CN102284515A CN2011102070274A CN201110207027A CN102284515A CN 102284515 A CN102284515 A CN 102284515A CN 2011102070274 A CN2011102070274 A CN 2011102070274A CN 201110207027 A CN201110207027 A CN 201110207027A CN 102284515 A CN102284515 A CN 102284515A
Authority
CN
China
Prior art keywords
blow tank
lifting
receiving hopper
lifting blow
lifting receiving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011102070274A
Other languages
Chinese (zh)
Other versions
CN102284515B (en
Inventor
何晓平
周贵禄
刘珂
杨鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SICHUAN SANZHOU SPECIAL STEEL PIPE CO Ltd
Original Assignee
SICHUAN SANZHOU SPECIAL STEEL PIPE CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUAN SANZHOU SPECIAL STEEL PIPE CO Ltd filed Critical SICHUAN SANZHOU SPECIAL STEEL PIPE CO Ltd
Priority to CN 201110207027 priority Critical patent/CN102284515B/en
Publication of CN102284515A publication Critical patent/CN102284515A/en
Application granted granted Critical
Publication of CN102284515B publication Critical patent/CN102284515B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Metal Rolling (AREA)

Abstract

The invention discloses an added lifting receiving hopper of a puncher, comprising at least three sections of lifting receiving hopper and a lifting receiving hopper base (4) which is connected with the sections of lifting receiving hopper; and the middle section (2) of the lifting receiving hopper is lifted up and down, ascends to be connected with a steel ingot (6), and descends to form a whole with the front section (1) of the lifting receiving hopper and the rear section (3) of the lifting receiving hopper. The invention provides the added sectional lifting receiving hopper of the puncher, wherein the middle section of the lifting receiving hoper ascends to receive the steel ingot which is transported by a ingot transportation trolley, descends to form the whole with the front section and the rear section, so that a blank is prevented from directly hitting the receiving hopper; blank size adjusting mechanisms are arranged in the front section and the rear section of the lifting receiving hopper and are used for adjusting blanks with different diameters, so that the blanks are on a fixed rolling centerline; and the added lifting receiving hopper of the puncher has the advantages that: the structure is simple, the equipment repair is convenient, the safety factor is high, a use process is simple, and equipment is not damaged when in use and the like.

Description

Punch is set up the lifting blow tank
Technical field
The present invention relates to a kind of punch and set up the lifting blow tank.
Background technology
At present, punch commonly used is the heaviest with blank to be 9 tons, and its continuous casting billet diameter is Φ 390 ~ 620 mm, punch blow tank commonly used is between two Hooks coupling universal couplings, influenced by operating mode, its equipment absolute altitude is lower than rolling centerline, and the conventional feeds method is that blank is delivered to the blow tank top by the ingot dolly, directly place on the blow tank, be subjected to effect of altitude, blank will directly be pounded on blow tank, cause device damage easily, Equipment Foundations are destroyed, and equipment such as possibly can't repair at problem; If directly blank is rolled into blow tank, can cause device damage equally, problems such as Equipment Foundations destruction; When blank diameter is inconsistent, the blank that does not meet blow tank charging size can't use, and have the blank selectivity and use, safety coefficient is low during use, and the use complexity causes device damage easily during use, Equipment Foundations are destroyed, and equipment such as can't repair at shortcoming.
Summary of the invention
Purpose of the present invention promptly is to overcome the deficiencies in the prior art, and a kind of safety coefficient height is provided, and use is easy, can not cause device damage during use, and punch easy to maintenance is set up the lifting blow tank.
The objective of the invention is to be achieved through the following technical solutions: punch is set up the lifting blow tank, the lifting blow tank base that it comprises at least three sections lifting blow tanks and links to each other with the lifting blow tank, the lifting blow tank is installed on the lifting blow tank base, three sections lifting blow tanks comprise lifting blow tank leading portion, lifting blow tank stage casing and lifting blow tank back segment, lifting blow tank stage casing includes hoist cylinder, the stage casing oscilaltion of lifting blow tank, the ingot dolly links to each other with steel ingot, rise on the lifting blow tank stage casing and link to each other the decline of lifting blow tank stage casing and lifting blow tank leading portion and integral body of lifting blow tank back segment formation with steel ingot; Described lifting blow tank stage casing range is 0~1200mm; All establish the blank size-regulating mechanism in described lifting blow tank leading portion and the lifting blow tank back segment.
The invention has the beneficial effects as follows: the invention provides a kind of segmented punch and set up the lifting blow tank; simple in structure; maintenance of equipment is convenient; rise on the lifting blow tank stage casing to catch and transport next steel ingot by the ingot dolly; descend with before; back segment forms an integral body; avoided blank directly to pound on blow tank; thereby protected equipment; be equipped with the blank size-regulating mechanism in lifting blow tank leading portion and the lifting blow tank back segment, lifting blow tank stage casing transported the blank of the different-diameter that comes and adjust, blank all is on the fixing rolling centerline; and blank is sent into punch by blank pushing machine; thereby fully use raw material, avoided waste of raw materials, have simple in structure; maintenance of equipment is convenient; the safety coefficient height, use is easy, can not cause advantages such as device damage during use.
Description of drawings
Fig. 1 is an ingot vehicle structure schematic diagram of the present invention.
Fig. 2 is a structural representation of the present invention.
Fig. 3 is M-M position profile figure among Fig. 2.
Fig. 4 is C-C position profile figure among Fig. 1, Fig. 2.
Among the figure, 1-lifting blow tank leading portion, 2-lifting blow tank stage casing, 3-lifting blow tank back segment, 4-lifting blow tank base, 5-hoist cylinder, 6-steel ingot, 7-ingot dolly.
The specific embodiment
The present invention will be further described below in conjunction with accompanying drawing:
As Fig. 1, Fig. 2, Fig. 3, shown in Figure 4, punch is set up the lifting blow tank, it comprises lifting blow tank leading portion 1, lifting blow tank stage casing 2 and lifting blow tank back segment 3, and the lifting blow tank base 4 that links to each other with the lifting blow tank, the lifting blow tank is installed on the lifting blow tank base 4, lifting blow tank stage casing 2 includes hoist cylinder 5,2 oscilaltions of lifting blow tank stage casing, ingot dolly 7 links to each other with steel ingot 6, rise and link to each other with steel ingot 6 in lifting blow tank stage casing 2, lifting blow tank stage casing 2 descends and lifting blow tank leading portion 1 and lifting blow tank back segment 3 form an integral body, the lifting interval in described lifting blow tank stage casing 2 is 0~1200mm, all establishes the blank size-regulating mechanism in described lifting blow tank leading portion 1 and the lifting blow tank back segment 3.
The course of work of the present invention: ingot dolly 7 is clamped heated steel ingot 6, rise to predetermined altitude, be transported to lifting blow tank top by ingot dolly 7, rise in lifting blow tank stage casing 2, the ingot dolly places steel ingot 6 on the lifting blow tank stage casing 2, lifting blow tank stage casing 2 drops to the height that lifting blow tank leading portion 1 and lifting blow tank back segment 3 are adjusted, three sections blow tanks form the blow tank of an integral body, all establish the blank size-regulating mechanism in lifting blow tank leading portion 1 and the lifting blow tank back segment 3, the blank that lifting blow tank stage casing 2 is transported the different-diameter that comes carries out size adjustment, blank is on the fixing rolling centerline, and by blank pushing machine just blank send into punch.

