CN102155006B - Steel structure open web combined dam - Google Patents

Steel structure open web combined dam Download PDF

Info

Publication number
CN102155006B
CN102155006B CN2011100634107A CN201110063410A CN102155006B CN 102155006 B CN102155006 B CN 102155006B CN 2011100634107 A CN2011100634107 A CN 2011100634107A CN 201110063410 A CN201110063410 A CN 201110063410A CN 102155006 B CN102155006 B CN 102155006B
Authority
CN
China
Prior art keywords
steel work
skeleton
buttress
dam
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011100634107A
Other languages
Chinese (zh)
Other versions
CN102155006A (en
Inventor
魏群
刘尚蔚
张国新
李蒲健
魏鲁双
孙凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China University of Water Resources and Electric Power
Original Assignee
North China University of Water Resources and Electric Power
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North China University of Water Resources and Electric Power filed Critical North China University of Water Resources and Electric Power
Priority to CN2011100634107A priority Critical patent/CN102155006B/en
Publication of CN102155006A publication Critical patent/CN102155006A/en
Application granted granted Critical
Publication of CN102155006B publication Critical patent/CN102155006B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a steel structure open web combined dam. The steel structure open web combined dam comprises a certain number of concrete buttresses, a concrete bearing platform below the buttresses, and a steel structure panel on the buttresses; a seepage-proofing wall is arranged below the concrete bearing platform; the cross section of the steel structure combined panel is matched with that of each buttress, and is wrapped on the buttresses and two sides of the buttresses; the steel structure combined panel comprises an internal framework and a plurality of unit steel plates which are wrapped on two surfaces of the framework; a splicing gap between adjacent unit steel plates is positioned at the framework; the edges of the unit steel plates are connected to the framework through a fastening piece; and a sealing structure is arranged at the splicing gap between adjacent unit steel plates. In the dam, the steel structure panel is adopted, seepage-proofing capacity is improved, construction is simplified and cost is reduced, and the dam is favorable for environment-friendliness.

