CN102522820A - Testing method of synchronous coordination for primary station injection and secondary injection of distribution automation system - Google Patents

Testing method of synchronous coordination for primary station injection and secondary injection of distribution automation system Download PDF

Info

Publication number
CN102522820A
CN102522820A CN2011103880052A CN201110388005A CN102522820A CN 102522820 A CN102522820 A CN 102522820A CN 2011103880052 A CN2011103880052 A CN 2011103880052A CN 201110388005 A CN201110388005 A CN 201110388005A CN 102522820 A CN102522820 A CN 102522820A
Authority
CN
China
Prior art keywords
test
main website
fault
injection
tested
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011103880052A
Other languages
Chinese (zh)
Other versions
CN102522820B (en
Inventor
刘健
张小庆
赵树仁
陈宜凯
刘彬
彭书涛
左宝峰
尹俊钢
张钰声
丁彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
National Network Xi'an Environmental Protection Technology Center Co ltd
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shaanxi Electric Power Co Ltd
Original Assignee
Electric Power Research Institute of State Grid Shanxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of State Grid Shanxi Electric Power Co Ltd filed Critical Electric Power Research Institute of State Grid Shanxi Electric Power Co Ltd
Priority to CN201110388005.2A priority Critical patent/CN102522820B/en
Publication of CN102522820A publication Critical patent/CN102522820A/en
Application granted granted Critical
Publication of CN102522820B publication Critical patent/CN102522820B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a testing method of synchronous coordination for primary station injection and secondary injection of a distribution automation system. Basing on a GPS (Global Positioning System) time synchronization technology, protection action trip information of a converting station outlet switch can be injected to a tested distribution automation system primary station from a home-made primary station injection testing platform, the information of voltage and current before and after a fault can be synchronously injected at the positions of other feeder switches from a home-made secondary injection testing device, through the coordination of the protection action trip information and the information of the voltage and the current, an actual fault scene of an electric distribution network can be simulated, a fault processing function of the distribution automation system can be tested, a test without power cut can be realized, the safety for testing is increased, and more fault phenomena of the switch and more complex fault scenes can be simulated by the primary station.

