CN102157299A - Online monitoring gas relay - Google Patents

Online monitoring gas relay Download PDF

Info

Publication number
CN102157299A
CN102157299A CN2011100700151A CN201110070015A CN102157299A CN 102157299 A CN102157299 A CN 102157299A CN 2011100700151 A CN2011100700151 A CN 2011100700151A CN 201110070015 A CN201110070015 A CN 201110070015A CN 102157299 A CN102157299 A CN 102157299A
Authority
CN
China
Prior art keywords
ball float
gas
buchholz relay
line monitoring
fulcrum
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011100700151A
Other languages
Chinese (zh)
Other versions
CN102157299B (en
Inventor
刘畅
Original Assignee
Liu Chang International Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liu Chang International Co Ltd filed Critical Liu Chang International Co Ltd
Priority to CN 201110070015 priority Critical patent/CN102157299B/en
Publication of CN102157299A publication Critical patent/CN102157299A/en
Application granted granted Critical
Publication of CN102157299B publication Critical patent/CN102157299B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Housings And Mounting Of Transformers (AREA)

Abstract

The invention belongs to the protective field of transformer, specifically relates to an online monitoring gas relay. The prior gas relay only sends out alarming signals after the gas is much enough and the relay acts, and can not online monitor the amount of the generated gas. The online monitoring gas relay related by the invention comprises a shell, an air release valve and a floating ball; the online monitoring gas relay is characterized in that a support point is disposed in the shell; the support point is provided with a conductive lever; the conductive lever and the support point are in rotary connection; one end of the conductive lever is connected to the floating ball, and the other end is in contacted connection with the nodes of a multi-node disc; the nodes on the multi-node disc are respectively connected to leads disposed in parallel; equivalent resistors are connected between the adjacent leads; and the resistor at the tail end is connected to the support point by a return lead. The online monitoring gas relay related by the invention can realize the online monitor of gas amount in mesh gas.

