CN102251542A - Construction method for deviation correction of pile foundation by high-pressure spraying disturbance and construction equipment used in same - Google Patents

Construction method for deviation correction of pile foundation by high-pressure spraying disturbance and construction equipment used in same Download PDF

Info

Publication number
CN102251542A
CN102251542A CN2011100958638A CN201110095863A CN102251542A CN 102251542 A CN102251542 A CN 102251542A CN 2011100958638 A CN2011100958638 A CN 2011100958638A CN 201110095863 A CN201110095863 A CN 201110095863A CN 102251542 A CN102251542 A CN 102251542A
Authority
CN
China
Prior art keywords
disturbance
construction
pressure
pile foundation
high pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011100958638A
Other languages
Chinese (zh)
Inventor
张继红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2011100958638A priority Critical patent/CN102251542A/en
Publication of CN102251542A publication Critical patent/CN102251542A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention relates to a construction method for deviation correction of a pile foundation by high-pressure spraying disturbance and construction equipment used in the construction method. According to the deviation correction method for the pile foundation by high-pressure spraying disturbance, soil mass (5) around a pile or near a pile tip is subjected to high-pressure spraying disturbance so that the strength of the soil mass (5) is reduced and the pile (6) sinks under the action of load, thus achieving the purpose of deviation correction of a pile foundation. The construction equipment used in the method comprises a high-pressure delivery pump (1), a pore-forming fluid director (2) and a high-pressure spraying nozzle (3), wherein the soil mass (5) is disturbed by a hydraulic monitor generated at the high-pressure spraying nozzle (3). With the invention, deviation correction construction of the pile foundation can be successfully realized, the construction quality is reliable and efficient, and the safety of an original building or a structure (7) can be ensured during the process of deviation correction construction.

