CN102425100A - Wide-bodied pedestrian overpass erected among buildings - Google Patents

Wide-bodied pedestrian overpass erected among buildings Download PDF

Info

Publication number
CN102425100A
CN102425100A CN2011102792783A CN201110279278A CN102425100A CN 102425100 A CN102425100 A CN 102425100A CN 2011102792783 A CN2011102792783 A CN 2011102792783A CN 201110279278 A CN201110279278 A CN 201110279278A CN 102425100 A CN102425100 A CN 102425100A
Authority
CN
China
Prior art keywords
steel
bridge
building
main bridge
truss
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011102792783A
Other languages
Chinese (zh)
Inventor
刘志宏
韩建强
方海龙
郭铭德
黄泽珍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Design Institute
Original Assignee
Guangzhou Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Design Institute filed Critical Guangzhou Design Institute
Priority to CN2011102792783A priority Critical patent/CN102425100A/en
Publication of CN102425100A publication Critical patent/CN102425100A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to a wide-bodied pedestrian overpass erected among buildings, which is characterized in that a double-column pier is arranged between the buildings at both sides of a road and the road; the bottom part of the double-column pier is connected with a bored pile foundation assorted with the double-column pier; the top part of the pier is provided with a bent cap; the main bridge of the wide-bodied pedestrian overpass is arranged on the upper surface of the bent cap; cantilevers at both ends of the main bridge are respectively and fixedly connected with the buildings; the main bridge mainly comprises a through steel truss, a bottom sealing steel plate and a deck pavement; the steel truss is formed by connecting upper chord members, lower chord members, web members with steel cross bars; the bottom sealing steel plate is fixed on the lower surfaces of the steel cross bars; and the deck pavement is arranged above the steel cross bars. The wide-bodied pedestrian overpass erected among the buildings has the characteristics as follows: the modeling conception is novel; the design is particular; the service function and the sightseeing function are integrated; higher additional loads can be borne; the designed deck width is large; the stress condition is brighter and clearer; the workload of the design calculation can be greatly reduced; and simultaneously, the construction is convenient, and the influence of the construction process on traffic is less.

Description

架设于建筑物之间的宽体人行天桥Wide body pedestrian bridge erected between buildings

技术领域 technical field

本发明涉及一种架设于建筑物之间的宽体人行天桥,广泛适用于建筑物之间的连接通行。属于人行天桥建造技术领域。The invention relates to a wide-body pedestrian bridge erected between buildings, which is widely used for connecting and passing between buildings. It belongs to the technical field of pedestrian bridge construction.

背景技术 Background technique

人行天桥又称人行立交桥。一般建造在车流量大、行人稠密的地段,或者交叉口、广场及铁路上面。人行天桥只允许行人通过,用于避免车流和人流平面相交时的冲突,保障人们安全的穿越,提高车速,减少交通事故。Pedestrian bridges are also known as pedestrian overpasses. It is generally built in areas with large traffic volume and dense pedestrians, or on intersections, squares and railways. Pedestrian bridges only allow pedestrians to pass, and are used to avoid conflicts when the planes of traffic and pedestrians intersect, ensure people's safe crossing, increase vehicle speed, and reduce traffic accidents.