Description

The on-line monitoring Buchholz relay
Technical field
The invention belongs to transformer explosion-protection equipment field, be specifically related to a kind of on-line monitoring Buchholz relay.
Background technology
Power transformer is the great equipment of operation power, costs an arm and a leg.The online protection of transformer is particularly important.Buchholz relay is of paramount importance first protection of transformer, and Buchholz relay is installed on the pipeline between transformer and the conservator, fills with insulating oil when transformer normally moves.The Buchholz relay of prior art comprises that housing, vent valve, housing the inside are provided with light gas and heavy gas, light gas is made of top ball float and light gas tongue tube, the top ball float is connected with magnet, the top is provided with light gas dry reed switch, heavy gas comprises that bottom ball float, stream oil baffle and heavy gas tongue tube, baffle plate are rotatably connected with fixing point, and the bottom ball float is connected with magnet.
When producing gas in the transformer, to conservator, gas at first concentrates in first chamber of Buchholz relay by pipeline in the gas rising.Simultaneously, oil level descends, and the top ball float drives magnet and is moved to the light gas tongue tube in top, and alarm signal is sent in light gas tongue tube action.When important electrical breakdown accident takes place in transformer, will produce in inside and continue or interrupted arc burning insulating oil, (particularly turn-to-turn short circuit produces the rapid imflammable gas of sending out etc.) methane gas will continue to produce, the bottom ball float will start heavy gas tongue tube simultaneously, the action of heavy gas often is accompanied by flowing of oil, and oil stream plate washer and bottom ball float have relevant action.The action of oil stream plate washer can make heavy gas tongue tube move by displacement magnet equally.Heavy gas dry-reed tube switch action is commonly used to be connected to trip breaker, thereby transformer and electrical network are disconnected, and is out of service.Rise up into Buchholz relay on the gas by oil decomposition when light gas mainly is reflected in operation or minor failure, air pressure descends pasta, the ball float of relay falls with pasta, when magnet is moved to light gas tongue tube, contacting sends alarm signal, and light gas action does not mean that transformer necessarily has problem.Fortune inspection personnel can emit sampling with gas by the vent valve of Buchholz relay; After analyzing, the composition that can move by gas determines whether that transformer needs interruption maintenance.The action of heavy gas has reflected that necessarily great fault has appearred in transformer.
The light gas of existing Buchholz relay all is when waiting gas abundant, usually (250ml~just can move when 350ml) displacement of first ball float drives magnet to tongue tube.If be gas at the beginning by discharge generation, usually can the big fault of very fast initiation, as partial short-circuit etc.
If after the light gas action of relay, take measures, probably when light gas tongue tube did not move, important accident had just taken place and has directly caused heavy gas action in transformer again.With existing product in the world, the generation that we can't the on-line monitoring minimum gas at present.Can not how much carry out the on-line continuous monitoring to producing gas, the transformer of normal operation does not have gas to produce, if partial discharge is enough serious, the generation that we again can the early detection pernicious gas just can be avoided great Accident of Transformer effectively.
Summary of the invention
In order to overcome the shortcoming of prior art, the purpose of this invention is to provide a kind of on-line monitoring Buchholz relay, can not carry out the gas on-line monitoring to solve the prior art Buchholz relay, can not carry out the problem of real-time guard to transformer.
To achieve these goals, the technical solution used in the present invention is: the explosion-proof Buchholz relay of a kind of on-line monitoring, comprise housing, vent valve, top ball float and heavy gas, it is characterized in that: be provided with a fulcrum in the housing, fulcrum is provided with a conduction lever, described conduction lever and fulcrum are rotationally connected, described conduction lever one end is connected with the top ball float, and the node contact that the other end is connected with the multinode dish connects, and the node on the multinode dish is connected with the lead that be arranged in parallel respectively, be connected with equivalent resistance between the adjacent wires, and connect by return wire between terminal resistance and the fulcrum.
Be provided with balancing weight below the ball float of above-mentioned top, described balancing weight is hinged with the conduction lever with the top ball float respectively.
The averag density of above-mentioned top ball float equals the density of oil, is provided with one and the connecting rod that equates of oil density then in the bottom of top ball float, and described connecting rod is hinged with the conduction lever with the top ball float respectively.
Be in series with the TC10-R current converter on the above-mentioned wire loop.
The number of lead wires of above-mentioned multinode dish is 25-35;
The resistance of the resistance of above-mentioned equivalence is 5 ohm or 10 ohm.
Above-mentioned conduction lever is positioned at the flexible silver tipped contact of end rivet welding of multinode dish one side.
Lead in the above-mentioned loop is two or three parallel connections.
Distance between above-mentioned fulcrum and the top ball float is greater than the distance of fulcrum and multinode dish.Measure sensitiveer.
Description of drawings
Fig. 1 is the prior art constructions schematic diagram,
Fig. 2 is a structural representation of the present invention,
Fig. 3 is the partial schematic diagram of a kind of embodiment,
Fig. 4 is the partial schematic diagram of another embodiment,
Wherein, 1-housing, 2-vent valve, 3-top ball float, 4-magnet, the light gas tongue tube of 5-, 6-mercury node, 7-bottom ball float, the heavy gas dry-reed contact of 8-, 9-magnet, 10-flows oil baffle, 11-fulcrum, 12-conducts electricity lever, 13-multinode dish, 14-lead, 15-resistance, 16-return wire, 17-balancing weight, the 18-current converter, 19-connecting rod, 20-connecting plate.
Embodiment
The present invention will be further described below in conjunction with the drawings and specific embodiments.
Referring to Fig. 1, a kind of Buchholz relay of the prior art, the Buchholz relay of prior art comprises that housing 1, vent valve 2, housing 1 the inside are provided with light gas and heavy gas, light gas is made of top, top ball float 3 and light gas tongue tube 5, top, top ball float 3 is connected with magnet 4, be provided with mercury contact 6 above the magnet 4, heavy gas comprises that bottom ball float 7, stream oil baffle 10 and heavy gas tongue tube 8, stream oil baffle 10 are rotatably connected with fixing point, and bottom ball float 7 is connected with magnet 9.
