CN102493452A - 注浆植桩工法及设备 - Google Patents

注浆植桩工法及设备 Download PDF

Info

Publication number
CN102493452A
CN102493452A CN2011103904517A CN201110390451A CN102493452A CN 102493452 A CN102493452 A CN 102493452A CN 2011103904517 A CN2011103904517 A CN 2011103904517A CN 201110390451 A CN201110390451 A CN 201110390451A CN 102493452 A CN102493452 A CN 102493452A
Authority
CN
China
Prior art keywords
pile
machine
slurry
soil
grouting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011103904517A
Other languages
English (en)
Inventor
蔡嘉明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2011103904517A priority Critical patent/CN102493452A/zh
Publication of CN102493452A publication Critical patent/CN102493452A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明公开一种注浆植桩工法及设备,属于土木工程技术领域,解决了现有成桩施工过程中存在挤土效应、施工机具对桩体造成损伤、承载力不能充分发挥的问题,包括取土成孔,浆体注入,桩体植入,端承送桩步骤。本发明还提供了实施上述工法的设备,由机座、机架、支承部件、起吊器构成,机架内设置有动力头,其下端设有夹持装置,机座内有导向器。本发明减少了挤土效应,桩身不受施工机具损伤,提高了桩身承载力。

Description

注浆植桩工法及设备
技术领域
本发明属于土木工程技术领域,特别涉及一种成桩工艺及其施工设备。
背景技术
目前在工程中的各类预制桩、管桩、钢桩施工中,其成桩工艺有打入式、压入式、振入式几种。在成桩施工过程中不仅存在挤土效应、噪声污染、振动影响缺陷,而且在穿越复杂地质或硬土层时,还存在成桩到位率保证度低、施工机具对桩体造成严重的损伤、承载力不能充分发挥、辅助成桩措施效果差异性大和费用高等问题。这些不足和问题都使桩体质量优势不能充分发挥,也使各类预制桩在高承载力、高成桩质量、高性价比方面受到很大影响。
发明内容
为解决现有成桩施工过程中存在挤土效应、噪声污染、振动影响,以及成桩到位率保证度低、施工机具对桩体造成严重的损伤、承载力不能充分发挥、辅助成桩措施效果差异性大和费用高的问题,本发明提供一种注浆植桩工法,包括下述步骤:取土成孔,浆体注入,桩体植入,端承送桩。
上述方案中,按以下顺序实施各步骤:
首先实施取土成孔步骤,然后实施浆体注入步骤,再实施桩体植入步骤,最后实施端承送桩步骤;
或者,首先同时实施取土成孔步骤和浆体注入步骤,再实施桩体植入步骤,最后实施端承送桩步骤;
或者,首先实施取土成孔步骤,然后实施桩体植入步骤,再实施端承送桩步骤,最后实施浆体注入步骤。
上述方案中,所述浆体注入步骤中的浆体采用砂浆、水泥浆、膨润土水泥浆、粉煤灰水泥浆或专用防腐砂浆中的一种或两种以上组合。
上述方案中,所述取土成孔和浆体注入步骤采用钻孔机、旋挖机、冲抓机、冲孔机、套管机、长螺旋机、深搅机或喷搅机中的一种设备来实施;
所述桩体植入和端承送桩步骤采用静力压桩机、振动打桩机、柴油锤打桩机、液压高频锤打桩机或锤式打桩机中的一种设备来实施。
本发明还提供了一种实施上述注浆植桩工法的设备:
具有机座和安装在机座上的机架,机座下方有支承部件,机架顶部有起吊器;
机架内设置有动力头,动力头下端设有夹持装置;
位于动力头竖直下方的机座内有导向器。
上述方案中,所述夹持装置为夹管机或夹桩机,分别用于实施取土成孔步骤和浆体注入步骤时联接导向管,或者实施桩体植入步骤和端承送桩时联接桩体;
所述支承部件为移动步履或液压支座。
上述设备实施取土成孔,浆体注入,桩体植入,端承送桩的具体过程如下:
取土成孔:注浆植桩设备就位后,导向管对准桩位,此时导向管内配有長螺旋取土注浆器并由动力头提供动力,启动动力头开始取土,一直取土到设计桩底标高从而完成整个桩孔取土。
浆体注入:从设计桩底标高开始浆体注入,边注浆边提升导向管直到地面,从而完成整个桩孔的浆体注入。
桩体植入:用动力头下端的夹桩机夹好桩体,将桩尖对准桩孔均速插入已注浆的桩孔内,从而将单节或多节桩植入桩孔内。
端承送桩:当桩体达到设计桩底标高时,在桩顶由动力头施加竖向压力,从而使桩尖与桩孔底部紧密结合达到端承要求。
上述设备中的起吊器是注浆植桩机的起重机械,用来完成起吊桩体、导向管、设备组装或拆卸、另配件吊运等起重工作。
本发明注浆植桩工法将挤土桩改善为非挤土桩或低挤土桩,最大限度的减少挤土效应引起的不良影响,在保证桩体设计标高到位率的前题下,确保桩身穿越坚硬土层时不受施工机具损伤而留下质量隐患,同时注浆增大桩土共同受力面积,在提高承载力的同时为桩体和桩接头提供有效保护,相比打入式、压入式、振入式成桩工法更为环保安全高效,更能发挥预制桩、管桩、钢桩桩体质量好承载力性价比高的优势。
随着工程建设对桩基工程的环保、质量要求旳提高,本发明植入式桩工方法在减少挤土效应、适应环保要求、保障成桩质量、发挥预制桩优势、降低工程造价等方面将会有广阔的前景。
附图说明
图1为本发明取土成孔步骤所形成的桩孔示意图;
图2为本发明浆体注入步骤中的浆体位置的示意图;
图3为本发明桩体植入步骤的实施示意图;
图4为本发明端承送桩步骤的实施示意图;
图5为实施本发明注浆植桩机的示意图;
图6为本发明中使用钻孔机实施取土成孔和浆体注入时的示意图;
图7为本发明中使用套管机实施取土成孔和浆体注入时的示意图;
图8为本发明中使用长螺旋机在实施取土成孔和浆体注入时的示意图;
图9为本发明中使用深搅机在实施取土成孔和浆体注入时的示意图。
具体实施方式
如图1-4所示的注浆植桩工法,包括下述步骤:取土成孔,浆体注入,桩体植入,端承送桩;
上述浆体注入的方式采用取土后注浆方式,或者边取土边注浆方式,或者植桩前注浆方式,或者植桩后注浆方式;
所述浆体注入步骤中的浆体采用砂浆、水泥浆、膨润土水泥浆、粉煤灰水泥浆、专用防腐砂浆中的一种或两种以上组合;
所述取土成孔和浆体注入步骤采用钻孔机、旋挖机、冲抓机、冲孔机、套管机、长螺旋机、深搅机或喷搅机中的一种设备来实施;
所述桩体植入和端承送桩步骤采用静力压桩机、振动打桩机、柴油锤打桩机、液压高频锤打桩机或锤式打桩机中的一种设备来实施;
图6-9分别示出了钻孔机、套管机、长螺旋机、深搅机在实施取土成孔、浆体注入时的示意图。
一种实施注浆植桩工法的设备,如图5所示,其结构如下:
具有机座2和安装在机座2上的机架4,机座2下方有位于作业地面1之上的支承部件8,机架4顶部有起吊器5;
机架4内设置有动力头6,动力头6下端设有夹持装置;
位于动力头6竖直下方的机座2内有导向器3。
所述夹持装置为夹管机或夹桩机,分别用于实施取土成孔步骤和浆体注入步骤时联接导向管7,或者实施桩体植入步骤和端承送桩时联接桩体;
作业时,所述夹持装置、导向管7或桩体、导向器3,均位于作业桩体9的竖直上方。
所述支承部件为移动步履或液压支座。

