CN102363999B - A kind of wallboard linkage and adopt the wall construction method of this device - Google Patents

A kind of wallboard linkage and adopt the wall construction method of this device Download PDF

Info

Publication number
CN102363999B
CN102363999B CN201110348483.0A CN201110348483A CN102363999B CN 102363999 B CN102363999 B CN 102363999B CN 201110348483 A CN201110348483 A CN 201110348483A CN 102363999 B CN102363999 B CN 102363999B
Authority
CN
China
Prior art keywords
component
side plan
wallboard
hole
linkage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201110348483.0A
Other languages
Chinese (zh)
Other versions
CN102363999A (en
Inventor
韦骏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGDONG SOBEN GREEN NEW MATERIAL Co Ltd
Original Assignee
GUANGDONG SOBEN GREEN NEW MATERIAL Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG SOBEN GREEN NEW MATERIAL Co Ltd filed Critical GUANGDONG SOBEN GREEN NEW MATERIAL Co Ltd
Priority to CN201110348483.0A priority Critical patent/CN102363999B/en
Publication of CN102363999A publication Critical patent/CN102363999A/en
Application granted granted Critical
Publication of CN102363999B publication Critical patent/CN102363999B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Finishing Walls (AREA)

Abstract

The invention discloses a kind of wallboard surface construction deadlight linkage and adopt the wall construction method of this linkage, belong to building engineering field.This linkage comprises component 1, component 2, and component 1 shape of cross section is shape, wherein left side plan can be connected with wallboard, right side plan is arranged some through holes, and component 2 shape of cross section is shape, wherein right side plan is arranged some through holes, can be connected, left side plan is arranged some through holes with building foundation wall, and component 1 right side plan and component 2 left side plan are stacked adduction and wallboard to install thickness suitable.Wall construction method comprises and is separately fixed on building foundation wall and wallboard by component 2, component 1, component 2, component 1 compact siro spinning technology simultaneously.Adopt the present invention, can guarantee the snapping amount of structure (button) part and panel during installation, the three-dimensional of component 1 and component 2 is adjustable makes installation site determine, safe and reliable secure, efficiency quick and easy for installation is high.

