CN102261936A - 高加危急疏水泄漏流量确定方法 - Google Patents

高加危急疏水泄漏流量确定方法 Download PDF

Info

Publication number
CN102261936A
CN102261936A CN 201110158100 CN201110158100A CN102261936A CN 102261936 A CN102261936 A CN 102261936A CN 201110158100 CN201110158100 CN 201110158100 CN 201110158100 A CN201110158100 A CN 201110158100A CN 102261936 A CN102261936 A CN 102261936A
Authority
CN
China
Prior art keywords
flow
height
adds
flow rate
hydrophobic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201110158100
Other languages
English (en)
Other versions
CN102261936B (zh
Inventor
丁俊齐
郑威
郝玉振
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Original Assignee
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd filed Critical Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Priority to CN2011101581003A priority Critical patent/CN102261936B/zh
Publication of CN102261936A publication Critical patent/CN102261936A/zh
Application granted granted Critical
Publication of CN102261936B publication Critical patent/CN102261936B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Examining Or Testing Airtightness (AREA)

Abstract

本发明公开了一种高加危急疏水泄漏流量确定方法。步骤为:1)将现场高加危急疏水手动门关闭,保证高加危急疏水不泄漏,然后以新加装的ASME标准凝结水流量喷嘴测量出的流量为基准,通过#1GJ-#3GJ三个高加疏水和除氧器热平衡计算出给水流量;2)用实际测量的主凝结水流量为基准计算出给水流量,用计算出的给水流量校核现场给水流量喷嘴测量出的给水流量,确定出现场给水流量测量偏差;3)保持机组在高加危急疏水手动门不关闭的状态下重新进行测量,通过现场给水流量喷嘴测量出的给水流量和其测量偏差,确定出该状态下的实际给水流量;4)用实测的凝结水流量和修正后的给水流量为基准,通过三个高加疏水和除氧器热平衡迭代计算出高加危急疏水泄漏量。

