CN102522280A - Operation method for 10kV drop-out fuse - Google Patents

Operation method for 10kV drop-out fuse Download PDF

Info

Publication number
CN102522280A
CN102522280A CN2011104066447A CN201110406644A CN102522280A CN 102522280 A CN102522280 A CN 102522280A CN 2011104066447 A CN2011104066447 A CN 2011104066447A CN 201110406644 A CN201110406644 A CN 201110406644A CN 102522280 A CN102522280 A CN 102522280A
Authority
CN
China
Prior art keywords
phase
switching
fuse
fusion tube
drop
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011104066447A
Other languages
Chinese (zh)
Inventor
杨爱宝
尹校
王磊
范丙光
任凯凯
王伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Dongying Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
Dongying Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dongying Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical Dongying Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority to CN2011104066447A priority Critical patent/CN102522280A/en
Publication of CN102522280A publication Critical patent/CN102522280A/en
Pending legal-status Critical Current

Links

Landscapes

  • Fuses (AREA)

Abstract

The invention relates to an operation method for a 10kV drop-out fuse; the technical scheme of the invention comprises the following steps: during the operation of switching out, firstly, switching out an intermediate phase, then, switching out a leeward edge phase, and finally, switching out a windward edge phase so as to change a three-phase operation of a distribution transformer into a two-phase operation; due to the smallest arc sparks during switching out of the intermediate phase, an interphase short circuit cannot be caused; during switching on, ensuring that the operating sequence is inversed with the operating sequence of switching out, i.e., firstly, switching on the windward edge phase, then switching on the leeward edge phase, and finally switching on the intermediate phase; and when a fusion tube is operated, moderately exerting force when the fusion tube is switched out and switched on so as to ensure that a duckbilled tongue can be tightly buckled with more than 2/3 that of the length of the tongue. The operation method for the 10kV drop-out fuse has the beneficial effects that not only the workload of maintenance personnel is reduced, but also the cases of completely losing a protective function of a drop-out fuse, enlarging the range of power failure when a short circuit happens in a line, and then bypassing a 10kV outgoing line of a substation to cause tripping of a main circuit breaker to cause power failure of the whole line due to the inappropriate operation of maintenance personnel are avoided.

