CN102444089B - Prefabricated part assembled windproof open cut tunnel in gale region and joint assembling and connecting method thereof - Google Patents

Prefabricated part assembled windproof open cut tunnel in gale region and joint assembling and connecting method thereof Download PDF

Info

Publication number
CN102444089B
CN102444089B CN 201210001447 CN201210001447A CN102444089B CN 102444089 B CN102444089 B CN 102444089B CN 201210001447 CN201210001447 CN 201210001447 CN 201210001447 A CN201210001447 A CN 201210001447A CN 102444089 B CN102444089 B CN 102444089B
Authority
CN
China
Prior art keywords
prefabricated units
piece
open cut
joint
cut tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 201210001447
Other languages
Chinese (zh)
Other versions
CN102444089A (en
Inventor
李国良
王争鸣
黄双林
何永旺
杨国柱
靳宝成
严文翔
刘培硕
刘赪
田鹏
于介
谭永庆
贾元霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Survey and Design Institute Group Ltd
Original Assignee
China Railway First Survey and Design Institute Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Survey and Design Institute Group Ltd filed Critical China Railway First Survey and Design Institute Group Ltd
Priority to CN 201210001447 priority Critical patent/CN102444089B/en
Publication of CN102444089A publication Critical patent/CN102444089A/en
Application granted granted Critical
Publication of CN102444089B publication Critical patent/CN102444089B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to a prefabricated part assembled windproof open cut tunnel in the gale region and a joint assembling and connecting method thereof. The open cut tunnel structure manufactured by splicing prefabricated parts is adopted and the joints are the weak links and are complex in force bearing. The method comprises the following steps of: dividing a windproof open cut tunnel into 2m or 3m annular parts along the longitudinal direction and prefabricating the parts, wherein each annular part is divided into a vault block, two hance blocks and two side wall blocks; adopting an embedded post-poured concrete rigid connection method to connect side wall fabricated parts to a foundation longitudinal beam; adopting a post-poured concrete rigid connection method to connect arch prefabricated parts to arch springing prefabricated parts; adopting a bolted clamp plate type connection method to connect the arch springing prefabricated parts to the side wall fabricated parts; and connecting rings in each unit with mortises. The open cut tunnel and the method have the following advantages that: the pertinent connection methods are selected to splice the prefabricated parts of the open cut tunnel in the positions with different force bearing conditions, thus greatly speeding up the construction progress, ensuring the stability of the overall structure of the spliced open cut tunnel, meeting the rigidity requirement of the joints and ensuring safety and reliability in connection.

