CN102235151A - 砂卵石漂石层超前成孔方法 - Google Patents

砂卵石漂石层超前成孔方法 Download PDF

Info

Publication number
CN102235151A
CN102235151A CN2010101517322A CN201010151732A CN102235151A CN 102235151 A CN102235151 A CN 102235151A CN 2010101517322 A CN2010101517322 A CN 2010101517322A CN 201010151732 A CN201010151732 A CN 201010151732A CN 102235151 A CN102235151 A CN 102235151A
Authority
CN
China
Prior art keywords
forming method
leading
self
hole
type hollow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2010101517322A
Other languages
English (en)
Other versions
CN102235151B (zh
Inventor
刘昌用
郜强
董长明
刘莹
林永桢
资兵权
孙建华
张伟
喻树森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ranken Railway Construction Group Co Ltd
Original Assignee
CHENGDU RANKEN RAILWAY CONSTRUCTION Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHENGDU RANKEN RAILWAY CONSTRUCTION Ltd filed Critical CHENGDU RANKEN RAILWAY CONSTRUCTION Ltd
Priority to CN 201010151732 priority Critical patent/CN102235151B/zh
Publication of CN102235151A publication Critical patent/CN102235151A/zh
Application granted granted Critical
Publication of CN102235151B publication Critical patent/CN102235151B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明提供了一种砂卵石漂石层超前成孔方法,施工时先在前一榀格栅上,按设计焊好预留孔口管,待前一榀格栅混凝土喷射完成后,再在隧道上台阶上拼装导轨式重型风钻,安装完成后,安装自进式中空注浆锚杆到钻机上,开动钻机,并根据预留的位置调整导轨式重型风钻的高度与角度,准备就绪后开始钻孔,待钻孔深度达到要求后,分离自进式中空注浆锚杆与导轨式重型风钻,则打成一孔。本发明的超前成孔方法具有冲击和转钎扭矩大的特点,可分别调节冲击能、转钎速度及扭矩,打孔速度快,安装就位后2分钟左右就能成一孔,在砂卵石层中不易卡钎,重量轻,安装就位移位快,外形尺寸合理,占用空间小,比较适用于井下狭窄的作业场所,且成本低。