Description

A kind of pile foundation spray water with high pressure disturbance deviation rectification construction method and used construction equipment thereof
Technical field
The present invention relates to civil engineering king-pile foundation construction thing or structure correction engineering field.
Background technology
Along with developing rapidly of underground space development and urban construction, existing building or structure are because of various reasons such as soft foundation, contiguous excavation of foundation pit, the driving in peripheral tunnel, near large tracts of land preloadings, often occur that sedimentation appears in building or structure, differential settlement is bigger, cause building or structure to tilt, influence the normal use and the safety of building or structure, when building or structure relative settlement or tilt when excessive, then need the processing of rectifying a deviation.For pile foundation, sometimes because of designing the reasons such as influence of improper or peripheral contiguous engineering, also there is the inclination situation to occur, after building or structure base piling, its correction work difficulty is quite big, does not still have cost-effective construction technology at present.
The content of invention
First purpose of the present invention is to provide a kind of pile foundation disturbance deviation rectification construction method that sprays water with high pressure, and this pile foundation disturbance deviation rectification construction method that sprays water with high pressure can be realized the Deviation Correction Construction of pile foundation building or structure.
Above-mentioned purpose of the present invention is to realize by following a kind of pile foundation disturbance deviation rectification construction method that sprays water with high pressure, and the pile foundation disturbance deviation rectification construction method that sprays water with high pressure comprises the steps:
A) determine the incline direction of building or structure;
B), determine that Deviation Correction Construction need urge position, heavy place according to building or structure inclination situation;
C) near the soil body position the stake of definite disturbance of need spraying water with high pressure;
D) to the need soil body of the disturbance disturbance construction operation that sprays water with high pressure that sprays water with high pressure;
E) building or the structure to the need correction carry out settlement observation, and control intensity, amplitude and the duration of the disturbance construction operation that sprays water with high pressure according to observed result;
F) size according to the correction amount determines whether needs repeating step e), until finishing Deviation Correction Construction.
Second purpose of the present invention is to provide a kind of pile foundation disturbance Deviation Correction Construction equipment that sprays water with high pressure, and this pile foundation disturbance Deviation Correction Construction equipment that sprays water with high pressure can be realized the Deviation Correction Construction of pile foundation building or structure smoothly.
This pile foundation disturbance Deviation Correction Construction equipment that sprays water with high pressure comprises that high-pressure delivery pump, pore-forming air deflector and high-pressure injection mouth three parts form, high-pressure delivery pump wherein is an equipment from water under high pressure to the high-pressure injection mouth that carry, high-pressure delivery pump is connected with water source and pore-forming air deflector, the pore-forming air deflector is connected with the high-pressure injection mouth, and the pore-forming air deflector is the equipment of the high-pressure injection mouth being delivered to the precalculated position and water under high pressure being delivered to the high-pressure injection mouth.
Disturbance method for correcting error and construction equipment can be realized the pile foundation Deviation Correction Construction smoothly because pile foundation of the present invention sprays water with high pressure, reliable construction quality, and can guarantee the safety of original building in the Deviation Correction Construction process or structure.
Description of drawings
Fig. 1 is one embodiment of the present of invention generalized section;
The specific embodiment
As one embodiment of the present of invention, main purpose is to introduce a kind of pile foundation of the present invention spray water with high pressure disturbance deviation rectification construction method and used construction equipment thereof.At first introduce a kind of pile foundation of the present invention the spray water with high pressure structure construction and the operating principle thereof of the used construction equipment of disturbance correction in conjunction with Fig. 1.As shown in Figure 1, the pile foundation of the present invention disturbance Deviation Correction Construction equipment that sprays water with high pressure comprises high-pressure delivery pump (1), pore-forming air deflector (2) is formed with high-pressure injection mouth (3) three parts, high-pressure delivery pump wherein (1) is an equipment from water under high pressure to high-pressure injection mouth (3) that carry, high-pressure delivery pump (1) is connected with water source (4) and pore-forming air deflector (2), high-pressure delivery pump (1) is suction water from water source (4), by after the pressurization water under high pressure being sent into pore-forming air deflector (2), pore-forming air deflector (2) is connected with high-pressure injection mouth (3), pore-forming air deflector (2) is the equipment of high-pressure injection mouth (3) being delivered to the precalculated position and water under high pressure being delivered to high-pressure injection mouth (3), pore-forming air deflector (2) can be Drilling machineries such as jumbolter, water under high pressure is injected its peripheral soil body (5) by high-pressure injection mouth (3), in the soil body, form giant, can cut the soil body (5), disturbance and destruction, high-pressure injection mouth (3) can be by moving, rotate or swing expansion range of disturbance, behind the soil disturbance, just can sink under the effect of pile top load by the stake (6) that the soil body supports, thereby reach disturbance correction purpose.Present embodiment introduce a kind of pile foundation of the present invention disturbance deviation rectification construction method that sprays water with high pressure with the lower part in conjunction with Fig. 1.In the first step of this disturbance method for correcting error, can determine the incline direction of building or structure (7) according to the squareness measurement of settlement observation data or built construction thing or structure (7), entered for second step then.In this step, only need according to the observational data in the first step, it is heavy to reach the correction purpose to determine the stake (6) of the little side of sedimentation urge, needs the position of short heavy stake (6) to be Deviation Correction Construction and need urge to sink to locate the position, thereby finished for second step, entered for the 3rd step.In this step, reach the character of stake (6) bottom soil on every side according to stake (6), the spray water with high pressure soil body position of disturbance of definite need, the position that needs disturbed soil can be the soil of stake (6) bottom, also can be stake (6) soil on every side, can also all carry out disturbance soil and stake (6) soil on every side of stake (6) bottom.Can take the soil body position of the definite disturbance of need spraying water with high pressure of following method, as stake (6) soil on every side the sinking of stake (6) is played conclusive effect, can be only to the disturbance of spraying water of stake (6) soil on every side, if the soil of stake (6) bottom plays conclusive effect to the sinking of stake (6), can select the disturbance of spraying water of the soil of stake (6) bottom, if the soil of stake (6) bottom all plays an important role to the sinking of stake (6) with on every side soil, then to stake (6) soil and the disturbance of all spraying water of the soil of stake (6) bottom on every side.Thereby finished for the 3rd step, entered for the 4th step.In this step, the disturbance construction of spraying water with high pressure of can utilize a part is introduced before the present embodiment pile foundation to spray water with high pressure the soil body (5) that the used construction equipment of disturbance correction determines the 3rd step, utilize water under high pressure that high-pressure injection mouth (3) sprays that on every side soil of stake (6), the soil bottom the stake (6) are carried out disturbance, cutting, destroy the structure of the soil body, reduce the intensity of the soil body.Thereby finished for the 4th step, entered for the 5th step.In this step, in the 4th process of step to the soil disturbance construction, building or structure (7) to the need correction carry out settlement observation, and spray water with high pressure intensity, amplitude and the duration of disturbance construction operation according to observed result control, settling rate as stake (6) is too fast, can reduce range of disturbance, disturbance number of times, strength of turbulence and time, too slow as the subsidence velocity of stake (6), then can increase range of disturbance, disturbance number of times, strength of turbulence and time.Thereby finished for the 5th step, entered for the 6th step.In this step, the size according to the correction amount determines whether that needs repeat the 5th step until finishing Deviation Correction Construction.Thereby finish a kind of pile foundation of the present invention disturbance deviation rectification construction method that sprays water with high pressure.
This patent includes but not limited to other job practicess of the alternative use of professional person in this area.