Description

Steel work is combined dam on an empty stomach
Technical field
The present invention relates to the technical field of water resource infrastructure, particularly relate to a kind of steel work combined dam on an empty stomach.
Background technology
The antiseepage body of traditional buttress formula concrete face rockfill dam is made up of panel and toe board jointly; Panel and toe board all are that concrete constitutes; Concrete existence owing to the heat of hydration in work progress causes very easily appearance temperature crack of panel, and the existence in crack will cause dam body to produce infiltration, makes overall structure produce infiltration and stable problem; Large-area concrete slab is in case appearance damages simultaneously, and maintenance and repair is very inconvenient.
Summary of the invention
To the objective of the invention is in order addressing the above problem, a kind of steel work combined dam on an empty stomach to be provided.
Technical scheme of the present invention is: a kind of steel work is combined dam on an empty stomach; Contain concrete bearing platform and the steel work assembled panel on buttress below some concrete buttress, the buttress; Below concrete bearing platform, be provided with impervious wall; Described steel work assembled panel cross section and buttress cross section coupling are coated on above the buttress and both sides; This steel work assembled panel contains inner skeleton and overlays on two lip-deep unit of skeleton steel plate with several; Splicing slit between the adjacent unit steel plate is positioned at the skeleton place; Steel plate edge, described unit is connected on the skeleton through securing member, and the edge joint position of adjacent unit steel plate is provided with hermetically-sealed construction.
Described skeleton is to contain vertical beam and the crossbeam that intersects in length and breadth; Vertical beam and crossbeam all adopt i iron or channel-section steel, but preferred i iron, the joint face of described i iron is provided with screwed hole; Securing member passes the unit steel plate and is installed in this screwed hole, and the unit steel plate is fixed; The vertical beam of described skeleton bottom and the spacing of vertical beam are less than the spacing of the vertical beam and the vertical beam on skeleton top, and the crossbeam of described skeleton bottom and the spacing of crossbeam are less than the spacing of the crossbeam and the crossbeam on skeleton top.
Described hermetically-sealed construction contains approximate " several " font weather strip of cross section; Between the slit of two adjacent unit steel plates of the bossing clamping of sealing bar; Two lower edges of sealing bar are fitted in respectively between the surface of unit steel plate and skeleton, and are fixed by described securing member.
Described hermetically-sealed construction contains approximate " Ω " font weather strip of cross section, and two lower edges of sealing bar bottom are fitted in respectively between the surface of unit steel plate and skeleton, and are fixed by described securing member; Sealing bar top is cap, and this cap covers outside the seam of adjacent unit steel plate.
Be connected through stone bolt between the lower edges of described steel work assembled panel and the riverbed toe board, and be provided with hermetically-sealed construction; Between the edge at dam body two ends and riverbed toe board, being connected of described steel work assembled panel through stone bolt, and be provided with hermetically-sealed construction.
The lower edges of described steel work assembled panel embeds interior one section of riverbed toe board, and is provided with hermetically-sealed construction; In the edge at dam body two ends embeds the riverbed toe board one section of described steel work assembled panel, and be provided with hermetically-sealed construction.
Described concrete bearing platform and concrete buttress are the line of demarcation with the riverbed surface, are concrete bearing platform below, are concrete buttress above.
Described concrete bearing platform comprises the half dam body on cushion cap pedestal and its top, and the cushion cap pedestal is positioned at the riverbed, and the half dam body is positioned at top, riverbed, and described concrete buttress is positioned at half dam body top, the cross sectional shape of half dam body and buttress cross sectional shape coupling.
Be provided with inserts in the cavity between the described buttress, this inserts is a building waste.
Described steel work assembled panel surface is provided with the preserving and sealing coating of polyurea materials.Described buttress is a solid construction, or is hollow-core construction, or is the concrete truss structure of hollow out.
Beneficial effect of the present invention
1, this steel work empty stomach combined dam; Its panel adopts the steel work assembled panel, the set inside skeleton, and the skeleton both sides are coated with the unit steel plate respectively; The combined and spliced formation combining structure of unit panel; Skeleton is the structure of intersecting in length and breadth, is beneficial to the installation of the unit steel plate in the work progress, is convenient to constructor's walking and depositing of construction tool; The two-sided steel plate that is provided with can improve the barrier performance of this panel, also is beneficial to the maintenance of panel in use of later stage dam simultaneously, and when removing the unit steel plate of front during maintenance, the corresponding steel plate in back also has the antiseepage ability, does not influence the operate as normal on dam.