现有技术中,常见的过街天桥可以分为三大类,分别为悬挂式结构、承托式结构和混合式结构。1、悬挂式结构的过街天桥以桥栏杆为主要承重部件,供行人通过的桥板本身并不承重,悬挂在作为承重梁的桥栏上,这种结构的过街天桥将结构性部件和实用型部件结合在了一起,可以减少建筑材料的使用,相对降低工程造价,但是这种结构的过街天桥桥栏杆体积大、重量重,存在两方面缺陷:一方面行人在桥上的视线会被栏杆遮挡,另一方面体积这么庞大的栏杆横垣在马路中,对过往车辆和行人的视线形成阻碍,以及影响城市的景观。2、承托式结构的过街天桥将承重的桥梁直接架设在桥墩上,供行人行走的桥铺在桥梁之上,桥栏杆仅起保护行人的作用,并不承重,这一类的过街天桥存在造价相对较高的缺陷。3、混合式结构的过街天桥是上述两种结构的杂交体,桥栏和桥梁共同作为承重结构分担桥的荷载。这种结构的人行天桥存在如下缺陷:第一,能够承受外附荷载较小,设计的桥面宽度小(大都小于12m),能够承载的人流量有限,只能满足单一的使用功能,无法集观光功能于一体。第二,结构受力情况复杂,设计计算的工作量大,施工期间常常要中断道路交通,施工周期长。第三,无法与周边的建筑物连接、不能与周边环境相协调。In the prior art, common overpasses can be divided into three categories, namely suspended structures, supporting structures and hybrid structures. 1. The overpass with a suspended structure uses the bridge railing as the main load-bearing component. The bridge deck for pedestrians to pass through is not load-bearing, and is suspended on the bridge rail as a load-bearing beam. The overpass with this structure combines structural components with practical components. Together, the use of building materials can be reduced, and the project cost can be relatively reduced. However, the railings of the overpass bridge with this structure are large in size and heavy in weight, and there are two defects: on the one hand, the sight of pedestrians on the bridge will be blocked by the railings, and on the other hand On the one hand, such a huge railing wall is in the road, which hinders the sight of passing vehicles and pedestrians, and affects the city's landscape. 2. The supporting structure of the overpass directly erects the load-bearing bridge on the pier, and the bridge for pedestrians to walk on is laid on the bridge. The bridge railing only serves to protect pedestrians and does not bear weight. higher defect. 3. The cross-street bridge with hybrid structure is a hybrid of the above two structures, and the bridge rail and the bridge are used as load-bearing structures to share the load of the bridge. Pedestrian bridges with this structure have the following defects: first, they can bear small external loads, the designed bridge deck width is small (mostly less than 12m), and the flow of people that can carry is limited, which can only meet a single use function and cannot be aggregated. Sightseeing functions in one. Second, the stress of the structure is complex, the workload of design and calculation is large, the road traffic is often interrupted during the construction period, and the construction period is long. Third, it cannot be connected with the surrounding buildings and cannot coordinate with the surrounding environment.

发明内容 Contents of the invention

本发明的目的,是为了解决现有技术中的人行天桥存在无法与周边的建筑物连接、桥面宽度小、结构受力复杂、设计工作量大的缺点,提供一种架设于建筑物之间的宽体人行天桥,The purpose of the present invention is to solve the shortcomings of the pedestrian bridge in the prior art that it cannot be connected with the surrounding buildings, the width of the bridge deck is small, the structure is stressed, and the design workload is large, and to provide a pedestrian bridge erected between buildings. wide body pedestrian bridge,

本发明的目的可以通过采取如下技术方案达到:The purpose of the present invention can be achieved by taking the following technical solutions:

架设于建筑物之间的宽体人行天桥,其结构特点是:The structural characteristics of wide-body pedestrian bridges erected between buildings are:

1)在马路两侧的建筑物与马路之间设置双柱式桥墩,双柱式桥墩的底部连接有与之配套的钻孔灌注桩基础,在桥墩的顶部设置盖梁,宽体人行天桥的主桥设置在盖梁的上面;所述主桥的两端悬臂分别与建筑物固定连接;1) Set up double-column bridge piers between the buildings on both sides of the road and the road. The bottom of the double-column bridge piers is connected with the matching bored pile foundation, and the top of the bridge piers is set with a cover beam. The wide-body pedestrian bridge The main bridge is arranged on the top of the cover beam; the cantilevers at both ends of the main bridge are respectively fixedly connected with the building;

2)所述主桥主要由包括下承式钢桁架、封底钢板和桥面铺装,钢桁架由上弦杆、下弦杆、腹杆和钢横杆连接而成,封底钢板固定于钢横杆的下面,桥面铺装设于钢横杆的上方。2) The main bridge is mainly composed of under-supported steel trusses, bottom-sealed steel plates and bridge deck pavement. The steel trusses are connected by upper chords, lower chords, webs and steel cross-bars, and the bottom-sealed steel plates are fixed on the steel cross-bars. Below, the deck pavement is laid over the steel crossbars.

本发明的目的还可以通过采取如下技术方案达到:The purpose of the present invention can also be achieved by taking the following technical solutions:

本发明的一种实施方案是:所述主桥的两端悬臂分别通过连接机构与建筑物连接;所述连接机构包括两套由

Figure BDA0000092651180000021
形角钢与
Figure BDA0000092651180000022
形附加钢筋叠加焊接而成的固定件,以及带有伸缩缝的连接钢板,两套固定件分别对称布置在主桥的悬臂末端和建筑物上,连接钢板的两端分别与固定件焊接;所述连接钢板的伸缩缝中设有填嵌缝膏。One embodiment of the present invention is: the two ends of the cantilever of the main bridge are respectively connected to the building through the connecting mechanism; the connecting mechanism includes two sets of
Figure BDA0000092651180000021
Shaped angle steel with
Figure BDA0000092651180000022
The fixed piece welded by superimposed additional steel bars and the connecting steel plate with expansion joints, the two sets of fixing pieces are arranged symmetrically on the cantilever end of the main bridge and the building respectively, and the two ends of the connecting steel plate are respectively welded to the fixing piece; A caulking paste is provided in the expansion joints connecting the steel plates.

