CN102231500A - Method for installing intensive plug-in type bus duct - Google Patents

Method for installing intensive plug-in type bus duct Download PDF

Info

Publication number
CN102231500A
CN102231500A CN2011100836452A CN201110083645A CN102231500A CN 102231500 A CN102231500 A CN 102231500A CN 2011100836452 A CN2011100836452 A CN 2011100836452A CN 201110083645 A CN201110083645 A CN 201110083645A CN 102231500 A CN102231500 A CN 102231500A
Authority
CN
China
Prior art keywords
bus duct
support
installation
installing
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011100836452A
Other languages
Chinese (zh)
Inventor
聂在和
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Zhenzhong Electric Co Ltd
Original Assignee
Chengdu Zhenzhong Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Zhenzhong Electric Co Ltd filed Critical Chengdu Zhenzhong Electric Co Ltd
Priority to CN2011100836452A priority Critical patent/CN102231500A/en
Publication of CN102231500A publication Critical patent/CN102231500A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention provides a method for installing an intensive plug-in type bus duct, and the method comprises the following steps: unpacking equipment and checking; manufacturing a support; installing the support; installing a bus duct; and carrying out commissioning operation for checking and accepting. The method has the characteristics of homogeneity and standardization and can be used for avoiding the quality and safety hazards in the process of installing the bus duct.