Description

The operation method of 10kV fuse switch
Technical field:
The present invention relates to a kind of use of fuse switch, particularly a kind of operation method of 10kV fuse switch.
Background technology:
Fuse switch is the most frequently used a kind of protective switch of the short circuit of 10kV distribution line branch line and distribution transformer; It has economy, easy to operate, adapt to characteristics such as outdoor environment property is strong, be widely used in 10kV distribution line and distribution transformer primary side as protection with carry out the equipment throwing, cut the usefulness of operation.It is installed on the 10kV distribution line branch line, can dwindle the power failure scope, because of it has a tangible cut-off point, has possessed the function of isolating switch, has created a safety work environment for maintenance section circuit and equipment, has increased maintainer's the sense of security.Be installed on the distribution transformer, can be used as the main protection of distribution transformer, so, in 10kV distribution line and distribution transformer, obtained popularizing.Its operation principle is: the moving contact at cartridge fuse two ends relies on fuse (melt) to fasten, and after will going up moving contact and pushing " duckbilled " projection, the upper static contact that phosphorus bronze sheet etc. are processed heads on moving contact, so cartridge fuse is stuck in " duckbilled " lining securely.When short circuit current passes through fuse failure, produce electric arc, the vulcanized fiber tube of cartridge fuse liner produces a large amount of gas and is shut because of the cartridge fuse upper end under arcing, and gas sprays to the lower end, blows out electric arc.Because fuse failure, the last lower moving contact of cartridge fuse loses the power of fastening of fuse, and under the effect of cartridge fuse self gravitation and upper and lower fixed contact spring leaf, cartridge fuse falls rapidly, circuit is broken off, excision faulty section circuit or faulty equipment.The problem that exists in the existing rural power grids has not only increased the work of maintenance personnel amount; And impel attendant (especially rural power worker's) improper use; Fully lose the due defencive function of fuse switch; Be short-circuited in the line and can only the power failure expanded range be bypassed the immediate leadership to the tripping operation of the 10kV of electric substation outlet main breaker, causing completely, the road has a power failure.
Summary of the invention:
The object of the invention is exactly the above-mentioned defective that exists to prior art, and a kind of operation method of 10kV fuse switch is provided.
Its technical scheme is: be made up of following steps:
Undertaken by two people when (1) operating, people monitoring, insulating gloves is worn in one man operation, wears insulation boots, wears spectacles, the qualified insulating rod operation that the working voltage grade is complementary, quiescing under the weather of thunder and lightning or heavy rain;
(2) when operating a switch operation, phase in the middle of breaking is earlier drawn leeward limit phase again, breaks the limit phase of facining the wind at last, makes distribution transformer change two-phase operation into by three-phase operation, and the arc spark that phase time is produced in the middle of breaking is minimum, the unlikely phase fault that causes; Next is to break leeward limit phase, because middle phase is drawn back, leeward limit has increased by one times with windward side distance mutually, even there is overvoltage to produce, causes the possibility of phase fault also very little; Break the windward side phase time at last, capacitance current is over the ground only arranged, the electric spark of generation is then very slight;
Opposite when operating sequence is operated a switch when (3) closing a floodgate, close the windward side phase earlier, close leeward limit phase again, phase in the middle of closing at last;
(4) operation is during fusion tube, draws, the appropriateness of will exerting oneself when closing fusion tube, makes the duckbilled tongue can tightly fasten tongue length more than 2/3rds; It is several following to pressing down to hook duckbilled through brake pull-rod; Again gently the examination draw, the inspection whether get togather, fail during combined floodgate to put in place or do not close firm; Fuse upper static contact insufficient pressure very easily causes contact burn or fusion tube to fall voluntarily.
The invention has the beneficial effects as follows: not only reduced the work of maintenance personnel amount; And impel attendant (especially rural power worker's) improper use; Fully lose the due defencive function of fuse switch; Be short-circuited in the line and can only the power failure expanded range be bypassed the immediate leadership to the tripping operation of the 10kV of electric substation outlet main breaker, causing completely, the road has a power failure.
Embodiment:
Method of operation of the present invention is made up of following steps:
Undertaken by two people when (1) operating, people monitoring, insulating gloves is worn in one man operation, wears insulation boots, wears spectacles, the qualified insulating rod operation that the working voltage grade is complementary, quiescing under the weather of thunder and lightning or heavy rain;
(2) when operating a switch operation, phase in the middle of breaking is earlier drawn leeward limit phase again, breaks the limit phase of facining the wind at last, makes distribution transformer change two-phase operation into by three-phase operation, and the arc spark that phase time is produced in the middle of breaking is minimum, the unlikely phase fault that causes; Next is to break leeward limit phase, because middle phase is drawn back, leeward limit has increased by one times with windward side distance mutually, even there is overvoltage to produce, causes the possibility of phase fault also very little; Break the windward side phase time at last, capacitance current is over the ground only arranged, the electric spark of generation is then very slight;
Opposite when operating sequence is operated a switch when (3) closing a floodgate, close the windward side phase earlier, close leeward limit phase again, phase in the middle of closing at last;
(4) operation is during fusion tube, draws, the appropriateness of will exerting oneself when closing fusion tube, makes the duckbilled tongue can tightly fasten tongue length more than 2/3rds; It is several following to pressing down to hook duckbilled through brake pull-rod; Again gently the examination draw, the inspection whether get togather, fail during combined floodgate to put in place or do not close firm; Fuse upper static contact insufficient pressure very easily causes contact burn or fusion tube to fall voluntarily.
In addition, Maintenance management method is following:
(1) for making the operation that fuse can be more reliable, safe, remove the qualified products of selecting regular manufacturer production by rules and the accessory (comprise and melt part etc.) strictly, in operation maintenance management, should be specifically noted that following item:
It is suitable whether utensil rated current and melt and the load current value of 1. fusing matees, if mismate must be adjusted.
2. each operation of fuse must be careful conscientious, can not be careless, and particularly closing operation must make dynamic and static contact contact good.
3. must use standard melt in the fusion tube, forbid replacing melt, more ban the use of copper wire, aluminium wire and iron wire the contact colligation is lived to use with the copper wire aluminium wire.
4. to the fuse of new installation or replacing, the strict operation of checking and accepting, must satisfy the rules quality requirement, the fusion tube setting angle reaches the inferior horn that inclines about 25 °.
The same specification melt that 5. should more renew after the melt fusing can not connect the melt after the fusing and reinstalls fusion tube and continue to use.
6. should regularly make an inspection tour, be no less than night inspection one time in every month, check to have or not discharge spark and poor contact phenomenon that discharge is arranged, can will arrange as early as possible to handle with the sound of neighing to fuse.
(2) when spring inspection interruption maintenance, tackle the inspection that fuse is done following content:
Whether 1. quiet, moving contact contact coincide, closely intact, and the vestige of not burning is arranged.
2. whether the fuse rotary part is flexible, not corrosion arranged, rotate ineffective etc. unusually, and whether parts damage, spring has not corrosion.
3. melt itself does not have and sustains damage, and after long-term energising, having or not the heating elongation too much to become lax unable.
4. fusion tube aerogenesis in action pipe repeatedly whether burn with expulsion tube and expose to the sun and rain after whether damage deformation, length shorten.
5. clean insulator and inspection has not damaged, crackle or spark tracking, take upper and lower lead-in wire apart after, testing insulation resistance with the 2500V megger should be greater than 300M Ω.
6. check that fuse connects lead-in wire up and down non-loosening, discharge, superheating phenomenon are arranged.
Defective to above-mentioned item inspection goes out must conscientiously be overhauled processing.

