CN102361250A - 基于性能评价的运行复合绝缘子现场运行维护方法 - Google Patents

基于性能评价的运行复合绝缘子现场运行维护方法 Download PDF

Info

Publication number
CN102361250A
CN102361250A CN2011102550905A CN201110255090A CN102361250A CN 102361250 A CN102361250 A CN 102361250A CN 2011102550905 A CN2011102550905 A CN 2011102550905A CN 201110255090 A CN201110255090 A CN 201110255090A CN 102361250 A CN102361250 A CN 102361250A
Authority
CN
China
Prior art keywords
composite insulator
test
insulator
mechanical
carried out
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011102550905A
Other languages
English (en)
Other versions
CN102361250B (zh
Inventor
沈庆河
梁曦东
程学启
慕世友
王泽众
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Original Assignee
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd filed Critical Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Priority to CN201110255090.5A priority Critical patent/CN102361250B/zh
Publication of CN102361250A publication Critical patent/CN102361250A/zh
Application granted granted Critical
Publication of CN102361250B publication Critical patent/CN102361250B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明涉及一种基于性能评价的运行复合绝缘子现场运行维护方法,该方法简单、可操作性强,采用运行检测和抽样检测相结合,确定不同运行环境、不同批次复合绝缘子的机电性能和理化性能,进而制定有针对性的运行维护策略。既可减少不必要的维护,又能避免因复合绝缘子运行维护不当而造成的故障。它的步骤为:1)确定运行复合绝缘子的电气性能;2)确定运行复合绝缘子的机械性能;3)确定运行复合绝缘子的理化性能;4)确定运行复合绝缘子运行维护策略:分析评价运行复合绝缘子的电气、机械和理化性能,确定复合绝缘子的运行状态和老化状况,根据不同的情况有针对性制定不同复合绝缘子的运行维护策略。