Description

砂卵石漂石层超前成孔方法
技术领域
本发明涉及城市隧道在修建过程中采用浅埋暗挖法“十八字”指导方针中的“管超前”部分,是解决在砂卵石漂石层中超前成孔支护的方法。 
背景技术
城市隧道施工安全是最重要的,安全包含工程安全和人身不受伤害,超前小导管(或称钢管短管棚)注浆是地下工程自稳差的软弱围岩开挖前,在开挖面顶部前方的土体内按一定间距、仰角和长度,钻孔后布置Φ32~42mm的超前小导管,然后在管内进行注浆,加固土体。如图1所示。地下工程向前开挖后,由于在超前小导管加固土体的防护下,能保证在施作初期支护时围岩的稳定性;如果其设计和施工得当,能有效地防止在施工时顶部的坍塌。 
城市隧道在大粒径、高含量砂卵石漂石层中施工,采用盾构工法目前无比较成熟的经验可供参考。因此可以说,盾构工法在此类地层中的施工甚至可以说是一个世界性的难题,因为经过与目前世界上比较知名的盾构机生产厂家进行技术交流与研讨,并没有这方面的成功经验。采用浅埋暗挖法施工时,在该地层内采用不同的施工方法进行试验,得到不同的试验数据,通过试验数据可以看出,在现有的工法条件下,在砂卵石漂石层内施工超前小导管,仍然是一个没有攻克的难题,相关试验条件、内容与结论如下: 
北京地铁大兴线起新区间,起点位于南四环公益西桥处,与既有地铁四号线相接,终点位于新建新宫站,全长1941单延米,全部采用浅埋暗挖 法施工修建,其中起点HDK0+000~HDK0+450段,隧道结构起拱线以上部分全部位于砂卵石层中,卵石最大粒径达到390mm,一般粒径20~50mm,含量在50~70%之间,个别地段最大含量达到85%以上,细砂填充。 
各种工法在砂卵石中成孔的情况如下: 
引孔打入成孔法 
拱部超前小导管由现在的φ32×3.25改为φ25小导管,管长2.5m,管前端做成锥型,采用大锤直接向地层内砸,其打入深度不到1m。于是又采用风钻引孔后用高压风管吹孔的办法,先引孔后再插管,采用大锤砸入,还是不能解决该问题,最后又采用风镐向里面顶的办法,均无法解决该问题。 
YT-28风钻钻进成孔法 
采用YT-28风钻打自进式中空注浆锚杆,为了减少钻孔阻力,用自进式中空注浆锚杆代替焊接钢管超前小导管。根据现场实际试验效果可以看出,在采用该种方法后,因为该种风钻的冲击能及扭矩小,在该地层内能打入自进式中空注浆锚杆1.0~1.5m左右,但是打入长度仍是达不到设计的2.5m要求,同时打设的进度太慢,效率太低,一晚上(约5个小时)才成管5根。 
地质钻机钻进成孔法 
该工法是采用地质钻机能成孔,而且可打深孔,但是设备庞大笨重,占用空间大,在坑道狭小的空间中不便于安装定位移位,打孔作业及深孔注浆作业的每一循环作业时间长,浆液配制难,需专业队伍施工,经济成本高,达到10000元/m,一次性施工完成后可连续施工开挖9m长,但平均 日进度0.43m/天,工序转换困难。 
潜孔锤前进式、后退式深孔注浆法 
前进式深孔注浆前端采用φ140、φ110潜孔锤冲击成孔,在成孔过程中因潜孔锤直径经钻杆直径大,冲击成孔及退杆时容易卡钻、埋钻。且钻杆在冲击旋转的过程中磨损严重,平均每成3个孔就要更换一套钻杆(1.5m/根,共更换12根),φ75合金钻头旋转成孔虽然成孔时间短,但钻头及钻杆的磨损严重,平均每成2个孔就要更换一套钻杆及钻头(1.5m/根,共更换12根)。 
发明内容
为了弥补现有工法在砂卵石漂石层施工城市隧道时,无法打设超前小导管的缺陷,本发明选用一种90型或70型导轨式重型风钻(导轨式凿岩机,两种均为重型风钻之一,多用于矿山中硬及坚硬岩石中钻孔)与自进式中空注浆锚杆相结合的超前成孔方法,能够满足施工要求。 
施工时先在前一榀格栅上,按设计焊好预留孔口管,待前一榀格栅混凝土喷射完成后,再在隧道上台阶上拼装导轨式重型风钻,安装完成后,安装自进式中空注浆锚杆在钻机上,开动钻机,并根据预留的位置调整导轨式重型风钻的高度与角度,准备就绪后开始钻孔,钻孔过程中根据地质情况控制风力,达到分别调节冲击能与转钎速度与扭矩。待钻孔深度达到要求后退出导轨式重型风钻,则打成一孔。 
本发明的超前成孔方法具有冲击和转钎扭矩大的特点,可分别调节冲击能、转钎速度及扭矩,打孔速度快,安装就位后2分钟左右就能成一孔,在砂卵石层中不易卡钎,重量轻,安装就位移位快,外形尺寸合理,占用 空间小,比较适用于井下狭窄的作业场所,且成本低。在砂卵石漂石层内施工超前小导管具有方便、快速,打设长度满足设计要求,注浆后质量效果好等特点。 
附图说明
图1为传统超前小导管注浆施工示意图; 
图2为导轨式重型风钻结合自进式中空注浆锚杆的超前小导管示意图。 
图中:1:已施工隧道初支格栅  2:自进式中空注浆锚杆/超前小导管/钢管短管棚  3:导轨式重型风钻及相应支架  4:预留孔口管  5:未开挖部分隧道土体  6:超前小管棚注浆扩散加固区  7:上台阶核心土 
具体实施方式
首先,详细介绍本发明的导轨式重型风钻结合自进式中空注浆锚杆在砂卵石漂石层中超前成孔方法的原理。 
该原理是导轨式重型风钻在使用自进式中空注浆锚杆做为钻杆的情况下,在砂卵石漂石中施工超前小导管(钢管短管棚),即,利用导轨式重型风钻打入自进式中空注浆锚杆,做为超前小导管。因具有冲击和转钎扭矩大的特点,可分别调节冲击能、转钎速度及扭矩,打孔速度快,安装就位后2分钟左右就能成一孔,在砂卵石层中不易卡钎,重量轻,安装就位移位快,外形尺寸合理,占用空间小,比较适用于井下狭窄的作业场所,且成本低。结合本申请人设计的重型风钻支架(已申请专利,申请号为201020106742.X),在砂卵石漂石层内施工超前小导管具有方便、快速,打设长度满足设计要求,注浆后质量效果好等特点。 
下面,详细介绍本发明超前成孔方法的具体工法。 
1、前一榀格栅预留孔口管 
在隧道初支格栅安装之前,先根据设计要求的间距、仰角与需打设的自进式中空注浆锚杆钻头的大小,在格栅上焊接固定预留孔口管,孔口管采用普通钢管,大小以能穿过钻头为宜,确定好间距及仰角后,采用钢筋焊妆固定在格栅上,并做好孔口的封堵,以免喷射混凝土时喷入混凝土而不能使用。 
2、喷射混凝土施工 
3、超前小导管(钢筋短管棚)钻进施工 
在喷射混凝土施工完成后,根据隧道初支结构而专门设计制作的导轨式重型风钻(本发明的重点不在于导轨式重型风钻的具体结构,因此,在此不再详细描述其结构,可参考本申请人的先申请中公开的重型风钻支架的具体结构)在上台阶安装就位,清除孔口管上附着的喷射混凝土,连接好驱动用风阀系统,开动钻机先试运转试机及导轨滑动,确认各方无误后,安装自进式中空注浆锚杆到钻机上,将前端钻头通过预留的孔口管导入,并根据预留的位置调整导轨式钻机的高度与角度,再打开风阀系统,驱动钻机进行钻孔及导管打入施工。钻孔过程中根据地质情况控制风力,达到分别调节冲击能与转钎速度与扭矩。 
根据设计超前小导管(钢筋短管棚)的长度,可利用自进式中空注浆锚杆的连接器接长,以达到设计的长度。在钻进达到设计的长度后,停止钻进,利用风阀系统驱动钻机后退与自进式中空注浆锚杆分离,这样就钻成一孔并打入超前小导管(钢筋短管棚),进入下一循环,并按上述过程进行剩余超前小导管(钢筋短管棚)钻孔打入施工。 
虽然上面已经参考附图描述了本发明的实施例,但是本领域技术人员可以理解,在不脱离本发明范围和精神的情况下,可以对本发明作出各种不同的修改和变化。因此,应该理解上述的实施例不是限制,而是各个方面的举例说明。 

