CN102425100A - Wide-bodied pedestrian overpass erected among buildings - Google Patents
Wide-bodied pedestrian overpass erected among buildings Download PDFInfo
- Publication number
- CN102425100A CN102425100A CN2011102792783A CN201110279278A CN102425100A CN 102425100 A CN102425100 A CN 102425100A CN 2011102792783 A CN2011102792783 A CN 2011102792783A CN 201110279278 A CN201110279278 A CN 201110279278A CN 102425100 A CN102425100 A CN 102425100A
- Authority
- CN
- China
- Prior art keywords
- steel
- bridge
- building
- main bridge
- truss
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 70
- 239000010959 steel Substances 0.000 claims abstract description 70
- 230000007246 mechanism Effects 0.000 claims description 8
- 239000004575 stone Substances 0.000 claims description 2
- 239000011230 binding agent Substances 0.000 claims 1
- 239000000565 sealant Substances 0.000 claims 1
- 238000003466 welding Methods 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 14
- 238000000034 method Methods 0.000 abstract description 4
- 230000008569 process Effects 0.000 abstract description 3
- 238000007789 sealing Methods 0.000 abstract 2
- 230000008859 change Effects 0.000 description 3
- 230000007547 defect Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 206010039203 Road traffic accident Diseases 0.000 description 1
- 230000009471 action Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000004566 building material Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000010349 pulsation Effects 0.000 description 1
- 239000003351 stiffener Substances 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域 technical field
本发明涉及一种架设于建筑物之间的宽体人行天桥,广泛适用于建筑物之间的连接通行。属于人行天桥建造技术领域。The invention relates to a wide-body pedestrian bridge erected between buildings, which is widely used for connecting and passing between buildings. It belongs to the technical field of pedestrian bridge construction.
背景技术 Background technique
人行天桥又称人行立交桥。一般建造在车流量大、行人稠密的地段,或者交叉口、广场及铁路上面。人行天桥只允许行人通过,用于避免车流和人流平面相交时的冲突,保障人们安全的穿越,提高车速,减少交通事故。Pedestrian bridges are also known as pedestrian overpasses. It is generally built in areas with large traffic volume and dense pedestrians, or on intersections, squares and railways. Pedestrian bridges only allow pedestrians to pass, and are used to avoid conflicts when the planes of traffic and pedestrians intersect, ensure people's safe crossing, increase vehicle speed, and reduce traffic accidents.
现有技术中,常见的过街天桥可以分为三大类,分别为悬挂式结构、承托式结构和混合式结构。1、悬挂式结构的过街天桥以桥栏杆为主要承重部件,供行人通过的桥板本身并不承重,悬挂在作为承重梁的桥栏上,这种结构的过街天桥将结构性部件和实用型部件结合在了一起,可以减少建筑材料的使用,相对降低工程造价,但是这种结构的过街天桥桥栏杆体积大、重量重,存在两方面缺陷:一方面行人在桥上的视线会被栏杆遮挡,另一方面体积这么庞大的栏杆横垣在马路中,对过往车辆和行人的视线形成阻碍,以及影响城市的景观。2、承托式结构的过街天桥将承重的桥梁直接架设在桥墩上,供行人行走的桥铺在桥梁之上,桥栏杆仅起保护行人的作用,并不承重,这一类的过街天桥存在造价相对较高的缺陷。3、混合式结构的过街天桥是上述两种结构的杂交体,桥栏和桥梁共同作为承重结构分担桥的荷载。这种结构的人行天桥存在如下缺陷:第一,能够承受外附荷载较小,设计的桥面宽度小(大都小于12m),能够承载的人流量有限,只能满足单一的使用功能,无法集观光功能于一体。第二,结构受力情况复杂,设计计算的工作量大,施工期间常常要中断道路交通,施工周期长。第三,无法与周边的建筑物连接、不能与周边环境相协调。In the prior art, common overpasses can be divided into three categories, namely suspended structures, supporting structures and hybrid structures. 1. The overpass with a suspended structure uses the bridge railing as the main load-bearing component. The bridge deck for pedestrians to pass through is not load-bearing, and is suspended on the bridge rail as a load-bearing beam. The overpass with this structure combines structural components with practical components. Together, the use of building materials can be reduced, and the project cost can be relatively reduced. However, the railings of the overpass bridge with this structure are large in size and heavy in weight, and there are two defects: on the one hand, the sight of pedestrians on the bridge will be blocked by the railings, and on the other hand On the one hand, such a huge railing wall is in the road, which hinders the sight of passing vehicles and pedestrians, and affects the city's landscape. 2. The supporting structure of the overpass directly erects the load-bearing bridge on the pier, and the bridge for pedestrians to walk on is laid on the bridge. The bridge railing only serves to protect pedestrians and does not bear weight. higher defect. 3. The cross-street bridge with hybrid structure is a hybrid of the above two structures, and the bridge rail and the bridge are used as load-bearing structures to share the load of the bridge. Pedestrian bridges with this structure have the following defects: first, they can bear small external loads, the designed bridge deck width is small (mostly less than 12m), and the flow of people that can carry is limited, which can only meet a single use function and cannot be aggregated. Sightseeing functions in one. Second, the stress of the structure is complex, the workload of design and calculation is large, the road traffic is often interrupted during the construction period, and the construction period is long. Third, it cannot be connected with the surrounding buildings and cannot coordinate with the surrounding environment.
