CN102383377B - Construction method utilizing steel-strand strand pulling machine to perform fast strand pulling during construction of prestress structures - Google Patents

Construction method utilizing steel-strand strand pulling machine to perform fast strand pulling during construction of prestress structures Download PDF

Info

Publication number
CN102383377B
CN102383377B CN 201110253300 CN201110253300A CN102383377B CN 102383377 B CN102383377 B CN 102383377B CN 201110253300 CN201110253300 CN 201110253300 CN 201110253300 A CN201110253300 A CN 201110253300A CN 102383377 B CN102383377 B CN 102383377B
Authority
CN
China
Prior art keywords
strand
steel strand
lashing
steel
pulling machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201110253300
Other languages
Chinese (zh)
Other versions
CN102383377A (en
Inventor
杨基好
张国庆
段鹏
李永太
段胜伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 10 Engineering Group Co Ltd
Original Assignee
China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 10 Engineering Group Co Ltd filed Critical China Railway No 10 Engineering Group Co Ltd
Priority to CN 201110253300 priority Critical patent/CN102383377B/en
Publication of CN102383377A publication Critical patent/CN102383377A/en
Application granted granted Critical
Publication of CN102383377B publication Critical patent/CN102383377B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

The invention discloses a construction method utilizing a steel-strand strand pulling machine to perform fast strand pulling during construction of prestress structures, which belongs to the technical field of building construction. The steel-strand strand pulling machine is provided with two pairs of pressing wheels capable of clamping steel strands to advance or retreat are arranged at intervals. The steps are that fixing the steel-strand strand pulling machine on a movable strand pulling platform through a pull piece in suspension mode, cleaning mortar on a mortar filling port of an anchor backing plate on an opening of a prestress hole passage, then connecting the steel-strand strand pulling machine with the prestress hole passage to be strand-pulled, further utilizing the steel-strand strand pulling machine to enable the steel strands to be strand-pulled according to numbers till the steel strands reach predetermined positions, utilizing a cutting device to cut off the steel strands, and accordingly the strand pulling work of one steel strand is completed. Repeating the steps till the strand pulling work of all the steel strands of the prestress hole passage is completed, and the steel strands are automatically bundled according to stacking mode after cut from bottom to top. The construction method utilizing the steel-strand strand pulling machine to perform fast strand pulling during construction of prestress structures integrates fast blanking, fast bundling and fast stand-pulling into a whole, thereby being convenient to operate and fast and efficient in strand-pulling construction.