Claims (4)

1.一种砂卵石漂石层超前成孔方法,其中,在砂卵石漂石层这种类型的地层中,利用导轨式重型风钻打入自进式中空注浆锚杆,做为超前小导管,该方法包括以下步骤:
在隧道初支格栅安装之前,先根据设计要求的间距、仰角与需打设的自进式中空注浆锚杆钻头的大小,在格栅上焊接固定预留孔口管,确定好间距及仰角后,采用钢筋焊接固定在格栅上,并做好孔口的封堵;
喷射混凝土施工;
导轨式重型风钻在上台阶安装就位,清除孔口管上附着的喷射混凝土,连接好驱动用风阀系统,开动钻机先试运转试机及导轨滑动,确认各方无误后,安装自进式中空注浆锚杆到钻机上,将前端钻头通过预留的孔口管导入,并根据预留的位置调整导轨式钻机的高度与角度,再打开风阀系统,驱动钻机进行钻孔及超前小导管打入施工,在钻进达到设计的长度后,停止钻进,利用风阀系统驱动钻机后退与自进式中空注浆锚杆分离,这样就钻成一孔并打入超前小导管,进入下一循环,并按上述过程进行剩余超前小导管钻孔打入施工。
2.根据权利要求1所述的超前成孔方法,其特征在于:所述的孔口管采用普通钢管,大小以能穿过钻头为宜。
3.根据权利要求1或2所述的超前成孔方法,其特征在于:钻孔过程中根据地质情况控制风力,达到分别调节冲击能与转钎速度与扭矩。
4.根据前述任一权利要求所述的超前成孔方法,其特征在于:超前小导管的长度可利用自进式中空注浆锚杆的连接器接长,以达到设计的长度。
CN 201010151732 2010-04-21 2010-04-21 砂卵石漂石层超前成孔方法 Active CN102235151B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010151732 CN102235151B (zh) 2010-04-21 2010-04-21 砂卵石漂石层超前成孔方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010151732 CN102235151B (zh) 2010-04-21 2010-04-21 砂卵石漂石层超前成孔方法