发明内容 Contents of the invention
本发明的目的,是为了解决现有技术中的人行天桥存在无法与周边的建筑物连接、桥面宽度小、结构受力复杂、设计工作量大的缺点,提供一种架设于建筑物之间的宽体人行天桥,The purpose of the present invention is to solve the shortcomings of the pedestrian bridge in the prior art that it cannot be connected with the surrounding buildings, the width of the bridge deck is small, the structure is stressed, and the design workload is large, and to provide a pedestrian bridge erected between buildings. wide body pedestrian bridge,
本发明的目的可以通过采取如下技术方案达到:The purpose of the present invention can be achieved by taking the following technical solutions:
架设于建筑物之间的宽体人行天桥,其结构特点是:The structural characteristics of wide-body pedestrian bridges erected between buildings are:
1)在马路两侧的建筑物与马路之间设置双柱式桥墩,双柱式桥墩的底部连接有与之配套的钻孔灌注桩基础,在桥墩的顶部设置盖梁,宽体人行天桥的主桥设置在盖梁的上面;所述主桥的两端悬臂分别与建筑物固定连接;1) Set up double-column bridge piers between the buildings on both sides of the road and the road. The bottom of the double-column bridge piers is connected with the matching bored pile foundation, and the top of the bridge piers is set with a cover beam. The wide-body pedestrian bridge The main bridge is arranged on the top of the cover beam; the cantilevers at both ends of the main bridge are respectively fixedly connected with the building;
2)所述主桥主要由包括下承式钢桁架、封底钢板和桥面铺装,钢桁架由上弦杆、下弦杆、腹杆和钢横杆连接而成,封底钢板固定于钢横杆的下面,桥面铺装设于钢横杆的上方。2) The main bridge is mainly composed of under-supported steel trusses, bottom-sealed steel plates and bridge deck pavement. The steel trusses are connected by upper chords, lower chords, webs and steel cross-bars, and the bottom-sealed steel plates are fixed on the steel cross-bars. Below, the deck pavement is laid over the steel crossbars.
本发明的目的还可以通过采取如下技术方案达到:The purpose of the present invention can also be achieved by taking the following technical solutions:
本发明的一种实施方案是:所述主桥的两端悬臂分别通过连接机构与建筑物连接;所述连接机构包括两套由形角钢与形附加钢筋叠加焊接而成的固定件,以及带有伸缩缝的连接钢板,两套固定件分别对称布置在主桥的悬臂末端和建筑物上,连接钢板的两端分别与固定件焊接;所述连接钢板的伸缩缝中设有填嵌缝膏。One embodiment of the present invention is: the two ends of the cantilever of the main bridge are respectively connected to the building through the connecting mechanism; the connecting mechanism includes two sets of Shaped angle steel with The fixed piece welded by superimposed additional steel bars and the connecting steel plate with expansion joints, the two sets of fixing pieces are arranged symmetrically on the cantilever end of the main bridge and the building respectively, and the two ends of the connecting steel plate are respectively welded to the fixing piece; A caulking paste is provided in the expansion joints connecting the steel plates.