Description

Utilize the job practices of the quick lashing of steel strand strand pulling machine in the prestressed structure construction
Technical field
The present invention relates to the job practices of quick lashing in a kind of prestress engineering construction, belong to technical field of building construction.
Background technology
Prestressed structure is widely used in building field, as buildings such as bridge, longspan structures, is main stressed member.In work progress, correct blanking fast, lashing and the construction of volume bundle of prestress wire are particularly important to quality control.At present, in the pre-stress construction of Engineerings such as traffic, building, the lashing construction of prestress wire is adopted artificial lashing mostly, is manually cooperated hoist engine or the early stage not high strand pulling machine of efficient to draw lashing, and work progress is divided into blanking, compiles three construction technological process such as bundle, lashing, and speed of application is slow, during operating cost, consume a large amount of man power and materials, cost height, work efficiency are low, can not all satisfy after the steel strand lashing and compile beam request, and need carry out the blanking operation to steel strand in advance; In addition, when adopting early stage strand pulling machine to draw lashing, need to excise because early stage strand pulling machine can stay one section tail to advance after existing a dish line to wear, thereby cause waste, be unfavorable for reducing construction cost.
Summary of the invention
In order to overcome above shortcomings in the prior art, the invention provides a kind of quick blanking that collects prestress wire, fast compile bundle, lashing is in integrated job practices fast, it is safe and efficient, the efficiency of construction height, construction cost is low.
The present invention is achieved by the following technical solution: the job practices of utilizing the quick lashing of steel strand strand pulling machine in a kind of prestressed structure construction, but described steel strand strand pulling machine has the pinch roller that two pairs of clamping steel strand that arrange at interval advance or retreat, every pair of described pinch roller comprises upper pressure wheel and the lower pressure wheel that is driven rotation by driving mechanism, and concrete steps are as follows:
1) described steel strand strand pulling machine fixedly is suspended on movably on the lashing platform with draw piece, and makes the steel strand strand pulling machine be positioned at the position of the prestressed pore passage for the treatment of lashing;
2) mortar that will be arranged on the grouting port of the anchor plate on the prestress hole road junction is removed;
3) described steel strand strand pulling machine is connected with the prestressed pore passage for the treatment of lashing: according to wire length, fixedly install locating ring at the conductor barrel leading-out terminal, then the conductor barrel leading-out terminal is stuck on the mouth of described anchor plate, utilize hooked rod that the conductor barrel leading-out terminal is connected with described anchor plate, the other end of conductor barrel is connected with the line outlet of steel strand strand pulling machine;
4) incoming line of steel strand the end of a thread from the steel strand strand pulling machine penetrated, pass from its line outlet, and at the termination of steel strand suit guiding cap;
5) carry out lashing by numbering: the numbering that the inlet wire button of startup steel strand strand pulling machine makes steel strand restraint by volume enters prestressed pore passage along conductor barrel and reaches the target location until passing the other end;
6) will utilize the cutting equipment steel strand to cut off in the end of incoming cables, finish the lashing work of steel strand;
7) repeat above-mentioned steps 5) and step 6) until the lashing operation of all steel strand of finishing this prestressed pore passage, steel strand are compiled bundle automatically according to from bottom to top the mode that stacks after cutting;
8) dismounting steel strand strand pulling machine, mobile lashing platform carries out the lashing operation to next prestressed pore passage, until the volume bundle lashing operation of the steel strand of finishing all prestressed pore passages.
Fixing reliable for the ease of operation and assurance, the draw piece described in the step 1) of the present invention is hoist crane.Can adjust the position of steel strand strand pulling machine easily by hoist crane.
For the ease of the length that passes of the steel strand of determining to pass the prestressed pore passage other end easily, at the anchor plate of the other end of the prestressed pore passage for the treatment of lashing the scale of band magnetic-disc is set, determine the length that steel strand pass by scale.
For the ease of the movement of lashing platform, the bottom surface of described lashing platform is equipped with universal wheel for four jiaos.
Blanking, volume bundle owing to steel strand among the present invention carry out in the lashing process, and the steel strand blanking is quick, and the automatic volume that realizes is restrainted in the lashing process, and it integrates quick blanking, volume bundle, quick lashing fast, and easy to operate, lashing is constructed rapidly and efficiently.For example, to the lashing of the prefabricated case beam single hole single steel strand of high-speed railway 32m, adopt method of the present invention, but per minute threading 180m, the lashing time of single steel strand has reached 9S the soonest, and lashing reaches length and can reach 200m farthest; Secondly, the present invention is owing to adopted the steel strand strand pulling machine of the novel type that drives entirely, after dish steel strand have been worn, its rear still can move under the pinch roller clamping of driving entirely, avoided the waste of steel strand, for prefabricated case beam single hole single steel strand, the present invention can save the about 0.2m of steel strand length than early stage strand pulling machine.Technology advanced person of the present invention, easy to operate, avoided the workload of artificial lashing, reduced personnel's input, many difficult problems such as insecurity, the blanking error that has overcome artificial unwrapping wire is big, length consuming time, its construction safety is quick, steady quality, improved work efficiency, shortened the duration, saved the cost of engineering.