Description

Injection of electrical power distribution automatization system main website and secondary inject the method for testing of synchronous coordination
Technical field
The present invention relates to distribution network automated field, is the method for testing that a kind of electrical power distribution automatization system main website injection and secondary inject synchronous coordination specifically.
Background technology
Test to the distribution automation engineering; Can accomplish the fault simulation test of functional test such as remote measurement, remote control, remote signalling and a single switch overcurrent at present; But be difficult in advance a complete interconnected feeder line is carried out the test of functions such as fault simulation and fault detect, judgement, isolation; Functions such as distribution network automated network reconfiguration, the network optimization are not had good testing equipment and means yet, could verify the correctness and the validity of distribution automation system function after the scene of can only waiting until has an accident.
Professor Liu Dong of Shanghai Communications University studies the electrical power distribution automatization system measuring technology; Once published " electrical power distribution automatization system test " book; But the measuring technology and the delivery test method of each production procedure of enterprise are made in the major side recasting, are not suitable for the fielded system test.
Professor Liu Jian of Shaanxi Electric Power Research Institute has carried out certain research to the electrical power distribution automatization system measuring technology, has developed feeder automation experimental test platform.This testboard is difficult to carry out the fielded system test just towards the laboratory.
Abroad do not appear in the newspapers in the achievement in research aspect the electrical power distribution automatization system test yet; Recognize from the channel of investigation and academic exchange: the practice that adopts relay-protection tester simulation feeder fault is abroad arranged; But all be confined to laboratory tests, be difficult to carry out the fielded system test.
In sum, the present distribution network automated efficient system means of testing that still lacks.
The main website that in patent before, has proposed power distribution automation of this team injects the second synchronization of method of testing and power distribution automation and injects method of testing, and the means of testing that is suitable for the fielded system test of distribution network automated main website is provided.But the problem that still has following aspect: (1) main website injects method of testing only to main website, and can not test the cooperation of whole each link of electrical power distribution automatization system.(2) second synchronization is injected method of testing, go out wiretap for transformer station and need carry out special processing, and the fault that can simulate count limited, fault scenes is abundant inadequately.
Summary of the invention
The objective of the invention is to existing distribution network automated method of testing is improved, propose the method for testing that a kind of main website injects and secondary injection synchronous coordination cooperates.
Be used to realize that above-mentioned purpose test job flow process is following:
(1) main website injects test platform and inserts main website of system to be tested, and simulation transformer station goes out the automatization terminal and the electrical power distribution automatization system to be tested main website interactive information of wiretap.
(2) secondary injects to test and inserts system to be tested with synchronous fault generator, and generates the fault test scheme by command computer.
(3) main website inject test platform and secondary inject test macro to the time, to the time accomplish after, command computer issues time on-test to source of synchronising signal, and by time on-test of manual entry main website injection test platform.
(4) wait for time on-test; Time on-test arrives; The tripping operation information that injection test platform simulation generation transformer station of main website goes out wiretap sends to the power distribution automation main website; Start the troubleshooting process of main website, each source of synchronising signal starts the back according to synchronous output load current of existing plan and fault current in test simultaneously, the instantaneous or permanent fault of a circuit of simulation.
(5) test failure process analysis
Whether test record analysis that the tester gathers by command computer and the function of judging power distribution automation main station system to be tested and terminal FTU/DTU thereof and performance meet the requirements.
Compared with present technology, advantage of the present invention is: (1) but uninterrupted power test, the fail safe of test good (2) can produce the phenomenon of the failure of more switches, complex failure scene more by main website simulation.
Description of drawings
Fig. 1 injects the testing process that injects synchronous coordination with secondary for main website.
Fig. 2 injects the composition that injects synchronous coordination method of testing test macro with secondary for main website.
Fig. 3 injects the sketch map that test platform produces the phenomenon of the failure of more switches by main website.
Embodiment
Below will combine accompanying drawing and the content of invention is further specified, and inject the testing process that injects synchronous coordination with secondary according to the main website shown in the accompanying drawing 1, whole test process is specific as follows:
(1) main website injects test platform and inserts main website of system to be tested, and simulation transformer station goes out the automatization terminal and the electrical power distribution automatization system to be tested main website interactive information of wiretap.
(2) secondary injects to test and inserts system to be tested with synchronous fault generator, and generates the fault test scheme by command computer.
Each feeder switch place at the upper reaches, fault zone of preparing simulation; Synchronous fault generator is linked into the secondary side of distribution power automation terminal; Concrete grammar is: feeder switch CT secondary A phase or C phase current loop is even short in the FTU/DTU current testing terminal outside; It is inboard that fault simulation generator electric current joins FTU/DTU current testing terminal synchronously, and its weak point is opened in flakes.The switching value of feeder switch CT secondary A phase or C phase current signal (clamp), feeder line PT secondary voltage signal and feeder switch inserts the front-end sampling module simultaneously.
Inject the test command computer according to selected power distribution network circuit, ring main unit, on-pole switch parameter at secondary and set up the test circuit model; The artificial test parameters such as fault type (instantaneous or permanent fault), abort situation, trouble duration of setting; Command computer simulation calculation feeder line to be tested is nonserviceabled down and the current/voltage of each distribution terminal along the line in the fault treating procedure; Generate testing scheme, and be issued to synchronous fault simulation generator through communication port.
Less in test point, measurement circuit also can be by manual work to source of synchronising signal typing testing scheme than under the simple scenario.
The sketch map that whole main website injects and secondary injects synchronous coordination method of testing test macro is shown in accompanying drawing 2.
(3) main website inject test platform and secondary inject test macro to the time, to the time accomplish after, command computer issues time on-test to source of synchronising signal, and by time on-test of manual entry main website injection test platform.
(4) wait for time on-test; Time on-test arrives; The tripping operation information that injection test platform simulation generation transformer station of main website goes out wiretap sends to the power distribution automation main website; Start the troubleshooting process of main website, each source of synchronising signal starts the back according to synchronous output load current of existing plan and fault current in test simultaneously, the instantaneous or permanent fault of a circuit of simulation.
(5) test failure process analysis
Back power distribution automation main station system takes place detected overcurrent and switch motion information is made analysis in simulated failure, generates fault location information and Fault Isolation, the scheme that restores electricity, and by artificial or automatically perform.
Whether test record analysis that the tester gathers by command computer and the function of judging power distribution automation main station system to be tested and terminal FTU/DTU thereof and performance meet the requirements.
Certainly; When adopting main website to inject with secondary injection synchronous coordination method of testing; Also can inject test platform by main website produces the phenomenon of the failure of more switches rather than only to power supply point, injects the sketch map that test platform produces the phenomenon of the failure of more switches by main website, shown in accompanying drawing 3.

