CN102409666B - 防空洞走向上桩基础施工工艺 - Google Patents
防空洞走向上桩基础施工工艺 Download PDFInfo
- Publication number
- CN102409666B CN102409666B CN201110389423.3A CN201110389423A CN102409666B CN 102409666 B CN102409666 B CN 102409666B CN 201110389423 A CN201110389423 A CN 201110389423A CN 102409666 B CN102409666 B CN 102409666B
- Authority
- CN
- China
- Prior art keywords
- shelter
- pile foundation
- air
- bomb shelter
- trend
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
本发明公开了一种防空洞走向上桩基础施工工艺,包括如下工序:(1)向防空洞外壁注浆,使防空洞洞壁与洞外土体形成整体;(2)从防空洞内沿防空洞走向间隔向上垂直打孔,在地面上定位防空洞的宽窄、走向,按照桩基础图的布置在地面上放出桩位;(3)在防空洞与桩位重合的部位进行引孔;(4)在引孔处下护筒使所引的桩位与防空洞内其他空间分隔开;(5)在所引的桩位处开始桩基础施工。本发明桩基础稳固,强度高,桩基础质量高。
Description
技术领域
本发明属于建筑施工技术领域,特别涉及一种防空洞走向上桩基础施工工艺。
背景技术
中国专利ZL200610017568.X公开了一种防空洞加固施工工艺,包括如下工序:(1)沿防空洞走向,将防空洞洞壁间隔凿开一定宽度并深入原土层一定深度,在与洞壁凿开空间对应的洞内地面上凿开一定深度,向地面及洞壁凿开空间喷满混凝土形成加固框架;(2)在洞壁上间隔钻孔,向防空洞洞壁与其外侧土体间注浆填实间隙,使其地耐力接近或等于原土层地耐力;(3)在加固框架一侧砌砖墙,沿砖墙喷射混凝土与加固框架相接形成加固隔断。还包括工序(4)自防空洞洞顶对应地面向防空洞内间隔钻孔;(5)向防空洞内加固隔断之间注浆填实该空间。本发明主要是针对防空洞加固而提供的施工工艺,并未考虑到各种桩基础和防空洞重叠时如何施工。
发明内容
本发明的目的是提供一种防空洞走向上桩基础施工工艺,可以实现在防空洞上方进行打桩施工。
为达到上述目的,本发明采用的技术方案是:
防空洞走向上桩基础施工工艺,包括如下工序:(1)向防空洞外壁注浆,使防空洞洞壁与洞外土体形成整体;(2)从防空洞内沿防空洞走向间隔向上垂直打孔,在地面上定位防空洞的宽窄、走向,按照桩基础图的布置在地面上放出桩位;(3)在防空洞与桩位重合的部位进行引孔;(4)在引孔处下护筒使所引的桩位与防空洞内其他空间分隔开;(5)在所引的桩位处开始桩基础施工。
还包括工序(6)对防空洞内加固。
工序(3)中,引孔深度至穿过防空洞底部0~10米范围内,引孔直径与桩直径相等或大于桩直径0~2米。
工序(4)中在护筒外用砂石或支撑的方式对护筒进行固定。
本发明中,通过对防空洞洞壁外进行注浆加固,使防空洞洞壁与洞外土体形成整体;通过从防空洞内沿防空洞走向向上垂直打孔定位,在地面上放出桩位;在防空洞与桩位重合的部位采用机械或者人工挖孔等方式进行引孔,在引孔处下护筒,护筒采用钢筒、水泥筒等,将所引的桩位在防空洞内与其他空间分隔开,再对防空洞内进行加固,保证桩基础稳固,强度高;加固后利用桩机进行桩基础施工,护筒将所引的桩位在防空洞内与其他空间分隔开,保证桩基础的顺利实施,也能对桩基础起到保护的作用,强度高,桩基础质量高。
具体实施方式
实施例1:防空洞走向上桩基础施工工艺,包括如下工序:
(1)根据ZL200610017568.X向防空洞外壁注浆加固,在防空洞洞壁上每间隔2.0米用风钻在洞壁上钻三个小孔(均布),呈梅花形布置,孔中埋设长度为0.5米的六分管,用水泥(高标号)或水玻璃或其他的混合物将埋管与洞壁间隙封死,将水泥与土按照一定比列配置混合液待用,水灰比1:0.5.为增加流动性可加粉煤灰,待混凝土强度达到75%,开始通过洞壁上埋管向洞壁与周围土体间高压注浆,注浆压力不低于0.4MPa,使防空洞洞壁与洞外土体形成整体;
(2)定位:从防空洞内沿防空洞走向间隔向上垂直打孔,在地面上定位防空洞的宽窄、走向,按照桩基础图的布置在地面上放出桩位;
(3)在防空洞与桩位重合的部位采用机械或者人工挖孔等方式进行引孔:引孔深度至穿过防空洞底部,引孔直径与桩直径相等,修正所引的孔位剔除防空洞的毛边,并清除桩底的浮土或者建筑垃圾;
(4)在引孔处下护筒使所引的桩位与防空洞内其他空间分隔开,护筒采用钢筒或者塑料管筒或者砖石砌筒或者水泥筒等,在护筒外用砂石或支撑的方式对护筒进行固定;
(5)在所引的桩位处开始桩基础施工。
经上述处理后,防空洞可再次投入使用;如防空洞需报废,则根据ZL200610017568.X对防空洞内进行加固。
实施例2:
