CN102400460A - 一种防止灌注砼桩桩径变异的施工方法 - Google Patents

一种防止灌注砼桩桩径变异的施工方法 Download PDF

Info

Publication number
CN102400460A
CN102400460A CN2011103898338A CN201110389833A CN102400460A CN 102400460 A CN102400460 A CN 102400460A CN 2011103898338 A CN2011103898338 A CN 2011103898338A CN 201110389833 A CN201110389833 A CN 201110389833A CN 102400460 A CN102400460 A CN 102400460A
Authority
CN
China
Prior art keywords
concrete
pile
stake
diameter
pouring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011103898338A
Other languages
English (en)
Inventor
刘富华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kunming Jiecheng Foundation Engineering & Machine Co Ltd
Original Assignee
Kunming Jiecheng Foundation Engineering & Machine Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kunming Jiecheng Foundation Engineering & Machine Co Ltd filed Critical Kunming Jiecheng Foundation Engineering & Machine Co Ltd
Priority to CN2011103898338A priority Critical patent/CN102400460A/zh
Publication of CN102400460A publication Critical patent/CN102400460A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明属于一种建筑工程的钢筋混凝土桩的施工方法,具体涉及防止灌注砼桩桩径变异的施工方法。本方法的工艺步骤为:①根据勘测到的流塑、软塑、土洞或溶洞地层位置,对应剪裁柔性片材,制成直径为灌注砼桩的桩径+100mm和-50mm范围之间的柔性筒;②将柔性筒固定在钢筋笼的对应桩径会变异的位置;③起吊钢筋笼、安装到桩孔内;④安装灌注砼导管、砼料斗、砼漏斗,灌注砼,使柔性筒随着砼灌注的同时自下而上扩充到预设直径。本发明操作简易,增加成本很少,可有效地解决灌注砼桩的扩径、超灌、鼓包等现象,大大降低打桩的施工成本。

Description

一种防止灌注砼桩桩径变异的施工方法
技术领域
本发明属于一种建筑工程的钢筋混凝土桩的施工方法,具体涉及防止灌注砼桩桩径变异的施工方法。
背景技术
传统的建筑工程灌注砼桩的施工是在地面形成符合要求的桩孔,再将钢筋笼安装到桩孔中,然后灌注混凝土,待混凝土凝固后在桩孔中形成起支撑作用的钢筋混凝土灌注桩。然而,在施工中常常会遇到桩孔穿越软(流)塑地层、土洞、溶洞等特殊地层的情况,当灌注混凝土时桩体会出现扩径、超灌、鼓包等现象,造成了砼浪费、成本上升、桩体质量下降等问题。特别是在地下结构的施工中,这时需要将内侵的桩体混凝土再凿除,必然浪费大量的人力、物力,使工期大大拖延,大幅度增加打桩的施工成本。
发明内容
根据上述灌注砼桩施工存在的问题,本发明的目的是提供一种防止灌注砼桩桩径变异的施工方法,其工艺简单,施工容易,增加成本很少,可有效地解决灌注砼桩的扩径、超灌、鼓包等现象,大大降低打桩的施工成本。
实现本发明上述目的采取的技术方案是:①根据勘测到的流塑、软塑、土洞或溶洞地层位置,对应剪裁柔性片材,制成直径为灌注砼桩的桩径+100mm和-50mm范围之间的柔性筒;②将柔性筒固定在钢筋笼的对应桩径会变异的位置;③起吊钢筋笼、安装到桩孔内;④安装灌注砼导管、砼料斗、砼漏斗,灌注砼,使柔性筒随着砼灌注的同时自下而上扩充到预设直径。
本发明所述的柔性片材采用纺织布料、土工布、塑料彩带布或筛网材料,其厚度为0.26mm~1.34 mm,采用铁线、线绳或橡皮筋将柔性筒包容在钢筋笼外侧,铁线、线绳或橡皮筋的约束力应低于砼的流动扩张力。 
本发明的有益效果是:通过柔性筒包裹在钢筋笼外,约束了砼灌注量,灌注砼桩时防止了在软(流)塑地层、土洞、溶洞等特殊地层的位置出现扩径、超灌、鼓包等现象,保持桩径的统一,避免了围护灌注砼桩对地下结构产生内侵现象的桩体混凝土再凿除工作,消除了砼浪费,达到了节约成本、工期和控制桩体质量的目的。
附图说明
图1为本发明的施工流程示意图。
图2为本发明钢筋笼的结构示意图。
图3为本发明钢筋笼的横断面结构示意图。
图中:钢筋笼1、柔性筒2、折叠痕3、捆扎线4。
具体实施方式
参见图1,本发明的施工流程如下:①根据勘测到的流塑、软塑、土洞或溶洞地层位置,对应剪裁柔性片材,制成直径为灌注砼桩的桩径+100mm和-50mm范围之间的柔性筒;②将柔性筒固定在钢筋笼的对应桩径会变异的位置;③起吊钢筋笼、安装到桩孔内(普通桩孔或套管桩孔);④安装灌注砼导管、砼料斗、砼漏斗,灌注砼,使柔性筒随着砼灌注的同时自下而上扩充到预设直径。
参见图2、3,本发明的专用钢筋笼的制备方法如下:在钢筋笼1穿越软塑地层、土洞或溶洞地层的位置,将柔性筒2包裹在钢筋笼1外,柔性筒2采用纺织布料、土工布、塑料彩带布或筛网等材料制成筒形,其直径等于灌注砼桩的桩径,厚度为0.25mm~2.5 mm。由于柔性筒2包裹在钢筋笼1外时,其周长大于钢筋笼1的周长,因此在柔性筒2的周长方向留出一些折叠痕3,再通过捆扎线4固定在钢筋笼1上。捆扎线4可采用铁线、线绳或橡皮筋,当灌注砼时,由于其约束力小于砼流动状态的扩张力,铁线、线绳或橡皮筋被逐步挤开,使砼灌注桩的桩径自下而上扩充到预设直径。