本发明的一种实施方案是:在盖梁与钢桁架的下弦杆的连接处由上到下依次设有弦杆调平板、支座和支座垫石;在弦杆调平板底面焊接有抗震档块。An embodiment of the present invention is: at the connection between the cover beam and the lower chord of the steel truss, a chord leveling plate, a support and a support pad are arranged sequentially from top to bottom; block.
本发明的一种实施方案是:在所述下弦杆的相对两侧各设有加劲肋。An embodiment of the present invention is that stiffening ribs are provided on opposite sides of the lower chord.
本发明的一种实施方案是:在所述钢桁架的外侧设有花槽、在钢桁架的内侧设有水沟。One embodiment of the present invention is: a planter is provided on the outside of the steel truss, and a water ditch is provided on the inside of the steel truss.
本发明的一种实施方案是:在所述钢桁架的顶部设有钢梁屋架,在钢梁屋架上设有顶架钢板。One embodiment of the present invention is: a steel girder roof truss is arranged on the top of the steel truss, and a top frame steel plate is arranged on the steel girder roof truss.
本发明的一种实施方案是:在所述双柱式桥墩的两支承墩之间设有系梁。One embodiment of the present invention is: a tie beam is arranged between the two supporting piers of the double-column bridge pier.
本发明的一种实施方案是:所述主桥的桥面宽度为13.2米,跨度为28.50米,两端悬臂分别为9.630米和6.13米。An embodiment of the present invention is: the deck width of the main bridge is 13.2 meters, the span is 28.50 meters, and the cantilevers at both ends are 9.630 meters and 6.13 meters respectively.
本发明的有益效果:Beneficial effects of the present invention:
1、本发明由于将主桥的两端悬臂分别通过连接机构与建筑物连接,与路边建筑物构成和谐协调的整体结构,因此,可使整座天桥更显得轻巧美观,而桥下更是开阔简洁,车辆畅通无阻,具有造型构思新颖,建筑设计独特、集使用功能和观光功能于一体,能够承受较大的附加荷载、设计的桥面宽度大,受力情况更为清晰、明朗,能够大大减少设计计算的工作量,同时具有施工方便、施工过程对交通影响小的特点。特别是可将宽体天桥立面塑造成一条通透的、与周边环境十分协调的线条。1. Since the present invention connects the cantilevers at both ends of the main bridge to the building through the connecting mechanism, it forms a harmonious overall structure with the roadside buildings. Therefore, the whole overpass can be made more light and beautiful, and the under bridge is even more beautiful. Open and concise, unimpeded vehicles, with novel modeling concept, unique architectural design, integrating use function and sightseeing function, capable of bearing large additional load, designed with a large width of bridge deck, and the force situation is clearer and clearer, able to It greatly reduces the workload of design and calculation, and at the same time has the characteristics of convenient construction and little impact on traffic during the construction process. In particular, the façade of the wide-body overpass can be shaped into a transparent line that is in harmony with the surrounding environment.
2、本发明的主桥采用两端悬臂预制连续钢桁架结构型式,主桥的横向宽度为13.2米,集使用功能和观光功能于一体,能够承受较大的附加荷载、设计的桥面宽度大,受力情况更为清晰、明朗,能够大大减少设计计算的工作量。2. The main bridge of the present invention adopts the cantilever prefabricated continuous steel truss structure type at both ends. The transverse width of the main bridge is 13.2 meters. , the force situation is clearer and clearer, which can greatly reduce the workload of design calculation.
3、本发明在盖梁与钢桁架的下弦杆之间由上到下依次设有弦杆调平板、支座和支座垫石;在弦杆调平板底面焊接有抗震档块,能够满足结构所应有的抗风、抗震等性能。3. In the present invention, a chord leveling plate, a support and a support pad are sequentially arranged between the cover beam and the lower chord of the steel truss; an anti-seismic block is welded on the bottom of the chord leveling plate, which can meet the structural requirements. It should have wind resistance, earthquake resistance and other properties.
4、本发明的主桥分为两段钢桁架,钢桁架在工厂制作,现场拼焊,施工在天桥的整个施工过程中,可以尽快吊装上去,留出路面让汽车通行,交通基本不造成太大影响,具有施工方便和施工周期短的优点。4. The main bridge of the present invention is divided into two sections of steel trusses. The steel trusses are manufactured in the factory and welded on site. During the entire construction process of the overpass, the steel trusses can be hoisted up as soon as possible. It has the advantages of convenient construction and short construction period.