Description

基于性能评价的运行复合绝缘子现场运行维护方法
技术领域
本发明涉及基于性能评价的运行复合绝缘子现场运行维护方法,属于输电线路运行维护范畴。 
背景技术
由于硅橡胶复合绝缘子具有良好的憎水性和憎水性的迁移性,使得其抗污闪能力强,且具有不检零、不清扫、重量轻、运输安装方便等诸多优点。自九十年代以来,复合绝缘子在电力系统得到了广泛应用,成为输电线路防止污闪事故的有效手段之一。 
在长期的运行过程中,复合绝缘子在电气、机械和外部环境的共同作用下,会因潮湿、局部放电、电晕、紫外线、化学及生物侵袭等因素的影响而导致机电性能下降。全国不断有复合绝缘子闪络、机械强度下降、击穿、脆断、劣化及鸟害的信息报道,而复合绝缘子运行至今基本处于免维护状态,不同厂家、不同时期、不同工艺生产的运行在不同环境中的复合绝缘子运行可靠性是一个令人担心的问题。 
通过评估运行中复合绝缘子的机械性能、电气性能、材料的理化性能等,确定复合绝缘子的老化状况,从而在此基础上制定复合绝缘子运行维护的策略,提高维护的针对性和有效性,避免或减少因复合绝缘子运行维护不当而造成的故障,确保电网的安全稳定运行。 
发明内容
本发明解决了上述运行复合绝缘子现场运行维护的问题,提供了基于性能评价的运行复合绝缘子现场运行维护方法。 
为实现上述目的,本发明采用如下技术方案: 
一种基于性能评价的运行复合绝缘子现场运行维护方法,它的步骤为: 
1)确定运行复合绝缘子的电气性能:通过对运行复合绝缘子进行憎水性、污秽度和红外检测及陡波冲击电压试验,得到被检测绝缘子的各性能参数,对试验结果进行分析后确定不同运行环境、不同批次复合绝缘子的电气性能;
2)确定运行复合绝缘子的机械性能:通过对运行复合绝缘子进行机械破坏负荷试验,得到被检测绝缘子的机械性能参数,对试验结果进行分析后确定不同端部连接型式、不同批次复合绝缘子的机械性能;
3)确定运行复合绝缘子的理化性能:通过对运行复合绝缘子进行伞套材料老化性能检测和外观及端部密封性能试验,得到被检测绝缘子的各理化性能参数,对试验结果进行分析后确定不同厂家、不同批次复合绝缘子的理化性能;
4)确定运行复合绝缘子运行维护策略:分析评价运行复合绝缘子的电气、机械和理化性能,确定复合绝缘子的运行状态和老化状况,根据不同的情况有针对性制定不同复合绝缘子的运行维护策略,既可减少不必要的维护,又能避免因复合绝缘子运行维护不当而造成的故障,有利于电网的安全稳定运行。
有益效果:本发明方法简单、可操作性强,采用运行检测和抽样检测相结合,确定不同运行环境、不同批次复合绝缘子的机电性能和理化性能,进而制定有针对性的运行维护策略。既可减少不必要的维护,又能避免因复合绝缘子运行维护不当而造成的故障。 
具体实施方式
下面结合实施例对本发明做进一步说明 
1)复合绝缘子电气性能检测
(1)憎水性试验
a.监测点选择
每5~10km设置一个复合绝缘子“憎水性监测点”,监测点应选在输电线路沿线最脏污的地段。
b.检测周期 
根据DL/T 864标准规定的检测周期,并结合复合绝缘子的具体运行环境,确定复合绝缘子运行下列时间后应进行首次检测
中等及以下污秽地区(a、b、c级污区):10~12年。
重污秽地区(d级污区):8~10年。 
非常重污秽地区(e级污区):5~8年。 
特殊重污秽地区(e级污区中的水泥、石灰、铝、碱、冶炼等粉尘污染异常严重及距海1km以内的地区):3~5年。 
c.测量时间 
在秋季结合停电检修时进行测量。应选择晴好天气进行测量,若遇雨雾天气,应在雨雾停止一天后进行测量。
d.憎水性检测 
根据运行年限,利用停电机会选点登塔测量复合绝缘子的憎水性。抽查三支绝缘子,测量每支绝缘子的上﹑中、下三个位置的一片大伞和一片小伞上﹑下表面的憎水性,并记录测量时间﹑气象条件等,以备分析该批产品的外绝缘状况。
(2)污秽度检测 
现场污秽度主要通过测量现场摘取的复合绝缘子表面的等值盐密和灰密来确定,需要时应对污秽物的化学成份进行分析。测量时取复合绝缘子上、中、下三个部位各2片大伞和2片小伞,分别对每个伞的上、下伞面进行测量,以此判断复合绝缘子积污状况,并与憎水性检测结果相结合进行分析。
(3)复合绝缘子红外检测 
红外诊断技术是对运行中电气等设备的一种非接触无损检测和故障诊断的技术,可以实现电力设备运行现场大面积温度分布场的扫描和局部缺陷的定点测温,技术先进、检测快速、诊断正确。参照DL/T 864标准规定的首次抽样检测周期,挂网运行后8~10年进行第1次红外检测,若无异常,下一检测周期为5~8年;通过三相比较和不同位置比较,若有发热点较正常部位温差超过1℃,应进一步进行检测、分析,并进行跟踪复测;若有发热点较正常部位温差超过2℃,应结合巡视跟踪检测,利用停电机会更换、检查;若有发热点较正常部位温差超过5℃,应立即进行更换,并进行诊断性检查。
(4)复合绝缘子陡波冲击电压试验 
陡波冲击试验主要考核复合绝缘子内界面质量,要求绝缘子在0.1%浓度NaCl水溶液中沸煮24小时后,在48小时内做陡度不小于1000kV/ms正、负极性各五次的陡波冲击试验,用厚小于1mm、宽20mm的铜带缠绕在试品的杆径上做为电极,两次冲击试验间隔为1min,复合绝缘子应只发生外部闪络而不发生内部击穿为合格。
