CN102491192A - Tower crane introducing platform structure - Google Patents

Tower crane introducing platform structure Download PDF

Info

Publication number
CN102491192A
CN102491192A CN2011104213709A CN201110421370A CN102491192A CN 102491192 A CN102491192 A CN 102491192A CN 2011104213709 A CN2011104213709 A CN 2011104213709A CN 201110421370 A CN201110421370 A CN 201110421370A CN 102491192 A CN102491192 A CN 102491192A
Authority
CN
China
Prior art keywords
platform
introduction
tower
advances
power traction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011104213709A
Other languages
Chinese (zh)
Other versions
CN102491192B (en
Inventor
吴志纯
朱守寨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zoomlion Heavy Industry Science and Technology Co Ltd
Original Assignee
Zoomlion Heavy Industry Science and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zoomlion Heavy Industry Science and Technology Co Ltd filed Critical Zoomlion Heavy Industry Science and Technology Co Ltd
Priority to CN 201110421370 priority Critical patent/CN102491192B/en
Publication of CN102491192A publication Critical patent/CN102491192A/en
Priority to PCT/CN2012/081955 priority patent/WO2013086879A1/en
Application granted granted Critical
Publication of CN102491192B publication Critical patent/CN102491192B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/26Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Transportation (AREA)
  • Mechanical Engineering (AREA)
  • Jib Cranes (AREA)

Abstract

The invention provides a tower crane introducing platform structure, which comprises an introducing platform, a pull rod and a turning lifting mechanism, wherein the introducing platform has a hinge part which is hinged with the main body of the tower crane; the first end of the pull rod is connected to the main body of the tower crane, while the second end of the pull rod is connected to the introducing platform; and the turning lifting mechanism drives and is connected to the introducing platform, so as to ensure the introducing platform to turn around the hinge part. The tower crane introducing platform structure provided by the invention can prevent the interference of a hook and the platform and reduce potential safety hazard, meanwhile the structure can reduce the introducing platform size, so that the structure is convenient for use and transportation.