(1)根据ZL200610017568.X向防空洞外壁注浆,在防空洞洞壁上每间隔2.0米用风钻在洞壁上钻三个小孔(均布),呈梅花形布置,孔中埋设长度为0.5米的六分管,用水泥(高标号)或水玻璃或其他的混合物将埋管与洞壁间隙封死,将水泥与土按照一定比列配置混合液待用,水灰比1:0.5,为增加流动性可加粉煤灰,待混凝土强度达到75%,开始通过洞壁上埋管向洞壁与周围土体间高压注浆,注浆压力不低于0.4MPa,使防空洞洞壁与洞外土体形成整体;
(2)定位:从防空洞内沿防空洞走向间隔向上垂直打孔,在地面上定位防空洞的宽窄、走向,按照桩基础图的布置在地面上放出桩位;
(3)在防空洞与桩位重合的部位采用机械或者人工挖孔等方式进行引孔:引孔深度至穿过防空洞底部5米,引孔直径大于桩直径1米,修正所引的孔位剔除防空洞的毛边,并清除桩底的浮土或者建筑垃圾;
(4)在引孔处下护筒使所引的桩位与防空洞内其他空间分隔开,护筒采用钢筒或者塑料管筒或者砖石砌筒或者水泥筒等,在护筒外用砂石或支撑的方式对护筒进行固定;
(5)在所引的桩位处开始桩基础施工。
经上述处理后,防空洞可再次投入使用;如防空洞需报废,则根据ZL200610017568.X对防空洞内进行加固。
实施例3:
(1)根据ZL200610017568.X向防空洞外壁注浆加固,在防空洞洞壁上每间隔2.0米用风钻在洞壁上钻三个小孔(均布),呈梅花形布置,孔中埋设长度为0.5米的六分管,用水泥(高标号)或水玻璃或其他的混合物将埋管与洞壁间隙封死,将水泥与土按照一定比列配置混合液待用,水灰比1:0.5,为增加流动性可加粉煤灰,待混凝土强度达到75%,开始通过洞壁上埋管向洞壁与周围土体间高压注浆,注浆压力不低于0.4MPa,使防空洞洞壁与洞外土体形成整体;
(2)定位:从防空洞内沿防空洞走向间隔向上垂直打孔,在地面上定位防空洞的宽窄、走向,按照桩基础图的布置在地面上放出桩位;
(3)在防空洞与桩位重合的部位采用机械或者人工挖孔等方式进行引孔:引孔深度至穿过防空洞底部10米,引孔直径大于桩直径2米,修正所引的孔位剔除防空洞的毛边,并清除桩底的浮土或者建筑垃圾;
(4)在引孔处下护筒使所引的桩位与防空洞内其他空间分隔开,护筒采用钢筒或者塑料管筒或者砖石砌筒或者水泥筒等,在护筒外用砂石或支撑的方式对护筒进行固定;
(5)在所引的桩位处开始桩基础施工。
经上述处理后,防空洞可再次投入使用;如防空洞需报废,则根据ZL200610017568.X对防空洞内进行加固。
Claims (4)
1.防空洞走向上桩基础施工工艺,其特征在于,包括如下工序:(1)向防空洞外壁注浆,使防空洞洞壁与洞外土体形成整体;(2)从防空洞内沿防空洞走向间隔向上垂直打孔,在地面上定位防空洞的宽窄、走向,按照桩基础图的布置在地面上放出桩位;(3)在防空洞与桩位重合的部位进行引孔;(4)在引孔处下护筒使所引的桩位与防空洞内其他空间分隔开;(5)在所引的桩位处开始桩基础施工。
2.如权利要求1所述的防空洞走向上桩基础施工工艺,其特征在于,还包括工序(6)对防空洞内加固。
3.如权利要求1或2所述的防空洞走向上桩基础施工工艺,其特征在于,工序(3)中,引孔深度至穿过防空洞底部0~10米范围内,引孔直径与桩直径相等或大于桩直径0~2米。
4.如权利要求3所述的防空洞走向上桩基础施工工艺,其特征在于,工序(4)中在护筒外用砂石或支撑的方式对护筒进行固定。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110389423.3A CN102409666B (zh) | 2011-11-30 | 2011-11-30 | 防空洞走向上桩基础施工工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110389423.3A CN102409666B (zh) | 2011-11-30 | 2011-11-30 | 防空洞走向上桩基础施工工艺 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102409666A CN102409666A (zh) | 2012-04-11 |
CN102409666B true CN102409666B (zh) | 2014-05-07 |
Family
ID=45911986
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201110389423.3A Active CN102409666B (zh) | 2011-11-30 | 2011-11-30 | 防空洞走向上桩基础施工工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102409666B (zh) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103195090B (zh) * | 2013-04-15 | 2015-04-01 | 合肥建工集团有限公司 | 地下腔室上开小孔注砼软模成型支柱 |