Description

高加危急疏水泄漏流量确定方法
技术领域
本发明涉及一种高加危急疏水泄漏流量确定方法。
背景技术
在对300MW机组性能考核试验时,常发现机组存在高加危急疏水泄漏。高加疏水正常流程应为:#1高加疏水至#2高加疏水,#2高加疏水至#3高加疏水,#3高加疏水至除氧器,而危急疏水泄漏将直接通过疏水扩容器排至凝汽器,不但使二抽、三抽、四抽抽汽量增加,同时使凝汽器热负荷增加,对机组的经济性影响较大。由于泄漏量无法直接进行测量,因此也无法分析该泄漏量在机组实际运行过程中对机组经济性的影响,也无法分析其对试验结果的影响,不能给电厂提出确定的整改建议。
发明内容
本发明的目的就是为解决上述问题,提供一种高加危急疏水泄漏流量确定方法。
为实现上述目的,本发明采用如下技术方案:
一种高加危急疏水泄漏流量确定方法,步骤为:
1)将现场高加危急疏水手动门关闭,保证高加危急疏水不泄漏,然后以新加装的ASME标准凝结水流量喷嘴测量出的流量为基准,通过#1GJ-#3GJ三个高加疏水和除氧器热平衡计算出给水流量;
2)用计算出的给水流量校核现场给水流量喷嘴测量出的给水流量,确定出现场给水流量测量偏差ΔG,ΔG=用ASME标准凝结水流量计算出的给水流量-用现场给水流量喷嘴测量出的给水流量;
3)保持机组在高加危急疏水手动门不关闭的状态下重新进行测量,通过现场给水流量喷嘴测量出的给水流量和其测量偏差ΔG,确定出该状态下的实际给水流量及修正后的给水流量,确定方法为:修正后的给水流量=现场测量的给水流量+ΔG;
4)用实测的凝结水流量和修正后的给水流量为基准,通过三个高加疏水和除氧器热平衡计算出高加危急疏水泄漏量。
所述步骤1)中,三个高加疏水和除氧器的热平衡和质量平衡方程分别如下:
#1高加疏水热平衡方程:
G1=Gfw×(hGout1-hGin1)/(hGe1-hGdrain1)
#2高加疏水热平衡方程:
G2=(Gfw×(hGin1-hGin2)-G1×(hGdrain1-hGdrain2))/(hGe2-hGdrain2)
#3高加疏水热平衡方程:
G3=(Gfw×(hGin2-hGin3)-GviK×(hrh-hGdrain3)-(G1+G2)×
    (hGdrain2-hGdrain3))/(he30-hGdrain3)
G3I=G3+GviK
除氧器热平衡方程:
G4=((Gfw+Gaterh+Gatesup+Gdec)×(hdecout-hdecin)-(G1+G2+G3I)×
    (hGdrain3-hdecin)-GhbaclL×(hch-hdecin)+Gmaoqi×(hmaoqi-hdecin))/
    (he40-hdecin)
除氧器质量平衡方程:
GN=Gfw+Gaterh+Gatesup+Gdec-G1-G2-G3I-G4-GhbaclL+Gmaoqi
公式中各变量含义如下:
Gfw-给水流量,G1-一抽流量,G2-二抽流量,G3-三抽流量,G3I-#3高加进汽流量,G4-四抽流量,hGout1-#1高加出水焓,hGin1-#1高加进水焓,hGe1-#1高加进汽焓,hGdrain1-#1高加疏水焓,hGin2-#2高加进水焓,hGdrain2-#2高加疏水焓,hGe2-#2高加进汽焓,hGin3-#3高加进水焓,GviK-中压门杆至三抽漏汽流量,hrh-再热焓,hGdrain3-#3高加疏水焓,he30-三抽焓,Gaterh-过热减温水流量,Gatesup-再热减温水流量,Gdec-除氧器水位变化当量流量,hdecout-除氧器下水焓,hdecin-除氧器进水焓,GhbaclL-高压缸后轴封至除氧器漏汽流量,hch-高排焓,Gmaoqi-除氧器冒汽流量,hmaoqi-除氧器冒汽焓,he40-四抽焓。
本发明的有益效果是:通过现场系统调整和理论计算相结合计算出高加危急疏水泄漏量,分析其对机组实际经济性影响和对试验结果的影响。以某厂300MW机组为例,经计算:现场高加危急疏水泄漏量为75.8t/h,导致机组供电煤耗率升高约4g/kW.h。如果高加危急疏水手动门不隔离,对试验结果的影响非常大,计算出的热耗率将偏高730kJ/kW.h,会使试验结果严重失真。
附图说明
图1为系统结构及测量计算示意图;
下面结合附图与实施例对本发明做进步一说明。
图1给出了本发明确定高加危急疏水泄漏量的系统图。
其中1为ASME标准凝结水流量喷嘴,2为现场给水流量喷嘴,3为高加危急疏水手动门。
为了计算各加热器用汽量,进而根据新加装的经过校验的ASME标准流量喷嘴计算出给水流量,测量了各高加及除氧器的进汽压力、进汽温度、出水温度、进水温度、疏水温度,同时测量了过热器和再热器减温水流量,并利用现场给水流量喷嘴测量了给水流量。
本发明的方法为:
1、在做好现场安全措施的前提下将现场高加危急疏水手动门3关闭,保证高加危急疏水不泄漏,然后以新加装的ASME标准凝结水流量喷嘴1测量出的流量为基准,通过3个高加和除氧器热平衡计算出给水流量。
2、用实际测量的主凝结水流量为基准计算出给水流量,用计算出的给水流量校核现场给水流量喷嘴2测量出的给水流量,确定出现场给水流量测量偏差。
3、保持机组在高加危急疏水手动门3不关闭的状态下重新进行测量,通过现场给水流量喷嘴2测量出的给水流量和其测量偏差,确定出该状态下的实际给水流量。
4、用实测的凝结水流量和修正后的给水流量为基准,通过3个高加和除氧器热平衡计算出高加危急疏水泄漏量。

Claims (5)