Description

The tower power traction advances platform structure
Technical field
The present invention relates to engineering machinery field, particularly a kind of tower power traction advances platform structure.
Background technology
Existing swing arm tower machine, particularly medium and small model swing arm tower machine, introduction of method under adopt in jacking supernumerary segment process more.Because the introduction angle of swing arm tower machine is generally between 84 °~86 °, under the long situation of jib length, when introducing standard knot; Suspension hook is apart from the distance at body of the tower center; Therefore, requiring to introduce the platform extension must be longer, thereby causes swing arm tower machine when wide-angle (by a small margin) is worked; Suspension hook is prone to and introduces the platform interference, influences tower machine efficient working range and safety in utilization.
Simultaneously, different with the platform tower with the tup tower, the introduction amplitude of the different brachiums of swing arm tower machine has nothing in common with each other.Under the long situation of galianconism, corresponding the reducing of introduction amplitude of tower machine requires corresponding reduction to introducing the flat-bed extension; At this moment; The introduction platform that extension is big is also inapplicable, and is even more serious to the influence of tower machine operating range, and it is excessive to introduce the platform oad; Installation and transportation inconvenience, traffic cost is high.
A kind of introduction platform structure of the prior art has been shown among Fig. 1, has introduced platform structure and comprise single platform 21 and pull bar 22 introduced, supplied to introduce carriage walking by the track of forming by shaped steel on it.The shortcoming of this scheme is: (1) single platform 21 of introducing is made up of single platform; Its extension can not change in tower machine course of normal operation, in jib wide-angle (by a small margin), particularly under the long situation of galianconism; Easy and the platform interference of suspension hook; Both influence the efficient working range of swing arm tower machine, also had potential safety hazard, influenced swing arm tower machine safety in utilization.(2) introduction platform 21 sizes are big, and rigidity is little, and transportation is inconvenient.
The another kind of platform structure of introducing of the prior art has been shown among Fig. 2.This introduction platform structure improves on the introduction flat-bed basis in Fig. 1, introduces platform 23 in comprising, introduces platform 24, long draw 25 and short rod 26 outward and form, and introduces platform 24 outward and 23 on interior introduction platform is hinged with bearing pin 27.Jacking is introduced platform 24 outward and can upwards be overturn after finishing.The shortcoming of this scheme is: (1) lacks corresponding upset auxiliary device though introduce flat-bed and introduce platform 24 parts outward and can overturn, the upset inconvenience, and reversal rate is uncontrollable, is prone to cause platform to rock, and has potential safety hazard during aloft work.(2) though introduction platform extension can shorten, and the length that shortens is fixed, under galianconism length situation, introduce platform extension still long (for ease of overturning, its outer introduction platform 24 is shorter relatively), during wide-angle work, suspension hook still possibly interfered with platform.
Summary of the invention
The present invention provides a kind of tower power traction to advance platform, interferes to prevent suspension hook and flat-bed, reduces potential safety hazard, can reduce to introduce simultaneously the flat-bed size, easy to use and transportation.
The present invention realizes through following technical scheme: a kind of tower power traction advances platform structure, comprising: introduce platform, have and tower machine main body pivotally attached articulated section; Pull bar, first end is connected with tower machine main body, and second end is connected with the introduction platform; The upset lift system drives to connect and introduces platform, and the introduction platform is overturn around the articulated section.
Further, introduce platform and comprise outer platform and the interior introduction platform introduced, introduce platform outward and removably be connected with interior introduction platform.
Further, introducing platform outward is connected with interior introduction platform bolted connection or bearing pin.
Further, pull bar is flexible.
Further, pull bar is made up of the more piece bar.
Further, articulate connection between the more piece bar.
Further, upset lift system captive joint tower machine main body drives connection through steel rope and introduces platform.
Further, introduce platform and be provided with the cart stationary otic placode.
Further, interior introduction platform is provided with the stroke limit plate away from an end of tower machine main body.
Further, the stroke limit plate is detachable.
Through technique scheme, major advantage of the present invention is that the turning introduction platform of (1) compound type has the upset lift system; The platform upset is convenient, laborsaving; Reversal rate is stable, controlled, and the impulsive force that produces in the time of can effectively reducing the platform upset improves processing safety.(2) rigidity is introduced platform and can be introduced the platform extension through whole upset and the shortening of decomposition and combination dual mode, can effectively enlarge tower machine operating range, improves the tower machine and is suitable for safety.Simultaneously, it is detachable to introduce platform outward, and interior introduction platform can work independently, and is strong to the applicability of different brachium situation.(3) rigidity is introduced the detachable assembling mode of platform, and installation and transportation are convenient, can reduce traffic cost; Simultaneously, introduce simple in structurely, be easy to promote.
Description of drawings
The accompanying drawing that constitutes a part of the present invention is used to provide further understanding of the present invention, and illustrative examples of the present invention and explanation thereof are used to explain the present invention, does not constitute improper qualification of the present invention.In the accompanying drawings:
Fig. 1 shows the scheme drawing that a kind of tower power traction of the prior art advances platform structure;
Fig. 2 shows the scheme drawing that another kind of tower power traction of the prior art advances platform structure;
The tower power traction that Fig. 3 shows one embodiment of the present of invention advances the schematic side view of the long-armed long status of platform structure;
The tower power traction that Fig. 4 shows one embodiment of the present of invention advances the introduction flat-bed scheme drawing in the platform structure;
The tower power traction that Fig. 5 shows one embodiment of the present of invention advances the schematic side view that platform structure is in collapsed state;
The tower power traction that Fig. 6 shows one embodiment of the present of invention advances the schematic side view of the galianconism long status of platform structure; And
The tower power traction that Fig. 7 shows one embodiment of the present of invention advances the enlarged diagram of the positioning plate part of platform structure.
The specific embodiment
Below in conjunction with accompanying drawing embodiments of the invention are elaborated, but the multitude of different ways that the present invention can be defined by the claims and cover is implemented.
The tower power traction that one embodiment of the present of invention have been shown among Fig. 3 advances the side-looking signal of the long-armed long status of platform structure.Tower power traction of the present invention advances platform structure; Comprise: introduce platform 5, long draw 3 and short rod 6 and 2 three main portions of upset lift system; The pull bar that can be made up of three pair rod of pull bar wherein, this pull bar is designed to and can folds, and also can be flexible drag-line.1 on the frame body structure of climbing of the introduction platform 5 of rigidity and tower machine is hinged with bearing pin 7, and is connected with the shelf structure 1 that climbs through two groups of flexible draw bars 3,6, forms the stability under loading structure.Upset lift system 2 is fixed on the shelf structure 1 that climbs, and introduces platform 5 through steel rope 4 and rigidity and is connected, and is used to pack up steel rope 4 and orders about the 5 upset liftings of introduction platform.
The tower power traction that Fig. 4 shows one embodiment of the present of invention advances the introduction flat-bed scheme drawing in the platform structure.Rigidity is introduced platform 5 and is made up of interior introduction platform 8 and outer platform 11 two parts of introducing, and being rigidly connected is integral to adopt detouchable mode (connect etc. like Bolt Connection, multi-pin axle, connect for bearing pin among Fig. 4) between the two, is convenient to transport and installation.The interior introduction is designed with introduction cart stationary otic placode 9 and detachable dolly stroke limit plate 10 on the platform 8.Cart stationary otic placode 9 is connected with dolly, fixedly dolly.Stroke limit plate 10 is installed in to be introduced the flat-bed far-end and is used to limit dolly and moves.
Turning tower power traction of the present invention advances the flat-bed working process and is:
(1) as shown in Figure 5, under the long-armed long situation, rigidity introduction platform 5 is formed the detachable stroke limit plate 10 in not comprising on the introduction platform 8 by interior introduction platform 8 and the outer platform 11 of introducing.Behind the jacking supernumerary segment, will introduce dolly 12 and be connected, guarantee that dolly 12 can not slide when introducing platform 5 upsets with cart stationary otic placode 9 usefulness bearing pins; Remove long draw 3 and the outer bearing pin of introducing between the platform 11 that is connected, rotate upset lift system 2, steel rope 4 is packed up shortening; Make rigidity introduce upwards upset of platform 5, flexible draw bar 6 respective folded on the interior introduction platform, at this moment; Rigidity is introduced platform 5 extensions and is reduced, and is convenient to the work of tower machine.
(2) under the long situation of galianconism, swing arm tower machine is lower to introducing the overhanging dimensional characteristic of flat-bed, can reduce to introduce the overhanging size of flat-bed through following two kinds of methods:
First method, same situation (1) is the same, realizes through the platform upset.
Second method: like Fig. 6 and shown in Figure 7, remove the outer platform 11 of introducing, dolly stroke limit plate 10 is installed in interior introduction platform 8 ends; Accordingly; Dismounting is fixed on the outer flexible draw bar of introducing on the platform 11 3, and steel rope 4 is connected to above the cart stationary otic placode 9 of interior introduction platform outer end, at this moment; Introduce platform and have and tup tower machine and the similar structural shape of tack tower machine, have turn over function simultaneously.Through platform dismounting and upset, can significantly reduce and introduce the overhanging size of platform, be convenient to the work of tower machine.
Tower power traction according to the present invention advances platform structure, has following beneficial effect:
(1) rigidity introduction platform is made up of two parts, and platform can shorten introduction platform extension through whole upset and decomposition and combination dual mode, can effectively enlarge tower machine operating range, improves the tower machine and is suitable for safety.Simultaneously, it is detachable to introduce platform outward, and interior introduction platform can work independently, and is strong to the applicability of different brachium situation.
(2) the turning introduction platform of novel combination type has the upset lift system, and the platform upset is convenient, laborsaving, and reversal rate is stable, controlled, and the impulsive force that produces in the time of can effectively reducing the platform upset improves processing safety.
(3) rigidity is introduced the detachable assembling mode of platform, and installation and transportation are convenient, can reduce traffic cost; Simultaneously, introduce simple in structurely, be easy to promote.
The above is merely the preferred embodiments of the present invention, is not limited to the present invention, and for a person skilled in the art, the present invention can have various changes and variation.All within spirit of the present invention and principle, any modification of being done, be equal to replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (10)