附图说明 Description of drawings
图1是本发明具体实施例的人行天桥得整体结构立面图。Fig. 1 is the elevation view of the whole structure of the pedestrian bridge of the specific embodiment of the present invention.
图2是图1中A-A向剖视图。Fig. 2 is a sectional view along line A-A in Fig. 1 .
图3是本发明具体实施例的桥墩、桩基的立面图。Fig. 3 is an elevation view of a bridge pier and a pile foundation according to a specific embodiment of the present invention.
图4是本发明具体实施例的桥墩、桩基的侧视图。Fig. 4 is a side view of a bridge pier and a pile foundation according to a specific embodiment of the present invention.
图5是图3中A-A向剖视图。Fig. 5 is a sectional view along A-A in Fig. 3 .
图6是图3中B-B向剖视图。Fig. 6 is a cross-sectional view along B-B in Fig. 3 .
图7是本发明具体实施例的盖梁与钢桁架的下弦杆连接处的结构示意图。Fig. 7 is a structural schematic diagram of the connection between the cover beam and the lower chord of the steel truss according to the specific embodiment of the present invention.
图8是图7中A-A向剖视图。Fig. 8 is a sectional view along line A-A in Fig. 7 .
图9是图7中B-B向剖视图。Fig. 9 is a cross-sectional view along B-B in Fig. 7 .
图10是本发明具体实施例的连接机构的结构示意图。Fig. 10 is a schematic structural diagram of a connection mechanism of a specific embodiment of the present invention.
具体实施方式 Detailed ways
具体实施例:Specific examples:
参照图1∽图6,本实施例包括架设于马路两侧的双柱式桥墩1及与之配套的钻孔灌注桩基础2,设置于桥墩1顶部的盖梁3,设置于盖梁3上面的主桥4;主桥4的两端悬臂分别与建筑物5连接;所述主桥4主要由两段焊接的下承式钢桁架4-1、封底钢板4-2和桥面铺装4-3构成,钢桁架4-1由上弦杆4-1-1、下弦杆4-1-2、腹杆4-1-3和钢横杆4-1-4连接而成,封底钢板4-2固定于钢横杆4-1-4的下面,桥面铺装4-3设于钢横杆4-1-4的上方。所述主桥4的宽面宽度为13.2米,跨度为28.50m,两端悬臂分别为9.630米和6.13米。所述钢桁架4-1的外侧设有花槽4-1-6、其内侧设有水沟4-1-7。所述钢桁架4-1的顶部设有钢梁屋架4-1-8,钢梁屋架4-1-8上设有顶架钢板4-1-9。所述双柱式桥墩1的两个桥墩之间设有系梁11。With reference to Fig. 1 ~ Fig. 6, present embodiment comprises the double-
参照图7、图8和图9,在盖梁3与钢桁架4-1的下弦杆4-1-2之间由上到下依次设有弦杆调平板7、支座8和支座垫石9;在弦杆调平板7底面焊接有抗震档块10。所述下弦杆4-1-2的两对侧分别设有加劲肋下弦杆4-1-5。Referring to Fig. 7, Fig. 8 and Fig. 9, between the
参照图10,所述主桥4的两端悬臂分别通过连接机构与建筑物连接;所述连接机构包括两套由形角钢6-1与形附加钢筋6-2叠加焊接而成的固定件,以及带有伸缩缝的连接钢板6-3,两套固定件分别对称布置在主桥4的悬臂末端和建筑物5上,连接钢板6-3的两端分别与固定件焊接;所述连接钢板6-3的伸缩缝6-3-1中设有填嵌缝膏。Referring to Fig. 10, the cantilevers at both ends of the
本发明的施工方法如下:Construction method of the present invention is as follows:
主桥两片钢桁架采用吊装技术,吊装完成后现浇砼主桥结构。人行天桥位于交通繁忙的珠江大道上,施工期间不能中断道路交通,因此钢桁架必须在工厂制作,现场拼焊施工。The two steel trusses of the main bridge adopt hoisting technology, and the main bridge structure is cast in place after the hoisting is completed. The pedestrian bridge is located on the busy Pearl River Avenue, and the road traffic cannot be interrupted during the construction period. Therefore, the steel truss must be fabricated in the factory and welded on site.