Publications (2)

Publication Number Publication Date
CN102235151A true CN102235151A (zh) 2011-11-09
CN102235151B CN102235151B (zh) 2013-05-08

Family

ID=44886212

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010151732 Active CN102235151B (zh) 2010-04-21 2010-04-21 砂卵石漂石层超前成孔方法

Country Status (1)

Country Link
CN (1) CN102235151B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105019917A (zh) * 2015-08-13 2015-11-04 青岛业高建设工程有限公司 冲击钻进式超前旋喷管棚施工装置及施工方法
CN106401462A (zh) * 2016-10-31 2017-02-15 广西固瑞科技股份有限公司 一种跟踪钻头的钻孔方法
CN107605509A (zh) * 2017-11-08 2018-01-19 中铁十局集团有限公司 砂卵石地层小曲线半径浅埋隧道暗挖法超前支护施工方法
CN111577335A (zh) * 2020-05-27 2020-08-25 蒋贵伟 一种隧道施工小导管注浆机

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02252891A (ja) * 1989-03-28 1990-10-11 Fujita Corp トンネル切羽の安定工法
JP2000337077A (ja) * 1999-05-26 2000-12-05 Ohbayashi Corp トンネルの施工方法
US20030085037A1 (en) * 2001-08-06 2003-05-08 Roane Thomas O. Multilateral open hole gravel pack completion
CN1419034A (zh) * 2002-11-29 2003-05-21 赵大军 一种松散破碎地层的潜孔锤冲击静压跟管钻孔方法
CN101328811A (zh) * 2008-07-25 2008-12-24 北京市政建设集团有限责任公司 Tgrm分段前进式超前深孔注浆施工工艺
JP2009281055A (ja) * 2008-05-22 2009-12-03 Taisei Corp 井戸トンネルの構築方法及び保護管ユニット

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02252891A (ja) * 1989-03-28 1990-10-11 Fujita Corp トンネル切羽の安定工法
JP2000337077A (ja) * 1999-05-26 2000-12-05 Ohbayashi Corp トンネルの施工方法
US20030085037A1 (en) * 2001-08-06 2003-05-08 Roane Thomas O. Multilateral open hole gravel pack completion
CN1419034A (zh) * 2002-11-29 2003-05-21 赵大军 一种松散破碎地层的潜孔锤冲击静压跟管钻孔方法
JP2009281055A (ja) * 2008-05-22 2009-12-03 Taisei Corp 井戸トンネルの構築方法及び保護管ユニット
CN101328811A (zh) * 2008-07-25 2008-12-24 北京市政建设集团有限责任公司 Tgrm分段前进式超前深孔注浆施工工艺