Claims (1)

1. an electrical power distribution automatization system main website injects the method for testing with secondary injection synchronous coordination, it is characterized in that, may further comprise the steps:
(1) main website injects test platform and inserts main website of system to be tested, and simulation transformer station goes out the automatization terminal and the electrical power distribution automatization system to be tested main website interactive information of wiretap;
(2) secondary injects to test and inserts system to be tested with synchronous fault generator, and generates the fault test scheme by command computer;
(3) main website inject test platform and secondary inject test macro to the time, to the time accomplish after, command computer issues time on-test to source of synchronising signal, and by time on-test of manual entry main website injection test platform;
(4) wait for time on-test; Time on-test arrives; The tripping operation information that injection test platform simulation generation transformer station of main website goes out wiretap sends to the power distribution automation main website; Start the troubleshooting process of main website, each source of synchronising signal starts the back according to synchronous output load current of existing plan and fault current in test simultaneously, the instantaneous or permanent fault of a circuit of simulation;
(5) test failure process analysis
Whether test record analysis that gathers according to command computer and the function of judging power distribution automation main station system to be tested and terminal FTU/DTU thereof and performance meet the requirements.
CN201110388005.2A 2011-11-29 2011-11-29 Testing method of synchronous coordination for primary station injection and secondary injection of distribution automation system Active CN102522820B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110388005.2A CN102522820B (en) 2011-11-29 2011-11-29 Testing method of synchronous coordination for primary station injection and secondary injection of distribution automation system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110388005.2A CN102522820B (en) 2011-11-29 2011-11-29 Testing method of synchronous coordination for primary station injection and secondary injection of distribution automation system

Publications (2)

Publication Number Publication Date
CN102522820A true CN102522820A (en) 2012-06-27
CN102522820B CN102522820B (en) 2014-07-02

Family

ID=46293642

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110388005.2A Active CN102522820B (en) 2011-11-29 2011-11-29 Testing method of synchronous coordination for primary station injection and secondary injection of distribution automation system

Country Status (1)

Country Link
CN (1) CN102522820B (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102901896A (en) * 2012-10-12 2013-01-30 上海晟东电力科技有限公司 Preset automatic feeder test method for distribution network
CN102928688A (en) * 2012-09-24 2013-02-13 上海晟东电力科技有限公司 Method for synchronously testing automatic isolation of feeder fault from multiple points
CN103051065A (en) * 2012-12-29 2013-04-17 安徽科大智能电网技术有限公司 Distribution-automation distributed type FA (feeder automation) linkage test method and system
CN103810915A (en) * 2012-11-15 2014-05-21 国家电网公司 Adjusting and controlling integrated simulation method and system
CN104007366A (en) * 2014-06-12 2014-08-27 国网上海市电力公司 Feeder automation test system with automatic interference input function
CN105159273A (en) * 2015-07-29 2015-12-16 国家电网公司 System testing method of power grid distributed stability control devices
CN106597144A (en) * 2016-11-18 2017-04-26 国电南瑞科技股份有限公司 Centralized FA planning function detection method based on simulated transmission
CN106602718A (en) * 2015-10-19 2017-04-26 中国电力科学研究院 Method of testing distribution automation system time setting function and time keeping performance
CN108023659A (en) * 2017-11-06 2018-05-11 北京旋极信息技术股份有限公司 A kind of direct fault location markers unified approach, control device and fault injection system
CN110174566A (en) * 2019-05-16 2019-08-27 李勇 A kind of power distribution automation test macro and method based on cloud
CN111694288A (en) * 2020-05-20 2020-09-22 国网河北省电力有限公司电力科学研究院 On-site feeder automation function closed-loop automatic test platform
CN111830846A (en) * 2020-07-24 2020-10-27 贵州电网有限责任公司 Power distribution network fault testing method and system based on simulation testing platform
CN112037084A (en) * 2020-07-24 2020-12-04 贵州电网有限责任公司 Method and system for testing fault processing, testing and analyzing of power distribution main station
CN112379257A (en) * 2020-11-13 2021-02-19 贵州电网有限责任公司 High-precision fault inversion method without static error automatic feedback
CN115864326A (en) * 2022-11-18 2023-03-28 华北电力科学研究院有限责任公司 Testing method, device and system based on local feeder