1. a tower power traction advances platform structure, it is characterized in that, comprising:
Introduce platform (5), have and tower machine main body (1) pivotally attached articulated section (7);
Pull bar (3,6), first end is connected with said tower machine main body (1), and second end is connected with said introduction platform (5);
Upset lift system (2) drives connection said introduction platform (5), and said introduction platform (5) is overturn around said articulated section (7).
2. tower power traction according to claim 1 advances platform structure, it is characterized in that, said introduction platform (5) comprises outer platform (11) and the interior introduction platform (8) introduced, and the said outer platform (11) of introducing removably is connected with the said interior platform (8) of introducing.
3. tower power traction according to claim 2 advances platform structure, it is characterized in that, the said outer platform (11) of introducing is connected with said interior introduction platform (8) bolted connection or bearing pin.
4. tower power traction according to claim 1 advances platform structure, it is characterized in that, said pull bar (3,6) is flexible.
5. tower power traction according to claim 1 advances platform structure, it is characterized in that, said pull bar (3,6) is made up of the more piece bar.
6. tower power traction according to claim 5 advances platform structure, it is characterized in that, articulates between the said more piece bar to connect.
7. tower power traction according to claim 1 advances platform structure, it is characterized in that, said upset lift system (2) is fixedly connected on the said tower machine main body (1), drives through steel rope (4) to connect said introduction platform (5).
8. tower power traction according to claim 1 advances platform structure, it is characterized in that, said introduction platform (5) is provided with cart stationary otic placode (9).
9. tower power traction according to claim 2 advances platform structure, it is characterized in that, said interior introduction platform (8) is provided with stroke limit plate (10) away from an end of said tower machine main body (1).
10. tower power traction according to claim 9 advances platform structure, it is characterized in that, said stroke limit plate (10) is detachable.
CN 201110421370 2011-12-15 2011-12-15 Tower crane introducing platform structure Active CN102491192B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN 201110421370 CN102491192B (en) 2011-12-15 2011-12-15 Tower crane introducing platform structure
PCT/CN2012/081955 WO2013086879A1 (en) 2011-12-15 2012-09-25 Tower crane access platform structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110421370 CN102491192B (en) 2011-12-15 2011-12-15 Tower crane introducing platform structure