2)复合绝缘子机械破坏负荷试验 
对绝缘子进行额定机械负荷耐受试验时,试验期间若发生芯棒破坏、芯棒完全抽出或端部附件损坏,记录此破坏值。耐受试验通过的试品,再将负荷升至试品破坏,记录机械破坏负荷值。通过复合绝缘子机械破坏负荷值可计算出该绝缘子的机械强度裕度,以此来判断复合绝缘子的机械稳定性和残余强度变化趋势。
3)复合绝缘子理化性能检测 
(1)外观及端部密封性能老化检查
按照DL/T 864标准对运行复合绝缘子伞套进行粉化、裂纹和开裂、起痕、树枝状通道、蚀损、绝缘子密封情况检查,并检查绝缘子的钢脚或钢帽锈蚀、钢脚弯曲、电弧烧损等情况。
(2)硬度检测 
用硬度计进行复合绝缘子伞套材料的硬度检测。
(3)脆性检查 
手工对复合绝缘子伞裙对折三次进行脆性检查。
策略 
(1)一般复合绝缘子的维护策略
a.若复合绝缘子的憎水性在HC1~HC2、等值附盐密度小于0.2 mg/cm2、灰密小于1.0 mg/cm2、伞套硬度与初始值相比大于0.95、机械破坏负荷与额定机械负荷之比大于1.2、陡波冲击电压试验通过,在外观及端部密封良好、红外测温时温度无异常升高等现象的前提下,则该批绝缘子在5年内可免维护,然后进行抽样检测,以确定下一维护周期。
b.若复合绝缘子满足下列任一条件:憎水性为HC3、等值附盐密度为0.2~0.4 mg/cm2、灰密为2.0~3.0mg/cm2、伞套硬度与初始值相比为0.92~0.95、机械破坏负荷与额定机械负荷之比为1.05~1.2,在外观及端部密封良好、红外测温时温度无异常升高等现象的前提下,则该批绝缘子在3~5年内可免维护,然后进行抽样检测,以确定下一维护周期。 
c.若复合绝缘子满足下列任一条件:憎水性为HC4、等值附盐密度为0.4~0.5mg/cm2、灰密为3.0~4.0mg/cm2、伞套硬度与初始值相比为0.90~0.92、机械破坏负荷与额定机械负荷之比为1.00~1.05,在外观及端部密封良好、红外测温时温度无异常升高、表面无粉化和变脆等现象的前提下,该批绝缘子在3年内可免维护,然后进行抽样检测,以确定下一维护周期。 
d.若复合绝缘子满足下列任一条件:憎水性为HC5、等值附盐密度为0.5~0.6mg/cm2、灰密为4.0~5.0mg/cm2、伞套硬度与初始值相比为0.88~0.90、机械破坏负荷与额定机械负荷之比为0.90~1.00、红外测温时温度异常升高超过1~2℃,在外观及端部密封良好、表面无粉化和变脆等现象的前提下,该批绝缘子在2~3年内可免维护,然后进行抽样检测,以确定下一维护周期。 
e.若复合绝缘子满足下列任一条件:憎水性为HC6、等值附盐密度为0.6~0.7mg/cm2、灰密为5.0~6.0mg/cm2、伞套硬度与初始值相比为0.82~0.88、机械破坏负荷与额定机械负荷之比为0.80~0.90、红外测温时温度异常升高超过2~5℃,在外观及端部密封良好、表面无粉化和变脆等现象的前提下,该批绝缘子在1年内可免维护,然后进行抽样检测,以确定下一维护周期。 
f.若复合绝缘子满足下列任一条件:憎水性为HC7、等值附盐密度大于0.7mg/cm2、灰密大于6.0mg/cm2、伞套硬度与初始值相比大于0.82、机械破坏负荷与额定机械负荷之比小于0.80、红外测温时温度异常升高超过5℃,则需进行更换,并扩大抽样检测,以确定更换范围。 
(2)异常复合绝缘子的维护策略 
a.伞套脆化、粉化或破裂:此复合绝缘子伞套材料已严重老化,无需再进行电气和机械性能测试,直接进行更换;
b.伞套出现漏电起痕与蚀损,且累计长度大于绝缘子爬电距离的10%或蚀损深度大于所处位置材料厚度的30%:此绝缘子已严重受损,继续运行将威胁线路的安全运行,应进行更换。此种情况的出现一般与运行环境密切相关,适当摘取部分绝缘子进行电气、机械和理化性能试验,以确定更换范围;
c.绝缘子各联接部位密封失效、出现可见裂缝和滑移:此种情况会导致复合复合绝缘子的伞套失去对芯棒的保护,造成芯棒机械性能下降,易产生断裂事故,需进行更换。此种情况的出现一般与制造工艺密切相关,适当摘取部分绝缘子进行机械和理化性能试验,以确定更换范围;
d.机械破坏负荷小于0.80的额定机械负荷:此复合绝缘子机械性能已严重下降,机械稳定性差,需进行更换。此种情况的出现一般与制造工艺密切相关,适当摘取同批次的部分绝缘子进行机械性能试验,以确定更换范围;
e.陡波冲击电压试验发生绝缘子内部击穿或复合绝缘子红外测温时温度异常升高超过5℃:此种情况的出现说明绝缘子的芯棒与护套间界面已存在严重缺陷,需尽快进行更换,并适当摘取同批次的部分绝缘子进行电气性能试验,以确定更换范围;
f.复合绝缘子憎水性丧失:此种情况的出现一般与运行环境和产品配方密切相关,尽快适当摘取同厂家相同批次的部分绝缘子进行电气、机械和理化性能试验,以确定更换范围。
 上述虽然对本发明的具体实施方式进行了描述,但并非对本发明保护范围的限制,所属领域技术人员应该明白,在本发明的技术方案的基础上,本领域技术人员不需要付出创造性劳动即可做出的各种修改或变形仍在本发明的保护范围以内。 
  