本发明的一种实施方案是:在盖梁与钢桁架的下弦杆的连接处由上到下依次设有弦杆调平板、支座和支座垫石;在弦杆调平板底面焊接有抗震档块。An embodiment of the present invention is: at the connection between the cover beam and the lower chord of the steel truss, a chord leveling plate, a support and a support pad are arranged sequentially from top to bottom; block.

本发明的一种实施方案是:在所述下弦杆的相对两侧各设有加劲肋。An embodiment of the present invention is that stiffening ribs are provided on opposite sides of the lower chord.

本发明的一种实施方案是:在所述钢桁架的外侧设有花槽、在钢桁架的内侧设有水沟。One embodiment of the present invention is: a planter is provided on the outside of the steel truss, and a water ditch is provided on the inside of the steel truss.

本发明的一种实施方案是:在所述钢桁架的顶部设有钢梁屋架,在钢梁屋架上设有顶架钢板。One embodiment of the present invention is: a steel girder roof truss is arranged on the top of the steel truss, and a top frame steel plate is arranged on the steel girder roof truss.

本发明的一种实施方案是:在所述双柱式桥墩的两支承墩之间设有系梁。One embodiment of the present invention is: a tie beam is arranged between the two supporting piers of the double-column bridge pier.

本发明的一种实施方案是:所述主桥的桥面宽度为13.2米,跨度为28.50米,两端悬臂分别为9.630米和6.13米。An embodiment of the present invention is: the deck width of the main bridge is 13.2 meters, the span is 28.50 meters, and the cantilevers at both ends are 9.630 meters and 6.13 meters respectively.

本发明的有益效果:Beneficial effects of the present invention:

1、本发明由于将主桥的两端悬臂分别通过连接机构与建筑物连接,与路边建筑物构成和谐协调的整体结构,因此,可使整座天桥更显得轻巧美观,而桥下更是开阔简洁,车辆畅通无阻,具有造型构思新颖,建筑设计独特、集使用功能和观光功能于一体,能够承受较大的附加荷载、设计的桥面宽度大,受力情况更为清晰、明朗,能够大大减少设计计算的工作量,同时具有施工方便、施工过程对交通影响小的特点。特别是可将宽体天桥立面塑造成一条通透的、与周边环境十分协调的线条。1. Since the present invention connects the cantilevers at both ends of the main bridge to the building through the connecting mechanism, it forms a harmonious overall structure with the roadside buildings. Therefore, the whole overpass can be made more light and beautiful, and the under bridge is even more beautiful. Open and concise, unimpeded vehicles, with novel modeling concept, unique architectural design, integrating use function and sightseeing function, capable of bearing large additional load, designed with a large width of bridge deck, and the force situation is clearer and clearer, able to It greatly reduces the workload of design and calculation, and at the same time has the characteristics of convenient construction and little impact on traffic during the construction process. In particular, the façade of the wide-body overpass can be shaped into a transparent line that is in harmony with the surrounding environment.

2、本发明的主桥采用两端悬臂预制连续钢桁架结构型式,主桥的横向宽度为13.2米,集使用功能和观光功能于一体,能够承受较大的附加荷载、设计的桥面宽度大,受力情况更为清晰、明朗,能够大大减少设计计算的工作量。2. The main bridge of the present invention adopts the cantilever prefabricated continuous steel truss structure type at both ends. The transverse width of the main bridge is 13.2 meters. , the force situation is clearer and clearer, which can greatly reduce the workload of design calculation.

3、本发明在盖梁与钢桁架的下弦杆之间由上到下依次设有弦杆调平板、支座和支座垫石;在弦杆调平板底面焊接有抗震档块,能够满足结构所应有的抗风、抗震等性能。3. In the present invention, a chord leveling plate, a support and a support pad are sequentially arranged between the cover beam and the lower chord of the steel truss; an anti-seismic block is welded on the bottom of the chord leveling plate, which can meet the structural requirements. It should have wind resistance, earthquake resistance and other properties.

