CN102296866A - 复合材料输电杆塔横担和杆体的安装连接方法 - Google Patents

复合材料输电杆塔横担和杆体的安装连接方法 Download PDF

Info

Publication number
CN102296866A
CN102296866A CN2011101436758A CN201110143675A CN102296866A CN 102296866 A CN102296866 A CN 102296866A CN 2011101436758 A CN2011101436758 A CN 2011101436758A CN 201110143675 A CN201110143675 A CN 201110143675A CN 102296866 A CN102296866 A CN 102296866A
Authority
CN
China
Prior art keywords
composite material
metal
arm
cross
rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011101436758A
Other languages
English (en)
Other versions
CN102296866B (zh
Inventor
王钧
蔡浩鹏
杨小利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University of Technology WUT
Original Assignee
Wuhan University of Technology WUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University of Technology WUT filed Critical Wuhan University of Technology WUT
Priority to CN 201110143675 priority Critical patent/CN102296866B/zh
Publication of CN102296866A publication Critical patent/CN102296866A/zh
Application granted granted Critical
Publication of CN102296866B publication Critical patent/CN102296866B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)
  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

一种复合材料输电杆塔横担和杆体的安装连接方法,该方法使用金属连接部件(1)、带金属法兰盘(4)的复合材料杆体(2)、中间粘接金属衬套(5)的复合材料横担(3),所述的金属连接部件是上下两端为金属法兰盘的短管,中间有通孔,侧面开有螺栓孔(6),在所述的复合材料杆体和复合材料横担的连接部位金属连接部件分断杆塔,现场安装时,将金属连接部件的上下两端金属法兰盘分别与杆塔上下的复合材料杆体所带金属法兰盘通过螺栓固定,中间粘接金属衬套的复合材料横担从金属连接部件中间通孔穿过,横担不分节,然后螺栓穿过侧面螺栓孔固定金属衬套。本安装连接方法保证复合材料横担为一个整体,且横担安装方便,可靠性高。