Description

The windproof open cut tunnel of strong wind district splicing prefabricated components formula and joint assembly unit method of attachment thereof
Technical field
The invention belongs to the traffic engineering technical field, be specifically related to the windproof open cut tunnel of a kind of strong wind district splicing prefabricated components formula and joint assembly unit method of attachment thereof.
Background technology
In the strong wind area, as Bai Lifeng district and the three Shi Lifeng districts in Xinjiang, its core space not only wind-force is powerful, and the frequency height of strong wind occurs.The Lan-xing Railway second two-wire passes famous Bai Lifeng district, three Shi Lifeng districts, its wind-force is powerful, maximum wind velocity reaches 60m/s, the annual strong wind fate greater than strong gale in Bai Lifeng district was above 200 days, windburn is very serious, in order to guarantee train safe, quick, normal operation, reduces speed limit to greatest extent and stops wheel, need be with the relative isolation of external environment with environment, thus environment and the external world are independent of each other.Traditional wind shielding structure generally adopts the windbreak that certain altitude is set in the road both sides, can make external environment and the influence of driving within the walls that certain reducing arranged, but effect is not clearly, and long-pending sand phenomenon is serious on the contrary.Windproof open cut tunnel also can effectively solve the problems of the technologies described above, but Bai Lifeng district, three Shi Lifeng district core spaces, be located in the Gobi desert Desert Area, natural environment is abominable, and execution conditions are poor, needs to adopt prefabricated reinforced concrete structure, connection seam between the prefabricated units is the weak link of windproof open cut tunnel structure, stressed complexity is the key of open cut tunnel design and construction, and is very big to the stress influence of open cut tunnel structure.
Summary of the invention
The purpose of this invention is to provide a kind of structural integrity and the windproof open cut tunnel of strong wind district splicing prefabricated components formula that is connected durability and joint assembly unit method of attachment thereof that can effectively improve between spliced windproof open cut tunnel prefabricated units.
The technical solution adopted in the present invention is:
The joint assembly unit method of attachment of the windproof open cut tunnel of strong wind district splicing prefabricated components formula is characterized in that:
Realized by following steps:
Step 1: windproof open cut tunnel longitudinally is separated into 2m or the long annular construction member of 3m, and every ring divides five, the vault piece in the middle of namely the arch of arc is divided into and the haunch piece of both sides, the abutment wall piece of both sides; Vault piece, haunch piece and abutment wall piece all adopt prefabricated units;
Step 2: the pouring concrete mode that is rigidly connected is connected to abutment wall piece prefabricated units on the basic longeron after adopting flush type, the joint of abutment wall piece prefabricated units arranges the main muscle of the connection that laterally exposes, the joint of basis longeron arranges the main muscle of the connection that vertically exposes, after abutment wall piece prefabricated units place the holddown groove of basic longeron top interior, laterally connecting reinforcement is connected with vertical connecting reinforcement racking seizing, builds the microdilatancy pea gravel concreten on it;
Step 3: adopt the back pouring concrete mode that is rigidly connected that vault piece prefabricated units are connected on the haunch piece prefabricated units, the joint of vault piece prefabricated units and haunch piece prefabricated units all is embedded with and is connected the shaped steel anchor plate, the inboard that connects the shaped steel anchor plate arranges and connects the shaped steel anchor bar, the arranged outside that connects the shaped steel anchor plate connects shaped steel, after will connecting shaped steel and be connected and fixed by screw or welding, build the microdilatancy pea gravel concreten on it, wherein bury the main muscle of connection underground;
Step 4: adopt the board-like connected mode of bolt clip that haunch piece prefabricated units are connected on the abutment wall piece prefabricated units, the joint of haunch piece prefabricated units and abutment wall piece prefabricated units all is provided with the anchor bar that exposes, on the both sides sidewall of the joint of haunch piece prefabricated units and abutment wall piece prefabricated units pre-embedded steel slab is set all, anchor bar is set on the pre-embedded steel slab, be welded to connect steel plate outside two pre-embedded steel slabs up and down, and be connected and fixed pre-embedded bolt hole stiffener around the bolt hole with connecting bolt;
Step 5: vault piece prefabricated units, two haunch piece prefabricated units and two abutment wall piece prefabricated units connect into an annular construction member, initial ring, several standard rings and an end-rings are formed a linkage unit, ring joint between each annular construction member is set to " L " shape tongue and groove, and tongue-and-groove connects; Deformation joint is set between the linkage unit.
The windproof open cut tunnel of strong wind district splicing prefabricated components formula that joint assembly unit method of attachment as described obtains.
The present invention has the following advantages:
Manufacture method of the present invention, select for use connected mode targetedly that the prefabricated units of open cut tunnel are spliced in the different position of stress condition, guaranteed the integrally-built stability of spliced open cut tunnel, satisfied the rigidity requirement of seam, connect safe and reliable, construction speed is fast, the strong wind district operation that the condition that is applicable to is comparatively abominable, and operation maintenance work amount is little.
Description of drawings
Fig. 1 is pouring concrete rigid joint figure behind the arch.
Fig. 2 is the I-I sectional drawing among Fig. 1.
Fig. 3 is the II-II sectional drawing among Fig. 1.
Fig. 4 is arch springing joint plane outspread drawing.
Fig. 5 is arch springing joint sectional drawing.
Fig. 6 is foundation joint plane outspread drawing.
Fig. 7 is the I-I sectional drawing among Fig. 6.
Fig. 8 is the II-II sectional drawing among Fig. 6.
Fig. 9 cuts open figure for vertical tongue-and-groove connects.
Figure 10 is the A portion enlarged drawing among Fig. 9.
Among the figure, 1-vault piece prefabricated units, 2-connects main muscle, and 3-connects shaped steel, 4-connects the shaped steel anchor plate, and 5-connects shaped steel anchor bar, 6-microdilatancy pea gravel concreten, 7-haunch piece prefabricated units, 8-abutment wall piece prefabricated units, the 9-connecting bolt, 10-connects steel plate, 11-pre-embedded steel slab, the 12-anchor bar, 13-bolt hole stiffener, 14-basis longeron, 15-deformation joint, 16-connect main muscle, 17-microdilatancy pea gravel concreten, the initial ring of 18-, 19-standard ring, 20-end-rings.
The specific embodiment
The present invention will be described in detail below in conjunction with the specific embodiment.
The joint assembly unit method of attachment of the windproof open cut tunnel of strong wind of the present invention district splicing prefabricated components formula is realized by following steps:
Step 1: windproof open cut tunnel longitudinally is separated into 2m or the long annular construction member of 3m, and every ring divides five, the vault piece in the middle of namely the arch of arc is divided into and the haunch piece of both sides, the abutment wall piece of both sides; Vault piece, haunch piece and abutment wall piece all adopt prefabricated units.
Step 2: the pouring concrete mode that is rigidly connected is connected to abutment wall piece prefabricated units 8 on the basic longeron 14 after adopting flush type, the joint of abutment wall piece prefabricated units 8 arranges the main muscle 16 of the connection that laterally exposes, the joint of basis longeron 14 arranges the main muscle 16 of the connection that vertically exposes, after abutment wall piece prefabricated units 8 place the holddown groove of basic longeron 14 tops interior, laterally connecting reinforcement is connected with vertical connecting reinforcement racking seizing, builds microdilatancy pea gravel concreten 17 on it.
Step 3: adopt the back pouring concrete mode that is rigidly connected that vault piece prefabricated units 1 are connected on the haunch piece prefabricated units 7, the joint of vault piece prefabricated units 1 and haunch piece prefabricated units 7 all is embedded with and is connected shaped steel anchor plate 4, the inboard that connects shaped steel anchor plate 4 arranges and connects shaped steel anchor bar 5, the arranged outside that connects shaped steel anchor plate 4 connects shaped steel 3, after will connecting shaped steel 3 and be connected and fixed by screw or welding, build microdilatancy pea gravel concreten 17 on it, wherein bury the main muscle 2 of connection underground.
Step 4: adopt the board-like connected mode of bolt clip that haunch piece prefabricated units 7 are connected on the abutment wall piece prefabricated units 8, the joint of haunch piece prefabricated units 7 and abutment wall piece prefabricated units 8 all is provided with the anchor bar 12 that exposes, on the both sides sidewall of the joint of haunch piece prefabricated units 7 and abutment wall piece prefabricated units 8 pre-embedded steel slab 11 is set all, anchor bar 12 is set on the pre-embedded steel slab 11, be welded to connect steel plate 10 in two pre-embedded steel slab 11 outsides up and down, and be connected and fixed pre-embedded bolt hole stiffener 13 around the bolt hole with connecting bolt 9.
Step 5: vault piece prefabricated units 1, two haunch piece prefabricated units 7 and two abutment wall piece prefabricated units 8 connect into an annular construction member, initial ring 18, several standard rings 19 and an end-rings 20 are formed a linkage unit, ring joint between each annular construction member is set to " L " shape tongue and groove, and tongue-and-groove connects; Deformation joint 15 is set between the linkage unit.