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张利娜等: "全套管钻机在砂卵石地层中成孔施工工艺初探", 《铁道标准设计》, no. 2, 28 February 2010 (2010-02-28) *
阙庆珍: "密实砂卵石地层中超前小导管施工技术研究", 《山西建筑》, vol. 36, no. 3, 31 January 2010 (2010-01-31) *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105019917A (zh) * 2015-08-13 2015-11-04 青岛业高建设工程有限公司 冲击钻进式超前旋喷管棚施工装置及施工方法
CN106401462A (zh) * 2016-10-31 2017-02-15 广西固瑞科技股份有限公司 一种跟踪钻头的钻孔方法
CN106401462B (zh) * 2016-10-31 2018-09-21 广西固瑞科技股份有限公司 一种跟踪钻头的钻孔方法
CN107605509A (zh) * 2017-11-08 2018-01-19 中铁十局集团有限公司 砂卵石地层小曲线半径浅埋隧道暗挖法超前支护施工方法
CN111577335A (zh) * 2020-05-27 2020-08-25 蒋贵伟 一种隧道施工小导管注浆机
CN111577335B (zh) * 2020-05-27 2021-08-10 山东美固德新材料有限公司 一种隧道施工小导管注浆机

Also Published As

Publication number Publication date
CN102235151B (zh) 2013-05-08

Similar Documents

Publication Publication Date Title
CN105298463B (zh) 天然气水合物大井眼多分支径向水平井完井方法
CN103835729B (zh) 深部长距离巷道围岩地面预注浆加固工艺
CN100567698C (zh) 隧道超前支护风循环钻进施工方法及钻具
CN103088819B (zh) 预应力锚索施工方法
CN110409461A (zh) 一种基于装配式大直径管桩的基坑支护施工方法
CN107218045B (zh) 岩质地层暗挖地铁车站出入口暗挖段的快速施工方法
CN103306687A (zh) 软岩隧道长悬臂水平旋喷变形控制施工方法
CN103899318B (zh) 中硬地层隧道铣挖及配套机械化施工工法
CN101737005B (zh) 一种用于套取锚索的钻具及跟管套取锚索的施工方法
CN107023300A (zh) 一种采用棚护法建造地铁车站的施工方法
CN201714307U (zh) 重型风钻配套支架
CN106917627B (zh) 一种富水地层暗挖施工下导洞的超前支护方法
CN109441512B (zh) 钢筋混凝土对穿锚索及其施工方法
CN104895073B (zh) 可多次拆装的锚索施工系统及其施工方法
CN108035733A (zh) 一种岩质超大断面隧道钢架岩墙组合竖撑分部开挖方法
CN106837382B (zh) 一种地铁隧道围岩地面预注浆加固工艺
CN107133381A (zh) 一种巷道支护用锚杆的长度确定方法
CN107605509A (zh) 砂卵石地层小曲线半径浅埋隧道暗挖法超前支护施工方法
CN104234726A (zh) 一种穿越富水不整合接触带隧道的洞内降排水施工方法
CN107165661A (zh) 一种高地应力软弱围岩大变形隧道超长扩大头锚索施工方法
CN103321235A (zh) 一种复合土钉墙边坡支护方法
CN102235151B (zh) 砂卵石漂石层超前成孔方法
CN103410522A (zh) 浅埋暗挖法连续近距离下穿铁路桥的施工方法
CN109057802A (zh) 大断面浅埋隧道下穿高速公路施工方法
CN207513614U (zh) 浅埋隧道暗挖法超前支护结构及复合式超前小导管

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 610015 Sichuan province Chengdu City Shuncheng Street No. 206 Sichuan International Building, 19 floor

Applicant after: Chengdu Ranken Railway Construction Group Co., Ltd.

Address before: 610015 Sichuan province Chengdu City Shuncheng Street No. 206 Sichuan International Building, 19 floor

Applicant before: Chengdu Ranken Railway Construction, Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: CHENGDU RANKEN RAILWAY CONSTRUCTION, LTD. TO: CHENGDU RANKEN RAILWAY CONSTRUCTION GROUP CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 610015 Sichuan province Chengdu City Shuncheng Street No. 206 Sichuan International Building, 19 floor

Patentee after: RANKEN RAILWAY CONSTRUCTION GROUP CO., LTD.

Address before: 610015 Sichuan province Chengdu City Shuncheng Street No. 206 Sichuan International Building, 19 floor

Patentee before: Chengdu Ranken Railway Construction Group Co., Ltd.