CN102305705B CN 201110148243 CN201110148243A CN102305705B CN 102305705 B CN102305705 B CN 102305705B CN 201110148243 CN201110148243 CN 201110148243 CN 201110148243 A CN201110148243 A CN 201110148243A CN 102305705 B CN102305705 B CN 102305705B
Authority
CN
China
Prior art keywords
electric hoist
counterweight
multiproject
test bed
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201110148243
Other languages
Chinese (zh)
Other versions
CN102305705A (en
Inventor
陶成
殷学文
巫波
陆忠华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Special Equipment Safety Supervision Inspection Institute of Jiangsu Province
Original Assignee
Special Equipment Safety Supervision Inspection Institute of Jiangsu Province Wuxi Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Special Equipment Safety Supervision Inspection Institute of Jiangsu Province Wuxi Branch filed Critical Special Equipment Safety Supervision Inspection Institute of Jiangsu Province Wuxi Branch
Priority to CN 201110148243 priority Critical patent/CN102305705B/en
Publication of CN102305705A publication Critical patent/CN102305705A/en
Application granted granted Critical
Publication of CN102305705B publication Critical patent/CN102305705B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Testing Of Devices, Machine Parts, Or Other Structures Thereof (AREA)

Abstract

The invention relates to a multiproject electric hoist test bed which comprises two parallel upper beams, wherein the two parallel upper beams are fixed to a vertical column; two longitudinal rails are suspended and fixed under the two upper beams; one end of the trail is provided with a fixed pulley; a balance weight is connected to an electric hoist by the fixed pulley; and one rail is a light rail, and the other rail is a heavy rail. The fixed pulley changes the weight of the balance weight into the resistance of the electric hoist in the running direction, which is used for the climbing test of the electric hoist; and the two rails with different specifications are suspended under the upper beams by adopting a double-suspension technology, the electric hoist with different tonnages is met, and the equipment investment is reduced. The invention has simple and compact structure, is reasonable, can cover various types of electric hoists below 32 tonnages and improves the use efficiency of the test bed.