第一步:施工桩基、桥墩;同时工厂预制钢桁架。The first step: construction of pile foundations and bridge piers; at the same time, factory prefabricated steel trusses.
第二步:搭设临时支架,运输桁架半成品至施工现场,分块吊装,同时焊接。Step 2: Set up temporary supports, transport the semi-finished trusses to the construction site, hoist them in blocks and weld them at the same time.
第三步:安装桥面铺装和栏杆,挂设花盆,桥面装饰,成桥。The third step: install bridge pavement and railings, hang flower pots, decorate the bridge deck, and complete the bridge.
本发明的主要设计依据如下:The main design basis of the present invention is as follows:
1)设计参数:1) Design parameters:
根据《建筑结构荷载规范》GB 50009-20017.1.1采用:According to the "Building Structure Load Code" GB 50009-20017.1.1 adopts:
风荷载计算公式:Wk=βgz×μz×μs×W0。其中:Wk:作用在光伏方阵上的风荷载标准值(kN/m2),B gz:瞬时风压的阵风系数,按《建筑结构荷载规范》GB 50009-2001取定。Wind load calculation formula: Wk=βgz×μz×μs×W0. Among them: Wk: standard value of wind load acting on the photovoltaic array (kN/m2), B gz: gust coefficient of instantaneous wind pressure, determined according to "Code for Building Structure Loads" GB 50009-2001.
根据不同场地类型,按以下公式计算:βgz=K(1+2μf),其中K为地区粗糙度调整系数,μf为脉动系数:According to different site types, it is calculated according to the following formula: βgz=K(1+2μf), where K is the area roughness adjustment coefficient, and μf is the pulsation coefficient:
A类场地:βgz=0.92*(1+2μf)其中:μf=0.387*(Z/10)^(-0.12);Class A site: βgz=0.92*(1+2μf) where: μf=0.387*(Z/10)^(-0.12);
B类场地:βgz=0.89*(1+2μf)其中:μf=0.5(Z/10)^(-0.16);Class B venue: βgz=0.89*(1+2μf) where: μf=0.5(Z/10)^(-0.16);
C类场地:βgz=0.85*(1+2μf)其中:μf=0.734(Z/10)^(-0.22);Class C venue: βgz=0.85*(1+2μf) where: μf=0.734(Z/10)^(-0.22);
D类场地:βgz=0.80*(1+2μf)其中:μf=1.2248(Z/10)^(-0.3);Class D site: βgz=0.80*(1+2μf) where: μf=1.2248(Z/10)^(-0.3);
μz---风压高度变化系数,按《建筑结构荷载规范》GB 50009-2001取定,根据不同场地类型,按以下公式计算:μz---coefficient of wind pressure height change, determined according to "Code for Building Structure Loads" GB 50009-2001, and calculated according to the following formula according to different site types:
A类场地:μz=1.379×(Z/10)0.24;Class A venue: μz=1.379×(Z/10)0.24;
B类场地:μz=(Z/10)0.32;Class B venue: μz=(Z/10)0.32;
C类场地:μz=0.616×(Z/10)0.44;Class C venue: μz=0.616×(Z/10)0.44;
D类场地:μz=0.318×(Z/10)0.60;Class D venue: μz=0.318×(Z/10)0.60;
本工程属于B类地区,故μz=1.379×(Z/10)0.24,μs---风荷载体型系数,按《建筑结构荷载规范》GB 50009-2001取为:2.0,W0---基本风压,按现场风速测试风压图,取为0.7kN/m2This project belongs to Class B area, so μz=1.379×(Z/10)0.24, μs---wind load shape coefficient, according to "Building Structure Load Code" GB 50009-2001 is taken as: 2.0, W0---basic wind According to the on-site wind speed test wind pressure diagram, it is taken as 0.7kN/m2
2)地震作用:抗震设计烈度取为7度,地震影响系数取为0.08。2) Earthquake action: The seismic design intensity is taken as 7 degrees, and the seismic influence coefficient is taken as 0.08.
3)温度作用:年温度变化取为80摄氏度。3) Effect of temperature: the annual temperature change is taken as 80 degrees Celsius.