When being created in normal operation in the transformer, be full of oil in the relay, top, top ball float 3 is immersed in the oil, is in the come-up position, and light gas tongue tube 5 disconnects; 10 of oil baffles of stream since weight own and sagging, heavy gas tongue tube 8 also disconnects.When producing gas in the transformer, to conservator, gas at first concentrates in first chamber of Buchholz relay by pipeline in the gas rising.Simultaneously, oil level descends, and top, top ball float 3 drives magnet 4 and is moved to light gas tongue tube 5, and alarm signal is sent in light gas tongue tube 5 actions.When important electrical breakdown accident takes place in transformer, will produce in inside and continue or interrupted arc burning insulating oil, (particularly turn-to-turn short circuit produces the rapid imflammable gas of sending out etc.) methane gas will continue to produce, bottom ball float 7 will start heavy gas tongue tube 8 simultaneously, the action of heavy gas often is accompanied by flowing of oil, and oil stream plate washer 10 and bottom ball float 7 have relevant action.The action of oil stream plate washer 10 can make heavy gas tongue tube 8 move by displacement magnet 9 equally.Heavy gas tongue tube 8 actions are commonly used to be connected to trip breaker, thereby transformer and electrical network are disconnected, and are out of service.Rise up into Buchholz relay on the gas by oil decomposition when light gas mainly is reflected in operation or minor failure, air pressure descends pasta, the ball float of relay falls with pasta, and light gas dry-reed contact is connected and sent alarm signal, and light gas action does not mean that transformer necessarily has problem.Fortune inspection personnel can emit sampling with gas by the vent valve of Buchholz relay; After analyzing, the composition that can move by gas determines whether that transformer needs interruption maintenance.The action of heavy gas has reflected that necessarily great fault has appearred in transformer.
But the light gas of above-mentioned Buchholz relay all is when waiting gas abundant, usually (250ml~just can move when 350ml) displacement of top ball float drives magnet to tongue tube.If be gas at the beginning by discharge generation, usually can the big fault of very fast initiation, as partial short-circuit etc.If after the action of the light gas of relay, take measures, probably when light gas tongue tube 5 did not move, important accident had just taken place and has directly caused heavy gas action in transformer again, generation that can't the on-line monitoring minimum gas.Can not how much carry out the on-line continuous monitoring to producing gas.
Referring to Fig. 2, the explosion-proof Buchholz relay of a kind of on-line monitoring of the present invention, the explosion-proof Buchholz relay of a kind of on-line monitoring, comprise housing 1, vent valve 2, top ball float 3 and heavy gas, be provided with a fulcrum 11 in the housing 1, fulcrum 11 is provided with a conduction lever 12, and described conduction lever 12 and fulcrum 11 are rotationally connected, and described conduction lever 12 1 ends are connected with top ball float 3, node contact on the other end and the multinode dish 13 is connected, the node of multinode dish 13 is connected with the lead 14 that be arranged in parallel respectively, is connected with equivalent resistance 15 between the adjacent wires 14, and connects by return wire 16 between terminal resistance 15 and the fulcrum 11.Lead 14 numbers that described multinode dish 13 connects are 25-35, and the value of the resistance 15 of described equivalence is 5 ohm or 10 ohm.
Referring to Fig. 3 and Fig. 4, described loop return wire 16 is two parallel connections, is connected with TC10-R current converter 18.Two lead parallel connections can reduce the electric current that return wire produces greatly, can make measurement more accurate.Whole multinode dish 13 and lead 14 are arranged on above the connecting plate 20, and the inwall of connecting plate and Buchholz relay is fixedlyed connected.Be provided with balancing weight 17 below the top ball float 3, described balancing weight 17 is hinged with conduction lever 12 with top ball float 3 respectively, perhaps the averag density of top ball float 3 equals the density of oil, be provided with one and the connecting rod 19 that equates of oil density then in the bottom of top ball float 3, described connecting rod 19 is hinged with the conduction lever with top ball float 3 respectively.The purpose that balancing weight is set is that the averag density of top ball float 3 is equated with the density of oil, the top of ball float does not contact with inwall on the Buchholz relay when having gas in the relay like this, if there is gas to produce, when liquid level descends, the top of ball float also can be equal with oil level all the time, can reduce error like this, the error when ball float descends when especially opening most.Because ball float density is during less than the density of oil, gas need produce that ball float just can descend when a certain amount of, so do not detect changes in resistance this moment.
The course of work:
Conduction lever 12 and multinode dish 13 are formed the loop, are provided with current converter 18 in the loop.Top ball float 3 is on the pasta of Buchholz relay, top ball float 3 can rotate around fulcrum 11 by conduction lever 12, and the other end that drives conduction lever 12 is done corresponding rotation around fulcrum 11, when internal fault appears in transformer, the gas that produces will accumulate in the top of Buchholz relay, pasta is reduced, after pasta is reduced to a certain degree, top ball float 3 just sinks, top ball float 3 sinks and does counter-rotation by fulcrum 11 drive conduction levers 12 other ends, the lever 12 that then conducts electricity slides on multinode dish 13, thereby be connected with the different conductor 14 on the multinode dish 13, because the resistance 15 of resistance such as be provided with between the adjacent wires 14, so can produce electric current on the loop changes, and under the top ball float 3 dropping distances situation about equating, the electrorheological value is identical on the loop, so, just can calculate the distance that ball float fluctuates by the changing value that detects electric current on the loop, and then know what of gas flow in the Buchholz relay, so just can realize the on-line monitoring of Buchholz relay gas flow, if gas is too much, just can the gas that produce be bled off by vent valve 2, so just can detect what of gas flow in the Buchholz relay at any time, can prevent trouble before it happens, effectively avoid the generation of various harm.
The present invention when ball float along with pasta during to bottom offset, contact will change resistance value, thus the resistance value of this variable just corresponding the variation of gas.This resistance is connected to transmitter, and transmitter will be exported variable 4-20mA electric current and give distant place computer, and computer just can monitor the generation of gas at any time by the variation of electric current.This invention can be implemented continuous on-line monitoring to the gas flow that produces in the Buchholz relay.