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2935584Y (en) * 2006-08-09 2007-08-15 李东波 Automatic system analog simulation test apparatus of power distribution network
JP2010011585A (en) * 2008-06-25 2010-01-14 Fujitsu Ltd Tester and information processor
CN201955459U (en) * 2010-11-02 2011-08-31 华北电力大学 10kV distribution network line fault simulation test platform

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2935584Y (en) * 2006-08-09 2007-08-15 李东波 Automatic system analog simulation test apparatus of power distribution network
JP2010011585A (en) * 2008-06-25 2010-01-14 Fujitsu Ltd Tester and information processor
CN201955459U (en) * 2010-11-02 2011-08-31 华北电力大学 10kV distribution network line fault simulation test platform

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
"变电站综合自动化数字物理仿真培训系统的研究与设计": "周成林", 《中国优秀硕士学位论文全文数据库》, 28 October 2009 (2009-10-28) *
《电力系统自动化》 20090410 翁之浩等 "基于并行计算的馈线自动化仿真测试环境" 第33卷, 第7期 *
翁之浩等: ""基于并行计算的馈线自动化仿真测试环境"", 《电力系统自动化》, vol. 33, no. 7, 10 April 2009 (2009-04-10) *

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102928688A (en) * 2012-09-24 2013-02-13 上海晟东电力科技有限公司 Method for synchronously testing automatic isolation of feeder fault from multiple points
CN102901896B (en) * 2012-10-12 2016-03-02 上海金智晟东电力科技有限公司 The presetting system feeder test method of distribution network
CN102901896A (en) * 2012-10-12 2013-01-30 上海晟东电力科技有限公司 Preset automatic feeder test method for distribution network
CN103810915A (en) * 2012-11-15 2014-05-21 国家电网公司 Adjusting and controlling integrated simulation method and system
CN103810915B (en) * 2012-11-15 2016-03-30 国家电网公司 Regulation and control integrative simulation method and system
CN103051065A (en) * 2012-12-29 2013-04-17 安徽科大智能电网技术有限公司 Distribution-automation distributed type FA (feeder automation) linkage test method and system
CN104007366A (en) * 2014-06-12 2014-08-27 国网上海市电力公司 Feeder automation test system with automatic interference input function
CN105159273A (en) * 2015-07-29 2015-12-16 国家电网公司 System testing method of power grid distributed stability control devices
CN106602718A (en) * 2015-10-19 2017-04-26 中国电力科学研究院 Method of testing distribution automation system time setting function and time keeping performance
CN106602718B (en) * 2015-10-19 2019-04-19 中国电力科学研究院 A kind of test method of electrical power distribution automatization system time adjustment function and timekeeping performance
CN106597144B (en) * 2016-11-18 2019-05-17 国电南瑞科技股份有限公司 The planned function detecting method of centralized FA transmitted based on simulation
CN106597144A (en) * 2016-11-18 2017-04-26 国电南瑞科技股份有限公司 Centralized FA planning function detection method based on simulated transmission
CN108023659A (en) * 2017-11-06 2018-05-11 北京旋极信息技术股份有限公司 A kind of direct fault location markers unified approach, control device and fault injection system
CN110174566A (en) * 2019-05-16 2019-08-27 李勇 A kind of power distribution automation test macro and method based on cloud
CN111694288A (en) * 2020-05-20 2020-09-22 国网河北省电力有限公司电力科学研究院 On-site feeder automation function closed-loop automatic test platform
CN111694288B (en) * 2020-05-20 2023-04-18 国网河北省电力有限公司电力科学研究院 On-site feeder automation function closed-loop automatic test platform
CN111830846A (en) * 2020-07-24 2020-10-27 贵州电网有限责任公司 Power distribution network fault testing method and system based on simulation testing platform
CN112037084A (en) * 2020-07-24 2020-12-04 贵州电网有限责任公司 Method and system for testing fault processing, testing and analyzing of power distribution main station
CN111830846B (en) * 2020-07-24 2022-08-19 贵州电网有限责任公司 Power distribution network fault testing method and system based on simulation testing platform
CN112379257A (en) * 2020-11-13 2021-02-19 贵州电网有限责任公司 High-precision fault inversion method without static error automatic feedback
CN115864326A (en) * 2022-11-18 2023-03-28 华北电力科学研究院有限责任公司 Testing method, device and system based on local feeder