2, this dam work progress is simplified; Duration is short, onesize dam than original can the reduction of erection time 1/2, construction cost reduces by 1/4; Replace original concrete anti-seepage panel through the steel work face slab for water retaining; The crack can not occur,, be convenient to the maintenance in later stage yet because this steel work face slab for water retaining adopts fabricated structure.
3, be provided with approximate " several " font weather strip of cross section between the adjacent unit steel plate; Perhaps cross section is similar to " Ω " font weather strip; Above-mentioned two kinds of weather strips are when playing sealing function; Also have the certain shrink effect, when whole steel structure combined panel expanded with heat and contract with cold owing to variations in temperature, the sealing bar can change with the slit between the unit steel plate.
4, this dam adopts buttress formula structure, comes the support steel structure face slab for water retaining through the concrete buttress that some is set, and the structure of dam body itself has also been simplified many like this; The speed of construction can be further improved, and other fillers can be filled in the cavity between the buttress, the refuse such as building waste; So just can reduce a large amount of exploitations of material; Minimizing utilizes discarded in a large number building waste environment damage again, is beneficial to environmental protection with energy-saving and cost-reducing.
5, the original position of the steel work assembled panel on this dam can begin from the riverbed, also can begin at a certain height place on top, riverbed, and height is versatile and flexible, can according to circumstances choose, to adapt to the different environment situation.
Description of drawings
Fig. 1 faces one of structural representation for this steel work empty stomach combined dam;
Fig. 2 is one of A-A cross section structure sketch map of Fig. 1;
Fig. 3 be Fig. 1 A-A cross section structure sketch map two;
Fig. 4 is one of I portion structure for amplifying sketch map of Fig. 1 or Fig. 2 or Figure 10;
Fig. 5 be Fig. 1 or Fig. 2 or Figure 10 I portion structure for amplifying sketch map two;
Fig. 6 is the framework local structural representation of steel work assembled panel;
Fig. 7 looks sketch map for the cushion cap among Fig. 1 with a pier structure master;
Fig. 8 is the sectional structure sketch map in the B-B cross section of Fig. 7;
Fig. 9 faces two of structural representation for this steel work empty stomach combined dam;
Figure 10 is the C-C cross section structure sketch map of Fig. 9;
Figure 11 looks sketch map for cushion cap among Fig. 9 with a pier structure master;
Figure 12 is the cross section structure sketch map of the D-D of Figure 11;
Figure 13 is the buttress sketch map of hollow-core construction;
Figure 14 is the buttress sketch map of the concrete truss structure of hollow out.
The specific embodiment
Referring to Fig. 1-Figure 12,1. riverbeds among the figure, 2. riverbed, 3. unit steel plate, 4. securing member, 5. cushion cap, 6. impervious wall, 7. stone bolt, 8. buttress, 9. crossbeam, 10. vertical beam, approximate " several " font weather strip of 11. cross sections, approximate " Ω " font weather strip of 12. cross sections, wherein 5-1. half dam body, 5-2. cushion cap pedestal.
Embodiment one: referring to Fig. 1, Fig. 2, Fig. 4, Fig. 6-Fig. 8; A kind of steel work empty stomach combined dam among the figure; Contain concrete bearing platform and the steel work assembled panel on buttress below some concrete buttress, the buttress; Below concrete bearing platform, be provided with impervious wall, described steel work assembled panel cross section and buttress cross section coupling are coated on above the buttress and both sides; This steel work assembled panel contains inner skeleton and overlays on two lip-deep unit of skeleton steel plate with several; Splicing slit between the adjacent unit steel plate is positioned at the skeleton place; Steel plate edge, described unit is connected on the skeleton through securing member, and the edge joint position of adjacent unit steel plate is provided with hermetically-sealed construction.
Described skeleton is to contain vertical beam and the crossbeam that intersects in length and breadth, and vertical beam and crossbeam all adopt i iron, and the joint face of described i iron is provided with screwed hole, and securing member passes the unit steel plate and is installed in this screwed hole, and the unit steel plate is fixed; The vertical beam of described skeleton bottom and the spacing of vertical beam are less than the spacing of the vertical beam and the vertical beam on skeleton top, and the crossbeam of described skeleton bottom and the spacing of crossbeam are less than the spacing of the crossbeam and the crossbeam on skeleton top.
Described hermetically-sealed construction contains approximate " several " font weather strip of cross section; Between the slit of two adjacent unit steel plates of the bossing clamping of sealing bar; Two lower edges of sealing bar are fitted in respectively between the surface of unit steel plate and skeleton, and are fixed by described securing member.Be connected (as shown in Figure 2) through stone bolt between the lower edges of described steel work assembled panel and the riverbed toe board, and be provided with hermetically-sealed construction; Described steel work assembled panel between the edge at dam body two ends and riverbed toe board, be connected (draw among the figure, its structure is similar between the lower edges and riverbed toe board of steel work assembled panel) here through stone bolt, and be provided with hermetically-sealed construction.