Claims (2)

1. pile foundation disturbance deviation rectification construction method that sprays water with high pressure is characterized in that comprising the steps:
A) determine the incline direction of building or structure (7);
B), determine that Deviation Correction Construction need urge position, heavy place according to building or structure (7) inclination situation;
C) near the soil body (5) position the stake (6) of definite disturbance of need spraying water with high pressure;
D) to the need soil body (5) of the disturbance disturbance construction operation that sprays water with high pressure that sprays water with high pressure;
E) building or the structure (7) to the need correction carry out settlement observation, and control intensity, amplitude and the duration of the disturbance construction operation that sprays water with high pressure according to observed result;
F) size according to the correction amount determines whether needs repeating step e), until finishing Deviation Correction Construction.
2. pile foundation disturbance Deviation Correction Construction equipment that sprays water with high pressure, it is characterized in that comprising high-pressure delivery pump (1), pore-forming air deflector (2) and high-pressure injection mouth (3) three parts composition, high-pressure delivery pump wherein (1) is an equipment from water under high pressure to high-pressure injection mouth (3) that carry, high-pressure delivery pump (1) is connected with water source (4) and pore-forming air deflector (2), pore-forming air deflector (2) is connected with high-pressure injection mouth (3), and pore-forming air deflector (2) is the equipment of high-pressure injection mouth (3) being delivered to the precalculated position and water under high pressure being delivered to high-pressure injection mouth (3).
CN2011100958638A 2011-04-18 2011-04-18 Construction method for deviation correction of pile foundation by high-pressure spraying disturbance and construction equipment used in same Pending CN102251542A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011100958638A CN102251542A (en) 2011-04-18 2011-04-18 Construction method for deviation correction of pile foundation by high-pressure spraying disturbance and construction equipment used in same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011100958638A CN102251542A (en) 2011-04-18 2011-04-18 Construction method for deviation correction of pile foundation by high-pressure spraying disturbance and construction equipment used in same

Publications (1)

Publication Number Publication Date
CN102251542A true CN102251542A (en) 2011-11-23

Family

ID=44979086

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011100958638A Pending CN102251542A (en) 2011-04-18 2011-04-18 Construction method for deviation correction of pile foundation by high-pressure spraying disturbance and construction equipment used in same

Country Status (1)

Country Link
CN (1) CN102251542A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102979113A (en) * 2012-12-15 2013-03-20 陈向东 House rectification method
CN103104136A (en) * 2013-01-29 2013-05-15 中国水产科学研究院东海水产研究所 Simply-equipped rapid mud flat enclosure mesh arrangement method
CN103321261A (en) * 2013-07-18 2013-09-25 张继红 Construction method for directional expansion-rise deviation rectification
CN103363955A (en) * 2013-07-31 2013-10-23 陕西建工集团总公司 Construction method for settlement observation points of building
CN103410182A (en) * 2013-08-22 2013-11-27 天津大学 Unilateral pile foundation unloading horizontal top-level pull deviation rectifying and broken pile reinforcement construction method
CN105464395A (en) * 2015-10-27 2016-04-06 中冶集团武汉勘察研究院有限公司 Building inclination correcting method of disturbing pile-end bearing layer
CN106592615A (en) * 2016-11-17 2017-04-26 叶香雄 Deviation rectification construction method for inclined sink
CN107313602A (en) * 2016-04-26 2017-11-03 湖北建科结构加固有限责任公司 Building substrate is that sand changes the jetting forced falling rectifying deviation method filled out
CN108343260A (en) * 2018-04-08 2018-07-31 湖南化工地质工程勘察院有限责任公司 Inclined building correcting and then reinforcing structure and its construction method
CN109024719A (en) * 2018-09-14 2018-12-18 山东建筑大学 A kind of side disturbance drop resistance building inclination rectification method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2632156Y (en) * 2003-06-30 2004-08-11 唐业清 Incline-correcting apparatus by radials
CN101215929A (en) * 2007-12-26 2008-07-09 南京工业大学 Construction method for rectifying deviation of open caisson by using preset force
CN101787717A (en) * 2010-03-13 2010-07-28 中铁西北科学研究院有限公司 Controllable accurate combined inclination correction method
CN101793029A (en) * 2009-02-03 2010-08-04 叶长青 Method for correcting pile deviation
CN202039394U (en) * 2011-04-18 2011-11-16 张继红 Pile foundation high-pressure water jet perturbation deviation-correcting construction equipment

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2632156Y (en) * 2003-06-30 2004-08-11 唐业清 Incline-correcting apparatus by radials
CN101215929A (en) * 2007-12-26 2008-07-09 南京工业大学 Construction method for rectifying deviation of open caisson by using preset force
CN101793029A (en) * 2009-02-03 2010-08-04 叶长青 Method for correcting pile deviation
CN101787717A (en) * 2010-03-13 2010-07-28 中铁西北科学研究院有限公司 Controllable accurate combined inclination correction method
CN202039394U (en) * 2011-04-18 2011-11-16 张继红 Pile foundation high-pressure water jet perturbation deviation-correcting construction equipment