Claims (6)

1. 一种基于性能评价的运行复合绝缘子现场运行维护方法,其特征是,该方法的实现步骤如下: 
1)确定运行复合绝缘子的电气性能:通过对运行复合绝缘子进行憎水性、污秽度和红外检测及陡波冲击电压试验,将试验结果进行分析后确定不同运行环境、不同批次复合绝缘子的电气性能;
2)确定运行复合绝缘子的机械性能:通过对运行复合绝缘子进行机械破坏负荷试验,确定不同端部连接型式、不同批次复合绝缘子的机械性能;
3)确定运行复合绝缘子的理化性能:通过对运行复合绝缘子按照DL/T 864《标称电压高于1000V架空线路用复合绝缘子使用导则》标准进行伞套材料老化性能检测、按照GB/T 19519《标称电压高于1000V的交流架空线路用复合绝缘子定义、试验方法及验收准则》标准进外观及端部密封性能试验,将试验结果进行分析后确定不同厂家、不同批次复合绝缘子的理化性能;
4)确定运行复合绝缘子运行维护策略:分析评价运行复合绝缘子的电气、机械和理化性能,确定复合绝缘子的运行状态和老化状况,根据不同的情况制定不同复合绝缘子的运行维护策略。
2. 如权利要求1所述的基于性能评价的运行复合绝缘子现场运行维护方法,其特征是,所述步骤1)中,对运行复合绝缘子进行憎水性试验的方法如下:
a.监测点选择:每5~10km设置一个复合绝缘子“憎水性监测点”,监测点应选在输电线路沿线最脏污的地段;
b.检测周期:根据DL/T 864标准规定的检测周期,确定复合绝缘子运行下列时间后应进行首次检测:
中等及以下污秽地区:10~12年;
重污秽地区:8~10年;
非常重污秽地区:5~8年;
特殊重污秽地区:3~5年;
c.测量时间:在秋季结合停电检修时,选择晴好天气进行测量,若遇雨雾天气,应在雨雾停止一天后进行测量;
d.憎水性检测:抽查三支绝缘子,测量每支绝缘子的上﹑中、下三个位置的一片大伞和一片小伞上﹑下表面的憎水性,并记录测量时间和气象条件,以分析该批产品的外绝缘状况。
3.如权利要求1所述的基于性能评价的运行复合绝缘子现场运行维护方法,其特征是,所述步骤1)中,对运行复合绝缘子进行污秽度检测的方法如下:测量时取复合绝缘子上、中、下三个部位各2片大伞和2片小伞,分别对每个伞的上、下伞面进行测量,以此判断复合绝缘子积污状况。
4.如权利要求1所述的基于性能评价的运行复合绝缘子现场运行维护方法,其特征是,所述步骤1)中,对运行复合绝缘子进行红外检测的周期如下:参照DL/T 864标准规定的首次抽样检测周期,挂网运行后8~10年进行第1次红外检测,下一检测周期为5~8年。
5.如权利要求1所述的基于性能评价的运行复合绝缘子现场运行维护方法,其特征是,所述步骤1)中,对运行复合绝缘子进行陡波冲击电压试验的方法如下:绝缘子在0.1%浓度NaCl水溶液中沸煮24小时后,在48小时内做陡度不小于1000kV/ms正、负极性各五次的陡波冲击试验,用厚小于1mm、宽20mm的铜带缠绕在试品的杆径上做为电极,两次冲击试验间隔为1min,复合绝缘子应只发生外部闪络而不发生内部击穿为合格。
6.如权利要求1所述的基于性能评价的运行复合绝缘子现场运行维护方法,其特征是,所述步骤2)中,对运行复合绝缘子进行机械破坏负荷试验的方法如下:对绝缘子进行额定机械负荷耐受试验时,试验期间若发生芯棒破坏、芯棒完全抽出或端部附件损坏,记录此破坏值;耐受试验通过的试品,再将负荷升至试品破坏,记录机械破坏负荷值;通过复合绝缘子机械破坏负荷值可计算出该绝缘子的机械强度裕度,以此来判断复合绝缘子的机械稳定性和残余强度变化趋势。
CN201110255090.5A 2011-08-31 2011-08-31 基于性能评价的运行复合绝缘子现场运行维护方法 Active CN102361250B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110255090.5A CN102361250B (zh) 2011-08-31 2011-08-31 基于性能评价的运行复合绝缘子现场运行维护方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110255090.5A CN102361250B (zh) 2011-08-31 2011-08-31 基于性能评价的运行复合绝缘子现场运行维护方法