Description

A kind of wallboard linkage and adopt the wall construction method of this device
Technical field
The present invention relates to the connector in composite plate wall construction, belong to building engineering field, be especially incubated, linkage required for decorating wall erecting of panel, the invention still further relates to the construction method adopting this linkage metope.
Background technology
Due to the development of environmental protection requirement and New Building Materials, compound novel wall material is current and Future Development trend, for improving the requirement of site operation efficiency and wallboard adaptation suitability for industrialized production, the area that these combined wall boards manufacture is larger, also heavier, such as thermal insulation wall surface, decorated wall surface etc., so when constructing, except will directly be bonded on matrix metope as ceramic tile, the also necessary safety and firmness considering shingle nail, namely to be undertaken firmly by connector, otherwise, depend merely on cementing agent very easily to come off, instrument impact is not attractive in appearance, also may bring potential safety hazard or accident.
Prior art generally adopts ∏ shape connector, for connecting and fixing shingle nail, because this kind of connector one end is connected by screw building foundation wall, shingle nail is pushed down on the other end and the extension limit of connector, when using this connector, find that this connector need be crimped on plate face, carry out screw again and be fixed on building foundation wall, because cementing agent during construction does not have solidly very easily to be shifted, and connector and building foundation wall spacing are difficult to hold, the gap of panel is large and be difficult to accomplish neatly smooth, etc. these factors cause difficulty of construction large, quality difficulty is held, in most cases, panel obscission still happens occasionally.
There is the extensive research and practice of many technician for this reason, as on January 11st, 2011, the name of Jinan Housing Industrialization Development Center's application was called " combined wall board and production method and syndeton " thereof (number of patent application: CN201110004543.7), notification number: CN102108756A, open mouth: 2011.06.29 patented technology, a kind of combined wall board of this disclosure of the invention and production method thereof and syndeton, described combined wall board comprises base material and is bonded in the panel on two surfaces of base material, described base material side stretches out described panel, described base material another side is corresponding thereto recessed into described panel, the surface that described base material upper and lower surface and/or panel contact with base material is provided with multiple depressed part.A production method for combined wall board, comprises the following steps: 1) produce base material; 2) panel is produced; 3) face gluing panel and base material contacted, and by panel and substrate pressing.Combined wall board inside is provided with staggered depressed part or through hole, and reduce cost of production and alleviate weight, soundproof effect is good; Base material side stretches out described panel, and described base material another side is corresponding thereto recessed into described panel, can grafting during installation.
Also have on October 23rd, 2009 China Construction Decoration Engineering Co., Ltd., China Construction Decoration Engineering Co. Ltd. application name be called " large metal veneer suspending assembly " (patent No.: CN200910308680.2), notification number: CN101718138A, the day for announcing: 2010.06.02 patented technology, a kind of large metal veneer suspending assembly of this invention, is combined by upper and lower suspending assembly.Upper suspending assembly by upper supporting parts, hook of hanging oneself, upper switching fastener, two pieces hold out against chock, up-down adjustment screw before and after set screw form; Lower suspending assembly by lower supporting parts, hold out against chock under two pieces and lower limit fastener forms.The present invention adopts suspending way mounting decoration panel, utilize switching fastener and chock suspension hook to be fixed on mounting decoration panel to avoid using welding and bolt to fix, constructing operation is made to become convenient, being harmonized supporting parts position can be easily in place by plate face, by suspension hook set screw tuning plate face height and gap between plate and plate.Be applicable to indoor and outdoor decoration panel hanging construction works, be specially adapted to that monolithic decoration panel area is comparatively large, weight is comparatively large, mounting condition is restricted and installation accuracy requires higher occasion.
These construction assemblies, techniques and methods connect the safety and firmness solving complex shingle panel installation undoubtedly good result, there is certain reference function, but these construction assemblies, techniques and methods are obviously different from existing assembly construction method, complex structure, difficulty of construction is large, and efficiency is low.
Summary of the invention
The present invention is directed to complex structure weak effect in the construction of existing shingle nail, the deficiency of the low grade of the large efficiency of difficulty of construction, provides a kind of structure simple easy construction, a kind of wallboard linkage of successful, and adopts the wall construction method of this linkage.
The present invention is achieved in that a kind of wallboard linkage, and this device comprises component 1, component 2,
Described component 1 shape of cross section is shape, wherein left side plan 11 can be connected with wallboard 4, right side plan 12 is arranged some through holes 13;