Description of drawings
Fig. 1 is construction technique principle figure of the present invention;
Fig. 2 is the front view of the steel strand strand pulling machine among Fig. 1;
Fig. 3 is the B-B cross-sectional schematic of Fig. 2;
Fig. 4 is that A among Fig. 2 is to schematic diagram;
Among the figure, 1, the steel strand strand pulling machine, 2, steel strand, 3, cutting machine, 4, conductor barrel, 5, steel strand, 6, locating ring, 7, hooked rod, 8, anchor plate, 9, prestressed pore passage, 10, scale, 11, hoist crane, 12, upper pressure wheel, 13, lower pressure wheel, 14, governor motion, 15, motor, 16, incoming line, 17, line outlet, 18, the lashing platform, 19, universal wheel.
The specific embodiment
Also the present invention is further illustrated by reference to the accompanying drawings below by non-limiting embodiment:
Utilize the job practices of the quick lashing of steel strand strand pulling machine in a kind of prestressed structure construction, shown in accompanying drawing 2-4, it adopts steel strand strand pulling machine 1 to have two pairs of pinch rollers that have certain intervals to arrange, every pair of pinch roller comprises corresponding upper pressure wheel 12 and the lower pressure wheel 13 that arranges, upper pressure wheel 12 and lower pressure wheel 13 drive by driving mechanism and rotate, but last lower pressure wheel cooperates clamping steel strand 2 to advance or retreats.Described driving mechanism comprises motor 15 and the gear drive that is driven by motor 15, and gear drive drives upper pressure wheel 12 respectively and lower pressure wheel 13 rotates.Be provided with governor motion 14 on the top of each upper pressure wheel 12, be used for regulating the thrust size between upper pressure wheel 12 and the lower pressure wheel 13.
As shown in Figure 1, concrete construction technology step is as follows:
1) described steel strand strand pulling machine 1 usefulness draw piece fixedly is suspended on movably on the lashing platform 18, and the position of the prestressed pore passage 9 that steel strand strand pulling machine 1 is positioned at treat lashing;
In this step, described draw piece can be any type of draw piece of the prior art, and as wire rope, assembly pulley, hoist crane etc., fixing reliable for ease of operation and assurance, what present embodiment adopted has been to reuse cucurbit.Described lashing platform 18 is the tower structures that are welded by angle steel, screw-thread steel etc., and for ease of movement, cardan wheel with brake 19 is installed for four jiaos in its bottom surface.
2) mortar that will be arranged on the grouting port of the anchor plate 8 on 9 mouthfuls of the prestressed pore passages is removed;
3) described steel strand strand pulling machine is connected with the prestressed pore passage for the treatment of lashing: according to wire length, fixedly install locating ring 6 at conductor barrel 4 leading-out terminals, then conductor barrel 4 leading-out terminals are stuck on the mouth of described anchor plate 8, one end of hooked rod 7 is connected with injected hole on the anchor plate 8, the other end of hooked rod 7 is connected with the locating ring of conductor barrel 4, the other end of conductor barrel 4 is connected with the line outlet 17 of steel strand strand pulling machine 1, finishes the work that is connected of steel strand strand pulling machine 1 and prestressed pore passage;
4) from wire dispenser, pull out steel strand the end of a thread, the incoming line 16 of steel strand the end of a thread from steel strand strand pulling machine 1 penetrated, pass from its line outlet 17, and at the termination of steel strand suit guiding cap;
5) carry out lashing by numbering: the numbering that the inlet wire button of startup steel strand strand pulling machine 1 makes steel strand restraint by volume enters prestressed pore passage along conductor barrel 4 and reaches the target location until passing the other end; For the ease of the length that passes of the steel strand of determining to pass the prestressed pore passage other end easily, the scale 10 of band magnetic-disc can be set at the anchor plate of the other end of the prestressed pore passage for the treatment of lashing, determine the length that steel strand pass by scale 10.When needs trace is regulated the protruded length of steel strand, on the available finger tapping gauge tap advance or back is finely tuned.
6) regulate length after, utilize cutting machine 3 that steel strand are cut off in the end of incoming cables, finish the lashing work of steel strand, also finished blanking work simultaneously;
7) repeat above-mentioned steps 5) and step 6) until the volume bundle lashing operation of all steel strand of finishing this prestressed pore passage, at this, steel strand are to realize compiling fast and automatically bundle according to from bottom to top the mode of stacking after cutting;
8) dismounting steel strand strand pulling machine, mobile lashing platform carries out the lashing operation to next prestressed pore passage, until the volume bundle lashing operation of the steel strand of finishing all prestressed pore passages.
Other parts in the present embodiment adopt prior art, do not repeat them here.