Publications (2)

Publication Number Publication Date
CN102361250A true CN102361250A (zh) 2012-02-22
CN102361250B CN102361250B (zh) 2014-10-15

Family

ID=45586521

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110255090.5A Active CN102361250B (zh) 2011-08-31 2011-08-31 基于性能评价的运行复合绝缘子现场运行维护方法

Country Status (1)

Country Link
CN (1) CN102361250B (zh)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102680815A (zh) * 2012-04-16 2012-09-19 中国南方电网有限责任公司超高压输电公司天生桥局 一种复合绝缘子交界面的检测方法及系统
CN102879689A (zh) * 2012-10-12 2013-01-16 华北电力大学(保定) 一种复合绝缘子运行状态评估方法
CN103345637A (zh) * 2013-07-15 2013-10-09 国家电网公司 输电线路复合绝缘子憎水性在线检测系统及方法
CN103411970A (zh) * 2013-07-17 2013-11-27 同济大学 基于红外热像的交流输电线路绝缘子污秽状态检测方法
CN103632024A (zh) * 2012-08-27 2014-03-12 国家电网公司 输电线路形式的确定方法和装置
CN106771765A (zh) * 2017-01-05 2017-05-31 华北电力大学(保定) 一种运行中的复合绝缘子老化程度的多维参量评估方法
CN106971025A (zh) * 2017-03-03 2017-07-21 国网浙江省电力公司电力科学研究院 一种复合绝缘子爬电距离有效利用系数的确定方法
CN107229007A (zh) * 2017-07-25 2017-10-03 江苏祥源电气设备有限公司 一种复合绝缘子空气中冲击击穿试验方法
CN107885921A (zh) * 2017-10-27 2018-04-06 国家电网公司 复合绝缘子棒芯老化评价方法
CN108008258A (zh) * 2017-11-10 2018-05-08 国网江西省电力有限公司电力科学研究院 一种复合绝缘子芯棒与金具界面性能评估方法
CN108594030A (zh) * 2017-12-01 2018-09-28 国网北京市电力公司 避雷器性能确定方法及装置
CN108931607A (zh) * 2018-04-28 2018-12-04 国网山东省电力公司电力科学研究院 一种复合绝缘清洁修复剂效能评价的方法
CN109030460A (zh) * 2018-06-21 2018-12-18 平顶山学院 基于libs的复合绝缘子老化定量检测方法
CN111208393A (zh) * 2018-11-22 2020-05-29 国网河南省电力公司平顶山供电公司 一种线路绝缘子运行工况地面检测方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1558249A (zh) * 2004-01-20 2004-12-29 华北电力大学 一种带电检测高压直流输电线路绝缘子的方法
CN2745065Y (zh) * 2004-08-06 2005-12-07 华北电力大学(北京) 复合绝缘子憎水性及憎水迁移性在线检测装置

