技术", 《江苏建材》 *
杜彦凯等: "柔性边界幕墙索网张拉施工方法研究", 《施工技术》 *
陆勇祺等: "拉索结构点支式玻璃幕墙质量控制要点分析", 《广西城镇建设》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103216105A (zh) * 2013-04-18 2013-07-24 成军 悬挑拉索式双曲玻璃幕墙施工方法
CN103216105B (zh) * 2013-04-18 2015-07-22 南通四建幕墙工程有限公司 悬挑拉索式双曲玻璃幕墙施工方法
CN110158493A (zh) * 2019-06-26 2019-08-23 兰州有色冶金设计研究院有限公司 组合式抗风天幕及方法

Also Published As

Publication number Publication date
CN102561688B (zh) 2014-09-03

Similar Documents

Publication Publication Date Title
CN105604334B (zh) 一种用于大跨度钢桁架整体安装的快速施工方法
CN108560719B (zh) 超大跨度双层双向悬索结构的支撑安装方法
CN103075017B (zh) 超大跨度筒壳网格结构施工方法
CN103982040B (zh) 一种超高层建筑施工竖向综合运输装置
CN103061412B (zh) 一种劲性支撑穹顶结构的施工方法
CN105926765B (zh) 倒伞状正多边形钢结构模块及其安装方法
CN201599040U (zh) 一种用于盾构隧道的预制管片
CN104695341A (zh) 一种用于加固大跨度连续梁桥的非自平衡张弦梁结构
CN109537729A (zh) 一种适用于单层双向正交索网的施工方法
CN105442839A (zh) 一种悬挑结构模板排架的搭设方法
CN106988229A (zh) 一种拱梁组合连续刚构桥扣挂支结合式施工装置及方法
CN104846747A (zh) 一种基于自平衡体系的自锚式悬索桥吊杆张拉工艺
CN203334664U (zh) 超长悬挑桁架结构高空模板支撑系统
CN107476581A (zh) 一种钢结构双层悬挑结构吊装安装方法
CN103883128A (zh) 一种多层大跨度钢结构安装方法
CN102561688B (zh) 台风地区高、大跨度异形拉索幕墙的施工方法
CN107268422A (zh) 一种等跨自锚式悬索‑拱梁协作体系桥梁
CN108104260B (zh) 装配式建筑悬挑构件施工方法
Charnish et al. The bow: unique diagrid structural system for a sustainable tall building
CN103628691A (zh) 大跨度悬挑桁架施工支撑工艺
CN209099833U (zh) 配电站及其gis配电装置室
CN114837483B (zh) 一种高低跨门式钢架建筑结构及其施工工艺
CN104652853B (zh) 快速起吊安装建筑结构
CN105464215A (zh) 一种无法设置竖向临时支撑的悬挂结构逆作法施工方法
CN209685096U (zh) 一种施工电梯附墙桁架辅助支架

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160111

Address after: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Patentee after: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

Address before: 610032, No. nine, No. 156, building B, Gao Xing Road, Chengdu hi tech Development Zone, Sichuan

Patentee before: China Railway Erju Co., Ltd.

Patentee before: China Railway Second Bureau Decoration Engineering Co., Ltd.

TR01 Transfer of patent right

Effective date of registration: 20170824

Address after: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Co-patentee after: China Railway Second Bureau Decoration Engineering Co., Ltd.

Patentee after: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

Address before: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Patentee before: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

TR01 Transfer of patent right
CP01 Change in the name or title of a patent holder

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Co-patentee after: China Railway Second Bureau Decoration Engineering Co., Ltd.

Patentee after: China Railway No. 2 Engineering Group Co., Ltd.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Co-patentee before: China Railway Second Bureau Decoration Engineering Co., Ltd.

Patentee before: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

CP01 Change in the name or title of a patent holder