Claims (6)

1.一种注浆植桩工法,其特征在于包括下述步骤:取土成孔,浆体注入,桩体植入,端承送桩。
2.根据权利要求1所述的注浆植桩工法,其特征在于按以下顺序实施各步骤:首先实施取土成孔步骤,然后实施浆体注入步骤,再实施桩体植入步骤,最后实施端承送桩步骤;或者,
首先同时实施取土成孔步骤和浆体注入步骤,再实施桩体植入步骤,最后实施端承送桩步骤;或者,
首先实施取土成孔步骤,然后实施桩体植入步骤,再实施端承送桩步骤,最后实施浆体注入步骤。
3.根据权利要求1或2所述的注浆植桩工法,其特征在于:所述浆体注入步骤中的浆体采用砂浆、水泥浆、膨润土水泥浆、粉煤灰水泥浆或专用防腐砂浆中的一种或两种以上组合。
4.根据权利要求3所述的注浆植桩工法,其特征在于:所述取土成孔和浆体注入步骤采用钻孔机、旋挖机、冲抓机、冲孔机、套管机、长螺旋机、深搅机或喷搅机中的一种设备来实施;
所述桩体植入和端承送桩步骤采用静力压桩机、振动打桩机、柴油锤打桩机、液压高频锤打桩机或锤式打桩机中的一种设备来实施。
5.一种如权利要求1或2所述的注浆植桩工法的实施设备,其特征在于:具有机座(2)和安装在机座(2)上的机架(4),机座(2)下方有支承部件(8),机架(4)顶部有起吊器(5);机架(4)内设置有动力头(6),动力头(6)下端设有夹持装置;位于动力头(6)竖直下方的机座(2)内有导向器(3)。
6.根据权利要求5所述的设备,其特征在于:所述夹持装置为夹管机或夹桩机,分别用于实施取土成孔步骤和浆体注入步骤时联接导向管(7),或者实施桩体植入步骤和端承送桩时联接桩体;所述支承部件为移动步履或液压支座。
CN2011103904517A 2011-11-30 2011-11-30 注浆植桩工法及设备 Pending CN102493452A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011103904517A CN102493452A (zh) 2011-11-30 2011-11-30 注浆植桩工法及设备