Claims (8)

1. on-line monitoring Buchholz relay, comprise housing (1), vent valve (2), top ball float (3) and heavy gas, it is characterized in that: be provided with a fulcrum (11) in the housing (1), fulcrum (11) is provided with a conduction lever (12), described conduction lever (12) and fulcrum (11) are rotationally connected, described conduction lever (12) one ends are connected with top ball float (3), on the other end and the multinode dish (13) the node contact be connected, node on the multinode dish (13) is connected with the lead (14) that be arranged in parallel respectively, be connected with equivalent resistance (15) between the adjacent wires (14), and connect by return wire (16) between terminal resistance and the fulcrum (11).
2. on-line monitoring Buchholz relay according to claim 1 is characterized in that: be provided with balancing weight (17) below the described top ball float (3), described balancing weight (17) is hinged with conduction lever (12) with top ball float (3) respectively.
3. on-line monitoring Buchholz relay according to claim 1, it is characterized in that: the averag density of described top ball float (3) equals the density of oil, be provided with the connecting rod (19) that equates with oil density then in the bottom of ball float (3), described connecting rod (19) respectively and ball float (3) hinged with conduction lever (12).
4. according to the arbitrary described on-line monitoring Buchholz relay of claim 1-3, it is characterized in that: be in series with TC10-R current converter (18) on the described wire loop.
5. on-line monitoring Buchholz relay according to claim 4 is characterized in that: lead (14) number of described multinode dish (13) is 25-35, and the resistance of the resistance of described equivalence (15) is 5 ohm or 10 ohm.
6. on-line monitoring Buchholz relay according to claim 5 is characterized in that: described above-mentioned conduction lever (12) is positioned at the flexible silver tipped contact of end rivet welding of multinode dish (13) one sides.
7. on-line monitoring Buchholz relay according to claim 6 is characterized in that: described return wire (16) is two or three parallel connections.
8. on-line monitoring Buchholz relay according to claim 7 is characterized in that: the distance between described fulcrum (11) and the top ball float (3) is greater than the distance of fulcrum (11) and multinode dish (13).
CN 201110070015 2011-03-23 2011-03-23 Online monitoring gas relay Expired - Fee Related CN102157299B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110070015 CN102157299B (en) 2011-03-23 2011-03-23 Online monitoring gas relay

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110070015 CN102157299B (en) 2011-03-23 2011-03-23 Online monitoring gas relay

Publications (2)

Publication Number Publication Date
CN102157299A true CN102157299A (en) 2011-08-17
CN102157299B CN102157299B (en) 2013-02-27

Family

ID=44438723

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110070015 Expired - Fee Related CN102157299B (en) 2011-03-23 2011-03-23 Online monitoring gas relay

Country Status (1)

Country Link
CN (1) CN102157299B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102856116A (en) * 2012-09-12 2013-01-02 辽宁省电力有限公司电力科学研究院 Double floater and double contact gas relay
CN103021733A (en) * 2012-12-28 2013-04-03 浙江省电力设计院 Gas relay for optical fiber trip of intelligent substation
CN104134576A (en) * 2014-07-16 2014-11-05 国家电网公司 Three-pin reed switch type double-circuit trip node gas relay
CN106371015A (en) * 2016-12-11 2017-02-01 国家电网公司 Rapid operation identification method and device of gas relay
CN114242512A (en) * 2022-02-16 2022-03-25 贵州电网有限责任公司 Safe automatic exhaust device for main transformer gas relay