Also Published As

Publication number Publication date
CN102522820B (en) 2014-07-02

Similar Documents

Publication Publication Date Title
CN102522820B (en) Testing method of synchronous coordination for primary station injection and secondary injection of distribution automation system
CN102306953B (en) Test method for secondary injection of power distribution automatization system
CN103051065B (en) The distributed FA interlock method of testing of a kind of power distribution automation and system
CN102361346A (en) Master station full-digital scene testing method of power distribution automation system
CN108879964A (en) Type feed line automatization system field-checking is driven FA full-automatic testing method on the spot
CN104749466B (en) A kind of intelligent substation relay protection test system, method of testing and implementation method
CN203350377U (en) Automation relay protection testing device
CN102208801A (en) Operation method for safely applying line protection device to wind power station
CN102495322B (en) Synchronous performance test method for digital relay protection device based on IEC61850 (International Electrotechnical Commission 61850)
CN103607042B (en) The distribution network failure processing method of long fault indicator for overhead lines towards outskirts of a town
CN102323502B (en) Online closed loop test system for relay protection and test method thereof
CN103151839B (en) Intelligent substation test research system
CN205139272U (en) Join in marriage power -grid switch analog switch unit for equipment
CN108983006A (en) Type feeder automation switch terminal scene does not have a power failure full-automatic testing method on the spot
CN104090194A (en) Intelligent substation relay protection noninvasive test system and method
CN107491569B (en) Transformer substation system fault online simulation method based on IEC61850 standard GOOSE and SV technology
CN102426309A (en) Method for testing area spare power automatic switching system in engine room environment of master station
CN105548742A (en) Remote relay protection test system
CN105449847A (en) Digital transformer substation testing system
CN113887157A (en) Active distribution network automatic terminal network closed-loop test method based on RTDS
CN104076805A (en) Test system for automatic control equipment of power distribution network
CN104849591A (en) Power distribution automation integrated test detection device
CN103558466A (en) Method for on-line whole group logic calibration of 10kV protecting device
CN102508052B (en) Test method for field band channel operation of automatic bus transfer system of area network
CN206251112U (en) A kind of intelligent substation relay protection network pressure automatic testing equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA

Effective date: 20121130

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20121130

Address after: 710054 No. 308 Youyi East Road, Shaanxi, Xi'an

Applicant after: Shaanxi Electric Power Research Institute

Applicant after: State Grid Corporation of China

Address before: 710054 No. 308 Youyi East Road, Shaanxi, Xi'an

Applicant before: Shaanxi Electric Power Research Institute

C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 710054 No. 308 Youyi East Road, Shaanxi, Xi'an

Patentee after: SHAANXI ELECTRIC POWER Research Institute

Patentee after: STATE GRID CORPORATION OF CHINA

Address before: 710054 No. 308 Youyi East Road, Shaanxi, Xi'an

Patentee before: SHAANXI ELECTRIC POWER Research Institute

Patentee before: State Grid Corporation of China

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201013

Address after: 710054 Aerospace Middle Road 669, Chang'an District, Xi'an City, Shaanxi Province

Patentee after: STATE GRID SHAANXI ELECTRIC POWER Research Institute

Patentee after: STATE GRID CORPORATION OF CHINA

Patentee after: National Network (Xi'an) Environmental Protection Technology Center Co.,Ltd.

Address before: 710054 No. 308 Youyi East Road, Shaanxi, Xi'an

Patentee before: SHAANXI ELECTRIC POWER Research Institute

Patentee before: STATE GRID CORPORATION OF CHINA

TR01 Transfer of patent right

Effective date of registration: 20240626

Address after: No. 669, Hangtian Middle Road, Xi'an national civil aerospace industry base, Shaanxi 710100

Patentee after: Electric Power Research Institute of State Grid Shaanxi Electric Power Co.,Ltd.

Country or region after: China

Patentee after: STATE GRID CORPORATION OF CHINA

Patentee after: National Network (Xi'an) Environmental Protection Technology Center Co.,Ltd.

Address before: No.669, Hangtian Middle Road, Chang'an District, Xi'an City, Shaanxi Province

Patentee before: STATE GRID SHAANXI ELECTRIC POWER Research Institute

Country or region before: China

Patentee before: STATE GRID CORPORATION OF CHINA

Patentee before: National Network (Xi'an) Environmental Protection Technology Center Co.,Ltd.