4、本发明的主桥分为两段钢桁架,钢桁架在工厂制作,现场拼焊,施工在天桥的整个施工过程中,可以尽快吊装上去,留出路面让汽车通行,交通基本不造成太大影响,具有施工方便和施工周期短的优点。4. The main bridge of the present invention is divided into two sections of steel trusses. The steel trusses are manufactured in the factory and welded on site. During the entire construction process of the overpass, the steel trusses can be hoisted up as soon as possible. It has the advantages of convenient construction and short construction period.

附图说明 Description of drawings

图1是本发明具体实施例的人行天桥得整体结构立面图。Fig. 1 is the elevation view of the whole structure of the pedestrian bridge of the specific embodiment of the present invention.

图2是图1中A-A向剖视图。Fig. 2 is a sectional view along line A-A in Fig. 1 .

图3是本发明具体实施例的桥墩、桩基的立面图。Fig. 3 is an elevation view of a bridge pier and a pile foundation according to a specific embodiment of the present invention.

图4是本发明具体实施例的桥墩、桩基的侧视图。Fig. 4 is a side view of a bridge pier and a pile foundation according to a specific embodiment of the present invention.

图5是图3中A-A向剖视图。Fig. 5 is a sectional view along A-A in Fig. 3 .

图6是图3中B-B向剖视图。Fig. 6 is a cross-sectional view along B-B in Fig. 3 .

图7是本发明具体实施例的盖梁与钢桁架的下弦杆连接处的结构示意图。Fig. 7 is a structural schematic diagram of the connection between the cover beam and the lower chord of the steel truss according to the specific embodiment of the present invention.

图8是图7中A-A向剖视图。Fig. 8 is a sectional view along line A-A in Fig. 7 .

图9是图7中B-B向剖视图。Fig. 9 is a cross-sectional view along B-B in Fig. 7 .

图10是本发明具体实施例的连接机构的结构示意图。Fig. 10 is a schematic structural diagram of a connection mechanism of a specific embodiment of the present invention.

具体实施方式 Detailed ways

具体实施例:Specific examples:

参照图1∽图6,本实施例包括架设于马路两侧的双柱式桥墩1及与之配套的钻孔灌注桩基础2,设置于桥墩1顶部的盖梁3,设置于盖梁3上面的主桥4;主桥4的两端悬臂分别与建筑物5连接;所述主桥4主要由两段焊接的下承式钢桁架4-1、封底钢板4-2和桥面铺装4-3构成,钢桁架4-1由上弦杆4-1-1、下弦杆4-1-2、腹杆4-1-3和钢横杆4-1-4连接而成,封底钢板4-2固定于钢横杆4-1-4的下面,桥面铺装4-3设于钢横杆4-1-4的上方。所述主桥4的宽面宽度为13.2米,跨度为28.50m,两端悬臂分别为9.630米和6.13米。所述钢桁架4-1的外侧设有花槽4-1-6、其内侧设有水沟4-1-7。所述钢桁架4-1的顶部设有钢梁屋架4-1-8,钢梁屋架4-1-8上设有顶架钢板4-1-9。所述双柱式桥墩1的两个桥墩之间设有系梁11。With reference to Fig. 1 ~ Fig. 6, present embodiment comprises the double-column bridge pier 1 that is erected on both sides of the road and the bored pile foundation 2 that is matched with it, the cover beam 3 that is arranged on the top of pier 1, is arranged on the cover beam 3 The main bridge 4; the cantilevers at both ends of the main bridge 4 are connected with the building 5 respectively; -3 structure, the steel truss 4-1 is connected by the upper chord 4-1-1, the lower chord 4-1-2, the web 4-1-3 and the steel cross bar 4-1-4, and the back cover plate 4- 2. It is fixed under the steel crossbar 4-1-4, and the bridge deck pavement 4-3 is arranged above the steel crossbar 4-1-4. The wide face width of the main bridge 4 is 13.2 meters, the span is 28.50 meters, and the cantilevers at both ends are 9.630 meters and 6.13 meters respectively. The outer side of the steel truss 4-1 is provided with a planter 4-1-6, and the inner side is provided with a water ditch 4-1-7. The top of the steel truss 4-1 is provided with a steel girder roof truss 4-1-8, and the steel girder roof truss 4-1-8 is provided with a top frame steel plate 4-1-9. A tie beam 11 is arranged between two piers of the double-column pier 1 .