Description

复合材料输电杆塔横担和杆体的安装连接方法
技术领域:
本发明涉及一种用于复合材料输电杆塔横担和杆体的安装连接方法,本安装连接结构设计横担安装方便,可靠性高。
背景知识:
目前,国内外架空输电线路中,110kV以下使用的输电杆主要有木质杆、钢杆、混凝土杆和复合材料杆。由于横担承担载荷较小,左右回路横担通常是一个整体,通过螺栓或抱箍紧固安装在杆体侧面,如专利CN 1019536B采用U形抱箍安装固定。在110KV及以上等级的杆式输电线路中,多采用节段式钢管杆和钢制横担。由于横担承担载荷较大,左右回路横担通常独立制备,横担通过螺栓分别和杆体安装固定。
目前,复合材料杆塔和复合材料横担也开始应用在110KV及以上等级的杆式输电线路中,其横担和杆体连接的可靠性成为一个需要考虑的重要因素。本发明提供了一种复合材料输电杆塔横担和杆体的安装连接结构,在杆体和横担的连接部位,设计金属连接部件分断杆体,其主要特点在于:输电杆塔左右回路复合材料横担为一个整体且横担从杆体中间穿过固定,安装方便,可靠性高。
发明内容:
本发明的目的是为了满足复合材料输电杆塔横担和杆体安装方便及可靠性的要求,提供一种复合材料输电杆塔横担和杆体的安装连接方法。
本发明目的通过以下技术方案来达到:
一种复合材料输电杆塔横担和杆体的安装连接方法,该方法使用金属连接部件、带金属法兰盘的复合材料杆体、中间粘接金属衬套的复合材料横担,所述的金属连接部件是上下两端为金属法兰盘的短管,中间有通孔,侧面开有螺栓孔,在复合材料杆体和复合材料横担的连接部位金属连接部件分断杆塔,现场安装时,将金属连接部件的上下两端金属法兰盘分别与杆塔上下的复合材料杆体所带金属法兰盘通过螺栓固定,中间粘接金属衬套的复合材料横担从金属连接部件中间通孔穿过,横担不分节,然后螺栓穿过侧面螺栓孔固定金属衬套。
中间粘接金属衬套的复合材料横担从金属连接部件中间通孔穿过,然后螺栓穿过侧面螺栓孔安装固定。
本发明的技术方案中,输电杆塔的复合材料杆体分段制备,复合材料杆体制备好后,事先插入金属法兰盘中并粘结补强。
本发明的技术方案中,复合材料横担外形为圆形、矩形或梯形,采用手工、缠绕、拉挤或拉绕工艺制备,制备好后事先中间部位粘接金属衬套,并在安装部位侧壁制备螺栓孔。
本发明的技术方案中,金属衬套是与复合材料横担外形相同的圆形、矩形或梯形,或者是两块金属包于复合材料横担外。
本发明的技术方案中,金属连接部件的中间通孔,其形状和复合材料横担中间部位粘接的金属衬套截面一致。
本发明的技术方案中,结构上,左右回路复合材料横担为一个整体且横担从杆体中间穿过。
用本发明安装连接方法的复合材料杆塔和采用传统连接的复合材料杆塔相比,其最大特点是:横担和杆体安装方便,同时横担为一整体从中间穿过杆体,结构可靠性高。
附图说明:
图1为本发明的结构示意图。
图2为本发明结构局部剖视图。
图3为金属连接部件示意图。
图4为本发明实施例1的结构示意图。
图5为本发明实施例2的结构示意图。
其中:1-金属连接部件;2-复合材料杆体;3-复合材料横担;4-金属法兰盘;5-金属衬套;6-侧向螺栓孔。
具体实施方式:
下面结合附图和具体实施例对本发明进一步说明:
实施例1:
某110KV复合材料双回路直线塔,塔体为复合材料分段锥管,采用缠绕工艺制备,在工厂内和金属连接部件1连结的一头粘接金属法兰4;地线、上导线、中导线和下导线横担为圆形截面,由复合材料采用拉绕工艺制备,中间粘结金属衬套5。金属连接部件上下两端有法兰,中间为圆孔。现场安装时,金属连接部件和上下复合材料杆体通过法兰盘螺栓安装连接,而复合材料横担从金属连接部件中间穿过,然后螺栓穿过侧面螺栓孔6安装固定。其横担和复合材料塔体连接结构如图4所示。
实施例2:
某220KV复合材料双回路直线塔,地线、上导线、中导线和下导线横担为矩形截面,采用拉挤工艺制备,中间粘结金属衬套4;塔体为复合材料分段锥管,采用缠绕工艺制备,其中,仅下段复合材料塔体和金属连接部件连结的一头在工厂事先粘接好金属法兰;金属连接部件中间为矩形孔,和横担截面尺寸一致,上端为圆管段,在工厂直接和上段复合材料杆粘结在一起。现场安装时,金属连接部件下端法兰和下复合材料杆体通过法兰盘螺栓安装连接,而复合材料横担从金属连接部件中间孔穿过,然后螺栓穿过侧面螺栓孔安装固定。其横担和复合材料塔体连接结构如图5所示。
虽然在附图及实施例中已经描述了一些示例性实施方案,但是这些实施方案只是对广义发明进行举例说明,而不是对它进行限定,本发明并不限于所示和所述的具体结构,因为本领域普通技术人员很容易想到其它各种变型。

Claims (5)

1.一种复合材料输电杆塔横担和杆体的安装连接方法,其特征在于:该方法使用金属连接部件(1)、带金属法兰盘(4)的复合材料杆体(2)、中间粘接金属衬套(5)的复合材料横担(3),所述的金属连接部件(1)是上下两端为金属法兰盘的短管,中间有通孔,侧面开有螺栓孔(6),在复合材料杆体(1)和复合材料横担(3)的连接部位金属连接部件(1)分断杆塔,现场安装时,将金属连接部件(1)的上下两端金属法兰盘分别与杆塔上下的复合材料杆体(2)所带金属法兰盘(4)通过螺栓固定,中间粘接金属衬套(5)的复合材料横担(3)从金属连接部件(1)中间通孔穿过,横担不分节,然后螺栓穿过侧面螺栓孔(6)固定金属衬套(5)。
2.根据权利要求1所述的复合材料输电杆塔横担和杆体的安装连接方法,其特征在于:所述的复合材料杆体(1)分段制备,复合材料杆体制备好后,事先插入金属法兰盘(4)中并粘结补强。
3.根据权利要求1所述的复合材料输电杆塔横担和杆体的安装连接方法,其特征在于:所述的复合材料横担(3)外形为圆形、矩形或梯形,采用手工、缠绕、拉挤或拉绕工艺制备,制备好后事先中间部位粘接金属衬套(5),并在安装部位侧壁制备螺栓孔。
4.根据权利要求1所述的复合材料输电杆塔横担和杆体的安装连接方法,其特征在于:所述的金属衬套(5)是与复合材料横担(3)外形相同的圆形、矩形或梯形,或者是两块金属包于复合材料横担(3)外。
5.根据权利要求1所述的复合材料输电杆塔横担和杆体的安装连接方法,其特征在于:所述的金属连接部件(1)的中间通孔,其形状和复合材料横担(3)中间部位粘接的金属衬套(5)截面一致。
CN 201110143675 2011-05-31 2011-05-31 复合材料输电杆塔横担和杆体的安装连接方法 Expired - Fee Related CN102296866B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110143675 CN102296866B (zh) 2011-05-31 2011-05-31 复合材料输电杆塔横担和杆体的安装连接方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110143675 CN102296866B (zh) 2011-05-31 2011-05-31 复合材料输电杆塔横担和杆体的安装连接方法