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1558249A (zh) * 2004-01-20 2004-12-29 华北电力大学 一种带电检测高压直流输电线路绝缘子的方法
CN2745065Y (zh) * 2004-08-06 2005-12-07 华北电力大学(北京) 复合绝缘子憎水性及憎水迁移性在线检测装置

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
中华人民共和国国家发展和改革委员会: "《中华人民共和国电力行业标准DL/T 864-2004》", 9 March 2004 *
吴光亚等: "复合绝缘子的运行特性及可靠性分析", 《电瓷避雷器》 *
苏玫: "陡波试验在检测复合绝缘子中的作用", 《高压工程》 *

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102680815B (zh) * 2012-04-16 2016-01-20 中国南方电网有限责任公司超高压输电公司天生桥局 一种复合绝缘子交界面的检测方法及系统
CN102680815A (zh) * 2012-04-16 2012-09-19 中国南方电网有限责任公司超高压输电公司天生桥局 一种复合绝缘子交界面的检测方法及系统
CN103632024A (zh) * 2012-08-27 2014-03-12 国家电网公司 输电线路形式的确定方法和装置
CN102879689A (zh) * 2012-10-12 2013-01-16 华北电力大学(保定) 一种复合绝缘子运行状态评估方法
CN102879689B (zh) * 2012-10-12 2014-11-26 华北电力大学(保定) 一种复合绝缘子运行状态评估方法
CN103345637A (zh) * 2013-07-15 2013-10-09 国家电网公司 输电线路复合绝缘子憎水性在线检测系统及方法
CN103411970A (zh) * 2013-07-17 2013-11-27 同济大学 基于红外热像的交流输电线路绝缘子污秽状态检测方法
CN106771765A (zh) * 2017-01-05 2017-05-31 华北电力大学(保定) 一种运行中的复合绝缘子老化程度的多维参量评估方法
CN106971025A (zh) * 2017-03-03 2017-07-21 国网浙江省电力公司电力科学研究院 一种复合绝缘子爬电距离有效利用系数的确定方法
CN106971025B (zh) * 2017-03-03 2020-03-27 国网浙江省电力公司电力科学研究院 一种复合绝缘子爬电距离有效利用系数的确定方法
CN107229007B (zh) * 2017-07-25 2020-02-21 江苏祥源电气设备有限公司 一种复合绝缘子空气中冲击击穿试验方法
CN107229007A (zh) * 2017-07-25 2017-10-03 江苏祥源电气设备有限公司 一种复合绝缘子空气中冲击击穿试验方法
CN107885921A (zh) * 2017-10-27 2018-04-06 国家电网公司 复合绝缘子棒芯老化评价方法
CN108008258B (zh) * 2017-11-10 2019-12-06 国网江西省电力有限公司电力科学研究院 一种复合绝缘子芯棒与金具界面性能评估方法
CN108008258A (zh) * 2017-11-10 2018-05-08 国网江西省电力有限公司电力科学研究院 一种复合绝缘子芯棒与金具界面性能评估方法
CN108594030A (zh) * 2017-12-01 2018-09-28 国网北京市电力公司 避雷器性能确定方法及装置
CN108594030B (zh) * 2017-12-01 2021-03-16 国网北京市电力公司 避雷器性能确定方法及装置
CN108931607A (zh) * 2018-04-28 2018-12-04 国网山东省电力公司电力科学研究院 一种复合绝缘清洁修复剂效能评价的方法
CN109030460A (zh) * 2018-06-21 2018-12-18 平顶山学院 基于libs的复合绝缘子老化定量检测方法
CN109030460B (zh) * 2018-06-21 2020-09-11 平顶山学院 基于libs的复合绝缘子老化定量检测方法
CN111208393A (zh) * 2018-11-22 2020-05-29 国网河南省电力公司平顶山供电公司 一种线路绝缘子运行工况地面检测方法