Description

The method of intensive plug type bus duct is installed
Technical field
The present invention relates to bus duct and install, the method for intensive plug type bus duct particularly is installed under the specific form.
Background technology
At present domestic in high level and high-rise building, intensive plug type bus duct is widely adopted owing to having series of advantages.At present, have different challenges under the varying environment condition about being installed in of bus duct, especially for movable equipment, concave plane, especially for the indoor bus duct installing engineering below the 0.4kV in general industry, military installations, the civil buildings, still there is not good solution.
Summary of the invention
In order to solve above-mentioned drawback, the invention provides a kind of intensive plug type bus duct installation method, a kind of method that intensive plug type bus duct is installed, comprising equipment unpacks and to check inspections → rack making → support installation → bus duct installation → trial run examination, it is characterized in that: (1) is according to the structure type of job site, support should adopt angle steel, channel-section steel or round steel to make, and can adopt forms such as "-", " w ", " well " type.(2) stent applications cutting machine blanking, processing dimension worst error are 5mm.With bench drill, electric hand drill boring, forbid to use the gas cutting perforate, the aperture must not surpass diameter of bolt 2mm.(3) the suspension rod screw thread should adopt die head threading machine or tap processing, and fracture of wire must not be arranged.(4) support and suspension bracket are made and are finished, and should remove the weldering of removing slag, and brush antirust paint and finish paint.Wherein, the method for the intensive plug type bus duct of described installation is characterized in that: have spring between described support and the suspension bracket.
Description of drawings
Fig. 1: structural representation of the present invention.
Fig. 2: another structural representation of the present invention.
Among the figure: 1, bus duct 2, side dress pressing plate 3, expansion bolt 4, bolt and nut 5, suspension rod
6, angle steel suspension bracket 7, horizontal pressure foot
The tool execution mode
As Fig. 1, shown in 2, bus duct 1 has rated voltage, rated capacity, test report, Pareto diagram.Various shaped steel, the fastener of making support should pass through preservative treatment, and should adhere to specification; Expansion bolt, bolt, nut, pad, spring washer should be zinc coatings.Other material is as antirust paint, finish paint, welding rod etc.Main facility: workbench, bench vice, cutting machine, bench drill, electric hammer, die head threading machine, tap, electric welding machine, torque spanner, spanner etc.Testing tool: steel tape, steel set-square, level gauge, plumb bob, 500V megohm meter etc.Hole to be provided and built-in fitting are finished, and each layer of electric shaft ground is carried out.The operating procedure technological process: equipment is unpacked and is checked inspection → rack making → support installation → bus duct installation → trial run examination.Should make according to design and product documentation regulation.Specific requirement is: (1) according to the structure type of job site, support should adopt angle steel, channel-section steel or round steel to make, and can adopt 4 kinds of forms such as "-", " w ", " ", " well " type.(2) stent applications cutting machine blanking, processing dimension worst error are 5mm.With bench drill, electric hand drill boring, forbid to use the gas cutting perforate, the aperture must not surpass diameter of bolt 2mm.(3) the suspension rod screw thread should adopt die head threading machine or tap processing, and fracture of wire must not be arranged.(4) support and suspension bracket are made and are finished, and should remove the weldering of removing slag, and brush antirust paint and finish paint.Support install bus duct the corner and must mounting bracket with distribution box, cabinet junction, the straightway set spacing should be greater than 2m, support and suspension bracket must be installed firmly.Necessary backguy or ceiling hammer when support and suspension bracket are installed put down vertically to guarantee the horizontal of support in a row or suspension bracket, and spacing are provided with support or suspension bracket in accordance with regulations.Bus duct vertical run support: on every floor plate, every bus duct should be installed 2 channel-section steel supports, and an end is embedded within the walls, and the other end is fixed on the floor with expansion bolt.When two layers of channel-section steel support surpass 2m up and down, "-" font angle bar frame need be installed on the wall, angle bar frame is fixed on the wall with expansion bolt, and angle bar frame is welded on the angle bar frame, should guarantee that the vertical plane of all angle bar frames 2 in the vertical shaft becomes same vertical plane.Can adopt " w " type support, be fixed on the top board or on the wallboard with expansion bolt.The bus duct horizontal crouch to be installed, the installation of lying on one's side of bus duct level, and the weld of support should be removed welding slag, and brushes antirust paint and finish paint, must not pollute building.Press the bus duct Pareto diagram, begin upwards, install forward from initiating terminal (or electric shaft porch), its jack switch case height should meet design or bus duct factory regulation.(4) 1. vertical installation of bus duct measure good position earlier at the through-flooring place, with bolt two angle bar frames and bus duct are connected, antirattle spring, pad on the bolt sleeve that provides with manufacturer again, fastening nut is fixed on the channel-section steel support, and spring support group number is stipulated according to bus duct pattern and capacity by factory.With horizontal pressure foot and bolt, nut, flat shim, spring washer bus duct is fixed on "-" font angle bar frame, upwards installs by joint then, guarantee the perpendicularity (use plumb bob and hang vertical line) of bus duct, add cover plate, use bolted in end.The bus duct level is installed horizontal and is crouched and install: with horizontal pressure foot and bolt, nut, flat shim, spring washer bus duct (flat crouching) is fixed on the angle steel suspension bracket.With side dress pressing plate and bolt, nut, flat shim, spring washer bus duct (lying on one's side) is fixed on " " type angle steel suspension bracket.Guarantee the levelness of bus duct, add terminal cover, and use bolted in terminal.Dock connects: save bus ducts to connecting with two earlier, put into a bus connecting plate and insulation board every bus joint both sides, penetrate insulated bolt again, add flat shim, spring washer, the nut of screwing on then, fastening with torque spanner, the moment that reaches regulation gets final product, and fixes cover plate up and down at last.Bus duct connects the Tightening moment with insulated bolt: M10 is 55Nm; M12 is 75Nm; M16 is 115Nm.After 5 Installation Considerations (1) bus duct installs, further adjust, to guarantee the perpendicularity and the levelness of bus duct.When (2) the bus duct straightway is installed, to add a joint expansion joint about every 100m.(3) in installation, must carry out the measure that water leakage and anti-foreign matter enter.(4) bus duct earthing of casing bridging plate connects and should firmly prevent to become flexible, and forbids to weld, and bus duct shell two ends should be connected with protective earthing (zero) line.(5) finish the installation of inlet wire case and plug-in type switch-box by design drawing regulation.After 6 trial runs are checked and accepted (1) bus ducts and installed, should put in order, clean clean, shake with megohmmeter and to survey alternate, Relative Zero, relatively insulation resistance, and perform record.(2) after checkout adheres to specification, send electric no-load running 24h no abnormal phenomenon, handle the examination formality, hand over construction unit to use, submit the examination data simultaneously to.(3) examination data comprises: the receipt of handing over, design alteration record, work certificate, specification, test record, preoperation record etc.Attached: plug type bus duct is installed sea market quality standard 1. assurance project (1) models, specification, quality and must be adhered to specification, and product testing result must compliant.Insulation resistance should be greater than 10M Ω.(2) the spring-loaded device is installed and should be met design and product technology requirement.(3) temperature rise of bus duct joint should meet the product technology requirement.2. elementary item (1) bus duct installation qualification: 1. the suspension rod of suspension type bus duct or suspension bracket should have the adjustment bolt, bus duct vertically is installed is crossed the floor place elastic bearing frame should be set.The spacing of fixing point should meet product requirement, then must not be greater than 2m during as the product no standard.2. the connection of each section bus duct shell should be removable, and should there be the above clear distance of 3mm adjacent running through between busbar joint set bolt packing ring, and the fastening force of bolt is apart from the requirement that should meet product.Good: on qualified basis, the bus duct joint must not be arranged on wall, floor place, and sheath should be arranged, should be anti-blocking complete when passing the area of fire protection partition wall, and bus duct is anticorrosion complete.(2) annex installation qualification: the annex of bus duct, must adhere to specification as the installation of inlet wire joint, expansion joint, commutation joint, coupling box, the position is set should be convenient to operation, repairs, installation should be firm.Good: on qualified basis, used fix bolt-unfastening preventing packing ring is complete, paints complete.(3) ground connection (connecting to neutral) is qualified: each section bus duct should have jumper between the groove shell except that grounding requirement up to specification, and the earth connection specification meets corresponding standard, and reliable ground.When system is five-wire system system and PE line when directly reliably being connected with the bus duct shell, can consider not establish jumper, but must have the relevant technologies of manufacturer to prove.Good: on qualified basis, line alignment is reasonable, and colour code is correct, not contaminated equipment and building after the brushing.3. permissible variation project (1) set spacing is not more than 2m, and permissible variation is 100mm; The bus duct centreline spacing is not less than 0.4m, permissible variation 10mm side by side.(2) the perpendicularity permissible variation of bus duct is 1.5mm/m, and the total length permissible variation is not more than 10mm; The levelness permissible variation is 1mm/m, and the total length permissible variation is not more than 10mm.
The invention is not restricted to the foregoing description; in design scope of the present invention; the description of book according to the above description, those of ordinary skill in the art also can make some conspicuous changes, but these changes all should fall within the protection range of claim of the present invention.