Publications (2)

Publication Number Publication Date
CN102296866A true CN102296866A (zh) 2011-12-28
CN102296866B CN102296866B (zh) 2013-02-06

Family

ID=45357521

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110143675 Expired - Fee Related CN102296866B (zh) 2011-05-31 2011-05-31 复合材料输电杆塔横担和杆体的安装连接方法

Country Status (1)

Country Link
CN (1) CN102296866B (zh)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102979341A (zh) * 2012-11-15 2013-03-20 浙江永达电力实业股份有限公司 一种电杆
CN102979344A (zh) * 2012-11-15 2013-03-20 浙江永达电力实业股份有限公司 电杆连接装置
CN102979345A (zh) * 2012-11-15 2013-03-20 浙江永达电力实业股份有限公司 一种电杆
CN102979347A (zh) * 2012-12-24 2013-03-20 武汉理工大学 一种复合材料杆塔与爬梯支承座的连接结构
CN102979340A (zh) * 2012-11-15 2013-03-20 浙江永达电力实业股份有限公司 一种电杆连接装置
CN102995946A (zh) * 2012-11-21 2013-03-27 广东电网公司东莞供电局 一种输配电复合材料横担工装金具
CN103592180A (zh) * 2013-11-25 2014-02-19 国家电网公司 一种复合材料管轴压试验中构件夹持装置及其使用方法
CN105927632A (zh) * 2016-05-09 2016-09-07 华中科技大学 一种分段式复合材料电杆的连接装置及连接方法
NO20151112A1 (no) * 2015-09-01 2017-03-02 Statnett Sf Innfestingssystem for et langstrakt komposittelement, samt en høyspentmast med et slikt langstrakt komposittelement med gjennomgående åpninger og et spenningsfordelingselement.
WO2018009074A1 (en) * 2016-07-07 2018-01-11 Comrod As Overlying cross bar fastener
CN110924731A (zh) * 2019-12-13 2020-03-27 河南贝优特变压器有限公司 杆塔式综合配变台区
CN113700368A (zh) * 2021-08-11 2021-11-26 国网电力科学研究院武汉南瑞有限责任公司 一种门型复合材料电杆伸缩横梁组件及其组装方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3812668A1 (de) * 1988-04-15 1989-10-26 Siemens Ag Mastaufsatzleuchte
CN1042810A (zh) * 1988-11-15 1990-06-06 尤大千 低压玻璃钢架空电路横担
US5128648A (en) * 1990-01-22 1992-07-07 Brandi Frank J Line cutout for electrical distribution system
CN201574617U (zh) * 2009-12-21 2010-09-08 常熟风范电力设备股份有限公司 一种横担连接装置

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3812668A1 (de) * 1988-04-15 1989-10-26 Siemens Ag Mastaufsatzleuchte
DE3812668C2 (zh) * 1988-04-15 1992-01-30 Siemens Ag, 1000 Berlin Und 8000 Muenchen, De
CN1042810A (zh) * 1988-11-15 1990-06-06 尤大千 低压玻璃钢架空电路横担
US5128648A (en) * 1990-01-22 1992-07-07 Brandi Frank J Line cutout for electrical distribution system
CN201574617U (zh) * 2009-12-21 2010-09-08 常熟风范电力设备股份有限公司 一种横担连接装置