Described component 2 shape of cross section is shape, wherein right side plan 22 is arranged some through holes 23, can be connected, left side plan 21 is arranged some through holes 24 with building foundation wall 3;
Described component 1 right side plan 12 is superimposed with described component 2 left side plan 21, and to install thickness suitable with wallboard 4.
When described component 1 is superimposed with component 2, component 1 right side plan 12 is on component 2 left side plan 21.
Through hole 13 on described component 1 right side plan 12 is strip hole with the through hole 24 on component 2 left side plan 21.
Through hole 13 on described component 1 right side plan 12 is arranged in a crossed manner with the through hole 24 on component 2 left side plan 21.
Through hole on described component 1 13 mode arranged in a crossed manner with the through hole 24 on component 2 is that square crossing is arranged.
The setting vertical with left side plan 11 one-tenth of through hole 13 on described component 1, the through hole 24 on component 2 be arranged in parallel with right side plan 22.
Through hole 13 on described component 1 is in a parallel set with left side plan 11, and the through hole 24 on component 2 is vertical with right side plan 22 to be arranged.
Adopt a wall construction method for wallboard linkage, described construction method adopts above-mentioned wallboard linkage, and Specific construction comprises the steps:
A. wallboard 4 is bonded on building foundation wall 3 by cementing agent 5;
B. on above-mentioned wallboard 4 end face; Component 2 left side plan 21 is pressed on above-mentioned wallboard 4, and component 2 is fixed on building foundation wall 3 by through hole 23 on component 2 right side plan 22 by fixture 6;
C. by superimposed to component 1 right side plan 12 and described component 2 left side plan 21, and to install thickness suitable with wallboard 4, and component 1 left side plan 11 is connected on above-mentioned wallboard 4;
D. with the through hole 24 on component 2 left side plan 21, wallboard linkage is fixed on above-mentioned wallboard 4 with the through hole 13 that securing member 7 is each passed through on component 1 right side plan 12;
E. separately get wallboard 4 one end to be connected with component 1 left side plan 11, the other end is bonded on building foundation wall 3;
F. B, C, E, D step is continued, until complete wall construction.
Filler 8 is added respectively before and after step D..
In step e. after, at the external surface filling with sealant 10 of component 1 left side plan 11.
A kind of wallboard linkage of the present invention and adopt the wall construction method of this device to have following beneficial effect:
1. adopt the present invention, the snapping amount of structure (button) part and panel can be guaranteed during installation, the three-dimensional of component 1 and component 2 is adjustable make installation after unstressed generation, the three-dimensional of component 1 and component 2 is adjustable makes installation site determine, due to these effective measures, safe and reliable secure;
2. adopt the present invention, between plate with plate, the consistent of gap can effectively be controlled, and the reliable location of component 1 and component 2 makes plate surface evenness and position be guaranteed, and between plate and plate, the large I in gap is determined as required, and installation effect is guaranteed;
3. adopt the present invention, can to punch in advance location according to cellular snap line during installation, during installation, member position is the location of plate, the position of plate can be made once can accurately to locate, do not need repeatedly to move, the planeness of plate, plate can be made during installation to stitch width one-time positioning, and efficiency quick and easy for installation is high;
4. adopt the present invention, reduce human cost owing to locating the convenient amount of labour used that accurately can reduce, size is unrestricted reduces the consumption of weather proofing sealant and the consumption of wallboard cementing agent for plate seam, and installation cost is reduced, and installation effectiveness height can the reduction of erection time.
Accompanying drawing explanation
Below in conjunction with accompanying drawing to a kind of wallboard linkage of the present invention and adopt the wall construction embodiment of the method for this device to be described in detail.Following legend provides with non-limiting way for ease of understanding for the purpose of the present invention, namely the invention is not restricted to following legend and explanation thereof.
Fig. 1 is the normal connector plate surface construction seam crossing structural representation adopted in prior art;
Fig. 2 is a kind of wallboard linkage perspective view in the present invention;
Fig. 3 is the plate surface construction seam crossing structural representation adopting linkage of the present invention.
Marginal data
1----component 1; The left side plan of 11----component 1; The right side plan of 12---component 1;
Through hole on 13---component 1 right side plan; 2-----component 2; The left side plan of 21---component 2;
The right side plan of 22---component 2; Through hole on 23----component 2 right side plan 22;
Through hole on 24----component 2 left side plan 21; 3-----builds foundation wall; 4---wallboard;
5-----cementing agent; 6----fixture; 7-----securing member; 8----filler;
The existing connector of 9----; 10----fluid sealant
Detailed description of the invention