参照图7、图8和图9,在盖梁3与钢桁架4-1的下弦杆4-1-2之间由上到下依次设有弦杆调平板7、支座8和支座垫石9;在弦杆调平板7底面焊接有抗震档块10。所述下弦杆4-1-2的两对侧分别设有加劲肋下弦杆4-1-5。Referring to Fig. 7, Fig. 8 and Fig. 9, between the cover beam 3 and the lower chord 4-1-2 of the steel truss 4-1, a chord leveling plate 7, a support 8 and a support pad are sequentially arranged from top to bottom Stone 9; Welded with anti-seismic block 10 on the bottom surface of chord leveling plate 7. The two opposite sides of the lower chord 4-1-2 are respectively provided with a stiffener lower chord 4-1-5.

参照图10,所述主桥4的两端悬臂分别通过连接机构与建筑物连接;所述连接机构包括两套由

Figure BDA0000092651180000041
形角钢6-1与
Figure BDA0000092651180000042
形附加钢筋6-2叠加焊接而成的固定件,以及带有伸缩缝的连接钢板6-3,两套固定件分别对称布置在主桥4的悬臂末端和建筑物5上,连接钢板6-3的两端分别与固定件焊接;所述连接钢板6-3的伸缩缝6-3-1中设有填嵌缝膏。Referring to Fig. 10, the cantilevers at both ends of the main bridge 4 are respectively connected to the building through a connecting mechanism; the connecting mechanism includes two sets of
Figure BDA0000092651180000041
Shaped angle steel 6-1 with
Figure BDA0000092651180000042
Shaped additional steel bars 6-2 superimposed and welded fixing parts, and connecting steel plates 6-3 with expansion joints, the two sets of fixing parts are respectively symmetrically arranged on the cantilever end of the main bridge 4 and on the building 5, and the connecting steel plates 6- The two ends of 3 are respectively welded with the fixing parts; the expansion joint 6-3-1 of the connecting steel plate 6-3 is provided with caulking paste.

本发明的施工方法如下:Construction method of the present invention is as follows:

主桥两片钢桁架采用吊装技术,吊装完成后现浇砼主桥结构。人行天桥位于交通繁忙的珠江大道上,施工期间不能中断道路交通,因此钢桁架必须在工厂制作,现场拼焊施工。The two steel trusses of the main bridge adopt hoisting technology, and the main bridge structure is cast in place after the hoisting is completed. The pedestrian bridge is located on the busy Pearl River Avenue, and the road traffic cannot be interrupted during the construction period. Therefore, the steel truss must be fabricated in the factory and welded on site.

第一步:施工桩基、桥墩;同时工厂预制钢桁架。The first step: construction of pile foundations and bridge piers; at the same time, factory prefabricated steel trusses.

第二步:搭设临时支架,运输桁架半成品至施工现场,分块吊装,同时焊接。Step 2: Set up temporary supports, transport the semi-finished trusses to the construction site, hoist them in blocks and weld them at the same time.

第三步:安装桥面铺装和栏杆,挂设花盆,桥面装饰,成桥。The third step: install bridge pavement and railings, hang flower pots, decorate the bridge deck, and complete the bridge.

本发明的主要设计依据如下:The main design basis of the present invention is as follows:

1)设计参数:1) Design parameters:

根据《建筑结构荷载规范》GB 50009-20017.1.1采用:According to the "Building Structure Load Code" GB 50009-20017.1.1 adopts:

风荷载计算公式:Wk=βgz×μz×μs×W0。其中:Wk:作用在光伏方阵上的风荷载标准值(kN/m2),B gz:瞬时风压的阵风系数,按《建筑结构荷载规范》GB 50009-2001取定。Wind load calculation formula: Wk=βgz×μz×μs×W0. Among them: Wk: standard value of wind load acting on the photovoltaic array (kN/m2), B gz: gust coefficient of instantaneous wind pressure, determined according to "Code for Building Structure Loads" GB 50009-2001.

根据不同场地类型,按以下公式计算:βgz=K(1+2μf),其中K为地区粗糙度调整系数,μf为脉动系数:According to different site types, it is calculated according to the following formula: βgz=K(1+2μf), where K is the area roughness adjustment coefficient, and μf is the pulsation coefficient:

A类场地:βgz=0.92*(1+2μf)其中:μf=0.387*(Z/10)^(-0.12);Class A site: βgz=0.92*(1+2μf) where: μf=0.387*(Z/10)^(-0.12);

B类场地:βgz=0.89*(1+2μf)其中:μf=0.5(Z/10)^(-0.16);Class B venue: βgz=0.89*(1+2μf) where: μf=0.5(Z/10)^(-0.16);

C类场地:βgz=0.85*(1+2μf)其中:μf=0.734(Z/10)^(-0.22);Class C venue: βgz=0.85*(1+2μf) where: μf=0.734(Z/10)^(-0.22);