Also Published As

Publication number Publication date
CN102361250B (zh) 2014-10-15

Similar Documents

Publication Publication Date Title
CN102361250B (zh) 基于性能评价的运行复合绝缘子现场运行维护方法
Gubanski et al. Diagnostic methods for outdoor polymeric insulators
CN105388403B (zh) 一种基于硬度保留率的低压电缆剩余寿命快速检测方法
CN104166068B (zh) 电力系统钢芯铝绞线失效分析方法
TW201504637A (zh) 利用切片取樣評估電纜老劣化之方法
CN108008258B (zh) 一种复合绝缘子芯棒与金具界面性能评估方法
CN102928751A (zh) 一种基于行波原理的高压架空线路绝缘子在线监测方法
CN104931541B (zh) 一种混凝土中gfrp筋的长期性能监测方法
Tzimas et al. Asset management frameworks for outdoor composite insulators
JP6631593B2 (ja) 耐候性鋼の腐食予測方法および鋼構造物の腐食予測方法
CN104048913B (zh) 一种rtv材料老化程度判断方法
Jeong et al. Electrochemical performance evaluation of corrosion monitoring sensor for reinforced concrete structures
Cella et al. Electrical resistance changes as an alternate method for monitoring the corrosion of steel in concrete and mortar
CN112730112B (zh) 适用于反应堆结构部件材料长期服役后的环境断裂评估方法
Bashir et al. Ageing of transmission line insulators: The past, present and future
US9890947B2 (en) Prediction method for corrosion rate of steam generator tube using eddy current testing
Shaffner et al. Experience with a composite insulator testing instrument based on the electric field method
CN108037119A (zh) 一种基于典型高分子材料老化的大气环境严酷度评估方法
Zammit et al. Increasing the design strength of glass-fractography and stress testing
Takahashi et al. Evaluation of factors contributing to deterioration of track-slab in cold areas
Castro et al. Colombian experience on insulation pollution level measurement applying the ESDD methodology
Bradwell et al. Evaluation of plastics insulators for use on British Railways 25 kV overhead line electrification
Ramirez-Vazquez et al. Diagnostic of nonceramic insulators aged in a salt fog chamber by using electric field sensor
CN108931607A (zh) 一种复合绝缘清洁修复剂效能评价的方法
Wen et al. Partial discharge analysis of insulators in transmission lines in coastal heavy pollution areas

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA

Effective date: 20121219

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20121219

Address after: 250002 Ji'nan City Central District, Shandong, No. 2 South Road, No. 500

Applicant after: SHANDONG ELECTRIC POWER Research Institute

Applicant after: State Grid Corporation of China

Address before: 250002 Ji'nan City Central District, Shandong, No. 2 South Road, No. 500

Applicant before: SHANDONG ELECTRIC POWER Research Institute

C14 Grant of patent or utility model
GR01 Patent grant
CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 250003 No. 2000, Wang Yue Road, Shizhong District, Ji'nan, Shandong

Patentee after: Shandong Electric Power Research Institute

Patentee after: State Grid Corporation of China

Address before: 250002, No. 500, South Second Ring Road, Shizhong District, Shandong, Ji'nan

Patentee before: Shandong Electric Power Research Institute

Patentee before: State Grid Corporation of China

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 250003 No. 2000, Wang Yue Road, Shizhong District, Ji'nan, Shandong

Patentee after: SHANDONG ELECTRIC POWER Research Institute

Patentee after: STATE GRID CORPORATION OF CHINA

Address before: 250003 No. 2000, Wang Yue Road, Shizhong District, Ji'nan, Shandong

Patentee before: SHANDONG ELECTRIC POWER Research Institute

Patentee before: State Grid Corporation of China

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220125

Address after: 250003 No. 2000, Wang Yue Road, Shizhong District, Ji'nan, Shandong

Patentee after: ELECTRIC POWER RESEARCH INSTITUTE OF STATE GRID SHANDONG ELECTRIC POWER Co.

Patentee after: STATE GRID CORPORATION OF CHINA

Address before: 250003 No. 2000, Wang Yue Road, Shizhong District, Ji'nan, Shandong

Patentee before: SHANDONG ELECTRIC POWER Research Institute

Patentee before: STATE GRID CORPORATION OF CHINA