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB844853A (en) * 1956-05-25 1960-08-17 English Electric Co Ltd Improvements relating to protective relays for oil-filled apparatus
CN1154587A (en) * 1996-01-09 1997-07-16 郑扶才 Capacitor type gas relay
CN2412209Y (en) * 2000-01-27 2000-12-27 盘兴国 Liqud level measuring display
CN1894565A (en) * 2003-12-19 2007-01-10 西门子公司 Device and method for monitoring a gas volume in a unit filled with liquid
CN201323162Y (en) * 2008-12-23 2009-10-07 沈阳沈变所电气科技有限公司 Gas-actuated relay
CN201975338U (en) * 2011-03-23 2011-09-14 刘畅 On-line monitoring gas relay

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB844853A (en) * 1956-05-25 1960-08-17 English Electric Co Ltd Improvements relating to protective relays for oil-filled apparatus
CN1154587A (en) * 1996-01-09 1997-07-16 郑扶才 Capacitor type gas relay
CN2412209Y (en) * 2000-01-27 2000-12-27 盘兴国 Liqud level measuring display
CN1894565A (en) * 2003-12-19 2007-01-10 西门子公司 Device and method for monitoring a gas volume in a unit filled with liquid
CN201323162Y (en) * 2008-12-23 2009-10-07 沈阳沈变所电气科技有限公司 Gas-actuated relay
CN201975338U (en) * 2011-03-23 2011-09-14 刘畅 On-line monitoring gas relay

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102856116A (en) * 2012-09-12 2013-01-02 辽宁省电力有限公司电力科学研究院 Double floater and double contact gas relay
CN103021733A (en) * 2012-12-28 2013-04-03 浙江省电力设计院 Gas relay for optical fiber trip of intelligent substation
CN103021733B (en) * 2012-12-28 2015-09-23 浙江省电力设计院 A kind of optical fiber trip of intelligent substation Buchholz relay
CN104134576A (en) * 2014-07-16 2014-11-05 国家电网公司 Three-pin reed switch type double-circuit trip node gas relay
CN106371015A (en) * 2016-12-11 2017-02-01 国家电网公司 Rapid operation identification method and device of gas relay
CN106371015B (en) * 2016-12-11 2023-09-26 国家电网公司 Gas relay action rapid identification method and device
CN114242512A (en) * 2022-02-16 2022-03-25 贵州电网有限责任公司 Safe automatic exhaust device for main transformer gas relay
CN114242512B (en) * 2022-02-16 2024-04-16 贵州电网有限责任公司 A safe automatic exhaust device for main gas relay that becomes

Also Published As

Publication number Publication date
CN102157299B (en) 2013-02-27

Similar Documents

Publication Publication Date Title
CN102157299B (en) Online monitoring gas relay
WO2020224553A1 (en) Transformer monitoring apparatus and method based on non-electric-quantity comprehensive characteristic information
CN201975334U (en) Gas relay with on-line monitoring function
CN201975338U (en) On-line monitoring gas relay
CN203760377U (en) Temperature-sensitive switch with disconnection detection function and temperature-sensitive detector of temperature-sensitive switch
KR101255317B1 (en) Arrester Soundness Decision and Line Monitoring System by Measuring Leakage current of Arrester
CN109613426B (en) Aging diagnosis method for plum blossom contact of high-voltage circuit breaker
CN103234578A (en) Switchgear environment status parameter monitoring device based on ZigBee network
BRPI1011777B1 (en) method for detecting failure of a vacuum switch in a loaded tap changer and a loaded tap changer arrangement
CN103325627A (en) Fast and intelligent 10KV pole-mounted breaker
CN110018328A (en) A kind of power transformer on-Line Monitor Device and method based on transient state oil stream feature
CN104134576A (en) Three-pin reed switch type double-circuit trip node gas relay
US20140133054A1 (en) Safety apparatus and monitoring method for a power transformer, and related power transformer
CN105977090A (en) Outdoor integrated embedded pole
CN103063373A (en) Leak detector of capsule for transformer oil conservator
CN103620719A (en) Buchholz relay
CN203148469U (en) Monitoring device for switch cabinet environment parameters based on ZigBee network
CN204067186U (en) Three pin tongue tube type two-way tripping operation node Buchholz relays
CN202796772U (en) 10kV rapid intelligent column breaker
CN108168770A (en) A kind of on-load tap changers of transformers grease chamber pressure on-line monitoring system
CN208539573U (en) A kind of phase-change switch that can prevent detection automatically
CN115096354A (en) System for monitoring oil flow state inside transformer
CN213183028U (en) Cable of linear temperature-sensing fire detector
CN209029297U (en) A kind of internal filling vacuum interrupter of cushion
CN203325798U (en) Gas relay for transformer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130227

Termination date: 20200323