Claims (4)

1. utilize the job practices of the quick lashing of steel strand strand pulling machine during a prestressed structure is constructed, it is characterized in that: but described steel strand strand pulling machine has the pinch roller that two pairs of clamping steel strand that arrange at interval advance or retreat, every pair of described pinch roller comprises upper pressure wheel and the lower pressure wheel that is driven rotation by driving mechanism, and concrete steps are as follows:
1) described steel strand strand pulling machine fixedly is suspended on movably on the lashing platform with draw piece, and makes the steel strand strand pulling machine be positioned at the position of the prestressed pore passage for the treatment of lashing;
2) mortar that will be arranged on the grouting port of the anchor plate on the prestress hole road junction is removed;
3) described steel strand strand pulling machine is connected with the prestressed pore passage for the treatment of lashing: according to wire length, fixedly install locating ring at the conductor barrel leading-out terminal, then the conductor barrel leading-out terminal is stuck on the mouth of described anchor plate, utilize hooked rod that the conductor barrel leading-out terminal is connected with described anchor plate, the other end of conductor barrel is connected with the line outlet of steel strand strand pulling machine;
4) incoming line of steel strand the end of a thread from the steel strand strand pulling machine penetrated, pass from its line outlet, and at the termination of steel strand suit guiding cap;
5) carry out lashing by numbering: the numbering that the inlet wire button of startup steel strand strand pulling machine makes steel strand restraint by volume enters prestressed pore passage along conductor barrel and reaches the target location until passing the other end;
6) utilize cutting equipment that steel strand are cut off in the end of incoming cables, finish the lashing work of steel strand;
7) repeat above-mentioned steps 5) and step 6) until the lashing operation of all steel strand of finishing this prestressed pore passage, steel strand are compiled bundle automatically according to from bottom to top the mode that stacks after cutting;
8) dismounting steel strand strand pulling machine, mobile lashing platform carries out the lashing operation to next prestressed pore passage, until the volume bundle lashing operation of the steel strand of finishing all prestressed pore passages.
2. utilize the job practices of the quick lashing of steel strand strand pulling machine in the prestressed structure construction according to claim 1, it is characterized in that: the draw piece described in the step 1) is hoist crane.
3. utilize the job practices of the quick lashing of steel strand strand pulling machine in the prestressed structure construction according to claim 1 and 2, it is characterized in that: at the anchor plate of the other end of the prestressed pore passage for the treatment of lashing the scale of band magnetic-disc is set, is used for the length of determining that steel strand pass.
4. utilize the job practices of the quick lashing of steel strand strand pulling machine in the prestressed structure construction according to claim 1, it is characterized in that: the bottom surface of described lashing platform is equipped with universal wheel for four jiaos.
CN 201110253300 2011-08-30 2011-08-30 Construction method utilizing steel-strand strand pulling machine to perform fast strand pulling during construction of prestress structures Expired - Fee Related CN102383377B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110253300 CN102383377B (en) 2011-08-30 2011-08-30 Construction method utilizing steel-strand strand pulling machine to perform fast strand pulling during construction of prestress structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110253300 CN102383377B (en) 2011-08-30 2011-08-30 Construction method utilizing steel-strand strand pulling machine to perform fast strand pulling during construction of prestress structures

Publications (2)

Publication Number Publication Date
CN102383377A CN102383377A (en) 2012-03-21
CN102383377B true CN102383377B (en) 2013-08-14

Family

ID=45823178

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110253300 Expired - Fee Related CN102383377B (en) 2011-08-30 2011-08-30 Construction method utilizing steel-strand strand pulling machine to perform fast strand pulling during construction of prestress structures

Country Status (1)

Country Link
CN (1) CN102383377B (en)

Families Citing this family (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102619339B (en) * 2012-04-18 2014-07-23 中建六局工业设备安装有限公司 Construction method for multi-beam steel stranded wires to pass through long and thin narrow space at high altitude
CN103372915B (en) * 2012-04-25 2015-12-09 刘靖 A kind of self-locking strand pulling machine
CN102677589A (en) * 2012-05-02 2012-09-19 浙江天工建设集团有限公司 Construction method for penetration of ultra-long prestress steel strands by extruding-pushing method
CN103184798B (en) * 2013-03-20 2015-02-18 中国核工业华兴建设有限公司 Device and method for synchronously penetrating prestressed steel strand and anchoring block
CN104675121B (en) * 2013-11-29 2016-09-07 甘肃路桥建设集团有限公司 Bundle stand is compiled in a kind of prestress wire blanking
CN105780656B (en) * 2014-12-26 2017-11-17 中山市睿望达精密科技有限公司 Steel strand pulling machine
CN105269679A (en) * 2015-10-09 2016-01-27 中交第三航务工程局有限公司宁波分公司 Automatic bundle penetrating system and method
CN105649341A (en) * 2016-01-11 2016-06-08 中国建筑第二工程局有限公司 Long-distance steel strand pulling device and pulling construction method
CN109016117A (en) * 2016-06-18 2018-12-18 李学忠 A kind of device of the automatic tube-penetrating for precast bridge construction equipment
CN108643048A (en) * 2016-06-18 2018-10-12 陈炳兰 A kind of double driving devices of automatic tube-penetrating
CN108301329A (en) * 2016-06-18 2018-07-20 乌鲁木齐九品芝麻信息科技有限公司 A kind of automatic pipe lining machine and method
CN108868155B (en) * 2018-06-27 2020-10-20 中国核工业华兴建设有限公司 Movable steel strand pulling guide device and use method thereof
CN108951423B (en) * 2018-07-09 2020-04-03 云南春鹏钢绞线有限公司 Steel strand pulling device
CN111005319A (en) * 2019-12-14 2020-04-14 中冶天工集团有限公司 Accurate alignment installation device and installation method for box bridge prestressed tendons
CN110904855A (en) * 2019-12-26 2020-03-24 中交一公局第三工程有限公司 Strand-penetrating tool
CN112726404B (en) * 2020-12-24 2022-10-14 河北高达智能装备股份有限公司 Steel strand whole bundle weaving method and system
CN113458292A (en) * 2021-05-21 2021-10-01 中铁十六局集团第三工程有限公司 Steel strand wires unloading strorage device
CN114961272B (en) * 2022-05-10 2024-06-11 柳州欧维姆工程有限公司 Vertical prestress intelligent beam penetrating core equipment and construction method thereof
CN115383899A (en) * 2022-05-18 2022-11-25 中交一公局集团有限公司 Automatic steel strand penetrating and combining device
CN115045512B (en) * 2022-07-20 2023-08-04 中国核工业二四建设有限公司 Integral beam penetrating device and method for prestressed ultra-long circumferential steel beam of nuclear power station
CN117000913B (en) * 2023-09-05 2024-03-08 中建铁路投资建设集团有限公司 Continuous beam prestress steel strand cutting length control device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201043356Y (en) * 2007-04-06 2008-04-02 刘靖 Strand pulling machine
CN201495779U (en) * 2009-07-23 2010-06-02 刘靖 Novel steel strand pulling machine
CN201512958U (en) * 2009-05-27 2010-06-23 尹忠 Prestressed steel strand pricking machine
CN201843080U (en) * 2010-10-27 2011-05-25 四平市天力建筑机械配套有限公司 Double-beam steel stranded wire strand pulling machine