With reference to the connector plate surface construction seam crossing structural representation adopted normal in Fig. 1 prior art, because combined wall board area is heavier greatly, as being laid immediately on building foundation wall, very easily come off, cause safety problem, and directly impact is attractive in appearance, employing cross section is the connector of ∏ shape at most in the prior art, as shown in connector 9 existing in figure, wallboard 4 is pasted after building foundation wall 3, position between adjustment wallboard 4, then existing connector 9 is installed, one end is connected by screw building foundation wall, wallboard 4 is pushed down on the other end and the extension limit of existing connector 9, because cementing agent 5 during construction does not have solidly very easily to be shifted, and existing connector 9 is difficult to hold with building foundation wall 3 spacing, the gap of wallboard 4 is large and be difficult to accomplish neatly smooth, these factors cause difficulty of construction large, quality difficulty is held, in most cases, panel obscission is comparatively general, therefore, still there is larger hidden danger in this connector and connected mode, needs make improvements.Just in view of this consideration, through repeatedly studying and testing, develop connector of the present invention and connected mode, successful takes on a new look, and is now described in conjunction with the embodiments.
Reference Fig. 2 is a kind of wallboard linkage perspective view in the present invention, a kind of wallboard linkage, this device mainly comprises two components and component 1, component 2, component 1 shape of cross section is " ┝ " shape, wherein left side plan 11 can be connected with wallboard 4, right side plan 12 is arranged some through holes 13, through hole 13 is preferably the strip hole in diagram.
Component 2 shape of cross section is " ┛ " shape, wherein right side plan 22 is arranged some through holes 23, can be connected with building foundation wall 3, left side plan 21 be arranged some through holes 24, the shape of through hole can be circular or other shapes, is preferably the strip hole in diagram.
In construction, component 1 right side plan 12 is superimposed with described component 2 left side plan 21, and to install thickness suitable with wallboard 4, and when preferably component 1 is superimposed with component 2, component 1 right side plan 12 is on component 2 left side plan 21.Component 1, component 2 can adopt metalwork, also can adopt plastics or other composite materials, and the intensity of certain material must reach requirement.
During for construction, for reaching the optimum efficiency be connected and fixed, securing member 7 is not shifted through component 1, component 2, and the through hole 13 on fastener member 1 right side plan 12 is arranged in a crossed manner with the through hole 24 on component 2 left side plan 21, and square crossing arranges better.The setting vertical with left side plan 11 one-tenth of through hole 13 on component 1, the through hole 24 on component 2 be arranged in parallel with right side plan 22.Also can be that the through hole 13 on component 1 is in a parallel set with left side plan 11, and the through hole 24 on component 2 is vertical with right side plan 22 to be arranged.
Adopt a wall construction method for wallboard linkage, this construction method adopts above-mentioned wallboard linkage, and Specific construction comprises the steps:
A. wallboard 4 is bonded on building foundation wall 3 by cementing agent 5;
B., on above-mentioned wallboard 4 end face, component 2 is fixed on building foundation wall 3 by through hole 23 on component 2 right side plan 22 by fixture 6, and component 2 left side plan 21 is pressed on above-mentioned wallboard 4;
C. by superimposed to component 1 right side plan 12 and described component 2 left side plan 21, and to install thickness suitable with wallboard 4, and component 1 left side plan 11 is connected on above-mentioned wallboard 4;
D. with the through hole 24 on component 2 left side plan 21, wallboard linkage is fixed on above-mentioned wallboard 4 with the through hole 13 that securing member 7 is each passed through on component 1 right side plan 12, preferably adds filler 8 respectively afterwards before this step;
E. separately get wallboard 4 one end to be connected with component 1 left side plan 11, the other end is bonded on building foundation wall 3, as the external surface filling with sealant 10 at component 1 left side plan 11, can increase body of wall heat-insulating and sealing effect, can also increase aesthetic feeling;
F. B, C, E, D step is continued, until complete wall construction.
Reference Fig. 3 is the plate surface construction seam crossing structural representation adopting linkage of the present invention, namely the design sketch after linkage of the present invention is adopted, the snapping amount of structure (button) part and panel can be guaranteed during visible installation, the three-dimensional of component 1 and component 2 is adjustable make installation after unstressed generation, the three-dimensional of component 1 and component 2 is adjustable makes installation site determine, between plate with plate, the consistent of gap can effectively be controlled, the reliable location of component 1 and component 2 makes plate surface evenness and position be guaranteed, during installation, member position is the location of plate, the position of plate can be made once can accurately to locate, do not need repeatedly to move, due to these effective measures, safe and reliable secure, and efficiency quick and easy for installation is high
Certainly, the invention is not restricted to the embodiment addressed shown in accompanying drawing, the amendment done of spirit of Fan Yiben creation and equivalent transformation, or adopt various deformation on this basis, that introduces in the present invention as removed is connected on above-mentioned wallboard 4 by component 1 left side plan 11, also wallboard 4 can be pushed down in extension limit, the cross sectional shape of component 1 and component 2 can also be adopted to be deformed into respectively " ┗ ", " ㄣ " and combination after shape still similar, and other corresponding ways can also be adopted on the basis of wallboard fixing measure disclosed by the invention, specifically will be according to the situation, etc. all belong in scope.