D类场地:βgz=0.80*(1+2μf)其中:μf=1.2248(Z/10)^(-0.3);Class D site: βgz=0.80*(1+2μf) where: μf=1.2248(Z/10)^(-0.3);

μz---风压高度变化系数,按《建筑结构荷载规范》GB 50009-2001取定,根据不同场地类型,按以下公式计算:μz---coefficient of wind pressure height change, determined according to "Code for Building Structure Loads" GB 50009-2001, and calculated according to the following formula according to different site types:

A类场地:μz=1.379×(Z/10)0.24;Class A venue: μz=1.379×(Z/10)0.24;

B类场地:μz=(Z/10)0.32;Class B venue: μz=(Z/10)0.32;

C类场地:μz=0.616×(Z/10)0.44;Class C venue: μz=0.616×(Z/10)0.44;

D类场地:μz=0.318×(Z/10)0.60;Class D venue: μz=0.318×(Z/10)0.60;

本工程属于B类地区,故μz=1.379×(Z/10)0.24,μs---风荷载体型系数,按《建筑结构荷载规范》GB 50009-2001取为:2.0,W0---基本风压,按现场风速测试风压图,取为0.7kN/m2This project belongs to Class B area, so μz=1.379×(Z/10)0.24, μs---wind load shape coefficient, according to "Building Structure Load Code" GB 50009-2001 is taken as: 2.0, W0---basic wind According to the on-site wind speed test wind pressure diagram, it is taken as 0.7kN/m2

2)地震作用:抗震设计烈度取为7度,地震影响系数取为0.08。2) Earthquake action: The seismic design intensity is taken as 7 degrees, and the seismic influence coefficient is taken as 0.08.

3)温度作用:年温度变化取为80摄氏度。3) Effect of temperature: the annual temperature change is taken as 80 degrees Celsius.

以上所述,仅为本发明较佳的具体实施例,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的范围内,根据本发明的技术方案及其发明构思加以等同替换或改变,都属于本发明的保护范围。The above are only preferred specific embodiments of the present invention, but the scope of protection of the present invention is not limited thereto. Anyone familiar with the technical field within the scope of the disclosure of the present invention, according to the technical solutions of the present invention and Any equivalent replacement or change of the inventive concept falls within the protection scope of the present invention.

Claims (9)

1. be set up in the expanded letter pedestrian overcrossing between the building, it is characterized in that:
1) between the building (5) of road both sides and road, two-columned pier (1) is set; The bottom of two-columned pier (1) is connected with supporting with it bored pile foundation (2); At the top of bridge pier (1) bent cap (3) is set, the main bridge (4) of expanded letter pedestrian overcrossing be arranged on bent cap (3) above; The two ends cantilever of said main bridge (4) is fixedly connected with building (5) respectively;
2) said main bridge (4) is mainly by comprising lower support type steel truss (4-1), back cover steel plate (4-2) and deck paving (4-3); Steel truss (4-1) is formed by connecting upper chord (4-1-1), lower chord (4-1-2), web member (4-1-3) and steel cross bar (4-1-4); Back cover steel plate (4-2) be fixed in steel cross bar (4-1-4) below, deck paving (4-3) is located at the top of steel cross bar (4-1-4).
2. the expanded letter pedestrian overcrossing that is set up between the building according to claim 1 is characterized in that: the two ends cantilever of said main bridge (4) is connected with building (5) through bindiny mechanism respectively; Said bindiny mechanism comprises the fixture that two covers are welded by
Figure FDA0000092651170000011
shape angle steel (6-1) and the stack of
Figure FDA0000092651170000012
shape additional bar (6-2); And the connection steel plate (6-3) that has the shrinkage joint; Two cover fixtures are arranged symmetrically in respectively on the cantilevered distal end and building (5) of main bridge (4), and weld with fixture respectively at the two ends that connect steel plate (6-3); Be provided with in the shrinkage joint (6-3-1) of said connection steel plate (6-3) and fill out sealant.
3. the expanded letter pedestrian overcrossing that is set up between the building according to claim 1 and 2 is characterized in that: said lower support type steel truss (4-1) is made up of the steel truss welding of two sections same structures.
4. the expanded letter pedestrian overcrossing that is set up between the building according to claim 1 and 2 is characterized in that: the junction at the lower chord (4-1-2) of bent cap (3) and steel truss (4-1) is provided with chord member leveling board (7), bearing (8) and bearing pad stone (9) from top to bottom successively; Be welded with antidetonation link stopper (10) in chord member leveling board (7) bottom surface.
5. the expanded letter pedestrian overcrossing that is set up between the building according to claim 1 and 2 is characterized in that: respectively be provided with stiffening rib (4-1-5) in the relative both sides of said lower chord (4-1-2).
6. the expanded letter pedestrian overcrossing that is set up between the building according to claim 1 and 2 is characterized in that: be provided with colored groove (4-1-6) in the outside of said steel truss (4-1), be provided with ditch (4-1-7) in the inboard of steel truss (4-1).
7. the expanded letter pedestrian overcrossing that is set up between the building according to claim 1 and 2 is characterized in that: be provided with girder steel roof truss (4-1-8) at the top of said steel truss (4-1), on girder steel roof truss (4-1-8), be provided with upper frame steel plate (4-1-9).
8. the expanded letter pedestrian overcrossing that is set up between the building according to claim 1 and 2 is characterized in that: between two supporting piers of said two-columned pier (1), be provided with binder (11).
9. the expanded letter pedestrian overcrossing that is set up between the building according to claim 1 and 2 is characterized in that: the bridge deck width of said main bridge (4) is 13.2 meters, and span is 28.50 meters, and the two ends cantilever is respectively 9.630 meters and 6.13 meters.
CN2011102792783A 2011-09-20 2011-09-20 Wide-bodied pedestrian overpass erected among buildings Pending CN102425100A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011102792783A CN102425100A (en) 2011-09-20 2011-09-20 Wide-bodied pedestrian overpass erected among buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011102792783A CN102425100A (en) 2011-09-20 2011-09-20 Wide-bodied pedestrian overpass erected among buildings