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011103904517A CN102493452A (zh) 2011-11-30 2011-11-30 注浆植桩工法及设备

Publications (1)

Publication Number Publication Date
CN102493452A true CN102493452A (zh) 2012-06-13

Family

ID=46185308

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011103904517A Pending CN102493452A (zh) 2011-11-30 2011-11-30 注浆植桩工法及设备

Country Status (1)

Country Link
CN (1) CN102493452A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612164A (zh) * 2014-12-18 2015-05-13 中冶天工集团有限公司 一种劲性复合围护结构施工方法

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0325386A (ja) * 1989-06-22 1991-02-04 Mitsubishi Electric Corp 低周波数帯方位算出装置
CN1080681A (zh) * 1992-06-27 1994-01-12 化学工业部第一勘察设计院 引孔压浆沉桩成桩法
CN1202557A (zh) * 1998-06-05 1998-12-23 梁仁旺 钻孔复合桩
CN1352340A (zh) * 2001-11-30 2002-06-05 叶长生 钢筋混凝土预制桩钻孔取土植入桩工艺
CN1366114A (zh) * 2001-01-21 2002-08-28 陈如桂 一种建筑基础用的成孔预制注浆桩的施工方法
CN1414186A (zh) * 2002-05-10 2003-04-30 贾燎 套桩的成桩及设计方法
CN201050063Y (zh) * 2007-04-12 2008-04-23 武汉市天宝工程机械有限责任公司 多功能桩机
CN101230574A (zh) * 2007-01-24 2008-07-30 周兆弟 具有钻孔功能的桩机及钻孔静压方法
CN101725146A (zh) * 2009-12-02 2010-06-09 江守慈 管内螺旋引孔与静压沉桩交替分段渐进的静压沉桩施工工艺

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0325386A (ja) * 1989-06-22 1991-02-04 Mitsubishi Electric Corp 低周波数帯方位算出装置
CN1080681A (zh) * 1992-06-27 1994-01-12 化学工业部第一勘察设计院 引孔压浆沉桩成桩法
CN1202557A (zh) * 1998-06-05 1998-12-23 梁仁旺 钻孔复合桩
CN1366114A (zh) * 2001-01-21 2002-08-28 陈如桂 一种建筑基础用的成孔预制注浆桩的施工方法
CN1352340A (zh) * 2001-11-30 2002-06-05 叶长生 钢筋混凝土预制桩钻孔取土植入桩工艺
CN1414186A (zh) * 2002-05-10 2003-04-30 贾燎 套桩的成桩及设计方法
CN101230574A (zh) * 2007-01-24 2008-07-30 周兆弟 具有钻孔功能的桩机及钻孔静压方法
CN201050063Y (zh) * 2007-04-12 2008-04-23 武汉市天宝工程机械有限责任公司 多功能桩机
CN101725146A (zh) * 2009-12-02 2010-06-09 江守慈 管内螺旋引孔与静压沉桩交替分段渐进的静压沉桩施工工艺

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612164A (zh) * 2014-12-18 2015-05-13 中冶天工集团有限公司 一种劲性复合围护结构施工方法

Similar Documents

Publication Publication Date Title
CN104074186B (zh) 一种建筑地基中成孔的护筒装置及其施工方法
CN104294818B (zh) 混凝土桩的施工方法
CN104314078A (zh) 混凝土桩的施工设备及其施工方法
CN110273413A (zh) 一种预制桩的高效施工方法
CN104099925A (zh) 混凝土桩的施工装置及其施工方法
CN110258571A (zh) 一种灌注桩沉管压灌施工方法
CN105672316A (zh) 钢桩下沉减阻装置及施工方法
CN203213101U (zh) 一种植入注浆组合桩
CN104404956A (zh) 一种扩底桩的施工方法
CN201581394U (zh) 大桩尖注浆预制桩
CN108643166B (zh) 一种削弱打拔钢板桩土层振动的施工方法
CN102926382B (zh) 一种smw工法的施工方法
CN207739253U (zh) 带桩靴管桩桩端内锤击沉桩及同步端测注浆结构
CN104153355B (zh) 混凝土桩的施工装置及其施工方法
CN107542081A (zh) 一种深厚填石场地排水板的安装方法及用于该方法中的成孔装置
CN206090541U (zh) 一种冲击成孔的施工装置
CN102493452A (zh) 注浆植桩工法及设备
CN215669558U (zh) 基坑支护体系的前置式斜桩
CN112252312B (zh) 一种增强phc管桩整体受力性能的施工方法
CN214497521U (zh) 一种高压旋喷桩机
CN106149709B (zh) 预制灌注桩的成桩方法
CN104294817B (zh) 混凝土桩的施工方法
KR20120126704A (ko) 스크류파일 시공방법
CN103866763B (zh) 沉管压灌桩的做桩方法和专用装置及应用
CN112323781A (zh) 一种高承载抱压式锤击压灌成桩施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120613