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张怀根等: "某住宅楼纠偏加固技术研究", 《知识经济》, 30 June 2009 (2009-06-30) *

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102979113A (en) * 2012-12-15 2013-03-20 陈向东 House rectification method
CN103104136A (en) * 2013-01-29 2013-05-15 中国水产科学研究院东海水产研究所 Simply-equipped rapid mud flat enclosure mesh arrangement method
CN103104136B (en) * 2013-01-29 2016-03-30 中国水产科学研究院东海水产研究所 A kind of beach enclosure of simple and fast establishes network method
CN103321261A (en) * 2013-07-18 2013-09-25 张继红 Construction method for directional expansion-rise deviation rectification
CN103363955A (en) * 2013-07-31 2013-10-23 陕西建工集团总公司 Construction method for settlement observation points of building
CN103363955B (en) * 2013-07-31 2015-07-15 陕西建工集团总公司 Construction method for settlement observation points of building
CN103410182B (en) * 2013-08-22 2015-07-22 天津大学 Unilateral pile foundation unloading horizontal top-level pull deviation rectifying and broken pile reinforcement construction method
CN103410182A (en) * 2013-08-22 2013-11-27 天津大学 Unilateral pile foundation unloading horizontal top-level pull deviation rectifying and broken pile reinforcement construction method
CN105464395A (en) * 2015-10-27 2016-04-06 中冶集团武汉勘察研究院有限公司 Building inclination correcting method of disturbing pile-end bearing layer
CN105464395B (en) * 2015-10-27 2018-01-30 中冶集团武汉勘察研究院有限公司 A kind of building inclination rectification method for disturbing bearing course at pile end
CN107313602A (en) * 2016-04-26 2017-11-03 湖北建科结构加固有限责任公司 Building substrate is that sand changes the jetting forced falling rectifying deviation method filled out
CN106592615A (en) * 2016-11-17 2017-04-26 叶香雄 Deviation rectification construction method for inclined sink
CN108360545A (en) * 2016-11-17 2018-08-03 叶香雄 It tilts open caisson and combines deviation rectification construction method
CN108343260A (en) * 2018-04-08 2018-07-31 湖南化工地质工程勘察院有限责任公司 Inclined building correcting and then reinforcing structure and its construction method
CN109024719A (en) * 2018-09-14 2018-12-18 山东建筑大学 A kind of side disturbance drop resistance building inclination rectification method

Similar Documents

Publication Publication Date Title
CN102251542A (en) Construction method for deviation correction of pile foundation by high-pressure spraying disturbance and construction equipment used in same
CN205172598U (en) Pipe curtain spouts a supporting construction soon
CN104533467B (en) A kind of high artesian, the method for protecting support in fault disruption zone tunnel
CN108080409A (en) A kind of triple churning device and method thereof of soil remediation
CN102535449B (en) Construction method of stirring pile and solidifying agent device thereof
JP4520913B2 (en) Ground improvement method and existing structure foundation reinforcement method
CN107964974A (en) A kind of water-stop curtain constructing device and its construction method
CN103993594A (en) Liquefiable foundation device for micro-nano bubble processing and operation method
CN106087994A (en) A kind of high pressure jet grouting pore-forming dado structure and construction method thereof
CN105642665A (en) Method for repairing heavy metal contaminated site in situ by adopting stirring and injection system
CN101798823B (en) Construction method of performing remote deviation rectification by passageway method
JP2019070318A (en) Liquefaction countermeasure method for ground
EP1757771B1 (en) Method for consolidating and impermeabilizing the ground around a tunnel
CN202039394U (en) Pile foundation high-pressure water jet perturbation deviation-correcting construction equipment
CN103603357B (en) A kind of multi-platform without inner support self waterproofing foundation pit enclosure structure and constructional method thereof
CN208033274U (en) A kind of triple churning equipment of soil remediation
CN102383731A (en) High-pressure water jet flow pore-forming tool and device and poured pile construction method
CN103074887A (en) Drilling/spraying integrated foundation treatment method and special drilling rig component
CN109267575A (en) The construction method of pattern foundation pit supporting structure is cheated in the hole of Soft Soil Area
CN203080528U (en) Drilling and spraying integrated foundation treating special drilling tool assembly
CN108361037A (en) A kind of vertical shaft rapid constructing method and equipment
JP2007170008A (en) Liquefaction countermeasuring method
CN208563316U (en) Large-diameter cast-in-place pile bottom loose soil sediment treatment device
CN207959196U (en) A kind of three axis high pressure spray of long spire stirs device
CN108951623A (en) A kind of three axis high-pressure rotary-spray two-way stirring pile construction methods

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20111123