以上所述,仅为本发明较佳的具体实施例,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的范围内,根据本发明的技术方案及其发明构思加以等同替换或改变,都属于本发明的保护范围。The above are only preferred specific embodiments of the present invention, but the scope of protection of the present invention is not limited thereto. Anyone familiar with the technical field within the scope of the disclosure of the present invention, according to the technical solutions of the present invention and Any equivalent replacement or change of the inventive concept falls within the protection scope of the present invention.
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102792783A CN102425100A (en) | 2011-09-20 | 2011-09-20 | Wide-bodied pedestrian overpass erected among buildings |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102792783A CN102425100A (en) | 2011-09-20 | 2011-09-20 | Wide-bodied pedestrian overpass erected among buildings |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102425100A true CN102425100A (en) | 2012-04-25 |
Family
ID=45959126
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011102792783A Pending CN102425100A (en) | 2011-09-20 | 2011-09-20 | Wide-bodied pedestrian overpass erected among buildings |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102425100A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106958766A (en) * | 2017-04-07 | 2017-07-18 | 安徽建筑大学 | Road lamp structure device is reformed transform deeply in narrow lane in huizhou tradition colony |
CN108193591A (en) * | 2017-12-30 | 2018-06-22 | 贵阳铝镁设计研究院有限公司 | A kind of aluminum alloy pedestrian bridge steel bridge pier on the anti-edge of extended position band |
CN110067197A (en) * | 2019-05-27 | 2019-07-30 | 江苏工程职业技术学院 | One kind climbing wall-shaped bridge wind pressure alarming robot and control method |
CN112458886A (en) * | 2020-12-18 | 2021-03-09 | 南南铝工程有限责任公司 | Half calabash shape aluminum alloy pedestrian bridge connection structure |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3322951A1 (en) * | 1983-06-25 | 1985-01-03 | Johannes Dörnen, Stahlbauwerk, 4600 Dortmund | Truss bridge and method for producing it |
CN1263185A (en) * | 1999-02-10 | 2000-08-16 | 天津市市政工程设计研究院 | Hollow grid structure pedestrain overcrossing |
CN2420324Y (en) * | 2000-04-27 | 2001-02-21 | 黄太明 | Net truss for pedestrian overcrossing |
CN2830500Y (en) * | 2003-02-14 | 2006-10-25 | 周宪平 | Balance energy saving hoisting tower cable overline bridge |
CN101139813A (en) * | 2007-08-31 | 2008-03-12 | 西南交通大学 | A kind of steel truss of under-supported bridge |
EP1905900A2 (en) * | 2006-09-20 | 2008-04-02 | Eiffel Deutschland Stahltechnologie GmbH | Bridge with two framework-type plates and set for its manufacture |
KR20100108930A (en) * | 2009-03-31 | 2010-10-08 | 김학권 | The method of manufacturing for main girder with prefabricated truss type structure and the method of constructing for bridge by using the upper method |
CN101967793A (en) * | 2010-10-28 | 2011-02-09 | 南京工业大学 | Rapidly Assembled Segmented Composite Truss Bridge |
CN201891069U (en) * | 2010-10-21 | 2011-07-06 | 安徽省交通规划设计研究院 | Through steel pipe-concrete open type truss combination beam bridge |
JP2011149224A (en) * | 2010-01-22 | 2011-08-04 | Tomoe Corp | Connection structure of space truss |
CN202347425U (en) * | 2011-09-20 | 2012-07-25 | 广州市设计院 | Wide-body pedestrian overpass erected between buildings |
-
2011
- 2011-09-20 CN CN2011102792783A patent/CN102425100A/en active Pending
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3322951A1 (en) * | 1983-06-25 | 1985-01-03 | Johannes Dörnen, Stahlbauwerk, 4600 Dortmund | Truss bridge and method for producing it |
CN1263185A (en) * | 1999-02-10 | 2000-08-16 | 天津市市政工程设计研究院 | Hollow grid structure pedestrain overcrossing |
CN2420324Y (en) * | 2000-04-27 | 2001-02-21 | 黄太明 | Net truss for pedestrian overcrossing |
CN2830500Y (en) * | 2003-02-14 | 2006-10-25 | 周宪平 | Balance energy saving hoisting tower cable overline bridge |
EP1905900A2 (en) * | 2006-09-20 | 2008-04-02 | Eiffel Deutschland Stahltechnologie GmbH | Bridge with two framework-type plates and set for its manufacture |
CN101139813A (en) * | 2007-08-31 | 2008-03-12 | 西南交通大学 | A kind of steel truss of under-supported bridge |