CN103603508B (zh) * | 2013-11-19 | 2016-06-08 | 中国建筑第二工程局有限公司 | 一种桩基础在地下防空洞内的封堵灌注加固施工方法 |
CN104674796B (zh) * | 2015-03-06 | 2017-06-13 | 中国建筑第二工程局有限公司 | 一种地下防空洞灌注桩的模板系统及其施工方法 |
CN110144903B (zh) * | 2019-06-05 | 2021-04-09 | 中国建筑第七工程局有限公司 | 一种基坑支护遇防空洞的施工工法 |
CN110512594B (zh) * | 2019-08-20 | 2020-12-29 | 北京建材地质工程有限公司 | 旋挖钻机遇空洞成孔成桩的简易方法 |
CN113216148B (zh) * | 2021-05-13 | 2022-08-26 | 中建市政工程有限公司 | 承压水地下防空洞坍塌地段桩基施工方法 |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1936199A (zh) * | 2006-03-27 | 2007-03-28 | 李海广 | 防空洞加固施工工艺 |
-
2011
- 2011-11-30 CN CN201110389423.3A patent/CN102409666B/zh active Active
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1936199A (zh) * | 2006-03-27 | 2007-03-28 | 李海广 | 防空洞加固施工工艺 |
Non-Patent Citations (2)
Title |
---|
杨建忠.用人工挖孔桩处理人防地道.《山西建筑》.2001,第27卷(第6期),第40页右栏第2段至第3段,第41页左栏第4段. |
用人工挖孔桩处理人防地道;杨建忠;《山西建筑》;20011231;第27卷(第6期);第40页右栏第2段至第3段,第41页左栏第4段 * |
Also Published As
Publication number | Publication date |
---|---|
CN102409666A (zh) | 2012-04-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102409666B (zh) | 防空洞走向上桩基础施工工艺 | |
KR100707492B1 (ko) | 지하 공동부용 충전재 시공방법 | |
CN104695963B (zh) | 碎裂岩层中地铁隧道穿越建筑物的施工方法 | |
CN105649012B (zh) | 上软下硬地层地铁车站围护结构钻孔桩施工方法 | |
CN108005660A (zh) | 一种高速公路隧道施工方法 | |
CN103835729A (zh) | 深部长距离巷道围岩地面预注浆加固工艺 | |
CN104563099A (zh) | 多孔管法大直径高压旋喷桩施工方法 | |
CN108265706A (zh) | 一种在溶洞地质内的工程桩及成桩工艺 | |
CN106320331A (zh) | 一种高压旋喷桩成孔系统穿越块石层的施工方法 | |
CN106284295A (zh) | 多通道钻喷一体化喷射注浆施工方法 | |
CN104695457B (zh) | 一种新型竖井水平旋喷桩基坑封底隔水层的施工方法 | |
CN204825923U (zh) | 一种接力式基坑支护结构 | |
CN110685272A (zh) | 一种利用斜孔布袋桩治理软基沉降超限的方法 | |
CN103046765B (zh) | 防空洞加固后继续使用的施工工艺 | |
CN102995666A (zh) | 减少振动对周边建(构)筑物影响的施工方法 | |
CN102359101A (zh) | 一种湿陷性土的地基处理方法 | |
CN102220764A (zh) | 深基坑支护体系及其施工方法 | |
CN104631479B (zh) | 换土搅拌的止水帷幕的施工方法 | |
CN104831735B (zh) | 一种桩幕合一的止水支护结构及其施工方法和施工设备 | |
CN111561262A (zh) | 一种岩溶地区大尺寸桩孔旋挖钻机成孔方法 | |
CN204609897U (zh) | 一种管幕冻结法支护结构 | |
CN207080242U (zh) | 盾构隧道端头竹筋注浆锚杆杯型水平加固结构 | |
CN105350544A (zh) | 用于含有块石区域的止水帷幕及其施工方法 | |
CN101793024B (zh) | 基坑多头小直径深搅和高喷组合防渗墙的建造方法 | |
CN205296194U (zh) | 一种富水地层暗挖隧道咬合管幕 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |