CN102330424A - 一种吹填软土的复式真空管井真空预压加固方法 - Google Patents

一种吹填软土的复式真空管井真空预压加固方法 Download PDF

Info

Publication number
CN102330424A
CN102330424A CN201110187638A CN201110187638A CN102330424A CN 102330424 A CN102330424 A CN 102330424A CN 201110187638 A CN201110187638 A CN 201110187638A CN 201110187638 A CN201110187638 A CN 201110187638A CN 102330424 A CN102330424 A CN 102330424A
Authority
CN
China
Prior art keywords
vacuum
soft soil
soil
outer tube
compound
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201110187638A
Other languages
English (en)
Other versions
CN102330424B (zh
Inventor
张超杰
俞炯奇
吴雄伟
吴文华
姜建芳
魏海云
徐金岩
梅寒刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG GUANGCHUAN CONSULTING CO Ltd
Zhejiang Institute of Hydraulics and Estuary
Original Assignee
ZHEJIANG GUANGCHUAN CONSULTING CO Ltd
Zhejiang Institute of Hydraulics and Estuary
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG GUANGCHUAN CONSULTING CO Ltd, Zhejiang Institute of Hydraulics and Estuary filed Critical ZHEJIANG GUANGCHUAN CONSULTING CO Ltd
Priority to CN2011101876387A priority Critical patent/CN102330424B/zh
Publication of CN102330424A publication Critical patent/CN102330424A/zh
Application granted granted Critical
Publication of CN102330424B publication Critical patent/CN102330424B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

一种吹填软土的复式真空管井真空预压加固方法,复式真空管井包括内管、外管和滤膜,利用通到外管低端的内管,将外管内的水抽走并在外管内产生负压,实现将真空泵的负压直接施加到加固土体上;在加固初期,吹填软土含水量高,强度低,为了避免在负压作用下土颗粒向排水体移动而聚集成团柱,采用间歇性开启真空泵,以抽取重力作用下自由渗进排水体内的水为主要目的;在加固后期,持续开启真空泵,先低真空,后高真空,减弱粘性土颗粒在排水体周边形成团柱的作用,以实现加固过程的节能和高效;此外,由于不再需要通过铺设砂垫层将负压传递到土体中,本法能在砂源短缺的地方应用。本发明与传统真空预压相比,更适用于加固高含水量的吹填软土。

Description

一种吹填软土的复式真空管井真空预压加固方法
技术领域
本发明涉及一种吹填土软土造地大面积加固技术,属于土木工程地基处理工程技术领域。
背景技术
1952年杰尔曼教授(Kjellman)提出了真空预压加固软基方法,基本技术方法是先在需要加固的软土地基表面铺垫一层排水垫层,作为水平排水垫层,然后将袋装砂井或塑料排水板打入土体,作为竖直排水体,再将密封膜铺设在的排水垫层上,密封膜四周埋入土中,借埋设于排水垫层中的管道,将密封膜下土体中的空气抽出,使其形成相对负压,由于袋装砂井或塑料排水板渗透性较大,该负压能够传递到砂井深处,从而在砂井和砂井周围土体之间形成压力差使土体中的孔隙水进入砂井并被排出,最终达到地基加固效果的目的。但传统真空预压地基处理方法存在以下局限性:
1、传统真空预压加固软土时常用塑料排水板作为土体中的排水通道,真空泵提供的负压通过透水砂层和塑料排水板向下传递到软土层中,但向下传递过程中有负压损失,降低了加固效率。
2、吹填土是原状土经水力搬运沉淀形成,含水量高,结构性差,粘性土颗粒有较大的自由度,用真空预压法加固吹填土时,粘性土颗粒会在负压作用下向塑料排水板周边移动形成团柱而产生屏蔽作用,使得负压向土体内的传递减弱,影响土体中水的排出,减弱加固效果。
3、传统真空预压法需要铺设排水垫层。一般需严格采用含泥量小于5%的中粗纱,厚度约50cm左右,对于吹填或新近淤积的超软土,砂垫层需铺设80~100cm,在砂源缺乏的地方可操作性较差;此外,铺设砂垫层价格昂贵,导致工程投资大大增加。
发明内容
为了克服已有吹填土软土造地大面积加固技术的真空泵负压向土体中的传递效率较低、土体中不易排水、加固效果不显著、不适用于砂源缺乏的地方和成本高的不足,本发明提供一种提高真空泵负压向土体中的传递效率、使得土体中的水更易排出、提高加固效果、适用于砂源缺乏的地方、降低成本的吹填软土的复式真空管井真空预压加固方法。
本发明解决其技术问题所采用的技术方案是:
一种吹填软土的复式真空管井真空预压加固方法,采用复式真空管井,所述复式真空管井包括内管、外管和滤膜,所述外管下端封闭,所述外管上端设有封头,所述内管穿过所述封头伸入所述外管内腔底部,所述内管与所述封头密封连接,内管与抽真空排水管连通,所述外管的中下部外壁套装所述滤膜,有滤膜处外管的管壁开有透水孔;将内管直接与抽真空系统相连,将外管内的水抽走并在外管内产生负压,在加固初期,间歇性开启真空泵抽水,以井点降水的模式降低吹填软土的含水量;当加固土体含水量降到液限下5~8%时,持续开启真空泵,先低真空,后高真空,实现吹填软土的加固。
进一步,所述复式真空管井的内管和外管均为硬质管,所述加固方法包括以下步骤:
(1)、先筑围堰,后打设所述复式真空管井,再将各复式真空管井的内管与抽真空系统连接,然后开始在围堰内吹填软土,同时确保吹填过程中复式真空管群直立;
(2)、当吹填软土面高于复式真空管井滤膜的上端时,间歇性开启真空泵,抽取重力作用下渗进复式真空管井内的水,同时监测吹填软土面的高程变化,间断吹填软土,确保吹填软土面始终高于复式真空管井滤膜的上端;
(3)、当加固土体含水量降到液限下5~8%时,持续开启真空泵,前期先低真空,中后期逐渐高真空;
(4)、当预估吹填软土面加固沉降后的高程大于设计要求高程时,停止吹填软土,同时在吹填软土面上保留设定厚度上覆水;
(5)、当滤膜范围内土体加固到设计强度时,排掉上覆水,继续抽真空至吹填软土表面开裂。
或者是:所述复式真空管井的内管为软质管,所述加固方法包括以下步骤:
(1)、先筑围堰,后围堰内吹填软土,待吹填软土自重沉降到设定程度后打设复式真空管井;
(2)、将复式真空管井的内管与抽真空系统连接;
(3)、完成土工布和密封模铺设;
(4)、在抽真空前阶段间歇性开启真空泵;
(5)、当加固土体含水量降到液限下5~8%时,持续开启真空泵,前期先低真空,中后期逐渐高真空;
(6)、持续抽真空当加固达到设计强度时,抽真空结束。
本发明的技术构思为:复式真空管井主要由内管、外管和滤膜组成,根据内管和外管的材质是否可弯曲,分为硬质复式真空管井和软质复式真空管井。硬质复式真空管井的示意图见图1,软质复式真空管井的示意图见图3。采用硬质复式真空管井时,先打设硬质复式真空管井,后吹填泥浆;采用软质复式真空管井时,先吹填泥浆,后打设软质复式真空管井。上述两种加固方法的吹填泥浆和打设排水体的顺序虽然不同,但加固吹填软土的本技术方案是一致的。
利用通到外管低端的内管,将外管内的水抽走并在外管内产生负压,实现将真空泵的负压直接施加到加固土体上。
在加固初期,吹填软土含水量高,强度低,在负压作用下粘性土颗粒会向排水体移动而聚集成团柱,影响后期的加固效果。因此本阶段间歇性开启真空泵抽水,以井点降水的模式降低吹填软土的含水量,增加土的强度。
当井点降水模式降低吹填软土含水量的效率明显减弱时,持续开启真空泵,先低真空,后高真空,其目的也是减弱粘性土颗粒在排水体周边形成团柱的作用,以实现加固过程的节能和高效。
由于直接将内管直接与抽真空系统相连,故不再需要通过砂垫层将负压传递到排水体中。
本发明的有益效果主要表现在:提高真空泵负压向土体中的传递效率、使得土体中的水更易排出、提高加固效果、适用于砂源缺乏的地方、降低成本。
附图说明
图1为硬质复式真空管井示意图。
图中:1压力探头,2滤膜,3压力探头,4外管(硬质,PVC材质或镀锌管,外径约5cm,有滤膜处管壁开有透水孔,无滤膜处不开孔),5电极电缆,6硬质复式真空管井内水气流动方向,7内管(硬质,管壁不开孔,外径约2cm),8滤膜顶。
图2为复式真空管井群预压加固吹填软土示意简图。
图中:9原地面,10围堰,11吹填软土顶,12上覆水位面,13抽真空连接管,14真空表,15控制阀门,16真空泵。
图3为软质复式真空管井示意图。
图中:7内管(软质,弹簧塑料软管或可抽真空塑料软管,管壁不开孔,外径约2cm),4外管(软质,波纹滤管,外径约5cm)。
图4为软质复式真空管井预压加固吹填软土示意简图。
图中:a为复式真空波纹滤管内抽真空软管距波纹滤管底距离(约20cm),17密封构,18土工布,19密封膜。
具体实施方式
下面结合附图对本发明作进一步描述。
实施例1
参照图1和图2,一种吹填软土的复式真空管井真空预压加固方法,采用复式真空管井,所述复式真空管井包括内管7、外管4和滤膜2,所述外管4下端封闭,所述外管4上端设有封头,所述内管穿过所述封头伸入所述外管内腔底部,所述内管与所述封头密封连接,内管与抽真空排水管连通,所述外管的中下部外壁套装所述滤膜,有滤膜处外管的管壁开有透水孔;将内管直接与抽真空系统相连,将外管内的水抽走并在外管内产生负压,在加固初期,间歇性开启真空泵抽水,以井点降水的模式降低吹填软土的含水量;当加固土体含水量降到液限下5~8%时,持续开启真空泵,先低真空,后高真空,实现吹填软土的加固。
所述滤膜2上下端的外管内壁安装压力探头1、3,其中,滤膜顶8。所述压力探头1、3的电极电缆5穿过所述封头。6为硬质复式真空管井内水气流动方向。
先打设抽真空设备再进行吹填淤泥,这时采用图1设计的硬质复式真空管井,其外管可采用直径5cm的PVC管或1.5寸镀锌管,内管采用直径2cm的PVC管。布置示意图见图2,主要实施技术方案如下:
(1)、先筑围堰,后打设硬质复式真空管井,再将各硬质复式真空管井的内管与抽真空系统连接,然后开始在围堰内吹填软土,同时确保吹填过程中硬质复式真空管群直立。
(2)、当吹填软土面高于硬质复式真空管井滤膜的上端时,间歇性开启真空泵,抽取重力作用下渗进复式真空管井内的水,同时监测吹填软土面的高程变化,间断吹填软土,确保吹填软土面始终高于复式真空管井滤膜的上端。本阶段吹填土软土的含水量大,流动性强,开启真空泵主要是为了抽取复式真空管井内的水,而不应在吹填土中形成显著的负压区,以避免在复式真空管井周边形成具有密封性的粘性土颗粒团柱。
(3)、当加固土体含水量降到液限下5~8%时,持续开启真空泵,本阶段前期先低真空,中后期逐渐高真空,其目的也是尽量减弱复式真空管井周边形成粘性土颗粒团柱的现象。
(4)、当预估吹填软土面加固沉降后的高程大于设计要求高程时,停止吹填软土,同时在吹填软土面上保留一定厚度上覆水,该上覆水层起密封膜的作用。
(5)、当滤膜范围内土体加固到设计强度时,排掉上覆水,继续抽真空至吹填软土表面开裂。
实施例2
参照图3和图4,本实施例中,先吹填淤泥,再打设抽真空设备。这时采用图2设计的软质复式真空管井,外管4为直径5cm的波纹滤管,内管7采用直径2cm的弹簧塑料软管或可抽真空塑料软管。布置示意图见图4,主要实施技术步骤如下:
(1)、先筑围堰,后围堰内吹填软土,待吹填软土自重沉降到一定程度后打设复式真空波纹滤管。
(2)、将复式真空波纹滤管的抽真空软管与抽真空系统连接。
(3)、完成土工布和密封模铺设。
(4)、在抽真空前阶段间歇性开启真空泵,主要目的是抽取软质复式真空管井内的水,而不应在吹填土中形成显著的负压区,以避免在软质复式真空管井周边形成具有密封性的粘性土颗粒团柱。
(5)、当加固土体含水量降到液限下5~8%时,持续开启真空泵,本阶段前期先低真空,中后期逐渐高真空,其目的是尽量减弱复式真空波纹滤管周边形成粘性土颗粒团柱的现象。
(6)、持续抽真空当加固达到设计强度时,抽真空结束。
本实施例的其他工作过程与实施例1相同。

Claims (3)

1.一种吹填软土的复式真空管井真空预压加固方法,其特征在于:
采用复式真空管井,所述复式真空管井包括内管、外管和滤膜,所述外管下端封闭,所述外管上端设有封头,所述内管穿过所述封头伸入所述外管内腔底部,所述内管与所述封头密封连接,内管与抽真空排水管连通,所述外管的中下部外壁套装所述滤膜,有滤膜处外管的管壁开有透水孔;
将内管直接与抽真空系统相连,将外管内的水抽走并在外管内产生负压,在加固初期,间歇性开启真空泵抽水,以井点降水的模式降低吹填软土的含水量;当加固土体含水量降到液限下5~8%时,持续开启真空泵,先低真空,后高真空,实现吹填软土的加固。
2.如权利要求1所述的一种吹填软土的复式真空管井真空预压加固方法,其特征在于:所述复式真空管井的内管和外管均为硬质管;所述加固方法包括以下步骤:
(1)、先筑围堰,后打设所述复式真空管井,再将各复式真空管井的内管与抽真空系统连接,然后开始在围堰内吹填软土,同时确保吹填过程中复式真空管群直立;
(2)、当吹填软土面高于复式真空管井滤膜的上端时,间歇性开启真空泵,抽取重力作用下渗进复式真空管井内的水,同时监测吹填软土面的高程变化,间断吹填软土,确保吹填软土面始终高于复式真空管井滤膜的上端;
(3)、当加固土体含水量降到液限下5~8%时,持续开启真空泵,前期先低真空,中后期逐渐高真空;
(4)、当预估吹填软土面加固沉降后的高程大于设计要求高程时,停止吹填软土,同时在吹填软土面上保留设定厚度上覆水;
(5)、当滤膜范围内土体加固到设计强度时,排掉上覆水,继续抽真空至吹填软土表面开裂。
3.如权利要求1所述的一种吹填软土的复式真空管井真空预压加固方法,其特征在于:所述复式真空管井的内管为软质管;所述加固方法包括以下步骤:
(1)、先筑围堰,后围堰内吹填软土,待吹填软土自重沉降到设定程度后打设复式真空管井;
(2)、将复式真空管井的内管与抽真空系统连接;
(3)、完成土工布和密封模铺设;
(4)、在抽真空前阶段间歇性开启真空泵;
(5)、当加固土体含水量降到液限下5~8%时,持续开启真空泵,前期先低真空,中后期逐渐高真空;
(6)、持续抽真空当加固达到设计强度时,抽真空结束。
CN2011101876387A 2011-07-05 2011-07-05 一种吹填软土的复式真空管井真空预压加固方法 Expired - Fee Related CN102330424B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011101876387A CN102330424B (zh) 2011-07-05 2011-07-05 一种吹填软土的复式真空管井真空预压加固方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011101876387A CN102330424B (zh) 2011-07-05 2011-07-05 一种吹填软土的复式真空管井真空预压加固方法

Publications (2)

Publication Number Publication Date
CN102330424A true CN102330424A (zh) 2012-01-25
CN102330424B CN102330424B (zh) 2013-11-13

Family

ID=45482370

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011101876387A Expired - Fee Related CN102330424B (zh) 2011-07-05 2011-07-05 一种吹填软土的复式真空管井真空预压加固方法

Country Status (1)

Country Link
CN (1) CN102330424B (zh)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102966376A (zh) * 2012-11-08 2013-03-13 贵州开磷(集团)有限责任公司 一种矿体真空负压快速疏干法
CN103352458A (zh) * 2013-07-02 2013-10-16 南京瑞迪建设科技有限公司 膜下可控式真空负压井高效吸水固结法
CN103485326A (zh) * 2013-09-29 2014-01-01 中铁港航局集团有限公司 软弱地基加固处理中错开式开泵施工方法
CN103758110A (zh) * 2014-01-21 2014-04-30 河海大学 加固软黏土地基的方法
CN104452736A (zh) * 2014-12-05 2015-03-25 水利部交通运输部国家能源局南京水利科学研究院 一种间歇式真空预压装置及其进行软基处理的方法
CN104563063A (zh) * 2014-12-30 2015-04-29 浙江广川工程咨询有限公司 一种利用复式排水板的真空预压处理方法
CN105672244A (zh) * 2016-01-19 2016-06-15 南通大学 用于加固软黏土地基的排水装置、系统及处理方法
CN106545003A (zh) * 2016-11-25 2017-03-29 中交第二航务工程局有限公司 真空降水井逆作法加固吹填土的施工方法
CN106917398A (zh) * 2015-12-28 2017-07-04 中国二十冶集团有限公司 真空联合堆载预压中密封膜施工方法
CN109944230A (zh) * 2019-04-30 2019-06-28 交通运输部天津水运工程科学研究所 一种软土固结排水装置
CN111535293A (zh) * 2020-03-05 2020-08-14 东南大学 一种低位降水真空联合堆载预压加固深厚软基方法及系统
CN112176806A (zh) * 2020-10-16 2021-01-05 于胜泉 稳定型道路软基处理方法以及配套的软基处理施工系统
WO2022095291A1 (zh) * 2020-11-09 2022-05-12 中国海洋大学 一种用于加固软弱土体的双螺旋管、注浆成桩设备及其施工方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1147610A (en) * 1965-04-07 1969-04-02 Paul Willem Van Beveren Improved method for vertically draining soil, and an arrangement for performing this method
CN101100852A (zh) * 2007-08-06 2008-01-09 张志铁 双真空自载预压及土工复合填料低能量强夯加固软土的方法
CN101130952A (zh) * 2007-08-01 2008-02-27 汤连生 一种无密封快速真空预压强夯法
CN101219297A (zh) * 2007-09-11 2008-07-16 东南大学 高含水量疏浚淤泥堆场透气真空快速泥水分离方法
JP2009287261A (ja) * 2008-05-29 2009-12-10 East Nippon Expressway Co Ltd 地盤改良装置及び地盤改良工法
CN102061691A (zh) * 2009-11-12 2011-05-18 任再永 采用排水桩管填充式处理地基的施工方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1147610A (en) * 1965-04-07 1969-04-02 Paul Willem Van Beveren Improved method for vertically draining soil, and an arrangement for performing this method
CN101130952A (zh) * 2007-08-01 2008-02-27 汤连生 一种无密封快速真空预压强夯法
CN101100852A (zh) * 2007-08-06 2008-01-09 张志铁 双真空自载预压及土工复合填料低能量强夯加固软土的方法
CN101219297A (zh) * 2007-09-11 2008-07-16 东南大学 高含水量疏浚淤泥堆场透气真空快速泥水分离方法
JP2009287261A (ja) * 2008-05-29 2009-12-10 East Nippon Expressway Co Ltd 地盤改良装置及び地盤改良工法
CN102061691A (zh) * 2009-11-12 2011-05-18 任再永 采用排水桩管填充式处理地基的施工方法

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102966376A (zh) * 2012-11-08 2013-03-13 贵州开磷(集团)有限责任公司 一种矿体真空负压快速疏干法
CN103352458A (zh) * 2013-07-02 2013-10-16 南京瑞迪建设科技有限公司 膜下可控式真空负压井高效吸水固结法
CN103485326A (zh) * 2013-09-29 2014-01-01 中铁港航局集团有限公司 软弱地基加固处理中错开式开泵施工方法
CN103758110B (zh) * 2014-01-21 2015-07-29 河海大学 加固软黏土地基的方法
CN103758110A (zh) * 2014-01-21 2014-04-30 河海大学 加固软黏土地基的方法
CN104452736A (zh) * 2014-12-05 2015-03-25 水利部交通运输部国家能源局南京水利科学研究院 一种间歇式真空预压装置及其进行软基处理的方法
CN104563063B (zh) * 2014-12-30 2016-08-24 浙江广川工程咨询有限公司 一种利用复式排水板的真空预压处理方法
CN104563063A (zh) * 2014-12-30 2015-04-29 浙江广川工程咨询有限公司 一种利用复式排水板的真空预压处理方法
CN106917398A (zh) * 2015-12-28 2017-07-04 中国二十冶集团有限公司 真空联合堆载预压中密封膜施工方法
CN105672244A (zh) * 2016-01-19 2016-06-15 南通大学 用于加固软黏土地基的排水装置、系统及处理方法
CN105672244B (zh) * 2016-01-19 2017-06-23 南通大学 用于加固软黏土地基的排水装置、系统及处理方法
CN106545003A (zh) * 2016-11-25 2017-03-29 中交第二航务工程局有限公司 真空降水井逆作法加固吹填土的施工方法
CN106545003B (zh) * 2016-11-25 2018-08-14 中交第二航务工程局有限公司 真空降水井逆作法加固吹填土的施工方法
CN109944230A (zh) * 2019-04-30 2019-06-28 交通运输部天津水运工程科学研究所 一种软土固结排水装置
CN111535293A (zh) * 2020-03-05 2020-08-14 东南大学 一种低位降水真空联合堆载预压加固深厚软基方法及系统
CN112176806A (zh) * 2020-10-16 2021-01-05 于胜泉 稳定型道路软基处理方法以及配套的软基处理施工系统
CN112176806B (zh) * 2020-10-16 2021-10-29 于胜泉 稳定型道路软基处理方法以及配套的软基处理施工系统
WO2022095291A1 (zh) * 2020-11-09 2022-05-12 中国海洋大学 一种用于加固软弱土体的双螺旋管、注浆成桩设备及其施工方法
US11525231B2 (en) 2020-11-09 2022-12-13 Ocean University Of China Double-spiral-tube structure, grouting and pile forming device and construction method for strengthening soft soil

Also Published As

Publication number Publication date
CN102330424B (zh) 2013-11-13

Similar Documents

Publication Publication Date Title
CN102330424B (zh) 一种吹填软土的复式真空管井真空预压加固方法
CN102587352B (zh) 一种软土地基的热排水固结处理装置及其处理方法
CN101831903B (zh) 一种软地基处理方法
CN104120710B (zh) 一种真空预压联合吹填泥浆的软基加固处理方法
CN105239555A (zh) 一种袋装浆固碎石桩联合真空预压处理软土地基的方法
CN105064383B (zh) 插管式负压空气射流深井降水装置
CN102051875B (zh) 一种加固深层淤泥地基的方法
CN106677158B (zh) 一种新近吹填淤泥浅表层快速均匀处理方法及结构
CN201534973U (zh) 预埋式真空固结堆场
CN105453748A (zh) 一种立体全封闭绿化真空排碱装置及其使用方法
CN103215945B (zh) 非均质场地软土地基立体式组合动力排水固结系统和方法
CN107806079A (zh) 一种软土地基加固装置
CN201214787Y (zh) 刚性排水桩
CN204370403U (zh) 一种间歇式真空预压装置
CN202595725U (zh) 真空预压软土地基处理用的排水结构
CN104762951B (zh) 二次直排式真空预压处理新吹填淤泥造陆的施工方法
CN102912787B (zh) 粉细砂垫层滤管加密的真空预压方法
CN206512698U (zh) 一种新近吹填淤泥浅表层快速均匀处理结构
CN105970909B (zh) 井点塑排真空预压渗流固结联合降水预压动力固结法
CN105926577B (zh) 真空预压渗流固结法
CN205348204U (zh) 一种轻型井点降水系统
CN209760220U (zh) 一种用于新近吹填土再加固系统
CN106013046A (zh) 变应力路径井点塑排真空预压渗流固结分级加载法
CN105862714A (zh) 软土地基覆水型一体式井点塑排真空系统
CN203213129U (zh) 可控逆止式排水器

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 310020 Jianggan District, Zhejiang Province, Fung Road, No. 50 East Road, No.

Applicant after: Zhejiang Guangchuan Engineering Consulting Co., Ltd.

Applicant after: Zhejiang Institute of Hydraulics & Estuary

Address before: 310020 Jianggan District, Zhejiang Province, Fung Road, No. 50 East Road, No.

Applicant before: Zhejiang Guangchuan Consulting Co., Ltd.

Applicant before: Zhejiang Institute of Hydraulics & Estuary

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: ZHEJIANG GUANGCHUAN CONSULTING CO., LTD. TO: ZHEJIANG INSTITUTE OF HYDRAULICS + ESTUARY

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20131113

Termination date: 20200705

CF01 Termination of patent right due to non-payment of annual fee