Publications (1)

Publication Number Publication Date
CN102425100A true CN102425100A (en) 2012-04-25

Family

ID=45959126

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011102792783A Pending CN102425100A (en) 2011-09-20 2011-09-20 Wide-bodied pedestrian overpass erected among buildings

Country Status (1)

Country Link
CN (1) CN102425100A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106958766A (en) * 2017-04-07 2017-07-18 安徽建筑大学 Road lamp structure device is reformed transform deeply in narrow lane in huizhou tradition colony
CN108193591A (en) * 2017-12-30 2018-06-22 贵阳铝镁设计研究院有限公司 A kind of aluminum alloy pedestrian bridge steel bridge pier on the anti-edge of extended position band
CN110067197A (en) * 2019-05-27 2019-07-30 江苏工程职业技术学院 One kind climbing wall-shaped bridge wind pressure alarming robot and control method
CN112458886A (en) * 2020-12-18 2021-03-09 南南铝工程有限责任公司 Half calabash shape aluminum alloy pedestrian bridge connection structure

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3322951A1 (en) * 1983-06-25 1985-01-03 Johannes Dörnen, Stahlbauwerk, 4600 Dortmund Truss bridge and method for producing it
CN1263185A (en) * 1999-02-10 2000-08-16 天津市市政工程设计研究院 Hollow grid structure pedestrain overcrossing
CN2420324Y (en) * 2000-04-27 2001-02-21 黄太明 Net truss for pedestrian overcrossing
CN2830500Y (en) * 2003-02-14 2006-10-25 周宪平 Balance energy saving hoisting tower cable overline bridge
CN101139813A (en) * 2007-08-31 2008-03-12 西南交通大学 A kind of steel truss of under-supported bridge
EP1905900A2 (en) * 2006-09-20 2008-04-02 Eiffel Deutschland Stahltechnologie GmbH Bridge with two framework-type plates and set for its manufacture
KR20100108930A (en) * 2009-03-31 2010-10-08 김학권 The method of manufacturing for main girder with prefabricated truss type structure and the method of constructing for bridge by using the upper method
CN101967793A (en) * 2010-10-28 2011-02-09 南京工业大学 Rapidly Assembled Segmented Composite Truss Bridge
CN201891069U (en) * 2010-10-21 2011-07-06 安徽省交通规划设计研究院 Through steel pipe-concrete open type truss combination beam bridge
JP2011149224A (en) * 2010-01-22 2011-08-04 Tomoe Corp Connection structure of space truss
CN202347425U (en) * 2011-09-20 2012-07-25 广州市设计院 Wide-body pedestrian overpass erected between buildings