KR20100108930A (en) * | 2009-03-31 | 2010-10-08 | 김학권 | The method of manufacturing for main girder with prefabricated truss type structure and the method of constructing for bridge by using the upper method |
JP2011149224A (en) * | 2010-01-22 | 2011-08-04 | Tomoe Corp | Connection structure of space truss |
CN201891069U (en) * | 2010-10-21 | 2011-07-06 | 安徽省交通规划设计研究院 | Through steel pipe-concrete open type truss combination beam bridge |
CN101967793A (en) * | 2010-10-28 | 2011-02-09 | 南京工业大学 | Rapidly Assembled Segmented Composite Truss Bridge |
CN202347425U (en) * | 2011-09-20 | 2012-07-25 | 广州市设计院 | Wide-body pedestrian overpass erected between buildings |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106958766A (en) * | 2017-04-07 | 2017-07-18 | 安徽建筑大学 | Road lamp structure device is reformed transform deeply in narrow lane in huizhou tradition colony |
CN106958766B (en) * | 2017-04-07 | 2019-05-28 | 安徽建筑大学 | Do street lamp reconstruction structure device deeply in a kind of lane traditional settlement Nei Zhai |
CN108193591A (en) * | 2017-12-30 | 2018-06-22 | 贵阳铝镁设计研究院有限公司 | A kind of aluminum alloy pedestrian bridge steel bridge pier on the anti-edge of extended position band |
CN110067197A (en) * | 2019-05-27 | 2019-07-30 | 江苏工程职业技术学院 | One kind climbing wall-shaped bridge wind pressure alarming robot and control method |
CN112458886A (en) * | 2020-12-18 | 2021-03-09 | 南南铝工程有限责任公司 | Half calabash shape aluminum alloy pedestrian bridge connection structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104695341B (en) | Non-self-balanced beam string structure for reinforcing large-span continuous beam bridge | |
CN100543232C (en) | Double-layer continuous girder bridge with steel-concrete composite structure | |
CN111335142A (en) | Self-anchored cable-stayed arch bridge | |
CN103290784B (en) | Arched girder conjugative bridge construction method for hanging | |
CN108374319A (en) | A kind of through tied arch bridge structural unit and arch bridge structure and its construction method | |
CN103882801A (en) | Segment assembled type combined highway and railway cable-stayed bridge with inconsistent bridge deck widths of highway and railway | |
CN100562631C (en) | Spherical netted shell combined structure | |
CN102808373A (en) | Rapid assembly type truss string pedestrian steel bridge | |
CN107489090B (en) | A kind of circle bamboo space truss bridge based on joint structure mode | |
CN102425100A (en) | Wide-bodied pedestrian overpass erected among buildings | |
CN104452574A (en) | Novel ramp bridge structure and construction method thereof | |
CN112554031B (en) | Upper bearing type beam-arch combined rigid frame bridge for double-deck traffic | |
CN201151866Y (en) | Arch beam type overbridge | |
CN103015304B (en) | Prestressed concrete variable-cross-section box girder bridge with internal tilted-leg rigid frame and construction method of prestressed concrete variable-cross-section box girder bridge | |
CN215164570U (en) | Ultra-wide bridge floor open-type light combined bridge floor special-shaped arch bridge | |
CN110939067A (en) | Method for determining position of bridge closure section of collaboration system | |
CN216474457U (en) | Short T roof beam flood bridge flood fighting anchorage structure | |
CN201228341Y (en) | cable-stayed overpass | |
CN202347425U (en) | Wide-body pedestrian overpass erected between buildings | |
CN205557290U (en) | Monolithic purlin formula annular passenger footbridge | |
CN113174839A (en) | Ultra-wide bridge deck open type light combined bridge deck special-shaped arch bridge and construction method thereof | |
CN208995897U (en) | Suspension cable overpass | |
CN103485271B (en) | A prestressed cable truss bridge for pedestrians in mountainous rural areas | |
CN103031804B (en) | Slant leg rigid frame built-in prestressed concrete variable cross-section box girder bridge and construction method thereof | |
CN113622283A (en) | Horizontal pulling type pedestrian suspension bridge with hyperbolic paraboloid space crossed cable nets |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120425 |