Claims (1)

1. one kind adopts the wall construction method of wallboard linkage, it is characterized in that: described construction method adopts wallboard linkage, this device comprises component one (1), component two (2), described component one (1) shape of cross section is " ┝ " shape, wherein left side plan (11) is connected with wallboard (4), right side plan (12) is arranged some through holes (13), described component two (2) shape of cross section is " ┛ " shape, wherein right side plan (22) arranges some through holes (23), be connected with building foundation wall (3), left side plan (21) arranged some through holes (24), described component one (1) right side plan (12) and described component two (2) left side plan (21) are superimposed, and to install thickness suitable with wallboard (4), through hole (13) on component one (1) right side plan (12) is strip hole with the through hole (24) on component two (2) left side plan (21), and the through hole (13) on described component one (1) right side plan (12) is arranged with through hole (24) square crossing on component two (2) left side plan (21), when described component one (1) is superimposed with component two (2), component one (1) right side plan (12) is on component two (2) left side plan (21), through hole (13) on described component one (1) right side plan (12) and left side plan (11) are vertical setting, through hole (24) on component two (2) left side plan (21) and right side plan (22) are set in parallel,
Specific construction comprises the steps:
A. wallboard (4) is bonded in building foundation wall (3) by cementing agent (5);
B. on above-mentioned wallboard (4) end face, component two (2) is fixed in building foundation wall (3) by the upper through hole (23) of component two (2) right side plan (22) by fixture (6), and component two (2) left side plan (21) is pressed on above-mentioned wallboard (4);
C. by superimposed to component one (1) right side plan (12) and described component two (2) left side plan (21), and with wallboard (4), to install thickness suitable, and component one (1) left side plan (11) is connected on above-mentioned wallboard (4);
Wallboard linkage is fixed on above-mentioned wallboard (4) with the through hole (24) on component two (2) left side plan (21) by the through hole (13) D. using securing member (7) to be each passed through on component one (1) right side plan (12); Add filler (8) afterwards respectively before this step;
E. separately get wallboard (4) one end to be connected with component one (1) left side plan (11), the other end is bonded in building foundation wall (3); At the external surface filling with sealant (10) of component one (1) left side plan (11);
F. B, C, E, D step is continued, until complete wall construction.
CN201110348483.0A 2011-11-03 2011-11-03 A kind of wallboard linkage and adopt the wall construction method of this device Expired - Fee Related CN102363999B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110348483.0A CN102363999B (en) 2011-11-03 2011-11-03 A kind of wallboard linkage and adopt the wall construction method of this device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110348483.0A CN102363999B (en) 2011-11-03 2011-11-03 A kind of wallboard linkage and adopt the wall construction method of this device

Publications (2)

Publication Number Publication Date
CN102363999A CN102363999A (en) 2012-02-29
CN102363999B true CN102363999B (en) 2016-03-23

Family

ID=45690590

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110348483.0A Expired - Fee Related CN102363999B (en) 2011-11-03 2011-11-03 A kind of wallboard linkage and adopt the wall construction method of this device

Country Status (1)

Country Link
CN (1) CN102363999B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104763129B (en) * 2015-03-27 2018-07-27 浙江大丰建筑装饰工程有限公司 Use the attaching device and its application method of the building decoration panel of driving idler wheel
CN104763130B (en) * 2015-03-27 2018-06-08 贵州建工集团第三建筑工程有限责任公司 Use the attaching device and its application method of the building decoration panel that guide sleeve is oriented to
CN104712126B (en) * 2015-03-27 2017-03-29 南通建工集团股份有限公司 Using the building decoration panel and its attaching method of automatic sliding device
CN104746835B (en) * 2015-03-27 2016-09-07 浦江简丰环保科技有限公司 Use and insert guide pad and the building decoration panel of hydraulic means and attaching method thereof
CN107327053B (en) * 2016-03-28 2019-03-26 淮阴工学院 Glue injection type horizontal push device and curtain wall installing structure

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2186776Y (en) * 1993-12-29 1995-01-04 林法献 Outer wall marble setting mechanism
CN2330725Y (en) * 1998-02-27 1999-07-28 四川中策实业有限责任公司 Stone curtain wall hanging element
CN2433339Y (en) * 2000-08-16 2001-06-06 陈钦霖 Improved structure of stone steel hanging fixture
CN2499463Y (en) * 2001-10-16 2002-07-10 北京市第一建筑工程公司 Wind-proof anti-shock hanging piece for stone curtain wall
CN2499464Y (en) * 2001-10-16 2002-07-10 北京市第一建筑工程公司 Dovetail hanging piece for stone curtain wall
CN1715579A (en) * 2005-06-30 2006-01-04 淄博德惠来装饰瓷板有限公司 Dry hanging external and internal wall surface decoration structure of fibrous porcelain plate back lining and it's construction method
CN101215917A (en) * 2007-12-28 2008-07-09 瞿浩荣 Heat insulation decoration board and its connecting component on site construction method
CN202850434U (en) * 2011-11-03 2013-04-03 广东松本绿色板业股份有限公司 Wallboard connecting device