Description

Multiproject electric hoist test bed
Technical field
The present invention relates to the test unit of electric block, specifically a kind of Multiproject electric hoist test bed.
Background technology
Electric block is as a kind of easy hoisting machinery, because it has compact conformation, little from heavy and light, overall dimensions, and advantages such as simple to operate, applicability is strong and day by day be subject to user's favor have been widely used in the fields such as port and pier, metallurgical manufacturing, building industry, electric power facility, mining excavation and general manufacturing at present.The safe operation of electric block is that production operation normally moves, the assurance of equipment property safety and operating personnel's personal safety, is a important step in electric block research and development and the factory inspection process for the usability of electric block and the compbined test evaluation in life-span therefore.
Present test platform generally can only be realized the partial test project of electric block, and great majority can not be finished hill climbing test or durability test.
Summary of the invention
The present invention is directed to above-mentioned the deficiencies in the prior art, a kind of Multiproject electric hoist test bed is provided, this testing table can satisfy the examination requirements of electric block entry.
According to technical scheme provided by the invention, a kind of Multiproject electric hoist test bed, comprise two parallel entablatures that are fixed on the column, hang under two described entablatures and be fixed with longitudinally track, one end of described track is provided with fixed pulley, and the counterweight counterweight is connected on the electric block by described fixed pulley.
The two ends of described track are provided with dismountable block.
Described track has two, is respectively a light rail and a heavy rail.
Hang between two described entablatures and be fixed with operating corridor, an end of described operating corridor links to each other with ground by stair.
Described operating corridor is between two described tracks.
Also be provided with at least between two described entablatures other one link to each other with described track pass through the entablature that column fixes on the ground.
Be provided with the counterweight shallow hole on the ground between the described column, be provided with the counterweight dell in the described counterweight shallow hole.
The column spacing in described dell district is less than the column spacing in described shallow hole district.
The direction that hoists of described electric block is provided with displacement sensor for pull rope.
The trolley travelling direction of described electric block is provided with two light sensation sensors.
Compared with the prior art the present invention has the following advantages: the present invention becomes the gravity of counterweight counterweight by fixed pulley the resistance of electric block traffic direction, is used for the hill climbing test of electric block; The present invention disposes two kinds of counterweight melt pits of the depth, and shallow hole is used for conventional test, and dell is used for life-span and lifting altitude test, has reduced the ground input; The present invention adopts two Suspension Techniques, hangs the track of two kinds of different sizes under entablature, when satisfying the electric block of different tonnages, has reduced equipment investment.The present invention is simple, compact and reasonable for structure, can cover each pattern electric block below 32 tons, has improved the service efficiency of testing table.
Description of drawings
Fig. 1 is structural representation of the present invention.
Fig. 2 is the left view of Fig. 1.
Embodiment
The present invention is further illustrated below in conjunction with the embodiment in the accompanying drawing.
Among Fig. 1, Fig. 2, comprise ground 1, column 2, entablature 3, heavy rail 4, light rail 5, counterweight counterweight 6, fixed pulley 7, operating corridor 8, stair 9, shallow hole 10, dell 11 etc.
As shown in Figure 1 and Figure 2, the present invention is a kind of Multiproject electric hoist test bed, mainly comprises column 2 and entablature 3.Column 2 has four at least, is arranged in the both sides of length direction of rectangle pilot region and fixing with ground 1.Be fixed with respectively an entablature 3 on two root posts 2 of each side, these two entablatures 3 be arranged in parallel.3 times suspensions of two entablatures are fixed with longitudinally track, and an end of track is provided with fixed pulley 7, and counterweight counterweight 6 is connected on the electric block by fixed pulley 7.The gravity of counterweight counterweight 6 is become the resistance of electric block traffic direction by fixed pulley 7, be used for finishing hill climbing test.
Entablature adopts two suspension design for 3 times, and the track of suspension has two, is the track of different model specification, is respectively a light rail 5 and a heavy rail 4.Two tracks can satisfy the electric block test of different tonnages, have reduced equipment investment, and light rail 5 satisfies the electric block test below 5 tons, and heavy rail 4 satisfies the electric block test below 32 tons.
The two ends of track are provided with dismountable block, not slippage from the track when guaranteeing the smooth installation of electric block and test.
Hang between two entablatures 3 and be fixed with operating corridor 8, an end of operating corridor 8 links to each other with ground by stair 9, makes things convenient for the staff to overhaul.Operating corridor 8 is preferably between two tracks.
Also be provided with at least between two entablatures 3 other one link to each other with track pass through the entablature 3 that column 2 fixes on the ground.Improve the rigidity of test tracks by the number that increases entablature 3 and column 2.
Ground between column 2 is provided with the counterweight melt pit, and the counterweight melt pit divides shallow hole 10 and dell 11, and dell 11 is positioned at shallow hole 10.Shallow hole 10 is used for conventional test, and dell 11 is used for life-span and lifting altitude test, and counterweight counterweight 6 places melt pit, has reduced the ground input.Dell 11 districts will be used for durability test, so the column spacing in dell 11 districts is less than the column spacing in shallow hole 10 districts.
The direction that hoists of electric block is provided with displacement sensor for pull rope.By displacement sensor for pull rope, obtain in real time the relation of displacement and time, can calculate fast lifting velocity and braking glide quantity.
The trolley travelling direction of electric block is provided with two light sensation sensors.Measure mistiming and the distance of the light sensation sensor travelling speed that can fast calculate dolly of dolly by two light sensation sensors.
Testing table provided by the invention can select different counterweights to carry out the test of each pattern electric block below 32 tons, can realize the test such as lifting capacity, pulling speed, travelling speed, braking glide quantity, zero load, dynamic load, static load, climbing, life-span of electric block.The present invention is simple, compact and reasonable for structure, can cover each pattern electric block below 32 tons, has improved the service efficiency of testing table.

Claims (4)

1. Multiproject electric hoist test bed, comprise the two parallel entablatures (3) that are fixed on the column (2), the lower suspension of two described entablatures (3) is fixed with longitudinally track, one end of described track is provided with fixed pulley (7), and counterweight counterweight (6) is connected on the electric block by described fixed pulley (7);
The two ends of described track are provided with dismountable block; Described track has two, is respectively a light rail (5) and a heavy rail (4);
Hang between described two described entablatures (3) and be fixed with operating corridor (8), an end of described operating corridor (8) links to each other with ground by stair (9); Described operating corridor (8) is between two described tracks;
Be provided with counterweight shallow hole (10) on the ground between the described column (2), be provided with counterweight dell (11) in the described counterweight shallow hole (10).
2. according to Multiproject electric hoist test bed claimed in claim 1, it is characterized in that: also be provided with at least between two described entablatures (3) other one link to each other with described track pass through the entablature (3) that column (2) fixes on the ground.
3. according to Multiproject electric hoist test bed claimed in claim 1, it is characterized in that: the column spacing in described dell (11) district is less than the column spacing in described shallow hole (10) district.
4. according to Multiproject electric hoist test bed claimed in claim 1, it is characterized in that: the direction that hoists of described electric block is provided with displacement sensor for pull rope.
CN 201110148243 2011-06-02 2011-06-02 Multiproject electric hoist test bed Expired - Fee Related CN102305705B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110148243 CN102305705B (en) 2011-06-02 2011-06-02 Multiproject electric hoist test bed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110148243 CN102305705B (en) 2011-06-02 2011-06-02 Multiproject electric hoist test bed