Claims (2)

1. method that intensive plug type bus duct is installed, comprising equipment unpacks and to check inspections → rack making → support installation → bus duct installation → trial run examination, it is characterized in that: (1) is according to the structure type of job site, support should adopt angle steel, channel-section steel or round steel to make, and can adopt forms such as "-", " w ", " well " type.(2) stent applications cutting machine blanking, processing dimension worst error are 5mm.With bench drill, electric hand drill boring, forbid to use the gas cutting perforate, the aperture must not surpass diameter of bolt 2mm.(3) the suspension rod screw thread should adopt die head threading machine or tap processing, and fracture of wire must not be arranged.(4) support and suspension bracket are made and are finished, and should remove the weldering of removing slag, and brush antirust paint and finish paint.
2. according to the method for the intensive plug type bus duct of the described installation of claim 1, it is characterized in that: have spring between described support and the suspension bracket.
CN2011100836452A 2011-04-02 2011-04-02 Method for installing intensive plug-in type bus duct Pending CN102231500A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011100836452A CN102231500A (en) 2011-04-02 2011-04-02 Method for installing intensive plug-in type bus duct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011100836452A CN102231500A (en) 2011-04-02 2011-04-02 Method for installing intensive plug-in type bus duct

Publications (1)

Publication Number Publication Date
CN102231500A true CN102231500A (en) 2011-11-02

