CN102480109A - Method for replacing 10kV distribution line lead under load - Google Patents

Method for replacing 10kV distribution line lead under load Download PDF

Info

Publication number
CN102480109A
CN102480109A CN2010105631914A CN201010563191A CN102480109A CN 102480109 A CN102480109 A CN 102480109A CN 2010105631914 A CN2010105631914 A CN 2010105631914A CN 201010563191 A CN201010563191 A CN 201010563191A CN 102480109 A CN102480109 A CN 102480109A
Authority
CN
China
Prior art keywords
wire
wires
replacing
distribution line
new
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010105631914A
Other languages
Chinese (zh)
Inventor
罗洪舟
陈岳
宋朝晖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HARBIN ELECTRIC POWER BUREAU
State Grid Corp of China SGCC
Original Assignee
HARBIN ELECTRIC POWER BUREAU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HARBIN ELECTRIC POWER BUREAU filed Critical HARBIN ELECTRIC POWER BUREAU
Priority to CN2010105631914A priority Critical patent/CN102480109A/en
Publication of CN102480109A publication Critical patent/CN102480109A/en
Pending legal-status Critical Current

Links

Landscapes

  • Electric Cable Installation (AREA)

Abstract

一种带负荷更换10kV配电线路导线的方法,属于电力系统带电作业技术领域,采用了旁路作业技术,主要是在故障的耐张段内安装放线装置,用于释放短接线和新导线,同时利用该装置完成新旧导线的替换,与公知的更换导线方法相比,此方法不需要切断负荷,能够在不影响用户正常用电的情况下完成导线的更换工作。A method for replacing a 10kV distribution line conductor under load belongs to the technical field of live working in an electric power system and adopts a bypass working technology. A wire-releasing device is mainly installed in a faulty tension section to release a short-circuit wire and a new conductor. The device is used to replace the old and new conductors. Compared with the known conductor replacement method, this method does not require cutting off the load and can complete the conductor replacement work without affecting the normal power consumption of users.

Description

一种带负荷更换10kV配电线路导线的方法A Method of Replacing Conductors of 10kV Distribution Lines with Load

技术领域 technical field

本发明属于电力系统带电作业技术领域,特别指一种带负荷更换10kV架空配电线路导线的方法。The invention belongs to the technical field of live work in electric power systems, in particular to a method for replacing conductors of 10kV overhead power distribution lines with load.

背景技术 Background technique

10kV架空配电线路长期暴露在自然界中产生老化、由于施工质量问题以及日常维护不足、负荷过大、外力破坏等诸多因素而导致接点易发生烧损,从而伤及配电线路的干线,此种情况时有发生。若停电更换导线,则由于工作量大,导致停电维修时间过长,将严重影响供电可靠性指标。给供电企业造成较大的经济损失,同时停电时间过长,而给企业带来的社会负面影响更是无法估量,尤其发生在双回或多回并架的线路,其影响和损失也将成倍增加。The 10kV overhead distribution line is exposed to nature for a long time to cause aging. Due to many factors such as construction quality problems, insufficient daily maintenance, excessive load, and external force damage, the contacts are prone to burnout, thereby damaging the main line of the distribution line. Situations happen from time to time. If the wire is replaced due to a power outage, due to the heavy workload, the power outage maintenance time will be too long, which will seriously affect the power supply reliability index. It will cause large economic losses to power supply companies, and the power outage will be too long at the same time, and the negative impact on the society brought to enterprises is even more immeasurable, especially if it occurs in double-circuit or multi-circuit parallel lines, its impact and loss will also become multiplied.

发明内容 Contents of the invention

为了解决以上的问题,发明一种带负荷更换10kV配电线路导线的方法,在配电线路出现故障时,带着10kV配电线路负荷电流,更换损伤的绝缘导线。In order to solve the above problems, a method for replacing the wires of 10kV distribution lines with load is invented. When the distribution lines fail, the damaged insulated wires are replaced with the load current of the 10kV distribution lines.

本发明解决其技术问题所采用的技术方案是:The technical solution adopted by the present invention to solve its technical problems is:

1、在故障的耐张段内安装放线装置,用于释放短接线和新导线。同时利用该装置完成新旧导线的替换。1. Install a pay-off device in the faulty tension section to release short wires and new wires. At the same time, the device is used to complete the replacement of old and new wires.

2、短接故障相导线后,对故障点进行检查,必要时加固处理,防止断线。2. After short-circuiting the faulty phase conductor, check the fault point, and reinforce it if necessary to prevent disconnection.