Claims (3)

1. punch is set up the lifting blow tank, it is characterized in that: the lifting blow tank base (4) that it comprises at least three sections lifting blow tanks and links to each other with the lifting blow tank, the lifting blow tank is installed on the lifting blow tank base (4), three sections lifting blow tanks comprise lifting blow tank leading portion (1), lifting blow tank stage casing (2) and lifting blow tank back segment (3), lifting blow tank stage casing (2) includes hoist cylinder (5), lifting blow tank stage casing (2) oscilaltion, ingot dolly (7) links to each other with steel ingot (6), rise and link to each other with steel ingot (6) in lifting blow tank stage casing (2), lifting blow tank stage casing (2) descends and lifting blow tank leading portion (1) and lifting blow tank back segment (3) form an integral body.
2. punch according to claim 1 is set up the lifting blow tank, it is characterized in that: lifting interval, described lifting blow tank stage casing (2) is 0~1200mm.
3. punch according to claim 1 is set up the lifting blow tank, it is characterized in that: all establish the blank size-regulating mechanism in described lifting blow tank leading portion (1) and the lifting blow tank back segment (3).
CN 201110207027 2011-07-22 2011-07-22 Added lifting receiving hopper of puncher Active CN102284515B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110207027 CN102284515B (en) 2011-07-22 2011-07-22 Added lifting receiving hopper of puncher

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110207027 CN102284515B (en) 2011-07-22 2011-07-22 Added lifting receiving hopper of puncher

Publications (2)

Publication Number Publication Date
CN102284515A true CN102284515A (en) 2011-12-21
CN102284515B CN102284515B (en) 2013-06-26

Family

ID=45331421

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110207027 Active CN102284515B (en) 2011-07-22 2011-07-22 Added lifting receiving hopper of puncher

Country Status (1)

Country Link
CN (1) CN102284515B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2138349C1 (en) * 1998-05-13 1999-09-27 Открытое акционерное общество "Северсталь" Lifting table
CN101049611A (en) * 2007-05-16 2007-10-10 太原市通泽成套设备有限公司 Working front desk of piercing mill of seamless steel tube
CN201220242Y (en) * 2008-07-02 2009-04-15 中冶东方工程技术有限公司 Heavy caliber seamless steel pipe diagonal rolling reeling pierced billet pre-rotation guide disc apparatus
KR20090103583A (en) * 2008-03-28 2009-10-01 현대제철 주식회사 Strip moving roller table
CN101658874A (en) * 2009-09-15 2010-03-03 太原通泽重工有限公司 Multifunctional reeling mill foreground
CN201455438U (en) * 2009-07-10 2010-05-12 中色科技股份有限公司 Aluminum ingot saw cutting machine roller way with material receiving decks
CN201482804U (en) * 2009-08-12 2010-05-26 张家港恒立机械有限公司 Loading device
CN201625664U (en) * 2010-04-08 2010-11-10 重庆赛迪工业炉有限公司 Hydraulic lifting device
CN202185459U (en) * 2011-07-22 2012-04-11 四川三洲特种钢管有限公司 Lifting receiving groove added on perforator