1.一种高加危急疏水泄漏流量确定方法,其特征是,步骤为:
1)将现场高加危急疏水手动门关闭,保证高加危急疏水不泄漏,然后以新加装的ASME标准凝结水流量喷嘴测量出的流量为基准,通过#1GJ-#3GJ三个高加疏水和除氧器热平衡计算出给水流量;
2)用实际测量的主凝结水流量为基准计算出给水流量,用计算出的给水流量校核现场给水流量喷嘴测量出的给水流量,确定出现场给水流量测量偏差;
3)保持机组在高加危急疏水手动门不关闭的状态下重新进行测量,通过现场给水流量喷嘴测量出的给水流量和其测量偏差,确定出该状态下的实际给水流量;
4)用实测的凝结水流量和修正后的给水流量为基准,通过三个高加疏水和除氧器热平衡迭代计算出高加危急疏水泄漏量。
2.如权利要求1所述的高加危急疏水泄漏流量确定方法,其特征是,所述步骤1)中,三个高加疏水和除氧器的热平衡和质量平衡方程分别如下:
#1高加疏水热平衡方程:
G1=Gfw×(hGout1-hGin1)/(hGe1-hGdrain1)
#2高加疏水热平衡方程:
G2=(Gfw×(hGin1-hGin2)-G1×(hGdrain1-hGdrain2))/(hGe2-hGdrain2)
#3高加疏水热平衡方程:
G3=(Gfw×(hGin2-hGin3)-GviK×(hrh-hGdrain3)-(G1+G2)×
    (hGdrain2-hGdrain3))/(he30-hGdrain3)
G3I=G3+GviK
除氧器热平衡方程:
G4=((Gfw+Gaterh+Gatesup+Gdec)×(hdecout-hdecin)-(G1+G2+G3I)×
    (hGdrain3-hdecin)-GhbaclL×(hch-hdecin)+Gmaoqi×(hmaoqi-hdecin))/
    (he40-hdecin)
除氧器质量平衡方程:
GN=Gfw+Gaterh+Gatesup+Gdec-G1-G2-G3I-G4-GhbaclL+Gmaoqi
公式中各变量含义如下:
Gfw-给水流量,G1-一抽流量,G2-二抽流量,G3-三抽流量,G3I-#3高加进汽流量,G4-四抽流量,hGout1-#1高加出水焓,hGin1-#1高加进水焓,hGe1-#1高加进汽焓,hGdrain1-#1高加疏水焓,hGin2-#2高加进水焓,hGdrain2-#2高加疏水焓,hGe2-#2高加进汽焓,hGin3-#3高加进水焓,GviK-中压门杆至三抽漏汽流量,hrh-再热焓,hGdrain3-#3高加疏水焓,he30-三抽焓,Gaterh-过热减温水流量,Gatesup-再热减温水流量,Gdec-除氧器水位变化当量流量,hdecout-除氧器下水焓,hdecin-除氧器进水焓,GhbaclL-高压缸后轴封至除氧器漏汽流量,hch-高排焓,Gmaoqi-除氧器冒汽流量,hmaoqi-除氧器冒汽焓,he40-四抽焓。
3.如权利要求1所述的高加危急疏水泄漏流量确定方法,其特征是,所述步骤2)中,校核现场给水流量喷嘴测量出的给水流量,确定出现场给水流量测量偏差的ΔG的方法为:ΔG=用ASME标准凝结水流量计算出的给水流量-用现场给水流量喷嘴测量出的给水流量。
4.如权利要求1所述的高加危急疏水泄漏流量确定方法,其特征是,所述步骤3)中,通过现场给水流量喷嘴测量出的给水流量和其测量偏差,确定出该状态下的的实际给水流量即修正后的给水流量,确定方法为:修正后的给水流量=现场测量的给水流量+ΔG。
5.如权利要求1所述的高加危急疏水泄漏流量确定方法,其特征是,所述步骤4)中,计算出高加危急疏水的方法为:通过3各高加和除氧器热平衡及质量平衡进行计算。
CN2011101581003A 2011-06-14 2011-06-14 高加危急疏水泄漏流量确定方法 Active CN102261936B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011101581003A CN102261936B (zh) 2011-06-14 2011-06-14 高加危急疏水泄漏流量确定方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011101581003A CN102261936B (zh) 2011-06-14 2011-06-14 高加危急疏水泄漏流量确定方法

Publications (2)