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3322951A1 (en) * 1983-06-25 1985-01-03 Johannes Dörnen, Stahlbauwerk, 4600 Dortmund Truss bridge and method for producing it
CN1263185A (en) * 1999-02-10 2000-08-16 天津市市政工程设计研究院 Hollow grid structure pedestrain overcrossing
CN2420324Y (en) * 2000-04-27 2001-02-21 黄太明 Net truss for pedestrian overcrossing
CN2830500Y (en) * 2003-02-14 2006-10-25 周宪平 Balance energy saving hoisting tower cable overline bridge
EP1905900A2 (en) * 2006-09-20 2008-04-02 Eiffel Deutschland Stahltechnologie GmbH Bridge with two framework-type plates and set for its manufacture
CN101139813A (en) * 2007-08-31 2008-03-12 西南交通大学 A kind of steel truss of under-supported bridge
KR20100108930A (en) * 2009-03-31 2010-10-08 김학권 The method of manufacturing for main girder with prefabricated truss type structure and the method of constructing for bridge by using the upper method
JP2011149224A (en) * 2010-01-22 2011-08-04 Tomoe Corp Connection structure of space truss
CN201891069U (en) * 2010-10-21 2011-07-06 安徽省交通规划设计研究院 Through steel pipe-concrete open type truss combination beam bridge
CN101967793A (en) * 2010-10-28 2011-02-09 南京工业大学 Rapidly Assembled Segmented Composite Truss Bridge
CN202347425U (en) * 2011-09-20 2012-07-25 广州市设计院 Wide-body pedestrian overpass erected between buildings

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106958766A (en) * 2017-04-07 2017-07-18 安徽建筑大学 Road lamp structure device is reformed transform deeply in narrow lane in huizhou tradition colony
CN106958766B (en) * 2017-04-07 2019-05-28 安徽建筑大学 Do street lamp reconstruction structure device deeply in a kind of lane traditional settlement Nei Zhai
CN108193591A (en) * 2017-12-30 2018-06-22 贵阳铝镁设计研究院有限公司 A kind of aluminum alloy pedestrian bridge steel bridge pier on the anti-edge of extended position band
CN110067197A (en) * 2019-05-27 2019-07-30 江苏工程职业技术学院 One kind climbing wall-shaped bridge wind pressure alarming robot and control method
CN112458886A (en) * 2020-12-18 2021-03-09 南南铝工程有限责任公司 Half calabash shape aluminum alloy pedestrian bridge connection structure

Similar Documents

Publication Publication Date Title
CN104695341B (en) Non-self-balanced beam string structure for reinforcing large-span continuous beam bridge
CN100543232C (en) Double-layer continuous girder bridge with steel-concrete composite structure
CN111335142A (en) Self-anchored cable-stayed arch bridge
CN103290784B (en) Arched girder conjugative bridge construction method for hanging
CN108374319A (en) A kind of through tied arch bridge structural unit and arch bridge structure and its construction method
CN103882801A (en) Segment assembled type combined highway and railway cable-stayed bridge with inconsistent bridge deck widths of highway and railway
CN100562631C (en) Spherical netted shell combined structure
CN102808373A (en) Rapid assembly type truss string pedestrian steel bridge
CN107489090B (en) A kind of circle bamboo space truss bridge based on joint structure mode
CN102425100A (en) Wide-bodied pedestrian overpass erected among buildings
CN104452574A (en) Novel ramp bridge structure and construction method thereof
CN112554031B (en) Upper bearing type beam-arch combined rigid frame bridge for double-deck traffic
CN201151866Y (en) Arch beam type overbridge
CN103015304B (en) Prestressed concrete variable-cross-section box girder bridge with internal tilted-leg rigid frame and construction method of prestressed concrete variable-cross-section box girder bridge
CN215164570U (en) Ultra-wide bridge floor open-type light combined bridge floor special-shaped arch bridge
CN110939067A (en) Method for determining position of bridge closure section of collaboration system
CN216474457U (en) Short T roof beam flood bridge flood fighting anchorage structure
CN201228341Y (en) cable-stayed overpass
CN202347425U (en) Wide-body pedestrian overpass erected between buildings
CN205557290U (en) Monolithic purlin formula annular passenger footbridge
CN113174839A (en) Ultra-wide bridge deck open type light combined bridge deck special-shaped arch bridge and construction method thereof
CN208995897U (en) Suspension cable overpass
CN103485271B (en) A prestressed cable truss bridge for pedestrians in mountainous rural areas
CN103031804B (en) Slant leg rigid frame built-in prestressed concrete variable cross-section box girder bridge and construction method thereof
CN113622283A (en) Horizontal pulling type pedestrian suspension bridge with hyperbolic paraboloid space crossed cable nets

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120425