Claims (2)

1. the joint assembly unit method of attachment of the windproof open cut tunnel of strong wind district splicing prefabricated components formula is characterized in that:
Realized by following steps:
Step 1: windproof open cut tunnel longitudinally is separated into 2m or the long annular construction member of 3m, and every ring divides five, the vault piece in the middle of namely the arch of arc is divided into and the haunch piece of both sides, the abutment wall piece of both sides; Vault piece, haunch piece and abutment wall piece all adopt prefabricated units;
Step 2: the pouring concrete mode that is rigidly connected is connected to abutment wall piece prefabricated units (8) on the basic longeron (14) after adopting flush type, the joint of abutment wall piece prefabricated units (8) arranges the main muscle of the connection that laterally exposes (16), the joint of basis longeron (14) arranges the main muscle of the connection that vertically exposes (16), after abutment wall piece prefabricated units (8) place the holddown groove of basic longeron (14) top interior, laterally connecting reinforcement is connected with vertical connecting reinforcement racking seizing, builds microdilatancy pea gravel concreten (17) on it;
Step 3: adopt the back pouring concrete mode that is rigidly connected that vault piece prefabricated units (1) are connected on the haunch piece prefabricated units (7), the joint of vault piece prefabricated units (1) and haunch piece prefabricated units (7) all is embedded with and is connected shaped steel anchor plate (4), the inboard that connects shaped steel anchor plate (4) arranges and connects shaped steel anchor bar (5), the arranged outside that connects shaped steel anchor plate (4) connects shaped steel (3), after will connecting shaped steel (3) and be connected and fixed by screw or welding, build microdilatancy pea gravel concreten (17) on it, wherein bury connection main muscle (2) underground;
Step 4: adopt the board-like connected mode of bolt clip that haunch piece prefabricated units (7) are connected on the abutment wall piece prefabricated units (8), the joint of haunch piece prefabricated units (7) and abutment wall piece prefabricated units (8) all is provided with the anchor bar (12) that exposes, pre-embedded steel slab (11) all is set on the both sides sidewall of the joint of haunch piece prefabricated units (7) and abutment wall piece prefabricated units (8), anchor bar (12) is set on the pre-embedded steel slab (11), be welded to connect steel plate (10) outside two pre-embedded steel slabs (11) up and down, and be connected and fixed pre-embedded bolt hole stiffener (13) around the bolt hole with connecting bolt (9);
Step 5: vault piece prefabricated units (1), two haunch piece prefabricated units (7) and two abutment wall piece prefabricated units (8) connect into an annular construction member, an initial ring (18), several standard rings (19) and an end-rings (20) are formed a linkage unit, ring joint between each annular construction member is set to " L " shape tongue and groove, and tongue-and-groove connects; Deformation joint (15) is set between the linkage unit.
2. the windproof open cut tunnel of strong wind district splicing prefabricated components formula that obtains of joint assembly unit method of attachment as claimed in claim 1.
CN 201210001447 2012-01-05 2012-01-05 Prefabricated part assembled windproof open cut tunnel in gale region and joint assembling and connecting method thereof Active CN102444089B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201210001447 CN102444089B (en) 2012-01-05 2012-01-05 Prefabricated part assembled windproof open cut tunnel in gale region and joint assembling and connecting method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201210001447 CN102444089B (en) 2012-01-05 2012-01-05 Prefabricated part assembled windproof open cut tunnel in gale region and joint assembling and connecting method thereof