Claims (2)

1.一种防止灌注砼桩桩径变异的施工方法,其特征是工艺步骤如下:
①根据勘测到的流塑、软塑、土洞或溶洞地层位置,对应剪裁柔性片材,制成直径为灌注砼桩的桩径+100mm和-50mm范围之间的柔性筒;
②将柔性筒固定在钢筋笼的对应桩径会变异的位置;
③起吊钢筋笼、安装到桩孔内;
④安装灌注砼导管、砼料斗、砼漏斗,灌注砼,使柔性筒随着砼灌注的同时自下而上扩充到预设直径。
2.按权利要求1所述的防止灌注砼桩桩径变异的施工方法,其特征是:柔性片材采用纺织布料、土工布、塑料彩带布或筛网材料,其厚度为0.25mm~2.5 mm,采用铁线、线绳或橡皮筋将柔性筒包容在钢筋笼外侧,铁线、线绳或橡皮筋的约束力应低于砼的流动扩张力。
CN2011103898338A 2011-11-30 2011-11-30 一种防止灌注砼桩桩径变异的施工方法 Pending CN102400460A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011103898338A CN102400460A (zh) 2011-11-30 2011-11-30 一种防止灌注砼桩桩径变异的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011103898338A CN102400460A (zh) 2011-11-30 2011-11-30 一种防止灌注砼桩桩径变异的施工方法

Publications (1)

Publication Number Publication Date
CN102400460A true CN102400460A (zh) 2012-04-04

Family

ID=45883071

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011103898338A Pending CN102400460A (zh) 2011-11-30 2011-11-30 一种防止灌注砼桩桩径变异的施工方法

Country Status (1)

Country Link
CN (1) CN102400460A (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102767175A (zh) * 2012-07-11 2012-11-07 广州市恒盛建设工程有限公司 软土地基冲孔灌注桩混凝土浇注方法及其所用的钢筋笼
CN102852140A (zh) * 2012-10-10 2013-01-02 东华理工大学 一种帷幕式溶洞灌注桩施工方法及弹性网布
CN103114575A (zh) * 2013-01-31 2013-05-22 中冶交通工程技术有限公司 灌注桩用的钢筋笼及使用其的灌注桩施工方法
CN103603340A (zh) * 2013-12-06 2014-02-26 中冶建工集团有限公司 柔性防护防止塌孔的旋挖成孔灌注桩施工方法
CN104775426A (zh) * 2015-04-17 2015-07-15 王继忠 一种现浇混凝土桩的保护装置及其施工方法
CN106522209A (zh) * 2016-10-08 2017-03-22 金陵科技学院 旋挖施工溶洞钻孔灌注桩灌注工法
CN106759307A (zh) * 2016-11-29 2017-05-31 中国冶集团有限公司 灌注桩在溶洞地层灌注的保护装置及方法
CN108978643A (zh) * 2018-07-10 2018-12-11 广东华固工程有限公司 支护桩施工方法、钢筋笼结构及支护桩结构
CN110295602A (zh) * 2019-04-24 2019-10-01 浙江省钱塘江管理局勘测设计院 一种水下砼浇筑工艺

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1986975A (zh) * 2006-11-13 2007-06-27 福建永强岩土工程有限公司 全套管大直径振动取土灌注桩施工方法
CN101761082A (zh) * 2010-01-18 2010-06-30 大连阿尔滨集团有限公司 一种灌注桩水下混凝土的强制浇注设备及施工方法
CN101982614A (zh) * 2010-10-11 2011-03-02 昆明捷程桩工有限责任公司 全套管钻机凿取岩石成桩的方法
CN201891114U (zh) * 2010-11-11 2011-07-06 上海市政工程设计研究总院 双重径向网笼砂石桩
WO2011105703A2 (ko) * 2010-02-26 2011-09-01 Song Gi-Yong 암반 매립 일체화 구조의 강관-콘크리트 복합 말뚝 시공 방법 및 말뚝 구조물