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2138349C1 (en) * 1998-05-13 1999-09-27 Открытое акционерное общество "Северсталь" Lifting table
CN101049611A (en) * 2007-05-16 2007-10-10 太原市通泽成套设备有限公司 Working front desk of piercing mill of seamless steel tube
KR20090103583A (en) * 2008-03-28 2009-10-01 현대제철 주식회사 Strip moving roller table
CN201220242Y (en) * 2008-07-02 2009-04-15 中冶东方工程技术有限公司 Heavy caliber seamless steel pipe diagonal rolling reeling pierced billet pre-rotation guide disc apparatus
CN201455438U (en) * 2009-07-10 2010-05-12 中色科技股份有限公司 Aluminum ingot saw cutting machine roller way with material receiving decks
CN201482804U (en) * 2009-08-12 2010-05-26 张家港恒立机械有限公司 Loading device
CN101658874A (en) * 2009-09-15 2010-03-03 太原通泽重工有限公司 Multifunctional reeling mill foreground
CN201625664U (en) * 2010-04-08 2010-11-10 重庆赛迪工业炉有限公司 Hydraulic lifting device
CN202185459U (en) * 2011-07-22 2012-04-11 四川三洲特种钢管有限公司 Lifting receiving groove added on perforator

Also Published As

Publication number Publication date
CN102284515B (en) 2013-06-26

Similar Documents

Publication Publication Date Title
CN107138625A (en) A kind of die holder more changing device and its replacing options
CN206966454U (en) A kind of die holder more changing device
CN202185459U (en) Lifting receiving groove added on perforator
CN102284515B (en) Added lifting receiving hopper of puncher
CN206810994U (en) Diel erecting device
CN107671124A (en) A kind of replacing options of large-scale AGC hydraulic cylinders
CN208604586U (en) Large-scale headstock gear sunpender pitman shaft, which is worn, moves back shaft device
CN202963441U (en) Automatic travelling pouring device
CN201951962U (en) Automatically elevated car door conveying device
CN204661790U (en) One effectively can be corrected steel billet and to be dispelled the heat the hot cog transferring device of diastrophic steel billet
CN204639086U (en) The plate blank conveying device that a kind of track is variable
CN202398621U (en) Automatic lifting mechanism for flange ring rolling mill core roller
CN104785350B (en) Method for disassembling lower milling plate of medium-speed coal mill
CN106583542B (en) A kind of panel beating blanking changes into type automatic Transition system
CN103658435A (en) Mold testing blanking production line for mold testing pressure machine
CN217165812U (en) Device for rapidly processing roll breakage of finishing mill
CN202361810U (en) Plate blank conveying device shared by stepping beam-type heating furnace and push-type heating furnace
CN204517590U (en) Penetrate rotor device taken out by horizontal machine
CN102199679A (en) Construction method for tuyere
CN203459434U (en) Automatic lifting device for water draining plates
CN206794373U (en) A kind of Coil Box format roll deflector apron device
CN204771413U (en) Dismantle device of jumbo size tooth coupling
CN203946557U (en) A kind of shot-blasting machine with belt for lifting machine break detector apparatus
CN216105568U (en) Roll collar lifting frame of high-speed wire mill
CN202829356U (en) Safe hoisting mechanism for edge coiling and flanging of steel cylinder bell and spigot of PCCP (Pre-stressed Concrete Cylinder Pipe) water conveying pipeline

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20111221

Assignee: SICHUAN SANZHONG SCMP NUCLEAR EQUIPMENT MANUFACTURE Inc.

Assignor: SICHUAN SANZHOU SPECIAL STEEL PIPE Co.,Ltd.

Contract record no.: 2014510000086

Denomination of invention: Added lifting receiving hopper of puncher

Granted publication date: 20130626

License type: Exclusive License

Record date: 20140722

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model
PP01 Preservation of patent right
PP01 Preservation of patent right

Effective date of registration: 20180709

Granted publication date: 20130626

PD01 Discharge of preservation of patent
PD01 Discharge of preservation of patent

Date of cancellation: 20210709

Granted publication date: 20130626

DD01 Delivery of document by public notice
DD01 Delivery of document by public notice

Addressee: Fan Rong

Document name: Notice of termination of proceedings

PP01 Preservation of patent right
PP01 Preservation of patent right

Effective date of registration: 20231127

Granted publication date: 20130626