Publications (2)

Publication Number Publication Date
CN102305705A CN102305705A (en) 2012-01-04
CN102305705B true CN102305705B (en) 2013-05-01

Family

ID=45379587

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110148243 Expired - Fee Related CN102305705B (en) 2011-06-02 2011-06-02 Multiproject electric hoist test bed

Country Status (1)

Country Link
CN (1) CN102305705B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108765978A (en) * 2018-04-27 2018-11-06 榛硕(武汉)智能科技有限公司 A kind of novel speed early warning system
CN108765980A (en) * 2018-04-27 2018-11-06 榛硕(武汉)智能科技有限公司 A kind of vehicle overspeed warning device and method
CN111537829B (en) * 2020-06-05 2024-08-20 山西省工程机械有限公司 Quick test bench of electric block

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2173230Y (en) * 1993-09-14 1994-08-03 青州市机械设备制修厂 Fixed vertical column rotary arm carne
JP2948545B2 (en) * 1996-12-20 1999-09-13 株式会社ピー・エス Loading test equipment
CN201169512Y (en) * 2007-12-25 2008-12-24 胡建国 Clamp sling special for mounting electric hoist
CN101746593A (en) * 2008-12-09 2010-06-23 沈阳矿山机械有限公司 Heavy-hammer tower vehicle-type tension device
CN201583418U (en) * 2009-12-28 2010-09-15 天津津起起重设备有限公司 Electric hoist test bench
CN201716198U (en) * 2010-05-26 2011-01-19 卫华集团有限公司 Electric hoist test auxiliary device and test equipment using same
CN201852710U (en) * 2010-10-20 2011-06-01 北京起重运输机械设计研究院 Hoisting mechanism test bench
CN202092883U (en) * 2011-06-02 2011-12-28 江苏省特种设备安全监督检验研究院无锡分院 Multi-project electric hoist test stand

Also Published As

Publication number Publication date
CN102305705A (en) 2012-01-04

Similar Documents

Publication Publication Date Title
CN201753436U (en) Detachable lift type bridge inspection vehicle
CN105000482B (en) Tower crane with walking mechanism
CN202092883U (en) Multi-project electric hoist test stand
CN201053106Y (en) Bridge detection and maintenance device
CN104477736A (en) Shaft elevator installation method
CN201376848Y (en) Large-scale double-tower automatic-elevation hoisting equipment
CN105277353A (en) A high-altitude lifting basket type machine safety lock testing experiment table and testing method
CN102305705B (en) Multiproject electric hoist test bed
CN102323100B (en) Integrated trolley type electric hoist test stand
CN201990928U (en) Pontoon pier steel approach bridge lifting device
CN206359150U (en) A kind of hanging basket system
CN103306218A (en) Bottom width overhaul hanging basket of bridge
CN205873594U (en) Special construction elevator of cooling tower section of thick bamboo wall
CN202092861U (en) Electric cucurbit testing stand of integrated dolly type
CN203112355U (en) Garbage bridge grabbing crane
CN110160817A (en) Electric block tests reinforcement poise system and its application method
CN203534840U (en) Tower-type air winch performance test and experiment platform
CN202465109U (en) Motor-driven double-beam grab bucket gantry crane
CN202390106U (en) Lifting hook portal crane easy to maintain
CN105173983A (en) People and goods dual-purpose vertical-transportation building construction elevator
CN106012854B (en) The transporting equipment of prefabricated assembled overpass bridge plate
Sakurikar et al. Review of overhead crane and analysis of components depending on span
CN103196688A (en) Lever type dynamic load test platform with loads adjustable
CN114835025A (en) Manned carrying vertical shaft elevator
CN102913016B (en) Ground, subway train lowering or hoisting gear

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20161216

Address after: 210000 Nanjing, Gulou District, Jiangsu, No. 107 Main Street, grassland, building, Longjiang

Patentee after: SPECIAL EQUIPMENT SAFETY SUPERVISION INSPECTION INSTITUTE OF JIANGSU PROVINCE

Address before: 214171 Huishan Economic Development Zone, Jiangsu Province, No. 330 new road, No.

Patentee before: Jiangsu Province Special Equipment Safety Supervision Inspection Institute, Branch of Wuxi

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130501