3、在两侧短接点处,切断故障相导线使其退出运行后,分别在故障段内的直线杆横担处安装绝缘放线滑车,并将故障相导线导入放线滑车。3. At the short-circuit point on both sides, after cutting off the faulty phase wire to make it out of operation, install an insulating pay-off block at the cross-arm of the straight pole in the fault section, and guide the faulty phase wire into the pay-off block.

4、通过杆身绝缘放线装置,利用导线连接器将新、旧导线进行连接,施加牵引力,新导线传至杆上,旧导线退至杆下实现新旧导线的替换。4. Connect the new and old wires with the wire connector through the shaft insulation pay-off device, apply traction, the new wires are passed to the rod, and the old wires are retreated under the rod to realize the replacement of the new and old wires.

5、新导线投入运行,断开临时短接线,解列回收。5. When the new wire is put into operation, disconnect the temporary short-circuit wire, disassemble and recycle.

此方法还适用于裸导线更换为绝缘导线、将运行中的线路更换为大型号的绝缘导线。This method is also applicable to the replacement of bare wires with insulated wires, and the replacement of running lines with large-scale insulated wires.

本发明所产生的效益是:目前一条平均负荷大于300安培的10千伏配电线路,若停电迁移线路,从办理停电手续到交令送电需要8-10小时;根据目前的电价所损失的电量,折合人民币约为19098.8元。目前应用该项技术已经成功的迁移10千伏配电线路20条相当于为供电企业多创产值:38.2万元。目前1度电的社会效益为30元,挽回经济损失约1122336元。社会综合效益方面:电网可靠性大大提高的同时,提高了电力企业的社会形象,极大满足社会的用电需求,开拓了社会经济新的增长点,为供电地区经济的发展作好前期基础工作。同时对维护和提高政府的形象具有重要作用。The benefits produced by the present invention are: at present, a 10 kV power distribution line with an average load greater than 300 amperes, if the power outage moves the line, it takes 8-10 hours from going through the power outage procedure to ordering power transmission; according to the current electricity price, the loss Electricity, equivalent to RMB 19098.8. At present, the application of this technology has successfully migrated 20 10kV power distribution lines, which is equivalent to creating more output value for power supply enterprises: 382,000 yuan. At present, the social benefit of 1 kilowatt-hour of electricity is 30 yuan, and the economic loss is about 1,122,336 yuan. In terms of comprehensive social benefits: while the reliability of the power grid has been greatly improved, the social image of the power company has been improved, the electricity demand of the society has been greatly met, a new growth point of the social economy has been opened up, and the preliminary work has been done for the economic development of the power supply area. . At the same time, it plays an important role in maintaining and improving the image of the government.

具体实施方式 Detailed ways

(1)导线损伤需要更换时,一般需要更换整个耐张段的一相导线。因此短接点应该分别选择在耐张段中的两个耐张杆的过引线上,其位置应靠近故障段以外的一侧。如此非故障段的干线外皮可不破损,同时便于并列和解列。如果短接点任何一处受条件限制,可选择离故障点较近的直线杆,将其改为耐张杆后设为短接点。(1) When the wire is damaged and needs to be replaced, it is generally necessary to replace the one-phase wire of the entire tension section. Therefore, the short-circuit points should be respectively selected on the lead wires of the two tension rods in the tension section, and their positions should be close to the side other than the faulty section. In this way, the sheath of the main line of the non-faulty section can not be damaged, and at the same time, it is convenient for paralleling and splitting. If any of the short-circuit points is limited by conditions, you can choose a straight rod that is closer to the fault point, change it to a tension rod and set it as a short-circuit point.

(2)短接点设定后,在耐张段内的每个电杆横担上安装绝缘放线滑车,每个电杆身上距地面3.0米处安装绝缘放线装置。(2) After the short-circuit point is set, an insulating pay-off trolley is installed on each pole cross arm in the tension section, and an insulating pay-off device is installed on each pole body 3.0 meters from the ground.

(3)通过电杆身上的绝缘放线装置,释放短接线和待换的新导线至短接点。(3) Release the short wiring and the new wire to be replaced to the short contact point through the insulation release device on the pole body.

(4)通过接引线的方式空充短接线,核对相序后将短接线与故障相导线并列,实现故障点的短接目的。(4) By connecting the lead wires, empty-charge the short-circuit wires, and after checking the phase sequence, put the short-circuit wires in parallel with the faulty phase wires to achieve the purpose of short-circuiting the fault point.