Publication Number Publication Date
CN102261936A true CN102261936A (zh) 2011-11-30
CN102261936B CN102261936B (zh) 2012-07-25

Family

ID=45008657

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011101581003A Active CN102261936B (zh) 2011-06-14 2011-06-14 高加危急疏水泄漏流量确定方法

Country Status (1)

Country Link
CN (1) CN102261936B (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102867113A (zh) * 2012-08-23 2013-01-09 山东电力集团公司电力科学研究院 通过除氧器入口凝结水流量确定给水流量的方法
CN104748100A (zh) * 2015-04-21 2015-07-01 中国电力工程顾问集团中南电力设计院有限公司 高加紧急疏水降压逸汽系统
CN107368620A (zh) * 2017-06-02 2017-11-21 国网山东省电力公司电力科学研究院 一种低压加热器疏水泵进气和进水流量的计算方法
CN112070358A (zh) * 2020-08-11 2020-12-11 山东电力研究院 低真空供热机组电负荷调整区间确定方法及系统
CN112257019A (zh) * 2020-10-26 2021-01-22 山东电力研究院 带外置式蒸冷器的汽轮机给水大旁路泄漏量计算方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2380799Y (zh) * 1999-06-30 2000-05-31 青岛磐石容器制造有限公司 旋膜除氧器
CN1274162A (zh) * 2000-06-21 2000-11-22 北京和利时系统工程股份有限公司 一种核电站压水反应堆堆芯功率测量方法
CN2713304Y (zh) * 2004-06-04 2005-07-27 泰安市利德容器制造有限公司 内置式除氧器
CN2832261Y (zh) * 2005-10-19 2006-11-01 张和传 旋膜式除氧器
CN201762159U (zh) * 2010-07-21 2011-03-16 彭维奇 旋膜除氧器

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2380799Y (zh) * 1999-06-30 2000-05-31 青岛磐石容器制造有限公司 旋膜除氧器
CN1274162A (zh) * 2000-06-21 2000-11-22 北京和利时系统工程股份有限公司 一种核电站压水反应堆堆芯功率测量方法
CN2713304Y (zh) * 2004-06-04 2005-07-27 泰安市利德容器制造有限公司 内置式除氧器
CN2832261Y (zh) * 2005-10-19 2006-11-01 张和传 旋膜式除氧器
CN201762159U (zh) * 2010-07-21 2011-03-16 彭维奇 旋膜除氧器

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《山东电力技术》 20021231 丁俊齐等 200MW机组改造后性能考核试验 61-64 , 第2期 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102867113A (zh) * 2012-08-23 2013-01-09 山东电力集团公司电力科学研究院 通过除氧器入口凝结水流量确定给水流量的方法
CN102867113B (zh) * 2012-08-23 2015-08-05 山东电力集团公司电力科学研究院 通过除氧器入口凝结水流量确定给水流量的方法
CN104748100A (zh) * 2015-04-21 2015-07-01 中国电力工程顾问集团中南电力设计院有限公司 高加紧急疏水降压逸汽系统
CN104748100B (zh) * 2015-04-21 2016-06-29 中国电力工程顾问集团中南电力设计院有限公司 高加紧急疏水降压逸汽系统
CN107368620A (zh) * 2017-06-02 2017-11-21 国网山东省电力公司电力科学研究院 一种低压加热器疏水泵进气和进水流量的计算方法
CN107368620B (zh) * 2017-06-02 2021-07-09 国网山东省电力公司电力科学研究院 一种低压加热器疏水泵进气和进水流量的计算方法
CN112070358A (zh) * 2020-08-11 2020-12-11 山东电力研究院 低真空供热机组电负荷调整区间确定方法及系统
CN112257019A (zh) * 2020-10-26 2021-01-22 山东电力研究院 带外置式蒸冷器的汽轮机给水大旁路泄漏量计算方法
CN112257019B (zh) * 2020-10-26 2022-06-07 国网山东省电力公司电力科学研究院 带外置式蒸冷器的汽轮机给水大旁路泄漏量计算方法