Family

ID=44844045

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011100836452A Pending CN102231500A (en) 2011-04-02 2011-04-02 Method for installing intensive plug-in type bus duct

Country Status (1)

Country Link
CN (1) CN102231500A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103795012A (en) * 2014-01-27 2014-05-14 中铁建设集团设备安装有限公司 Hidden support and bridge device and installation method thereof
CN104078875A (en) * 2014-07-03 2014-10-01 镇江市江岛电器制造有限公司 Bus duct installing method
CN104134959A (en) * 2014-08-14 2014-11-05 陕西化建工程有限责任公司 Method for installing total-die-cast type medium-voltage busbar
CN111786337A (en) * 2020-07-22 2020-10-16 四川省第十一建筑有限公司 Construction method of reinforced bus duct

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2285020Y (en) * 1996-07-30 1998-06-24 上海塔汇电器厂 Straightway connecting device of concentrated bus slot
CN201590633U (en) * 2009-12-24 2010-09-22 贵阳铝镁设计研究院 Bus-suspending simple bracket

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2285020Y (en) * 1996-07-30 1998-06-24 上海塔汇电器厂 Straightway connecting device of concentrated bus slot
CN201590633U (en) * 2009-12-24 2010-09-22 贵阳铝镁设计研究院 Bus-suspending simple bracket

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《安装》杂志编辑部: "《安装工程实用技术》", 30 April 2001, article "密集型插接式母线槽的安装", pages: 315-318 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103795012A (en) * 2014-01-27 2014-05-14 中铁建设集团设备安装有限公司 Hidden support and bridge device and installation method thereof
CN104078875A (en) * 2014-07-03 2014-10-01 镇江市江岛电器制造有限公司 Bus duct installing method
CN104134959A (en) * 2014-08-14 2014-11-05 陕西化建工程有限责任公司 Method for installing total-die-cast type medium-voltage busbar
CN104134959B (en) * 2014-08-14 2016-08-24 陕西化建工程有限责任公司 The installation method of full mould casted middle voltage bus rod
CN111786337A (en) * 2020-07-22 2020-10-16 四川省第十一建筑有限公司 Construction method of reinforced bus duct

Similar Documents

Publication Publication Date Title
CN102231500A (en) Method for installing intensive plug-in type bus duct
CN104746874A (en) Construction site online safety monitoring system construction method
CN102231505A (en) Intensive plug-in type busbar
CN101928579B (en) Installing method of dry quenching fire automatic alarm system
CN205029156U (en) Bellows combination compression frock
CN104134959B (en) The installation method of full mould casted middle voltage bus rod
KR100450283B1 (en) A overhaul method of a water turbine generator
CN104065929A (en) Petroleum video monitoring installation process
CN108736406A (en) Wire casing laying and construction method
CN210517338U (en) Quick repeated grounding device of mobile switch box in building industry
CN111834954A (en) Laboratory power electrical system construction process
CN103454083A (en) Protection performance test method of shell of online monitoring device
CN105305332A (en) Electric engineering construction method
CN105186252B (en) A kind of combined bellows compression tooling
JP3210165U (en) Piping workability evaluation test equipment
Branford et al. SECTION 16050 ELECTRICAL WORK–GENERAL PART 1–GENERAL 1.01 DESCRIPTION
CN219717837U (en) Bent butt joint section tubular bus
KR20150046577A (en) Apparatus for protection potential multiguard of gas pipe line and method for remote control of that
CN113376475B (en) Insulation fault positioning method for low-voltage distribution board of nuclear power plant
CN110649555B (en) Flexible quick-connection plug supporting device
WO2021071447A1 (en) Digital earthing measuring earthed socket and group socket systems
MIL 1.3 APPLICABLE PUBLICATIONS
Zheng et al. On the Electrical Installment Technology of 10kV Switching Room
METAL SECTION 22 05 11 COMMON WORK RESULTS FOR PLUMBING
Bonding 1.06 DELIVERY, STORAGE, AND HANDLING

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20111102