Claims (1)

1. the operation method of a 10kV fuse switch is characterized in that being made up of following steps:
Undertaken by two people when (1) operating, people monitoring, insulating gloves is worn in one man operation, wears insulation boots, wears spectacles, the qualified insulating rod operation that the working voltage grade is complementary, quiescing under the weather of thunder and lightning or heavy rain;
(2) when operating a switch operation, phase in the middle of breaking is earlier drawn leeward limit phase again, breaks the limit phase of facining the wind at last, makes distribution transformer change two-phase operation into by three-phase operation, and the arc spark that phase time is produced in the middle of breaking is minimum, the unlikely phase fault that causes; Next is to break leeward limit phase, because middle phase is drawn back, leeward limit has increased by one times with windward side distance mutually, even there is overvoltage to produce, causes the possibility of phase fault also very little; Break the windward side phase time at last, capacitance current is over the ground only arranged, the electric spark of generation is then very slight;
Opposite when operating sequence is operated a switch when (3) closing a floodgate, close the windward side phase earlier, close leeward limit phase again, phase in the middle of closing at last;
(4) operation is during fusion tube, draws, the appropriateness of will exerting oneself when closing fusion tube, makes the duckbilled tongue can tightly fasten tongue length more than 2/3rds; It is several following to pressing down to hook duckbilled through brake pull-rod; Again gently the examination draw, the inspection whether get togather, fail during combined floodgate to put in place or do not close firm; Fuse upper static contact insufficient pressure very easily causes contact burn or fusion tube to fall voluntarily.
CN2011104066447A 2011-12-09 2011-12-09 Operation method for 10kV drop-out fuse Pending CN102522280A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011104066447A CN102522280A (en) 2011-12-09 2011-12-09 Operation method for 10kV drop-out fuse