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102979344A (zh) * 2012-11-15 2013-03-20 浙江永达电力实业股份有限公司 电杆连接装置
CN102979345A (zh) * 2012-11-15 2013-03-20 浙江永达电力实业股份有限公司 一种电杆
CN102979341A (zh) * 2012-11-15 2013-03-20 浙江永达电力实业股份有限公司 一种电杆
CN102979340A (zh) * 2012-11-15 2013-03-20 浙江永达电力实业股份有限公司 一种电杆连接装置
CN102995946B (zh) * 2012-11-21 2015-02-11 广东电网公司东莞供电局 一种输配电复合材料横担工装金具
CN102995946A (zh) * 2012-11-21 2013-03-27 广东电网公司东莞供电局 一种输配电复合材料横担工装金具
CN102979347B (zh) * 2012-12-24 2015-04-08 武汉理工大学 一种复合材料杆塔与爬梯支承座的连接结构
CN102979347A (zh) * 2012-12-24 2013-03-20 武汉理工大学 一种复合材料杆塔与爬梯支承座的连接结构
CN103592180A (zh) * 2013-11-25 2014-02-19 国家电网公司 一种复合材料管轴压试验中构件夹持装置及其使用方法
NO20151112A1 (no) * 2015-09-01 2017-03-02 Statnett Sf Innfestingssystem for et langstrakt komposittelement, samt en høyspentmast med et slikt langstrakt komposittelement med gjennomgående åpninger og et spenningsfordelingselement.
NO343191B1 (no) * 2015-09-01 2018-11-26 Statnett Sf Innfestingssystem som infester et langstrakt komposittelement til en søyle som forløper gjennom en åpning i det langstrakte komposittelementet.
CN105927632A (zh) * 2016-05-09 2016-09-07 华中科技大学 一种分段式复合材料电杆的连接装置及连接方法
WO2018009074A1 (en) * 2016-07-07 2018-01-11 Comrod As Overlying cross bar fastener
US10781600B2 (en) 2016-07-07 2020-09-22 Comrod As Overlying cross bar fastener
CN110924731A (zh) * 2019-12-13 2020-03-27 河南贝优特变压器有限公司 杆塔式综合配变台区
CN113700368A (zh) * 2021-08-11 2021-11-26 国网电力科学研究院武汉南瑞有限责任公司 一种门型复合材料电杆伸缩横梁组件及其组装方法

Also Published As

Publication number Publication date
CN102296866B (zh) 2013-02-06

Similar Documents

Publication Publication Date Title
CN102296866B (zh) 复合材料输电杆塔横担和杆体的安装连接方法
CN203296450U (zh) 带横担连接点的混凝土杆
CN102839845B (zh) 一种复合材料杆塔节点连接装置
KR101028147B1 (ko) 송전변전 배전 강재 전신주 이음장치
CN205637783U (zh) 焊接型电杆加固装置
CN202055599U (zh) 一种带有工装连接件的复合材料杆塔
CN202202483U (zh) 防松自锚连接器
CN103614974B (zh) 钢筋混凝土拱壳桥体的预应力型钢加固体系
CN201329968Y (zh) 钢丝绳夹具
CN105586826A (zh) 一种混凝土系杆拱桥吊杆下锚端连接结构及其施工方法
CN203700976U (zh) 钢筋混凝土拱壳桥体的预应力型钢加固体系
CN204311794U (zh) 一种复合材料变电站构架
CN203175139U (zh) 一种新型u形拉线抱箍
CN206220625U (zh) 纤维增强复合材料输配电杆的连接结构
CN204081085U (zh) 箱形钢柱连接结构
KR20220002670U (ko) 전주용 완철밴드 어셈블리
CN205046523U (zh) 一种装配式水渠
CN209568573U (zh) 一种剪力墙体的新型加固结构
CN202535012U (zh) 音叉式防滑型预绞丝防振锤
CN202989786U (zh) 旧桥体外预应力加固结构
CN203160794U (zh) 一种新型输电线路杆塔
KR101420668B1 (ko) Phc 파일
CN202271866U (zh) 采用张弦梁结构固定接触网悬挂的方式
CN204356955U (zh) 一种装配式的组合楼板总成
CN205206116U (zh) 一种预应力楼板

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130206

Termination date: 20150531

EXPY Termination of patent right or utility model