Also Published As

Publication number Publication date
CN102261936B (zh) 2012-07-25

Similar Documents

Publication Publication Date Title
CN104048842B (zh) 一种基于软测量技术的汽轮机热耗率在线监测方法
CN100437015C (zh) 汽轮机通流间隙变化在线监测方法
CN102967464B (zh) 凝汽式汽轮机高背压改造后的性能评价方法
CN107201921B (zh) 一种汽轮机热耗率在线监测系统及测量方法
CN103487272B (zh) 直接空冷机组空冷凝汽器进汽焓的计算方法
CN102261936B (zh) 高加危急疏水泄漏流量确定方法
Hafdhi et al. Energetic and exergetic analysis of a steam turbine power plant in an existing phosphoric acid factory
CN108181099B (zh) 一种核反应堆稳压器安全阀水封试验系统及其试验方法
CN103646176B (zh) 汽轮机汽封改造后节能效果的综合计算方法
CN201705397U (zh) 火电厂在线汽轮机热耗率监测装置
RU2537114C2 (ru) Установка для определения кпд секции паровой турбины, установка для расчёта истинного кпд секции среднего давления паровой турбины и установка для управления паровой турбиной
US8113764B2 (en) Steam turbine and a method of determining leakage within a steam turbine
CN108691585B (zh) 一种凝汽式汽轮机低压缸效率的计算方法
CN105225008A (zh) 一种预测汽轮机热力系统内部运行参数的方法
RU2012125202A (ru) Система для оценки эффективности секций паровой турбины (варианты)
RU2586802C2 (ru) Энергоустановка комбинированного цикла (варианты)
CN107543733A (zh) 一种凝汽器热负荷在线监测系统及测量方法
CN103528630A (zh) 高压旁路蒸汽泄漏量及减温水流量的计算方法
CN103900819A (zh) 汽轮机组通流部分汽封改造的节能效果测试与评价方法
CN103759769A (zh) 燃煤电站再热蒸汽流量软测量方法和装置
CN103267539B (zh) 一种卧式三段式给水加热器上端差及下端差的测算方法
CN112127958A (zh) 一种确定核电汽轮机抽汽参数的装置及方法
Sanaye et al. Transient thermal modelling of heat recovery steam generators in combined cycle power plants
CN105787195A (zh) 给水加热系统中外置式蒸汽冷却器进汽流量的计算方法
CN113221477B (zh) 一种确定循环水流量的热平衡计算方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA

Effective date: 20121227

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20121227

Address after: 250002 Ji'nan City Central District, Shandong, No. 2 South Road, No. 500

Patentee after: SHANDONG ELECTRIC POWER Research Institute

Patentee after: State Grid Corporation of China

Address before: 250002 Ji'nan City Central District, Shandong, No. 2 South Road, No. 500

Patentee before: SHANDONG ELECTRIC POWER Research Institute

CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 250003 No. 2000, Wang Yue Road, Shizhong District, Ji'nan, Shandong

Patentee after: Shandong Electric Power Research Institute

Patentee after: State Grid Corporation of China

Address before: 250002, No. 500, South Second Ring Road, Shizhong District, Shandong, Ji'nan

Patentee before: Shandong Electric Power Research Institute

Patentee before: State Grid Corporation of China

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 250003 No. 2000, Wang Yue Road, Shizhong District, Ji'nan, Shandong

Patentee after: SHANDONG ELECTRIC POWER Research Institute

Patentee after: STATE GRID CORPORATION OF CHINA

Address before: 250003 No. 2000, Wang Yue Road, Shizhong District, Ji'nan, Shandong

Patentee before: SHANDONG ELECTRIC POWER Research Institute

Patentee before: State Grid Corporation of China

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220126

Address after: 250003 No. 2000, Wang Yue Road, Shizhong District, Ji'nan, Shandong

Patentee after: ELECTRIC POWER RESEARCH INSTITUTE OF STATE GRID SHANDONG ELECTRIC POWER Co.

Patentee after: STATE GRID CORPORATION OF CHINA

Address before: 250003 No. 2000, Wang Yue Road, Shizhong District, Ji'nan, Shandong

Patentee before: SHANDONG ELECTRIC POWER Research Institute

Patentee before: STATE GRID CORPORATION OF CHINA