(5)利用电流测试仪确定短接线通流良好,用断引线的方式切断耐张段故障相两侧耐张杆上的引线,线路负荷电流全部通过临时短接线流过,耐张段内的故障相导线无电压。(5) Use the current tester to confirm that the short-circuit current is good, and cut off the lead wires on the tension rods on both sides of the fault phase of the tension section by breaking the lead wire. The load current of the line flows through the temporary short-circuit. There is no voltage in the faulty phase conductor.

(6)利用导线连接器连接新旧导线。打开每个电杆上固定旧导线(故障相)的绝缘子绑线,将其放入绝缘放线滑车。施加牵引力,实现新旧导线替换。将新导线固定在每个电杆的绝缘子上。(6) Use wire connectors to connect the old and new wires. Open the insulator binding wire that fixes the old wire (faulty phase) on each pole, and put it into the insulation pay-off trolley. Apply traction to replace old and new wires. Secure the new wires to the insulators on each pole.

(7)将新导线接入线路,断开临时短接线,线路负荷电流全部转入新导线带配,最终实现故障相导线的更换工作。(7) Connect the new wire to the line, disconnect the temporary short-circuit wire, and transfer all the load current of the line to the new wire belt distribution, and finally realize the replacement of the faulty phase wire.

Claims (5)

1.一种带负荷更换10kV配电线路导线的方法,其特征是:采用了旁路作业技术,不需要切断负荷,能够在不影响用户正常用电的情况下完成导线的更换工作。1. A method for replacing 10kV distribution line conductors with load, characterized in that: the bypass operation technology is adopted, the load does not need to be cut off, and the replacement of the conductors can be completed without affecting the normal power consumption of users. 2.根据权利要求1所述的一种带负荷更换10kV配电线路导线的方法,其特征是:在故障的耐张段内安装放线装置,用于释放短接线和新导线,同时利用该装置完成新旧导线的替换。2. A method for replacing 10kV distribution line conductors with load according to claim 1, characterized in that: a wire release device is installed in the strain-resistant section of the fault to release the short wiring and new conductors, and at the same time use the The device completes the replacement of old and new wires. 3.根据权利要求1所述的一种带负荷更换10kV配电线路导线的方法,其特征是:短接故障相导线后,对故障点进行检查,必要时加固处理,防止断线。3. A method for replacing the wires of a 10kV distribution line with load according to claim 1, characterized in that: after the faulty phase wires are short-circuited, the fault point is checked and reinforced if necessary to prevent disconnection. 4.根据权利要求1所述的一种带负荷更换10kV配电线路导线的方法,其特征是:在两侧短接点处,切断故障相导线使其退出运行后,分别在故障段内的直线杆横担处安装绝缘放线滑车,并将故障相导线导入放线滑车。4. A method for replacing the wires of a 10kV distribution line with load according to claim 1, characterized in that: after the faulty phase wires are cut off at the short-circuit points on both sides to make them quit running, the straight lines in the faulty section respectively An insulating pay-off block is installed at the cross-arm of the pole, and the faulty phase conductor is guided into the pay-off block. 5.根据权利要求1所述的一种带负荷更换10kV配电线路导线的方法,其特征是:通过杆身绝缘放线装置,利用导线连接器将新、旧导线进行连接,施加牵引力,新导线传至杆上,旧导线退至杆下实现新旧导线的替换。5. A method for replacing the wires of a 10kV distribution line with load according to claim 1, characterized in that: the new wire and the old wire are connected by a wire connector through a shaft insulation release device, and traction is applied to the new wire. The wire is passed to the rod, and the old wire is retreated under the rod to realize the replacement of the old and new wire.
CN2010105631914A 2010-11-29 2010-11-29 Method for replacing 10kV distribution line lead under load Pending CN102480109A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010105631914A CN102480109A (en) 2010-11-29 2010-11-29 Method for replacing 10kV distribution line lead under load

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010105631914A CN102480109A (en) 2010-11-29 2010-11-29 Method for replacing 10kV distribution line lead under load

Publications (1)

Publication Number Publication Date
CN102480109A true CN102480109A (en) 2012-05-30

Family

ID=46092641

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010105631914A Pending CN102480109A (en) 2010-11-29 2010-11-29 Method for replacing 10kV distribution line lead under load

Country Status (1)

Country Link
CN (1) CN102480109A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103594961A (en) * 2013-11-01 2014-02-19 国家电网公司 Method for replacing cable
CN107947029A (en) * 2018-01-03 2018-04-20 宁波华翔东方电力机具有限公司 A kind of distribution line crosses over shelves thread-changing coaster and its thread-changing method
CN112242665A (en) * 2020-09-29 2021-01-19 浙江大有实业有限公司带电作业分公司 Power distribution network overhead conductor replacing method
CN112582938A (en) * 2020-11-12 2021-03-30 国核电力规划设计研究院有限公司 Overhead ground wire replacing method
CN114614399A (en) * 2022-03-04 2022-06-10 国网浙江省电力有限公司金华供电公司 Working method of load-carrying shifting tension rod

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101888070A (en) * 2009-05-15 2010-11-17 上海市南电力工程有限公司 10KV bypass cable operation method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101888070A (en) * 2009-05-15 2010-11-17 上海市南电力工程有限公司 10KV bypass cable operation method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
佚名: "黑龙江电力公司带负荷更换10kV配电线路导线技术国内领先", 《内蒙古电力技术》, vol. 27, no. 4, 31 August 2009 (2009-08-31) *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103594961A (en) * 2013-11-01 2014-02-19 国家电网公司 Method for replacing cable
CN103594961B (en) * 2013-11-01 2016-08-24 国家电网公司 A kind of method changing cable
CN107947029A (en) * 2018-01-03 2018-04-20 宁波华翔东方电力机具有限公司 A kind of distribution line crosses over shelves thread-changing coaster and its thread-changing method
CN112242665A (en) * 2020-09-29 2021-01-19 浙江大有实业有限公司带电作业分公司 Power distribution network overhead conductor replacing method
CN112242665B (en) * 2020-09-29 2022-04-29 浙江大有实业有限公司带电作业分公司 Power distribution network overhead conductor replacing method
CN112582938A (en) * 2020-11-12 2021-03-30 国核电力规划设计研究院有限公司 Overhead ground wire replacing method
CN114614399A (en) * 2022-03-04 2022-06-10 国网浙江省电力有限公司金华供电公司 Working method of load-carrying shifting tension rod
CN114614399B (en) * 2022-03-04 2023-10-20 国网浙江省电力有限公司金华供电公司 An operating method for moving tension rods under load

Similar Documents

Publication Publication Date Title
CN102255274B (en) Direct-current ice melting method for overhead ground wire and composite optical fiber ground wire
EP3216644B1 (en) Distributed protection system for power supply at sections of electrified railway propulsion system
CN103247992B (en) The direct current ice melting method of the common overhead ground wire of transmission line and OPGW
CN101888073A (en) On-load opened and segmented operating method of 10kV line
CN101242087A (en) Ice fusion method for power transmission line
CN102480109A (en) Method for replacing 10kV distribution line lead under load
CN102403780A (en) Power supply device for bypass to operate without power failure
CN103532047B (en) A kind of operational method and device changing fuse switch on 10kV post
CN106980067B (en) Disconnection identification method based on comparison of zero-sequence voltage differential value
CN103368122B (en) Ground wire DC ice melting automatic connection system
CN202930802U (en) Movable type distribution transformer allowing uninterruptible power supply mounting and dismounting
CN201075318Y (en) Insulator string electrical arc discharge apparatus
CN104113002B (en) A kind of high tension cable cross connection grounding system switching device
CN206931917U (en) Low voltage failure, which does not have a power failure, handles shunting device
CN113851990A (en) Method for replacing box-type transformer with low-voltage side completely uninterrupted
CN202094322U (en) Multipurpose lead wiring device of large-scale transformer test
CN101907675B (en) Method for finding out fault of distribution network circuit
CN116131191A (en) Uninterrupted DC ice melting method for extra-high voltage DC line overhead ground wire
CN101552434A (en) Bypass current working method
CN102568973B (en) Temporary connecting device for live-line replacement of fuse tube of drop type fuse
CN201910386U (en) Temporary connecting device for live replacement of fuse tube of drop-out fuse
CN206195248U (en) Electrified bypass equipment who changes with equipment on pole multiloop shaft tower
CN103730201A (en) High-resistance steel core ice melting wire
CN101908750B (en) Self-adaptively grounded lightning wire deicing circuit
CN107121619B (en) A kind of electric substation's route protection service without power-off device and repair method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Effective date: 20121024

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 150010 HARBIN, HEILONGJIANG PROVINCE TO: 150001 HARBIN, HEILONGJIANG PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20121024

Address after: 150001 Heilongjiang city of Harbin province Daoli District Shangzhi Street No. 188

Applicant after: Harbin Electric Power Bureau

Applicant after: State Grid Corporation of China

Address before: 150010 Heilongjiang city of Harbin province Daoli District Shangzhi Street No. 188

Applicant before: Harbin Electric Power Bureau

C05 Deemed withdrawal (patent law before 1993)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120530