Publications (2)

Publication Number Publication Date
CN102444089A CN102444089A (en) 2012-05-09
CN102444089B true CN102444089B (en) 2013-09-25

Family

ID=46007001

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201210001447 Active CN102444089B (en) 2012-01-05 2012-01-05 Prefabricated part assembled windproof open cut tunnel in gale region and joint assembling and connecting method thereof

Country Status (1)

Country Link
CN (1) CN102444089B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111456759A (en) * 2020-01-23 2020-07-28 中铁二院工程集团有限责任公司 Assembled tunnel lining structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4885879A (en) * 1987-02-10 1989-12-12 Plantier Jean Louis Vault structure for protection of roadways against snow
CN101936043A (en) * 2010-08-11 2011-01-05 东南大学 Friction energy consumption type node connection device for self-centering pier column structure
JP2011036197A (en) * 2009-08-13 2011-02-24 Yukie Hayashida Method for installing covering material for tunnel cultivation, and covering material used for the same
RU104196U1 (en) * 2010-03-05 2011-05-10 Общество с ограниченной ответственностью "Кибермашина" DEVICE FOR PROTECTING ROADS, TAKEOPS, PEDESTRIAN WAYS FROM METEO SEPARATION AND SAND
CN102267175A (en) * 2011-05-11 2011-12-07 中铁四局集团第五工程有限公司 Process for prefabricating windproof open cut tunnel member in annular production line

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3375322B2 (en) * 2000-06-30 2003-02-10 岩手ハネダコンクリート株式会社 Concrete arched structure
CN201650302U (en) * 2010-03-25 2010-11-24 中铁二院工程集团有限责任公司 Eiking clear hole structure of existing high speed railway tunnel
CN102277839A (en) * 2011-04-29 2011-12-14 中铁二院工程集团有限责任公司 Open hole construction additionally arranged on existing electrified railway and rapid construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4885879A (en) * 1987-02-10 1989-12-12 Plantier Jean Louis Vault structure for protection of roadways against snow
JP2011036197A (en) * 2009-08-13 2011-02-24 Yukie Hayashida Method for installing covering material for tunnel cultivation, and covering material used for the same
RU104196U1 (en) * 2010-03-05 2011-05-10 Общество с ограниченной ответственностью "Кибермашина" DEVICE FOR PROTECTING ROADS, TAKEOPS, PEDESTRIAN WAYS FROM METEO SEPARATION AND SAND
CN101936043A (en) * 2010-08-11 2011-01-05 东南大学 Friction energy consumption type node connection device for self-centering pier column structure
CN102267175A (en) * 2011-05-11 2011-12-07 中铁四局集团第五工程有限公司 Process for prefabricating windproof open cut tunnel member in annular production line

Non-Patent Citations (8)

* Cited by examiner, † Cited by third party
Title
何永旺.兰新第二双线防风明洞预制方案研究.《国防交通工程与技术》.2011,(第04期),24-27.
何永旺.防风明洞预制构件接缝连接方式.《中国铁路》.2011,(第07期),51-53.
兰新第二双线防风明洞预制方案研究;何永旺;《国防交通工程与技术》;20110720(第04期);24-27 *
兰新铁路第二双线防风技术及工程设计;拉有玉等;《石家庄铁道大学学报(自然科学版)》;20101025(第04期);104-108 *
兰新铁路防风明洞结构形式设计研究;盛智平;《铁道建筑》;20110415(第04期);80-82 *
拉有玉等.兰新铁路第二双线防风技术及工程设计.《石家庄铁道大学学报(自然科学版)》.2010,(第04期),104-108.
盛智平.兰新铁路防风明洞结构形式设计研究.《铁道建筑》.2011,(第04期),80-82.
防风明洞预制构件接缝连接方式;何永旺;《中国铁路》;20110715(第07期);51-53 *