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL1037652C2 (en) * 2010-01-25 2011-07-26 Pieter Johan Christiaan Rutgers METHOD FOR APPLYING BINDING WIRE FROM A WIRE ROLL AROUND ARMING BARS, CUTTING, CLIPPING AND WINDING THEREOF

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201043356Y (en) * 2007-04-06 2008-04-02 刘靖 Strand pulling machine
CN201512958U (en) * 2009-05-27 2010-06-23 尹忠 Prestressed steel strand pricking machine
CN201495779U (en) * 2009-07-23 2010-06-02 刘靖 Novel steel strand pulling machine
CN201843080U (en) * 2010-10-27 2011-05-25 四平市天力建筑机械配套有限公司 Double-beam steel stranded wire strand pulling machine

Also Published As

Publication number Publication date
CN102383377A (en) 2012-03-21

Similar Documents

Publication Publication Date Title
CN102383377B (en) Construction method utilizing steel-strand strand pulling machine to perform fast strand pulling during construction of prestress structures
CN201272942Y (en) Mounting angle regulation apparatus for stay cable column end of stayed-cable bridge
CN101967796B (en) Method for arranging parallel steel wire stay cable
CN212025936U (en) Equipment for mounting continuous steel strand stay cable at tower end of cable-stayed bridge
CN202683870U (en) T beam steel strand feeding device of heavy haul railway
CN202441047U (en) Hanging basket guide device on curved surface
CN204001778U (en) New mobile type Semi-automatic combination formula steel stranded wire penetrating adapter all-in-one
CN105269679A (en) Automatic bundle penetrating system and method
CN202245901U (en) Winding mechanism arranged along curved surface
CN210918126U (en) A instrument is paintd to outer wall high security for building real mineral varnish
CN202809492U (en) Dragging system of steel truss girder obliquely crossing existing line through continuous jack in guide rail-free way
CN113235941B (en) Automatic beam penetrating machine for beam field
CN207047714U (en) A kind of full cast poling machine of bridge
CN204754245U (en) Wear muscle construction appurtenance
CN1541928A (en) Compensation balance type silk winding machine
CN202706029U (en) Top-end pulley frame of pile machine with rotary vertical post
CN202324653U (en) Prestress steel twisted wire strand pulling machine
CN202451169U (en) Guide and traction system for full-section needle-beam trolley during construction in large slope inclined shaft
CN201198570Y (en) Rigging drill head for built-in steel twisted bundle and steel twisted wire bundling apparatus
CN108975191B (en) Movable integral traction winch and using method thereof
CN201169499Y (en) Portable crane
CN221778303U (en) Outer surface operation platform for construction of stay cable anchoring structure on low-tower cable-stayed bridge tower
CN201678366U (en) Grab bucket electric hoist
CN203080415U (en) Stranding pulling machine used for 900 ton conditioning box girder steel strand punching
CN212258265U (en) Cable continuous laying device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130814

Termination date: 20140830

EXPY Termination of patent right or utility model