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1986975A (zh) * 2006-11-13 2007-06-27 福建永强岩土工程有限公司 全套管大直径振动取土灌注桩施工方法
CN101761082A (zh) * 2010-01-18 2010-06-30 大连阿尔滨集团有限公司 一种灌注桩水下混凝土的强制浇注设备及施工方法
WO2011105703A2 (ko) * 2010-02-26 2011-09-01 Song Gi-Yong 암반 매립 일체화 구조의 강관-콘크리트 복합 말뚝 시공 방법 및 말뚝 구조물
CN101982614A (zh) * 2010-10-11 2011-03-02 昆明捷程桩工有限责任公司 全套管钻机凿取岩石成桩的方法
CN201891114U (zh) * 2010-11-11 2011-07-06 上海市政工程设计研究总院 双重径向网笼砂石桩

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102767175A (zh) * 2012-07-11 2012-11-07 广州市恒盛建设工程有限公司 软土地基冲孔灌注桩混凝土浇注方法及其所用的钢筋笼
CN102852140A (zh) * 2012-10-10 2013-01-02 东华理工大学 一种帷幕式溶洞灌注桩施工方法及弹性网布
CN102852140B (zh) * 2012-10-10 2014-12-03 东华理工大学 一种帷幕式溶洞灌注桩施工方法及弹性网布
CN103114575A (zh) * 2013-01-31 2013-05-22 中冶交通工程技术有限公司 灌注桩用的钢筋笼及使用其的灌注桩施工方法
CN103603340A (zh) * 2013-12-06 2014-02-26 中冶建工集团有限公司 柔性防护防止塌孔的旋挖成孔灌注桩施工方法
CN103603340B (zh) * 2013-12-06 2016-03-09 中冶建工集团有限公司 柔性防护防止塌孔的旋挖成孔灌注桩施工方法
CN104775426A (zh) * 2015-04-17 2015-07-15 王继忠 一种现浇混凝土桩的保护装置及其施工方法
CN106522209A (zh) * 2016-10-08 2017-03-22 金陵科技学院 旋挖施工溶洞钻孔灌注桩灌注工法
CN106759307A (zh) * 2016-11-29 2017-05-31 中国冶集团有限公司 灌注桩在溶洞地层灌注的保护装置及方法
CN108978643A (zh) * 2018-07-10 2018-12-11 广东华固工程有限公司 支护桩施工方法、钢筋笼结构及支护桩结构
CN110295602A (zh) * 2019-04-24 2019-10-01 浙江省钱塘江管理局勘测设计院 一种水下砼浇筑工艺

Similar Documents

Publication Publication Date Title
CN102400460A (zh) 一种防止灌注砼桩桩径变异的施工方法
CN202323936U (zh) 防止灌注砼桩桩径变异的软包裹钢筋笼
CN108442365B (zh) 一种防堵塞强化透水桩及施工方法
CN102828498B (zh) 一种加固软弱地基的沉管筋箍碎石桩施工方法
CN106351218B (zh) 一种管桩断桩的补救方法
CN102926380A (zh) 桥梁灌注桩免凿桩头及其施工方法
CN104131556A (zh) 一种软硬夹层交互地基排水预应力管桩及施工方法
CN109989396A (zh) 结合后注浆工艺的新型挤扩支盘成型装置及其操作方法
CN104563118B (zh) 全套管振动取土预制灌注组合桩施工方法
CN102605770B (zh) 一种用于灌注桩的后压浆装置及施工方法
CN208309581U (zh) 防塌孔装置
CN102444129B (zh) 一种沉管灌注桩的活动进料斗及施工方法
CN204000859U (zh) 一种软硬夹层交互地基排水预应力管桩
CN110700245B (zh) 一种灌注桩的施工方法
CN105696468B (zh) 水中桥梁施工中的水下混凝土浇筑方法
CN102561378A (zh) 一种混凝土承台结构及所述混凝土承台结构的构建方法
CN100417856C (zh) 小截面环心应力抗压涵管及其制备工艺
CN202768000U (zh) 大孔径人工挖孔桩护壁钢筋罩
CN102296598A (zh) 现浇钢筋混凝土大直径管桩施工方法
CN109296133B (zh) 一种墙柱竖向钢筋绑扎连接结构及其绑扎连接方法
KR101869387B1 (ko) 강관 내 콘크리트 충전 간소화 공법
CN204940873U (zh) 一种劲性柱混凝土振捣的路径导管结构
CN102409675B (zh) 一种沉管灌注桩多料斗桩模及施工方法
CN203594030U (zh) 一种增强型打桩机
CN216339636U (zh) 一种建筑工程施工用防塌孔的地基加固结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120404