Also Published As

Publication number Publication date
CN102444089A (en) 2012-05-09

Similar Documents

Publication Publication Date Title
CN105484388B (en) A kind of prefabricated assembled shear wall perps attachment structure and its construction method
CN202440768U (en) Closed concrete windproof prefabricated assembled open cut tunnel in high wind area
CN109057004A (en) A kind of assembled steel-Combined concrete frame and its connection installation method
CN103161224A (en) Rectangular concrete filled steel tubular column - steel beam connection node and construction methods thereof
CN102966016B (en) The prefabricated runway structure of a kind of shield tunnel internal double layers
CN108589971A (en) A kind of closed-section steel deck combined concrete shear wall connecting node and production method
CN106869326B (en) The frame system and construction method that hollow steel tube concrete integral node is constituted
CN105863051A (en) Function-restorable assembly type end plate connection joint connection device
CN104947588A (en) Steel pipe concrete-combination beam cable stayed bridge floor system and construction method thereof
CN203021884U (en) Internal double-layer prefabricated carriageway structure of shield tunnel
CN104988951B (en) Straddle monorail underground section track wall construction and construction method thereof
CN103015310A (en) Sectional type concrete filled steel tube pier adopting non tension and shear limiting and construction method thereof
CN109854276A (en) A kind of small spacing multiple track tunnel hole support construction
CN102444089B (en) Prefabricated part assembled windproof open cut tunnel in gale region and joint assembling and connecting method thereof
CN204825963U (en) Stride single track ground of formula hypomere track wall structure
CN209227834U (en) A kind of assembly concrete-filled steel tube frame-shear-wall structure
CN103556563A (en) Steel-RPC (Reactive Powder Concrete) composite bridge
CN103669193B (en) A kind of laterally assembled Wavelike steel webplate combination T beam and construction method
CN110863417A (en) Steel-concrete combined beam bridge capable of being installed quickly and construction method thereof
CN103572780B (en) Vault immersed tube tunnel
CN202989763U (en) Sectional type concrete filled steel tube pier adopting non-pulling resistant and non-shearing resistant limitation
CN106869320B (en) The frame and its construction method that coupled column combination beam is constituted
CN205296391U (en) A baffle link up node that is used for rectangle steel core concrete column and H girder steel to connect
CN214783198U (en) Novel horizontal longitudinal connecting system for three-split steel box girder
CN203022129U (en) RSC combined node continuously cut on web and partially cut on flanges

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Li Guoliang

Inventor after: Tian Peng

Inventor after: Yu Jie

Inventor after: Tan Yongqing

Inventor after: Jia Yuanxia

Inventor after: Wang Zhengming

Inventor after: Huang Shuanglin

Inventor after: He Yongwang

Inventor after: Yang Guozhu

Inventor after: Jin Baocheng

Inventor after: Yan Wenxiang

Inventor after: Liu Peishuo

Inventor after: Liu Cheng

Inventor before: Li Guoliang

Inventor before: Li Lei

Inventor before: Tian Peng

Inventor before: Yu Jie

Inventor before: Tan Yongqing

Inventor before: Song Jiahui

Inventor before: Jia Yuanxia

Inventor before: Zhang Tai

Inventor before: Huang Shuanglin

Inventor before: He Yongwang

Inventor before: Yang Guozhu

Inventor before: Jin Baocheng

Inventor before: Yan Wenxiang

Inventor before: Liang Wenhao

Inventor before: Liu Peishuo

Inventor before: Liu Cheng

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: LI GUOLIANG HUANG SHUANGLIN HE YONGWANG YANG GUOZHU JIN BAOCHENG YAN WENXIANG LIANG WENHAO LIU PEISHUO LIU CHENG LI LEI TIAN PENG YU JIE TAN YONGQING SONG JIAHUI JIA YUANXIA ZHANG TAI TO: LI GUOLIANG WANG ZHENGMING HUANG SHUANGLIN HE YONGWANG YANG GUOZHU JIN BAOCHENG YAN WENXIANG LIU PEISHUO LIU CHENG TIAN PENG YU JIE TAN YONGQING JIA YUANXIA

C14 Grant of patent or utility model
GR01 Patent grant