Publications (2)

Publication Number Publication Date
CN102491192A true CN102491192A (en) 2012-06-13
CN102491192B CN102491192B (en) 2013-10-16

Family

ID=46183063

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110421370 Active CN102491192B (en) 2011-12-15 2011-12-15 Tower crane introducing platform structure

Country Status (2)

Country Link
CN (1) CN102491192B (en)
WO (1) WO2013086879A1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103058072A (en) * 2012-12-31 2013-04-24 大连理工大学 Large luffing jib tower crane introduction mechanism
WO2013086879A1 (en) * 2011-12-15 2013-06-20 中联重科股份有限公司 Tower crane access platform structure
CN103171980A (en) * 2013-04-03 2013-06-26 中联重科股份有限公司 Tower crane and launching beam and launching system thereof
CN103723638A (en) * 2014-01-13 2014-04-16 中联重科股份有限公司 Climbing frame of tower crane and tower crane
WO2022057082A1 (en) * 2020-09-21 2022-03-24 徐州建机工程机械有限公司 Foldable introducing mechanism

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108128714B (en) * 2017-12-13 2019-05-14 江麓机电集团有限公司 A kind of derrick crane introduction platform safety protective device
CN110027992B (en) * 2019-05-15 2024-04-12 沈阳建筑大学 Automatic jacking and positioning device and method for standard section of tower crane

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB714819A (en) * 1951-10-16 1954-09-01 Tichauer M Improvements in or relating to tower cranes and means for erecting same
DE1032908B (en) * 1953-09-22 1958-06-26 Tichauer Sarl M Tower crane with a height-adjustable, rotatable boom along a mast
DE1035334B (en) * 1955-01-04 1958-07-31 Maschf Augsburg Nuernberg Ag Procedure for erecting construction cranes
DE1245559B (en) * 1960-06-28 1967-07-27 Otto Kaiser K G Maschf Height-adjustable tower crane, especially high-rise crane
SU506570A1 (en) * 1972-07-21 1976-03-15 Центральное Конструкторское Бюро "Строймаш" Tower crane for construction work
DE3226211A1 (en) * 1981-12-21 1983-07-14 Liebherr-Werk Biberach Gmbh, 7950 Biberach Tower tip with counter-jib
CN201313792Y (en) * 2008-11-18 2009-09-23 江麓机电科技有限公司 Lengthened hinge introducing platform of tower crane
CN201334326Y (en) * 2008-12-31 2009-10-28 长沙中联重工科技发展股份有限公司 Pull rod for balance arm of flat-top tower crane

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3977531A (en) * 1973-05-03 1976-08-31 Sam P. Wallace Company, Inc. Stiff-leg crane
CN2665098Y (en) * 2003-12-29 2004-12-22 中国建筑科学研究院建筑机械化研究分院 Hydraulic hoisting level bridge
JP2009149438A (en) * 2007-11-29 2009-07-09 Manitowoc Crane Companies Ltd Connection system for crane boom segment
CN201495048U (en) * 2009-08-24 2010-06-02 中昇建机(南京)重工有限公司 Double movable-arm crane used for iron tower installation
CN201971572U (en) * 2010-09-27 2011-09-14 中昇建机(南京)重工有限公司 Movable arm type tower crane with suspension arm possible of being folded for dismounting
CN102491192B (en) * 2011-12-15 2013-10-16 中联重科股份有限公司 Tower crane introducing platform structure

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB714819A (en) * 1951-10-16 1954-09-01 Tichauer M Improvements in or relating to tower cranes and means for erecting same
DE1032908B (en) * 1953-09-22 1958-06-26 Tichauer Sarl M Tower crane with a height-adjustable, rotatable boom along a mast
DE1035334B (en) * 1955-01-04 1958-07-31 Maschf Augsburg Nuernberg Ag Procedure for erecting construction cranes
DE1245559B (en) * 1960-06-28 1967-07-27 Otto Kaiser K G Maschf Height-adjustable tower crane, especially high-rise crane
SU506570A1 (en) * 1972-07-21 1976-03-15 Центральное Конструкторское Бюро "Строймаш" Tower crane for construction work
DE3226211A1 (en) * 1981-12-21 1983-07-14 Liebherr-Werk Biberach Gmbh, 7950 Biberach Tower tip with counter-jib
CN201313792Y (en) * 2008-11-18 2009-09-23 江麓机电科技有限公司 Lengthened hinge introducing platform of tower crane
CN201334326Y (en) * 2008-12-31 2009-10-28 长沙中联重工科技发展股份有限公司 Pull rod for balance arm of flat-top tower crane

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013086879A1 (en) * 2011-12-15 2013-06-20 中联重科股份有限公司 Tower crane access platform structure
CN103058072A (en) * 2012-12-31 2013-04-24 大连理工大学 Large luffing jib tower crane introduction mechanism
CN103058072B (en) * 2012-12-31 2015-04-08 大连理工大学 Large luffing jib tower crane introduction mechanism
CN103171980A (en) * 2013-04-03 2013-06-26 中联重科股份有限公司 Tower crane and launching beam and launching system thereof
CN103171980B (en) * 2013-04-03 2015-07-15 中联重科股份有限公司 Tower crane and launching beam and launching system thereof
CN103723638A (en) * 2014-01-13 2014-04-16 中联重科股份有限公司 Climbing frame of tower crane and tower crane
CN103723638B (en) * 2014-01-13 2015-09-09 中联重科股份有限公司 The climbing support of tower crane and tower crane
WO2022057082A1 (en) * 2020-09-21 2022-03-24 徐州建机工程机械有限公司 Foldable introducing mechanism

Also Published As

Publication number Publication date
CN102491192B (en) 2013-10-16
WO2013086879A1 (en) 2013-06-20

Similar Documents

Publication Publication Date Title
CN102491192B (en) Tower crane introducing platform structure
CN202463955U (en) Non-snubbing equipment trailer
CN101712439B (en) Crane transition auxiliary device, transport trailer and method for dismantling crane
CN102659029B (en) Combined type movable hanger
CN201024052Y (en) Traction type crane
US9150390B2 (en) Modular mobile crane
CN201580913U (en) Crane transition auxiliary device, transportation trailer
CN103145052A (en) Movable circular track type crane
CN105036014A (en) Multifunctional working hanging basket for railway tunnel
CN203128069U (en) Movable circular-track type crane
CN102320331B (en) Traveling vehicle chassis
CN102826447B (en) Truss jib crane as well as getting-off structure and position transferring method thereof
CN202296907U (en) Suspension arm balanced movable arm tower crane capable of luffing based on steel rope traction
CN204340820U (en) A kind of blowout prevention service rig special vehicle
CN102303821A (en) Luffing tower crane with balanced type suspension arm based on traction luffing of steel rope
CN113321139A (en) Lifting hook assembly and lifting machinery
CN101955133B (en) Movable crane
CN101357743B (en) Crane hook magnification-changing mechanism of movable arm variation-amplitude crane
CN103253602B (en) The elevated super lifting device of crawler vehicle voluntarily and hoisting crane
CN104533461A (en) Tunnel construction trolley lateral movement device
CN103896166A (en) Pallet carrier lifting device and pallet carrier
CN216190463U (en) Novel 20T monorail crane heavy lifting beam
CN212292588U (en) Foldable introduction mechanism
CN110641565B (en) Box culvert handling tool car
CN203212252U (en) Container transportation vehicle hoisting device and container transportation vehicle

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP02 Change in the address of a patent holder

Address after: 415106 Dingcheng City, Changde Province, the town of irrigation district ZOOMLION Creek Industrial Park

Patentee after: ZOOMLION HEAVY INDUSTRY SCIENCE&TECHNOLOGY Co.,Ltd.

Address before: 410013 Yuelu District, Hunan, silver basin Road, No. 361, No.

Patentee before: ZOOMLION HEAVY INDUSTRY SCIENCE&TECHNOLOGY Co.,Ltd.

CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 410013 Yuelu District, Hunan, silver basin Road, No. 361, No.

Patentee after: ZOOMLION HEAVY INDUSTRY SCIENCE&TECHNOLOGY Co.,Ltd.

Address before: 415106 Dingcheng City, Changde Province, the town of irrigation district ZOOMLION Creek Industrial Park

Patentee before: ZOOMLION HEAVY INDUSTRY SCIENCE&TECHNOLOGY Co.,Ltd.