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011104066447A CN102522280A (en) 2011-12-09 2011-12-09 Operation method for 10kV drop-out fuse

Publications (1)

Publication Number Publication Date
CN102522280A true CN102522280A (en) 2012-06-27

Family

ID=46293164

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011104066447A Pending CN102522280A (en) 2011-12-09 2011-12-09 Operation method for 10kV drop-out fuse

Country Status (1)

Country Link
CN (1) CN102522280A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108957220A (en) * 2018-08-10 2018-12-07 国网江西省电力有限公司赣东北供电分公司 A kind of transmission of fuse switch state and fail analysis device based on Internet of Things
CN109058633A (en) * 2018-09-13 2018-12-21 安徽马钢设备检修有限公司 A kind of online installation method of water at atmospheric pressure pipeline meter

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
谢嘉宁: "10kV户外跌落式熔断器的运行维护管理", 《中国科技信息》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108957220A (en) * 2018-08-10 2018-12-07 国网江西省电力有限公司赣东北供电分公司 A kind of transmission of fuse switch state and fail analysis device based on Internet of Things
CN109058633A (en) * 2018-09-13 2018-12-21 安徽马钢设备检修有限公司 A kind of online installation method of water at atmospheric pressure pipeline meter

Similar Documents

Publication Publication Date Title
Russell et al. Distribution feeder caused wildfires: Mechanisms and prevention
CN102931609B (en) On-load changes the operational method of 10kV fuse switch
CN201845734U (en) Novel dropping type fuse
CN205845889U (en) It is provided with the high-voltage drop type anti-hemiplegia fuse of double fuse tube
CN102522280A (en) Operation method for 10kV drop-out fuse
CN201498291U (en) Detachable lightning arrester
CN201877234U (en) Detachable lightning arrester
CN203086121U (en) Falling type lightning arrester structure
CN106486327A (en) Outlet fuse switch and blowout method
CN112370679B (en) Special stores pylon of outdoor 35kV circuit breaker aerial work safety belt
CN103811239B (en) Fuse switch
Sato et al. Application of FDS fuses to DC 1000V photovoltaic systems
CN202258608U (en) Combined type compound jacket zinc oxide arrester
CN109411168B (en) Method for enabling low-voltage lightning arrester to have automatic separation function
CN104867776A (en) Fuse type load disconnection switch
Tao et al. Research on key technologies of thunder detection in Zibo distribution network
CN201515199U (en) Removable and suspensible drop-out type arrester
CN109742004A (en) A kind of power equipment falling type switch being easily installed
CN204229951U (en) Detachable metal oxide arrester
CN202473818U (en) Inductance current-limit high-voltage drop-type fuse
Wang Fault analysis and countermeasures for single phase grounding of 6kV distribution line in oil field
CN207218239U (en) A kind of overvoltage protection device
CN200993947Y (en) Fault release device for overvoltage protection device
CN109378146B (en) Method for ensuring product percent of pass of low-voltage lightning arrester with built-in hot-melt separation component
CN207441647U (en) A kind of fuse switch convenient to overhaul

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA

Free format text: FORMER OWNER: SHANDONG ELECTRIC POWER GROUP CORPORATION DONGYING POWER SUPPLY COMPANY

Effective date: 20121221

Owner name: SHANDONG ELECTRIC POWER GROUP CORPORATION DONGYING

Effective date: 20121221

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 257091 DONGYING, SHANDONG PROVINCE TO: 100031 XICHENG, BEIJING

TA01 Transfer of patent application right

Effective date of registration: 20121221

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant after: State Grid Corporation of China

Applicant after: Dongying Power Supply Branch of Shandong Electric Power Corporation

Address before: 257091 South Road, Dongying District, Shandong, No. 357, No.

Applicant before: Dongying Power Supply Branch of Shandong Electric Power Corporation

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120627