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2587977Y (en) * 2002-04-25 2003-11-26 林富商 Assembling structure member for wall hanged stone material
CN201062389Y (en) * 2007-06-08 2008-05-21 杜金泽 Latch hook type curtain wall column mounting regulating structure

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2186776Y (en) * 1993-12-29 1995-01-04 林法献 Outer wall marble setting mechanism
CN2330725Y (en) * 1998-02-27 1999-07-28 四川中策实业有限责任公司 Stone curtain wall hanging element
CN2433339Y (en) * 2000-08-16 2001-06-06 陈钦霖 Improved structure of stone steel hanging fixture
CN2499463Y (en) * 2001-10-16 2002-07-10 北京市第一建筑工程公司 Wind-proof anti-shock hanging piece for stone curtain wall
CN2499464Y (en) * 2001-10-16 2002-07-10 北京市第一建筑工程公司 Dovetail hanging piece for stone curtain wall
CN1715579A (en) * 2005-06-30 2006-01-04 淄博德惠来装饰瓷板有限公司 Dry hanging external and internal wall surface decoration structure of fibrous porcelain plate back lining and it's construction method
CN101215917A (en) * 2007-12-28 2008-07-09 瞿浩荣 Heat insulation decoration board and its connecting component on site construction method
CN202850434U (en) * 2011-11-03 2013-04-03 广东松本绿色板业股份有限公司 Wallboard connecting device

Also Published As

Publication number Publication date
CN102363999A (en) 2012-02-29

Similar Documents

Publication Publication Date Title
CN102363999B (en) A kind of wallboard linkage and adopt the wall construction method of this device
CN201679125U (en) Fireproofing heat-insulation composite wall decoration structure
CN104631747A (en) L-shaped component system for mounting thermal-insulating and decorating integrated board
CN202850434U (en) Wallboard connecting device
CN207110329U (en) A kind of wallboard fast fixing structure
CN204876302U (en) Plug -in type prefabricated exterior wall base plate
CN107130732B (en) Wallboard is assembled to canned type
CN206928583U (en) A kind of flush type wallboard
CN211748162U (en) Assembly type kitchen wall surface grid based on cabinet
CN211646875U (en) Decorative curtain wall
CN204475765U (en) A kind of platform mould keel
CN208072900U (en) A kind of convenient pressing device
CN212358798U (en) Assembled ceiling with triangular three-dimensional modeling design
CN201972349U (en) Decorative wall material module
CN211873647U (en) Novel wallboard structure
CN206233504U (en) A kind of back hanging type inner wall crystalline substance calcium board mounting structure
CN207194368U (en) A kind of embedded indoor decorating wallboard
CN113323239A (en) Grade mounting structure falls in assembled furred ceiling external corner
CN203008291U (en) Adjustable anchor supporting fastener
CN206928509U (en) A kind of closed type assembly wallboard
CN211499591U (en) Wall crown panel connecting piece with excellent firmness
CN203475744U (en) Three-dimensional thermal insulation decorative gusset plate
CN205296475U (en) Aerated concrete window wrap panel fixed establishment's last structure
CN205297164U (en) Aerated concrete window wrap panel fixed establishment
KR200423527Y1 (en) Device for fastening panel

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 529367 No. 108, red Creek Road, Chikan Town, Guangdong, Kaiping

Applicant after: SOBEN GREEN BUILDING SYSTEMS (GUANGDONG) CO.,LTD.

Address before: 529367 No. 108, red Creek Road, Chikan Town, Guangdong, Kaiping

Applicant before: GUANGDONG SOBEN GREEN BOARD Co.,Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: GUANGDONG SOBEN GREEN BOARD CO., LTD. TO: GUANGDONG SONGBEN GREEN NEW MATERIAL CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160323

Termination date: 20211103

CF01 Termination of patent right due to non-payment of annual fee