Described concrete bearing platform and concrete buttress are the line of demarcation with the riverbed surface, are concrete bearing platform below, are concrete buttress above.
Described steel work assembled panel surface is provided with the preserving and sealing coating of polyurea materials.Described buttress is a solid construction.
Embodiment two: referring to Fig. 1, Fig. 3, Fig. 4, Fig. 6-Fig. 8; Embodiment two and embodiment one are basic identical; Something in common does not repeat, and difference is that the lower edges of described steel work assembled panel embeds in the riverbed toe board one section (as shown in Figure 2), and is provided with hermetically-sealed construction; In the edge at dam body two ends embeds the riverbed toe board one section of described steel work assembled panel, and be provided with hermetically-sealed construction.
Embodiment three: referring to Fig. 1, Fig. 2, Fig. 5, Fig. 6-Fig. 8; Embodiment three and embodiment one are basic identical; Something in common does not repeat; Difference is that described hermetically-sealed construction contains approximate " Ω " font weather strip of cross section, and two lower edges of sealing bar bottom are fitted in respectively between the surface of unit steel plate and skeleton, and are fixed by described securing member; Sealing bar top is cap, and this cap covers outside the seam of adjacent unit steel plate.
Embodiment four: referring to Fig. 1, Fig. 3, Fig. 5, Fig. 6-Fig. 8; Embodiment four and embodiment two are basic identical; Something in common does not repeat; Difference is that described hermetically-sealed construction contains approximate " Ω " font weather strip of cross section, and two lower edges of sealing bar bottom are fitted in respectively between the surface of unit steel plate and skeleton, and are fixed by described securing member; Sealing bar top is cap, and this cap covers outside the seam of adjacent unit steel plate.
Embodiment five: referring to Fig. 9, Figure 10, Figure 11, Figure 12, Fig. 4; A kind of steel work empty stomach combined dam among the figure; Contain concrete bearing platform and the steel work assembled panel on buttress below some concrete buttress, the buttress; Below concrete bearing platform, be provided with impervious wall, described steel work assembled panel cross section and buttress cross section coupling are coated on above the buttress and both sides; This steel work assembled panel contains inner skeleton and overlays on two lip-deep unit of skeleton steel plate with several; Splicing slit between the adjacent unit steel plate is positioned at the skeleton place; Steel plate edge, described unit is connected on the skeleton through securing member, and the edge joint position of adjacent unit steel plate is provided with hermetically-sealed construction.
Described skeleton is to contain vertical beam and the crossbeam that intersects in length and breadth, and vertical beam and crossbeam all adopt i iron, and the joint face of described i iron is provided with screwed hole, and securing member passes the unit steel plate and is installed in this screwed hole, and the unit steel plate is fixed.
Described hermetically-sealed construction contains approximate " several " font weather strip of cross section; Between the slit of two adjacent unit steel plates of the bossing clamping of sealing bar; Two lower edges of sealing bar are fitted in respectively between the surface of unit steel plate and skeleton, and are fixed by described securing member.
Described concrete bearing platform comprises the half dam body on cushion cap pedestal and its top, and the cushion cap pedestal is positioned at the riverbed, and the half dam body is positioned at top, riverbed, and described concrete buttress is positioned at half dam body top, the cross sectional shape of half dam body and buttress cross sectional shape coupling.
Described steel work assembled panel surface is provided with the preserving and sealing coating of polyurea materials.Described buttress is a solid construction.
Embodiment six: referring to Fig. 9, Figure 10, Figure 11, Figure 12, Fig. 5; Embodiment six and embodiment five are basic identical; Something in common does not repeat; Difference contains approximate " Ω " font weather strip of cross section for the hermetically-sealed construction described in the embodiment six, and two lower edges of sealing bar bottom are fitted in respectively between the surface of unit steel plate and skeleton, and are fixed by described securing member; Sealing bar top is cap, and this cap covers outside the seam of adjacent unit steel plate.
Referring to Figure 13, Figure 14, the buttress in the foregoing description can also be hollow-core construction, or is the concrete truss structure of hollow out, can form more embodiment, does not detail one by one at this, all belongs to the protection domain of this patent.
Between the buttress in the foregoing description cavity in can be provided with inserts, this inserts is a building waste, also can form more embodiment, does not detail one by one at this, also belongs to the protection domain of this patent.

Claims (10)

1. steel work combined dam on an empty stomach; Contain concrete bearing platform and the steel work assembled panel on buttress below some concrete buttress, the buttress; Below concrete bearing platform, be provided with impervious wall; Described steel work assembled panel cross section and buttress cross section coupling are coated on above the buttress and both sides; This steel work assembled panel contains inner skeleton and overlays on two lip-deep unit of skeleton steel plate with several; Splicing slit between the adjacent unit steel plate is positioned at the skeleton place; Steel plate edge, described unit is connected on the skeleton through securing member, and the edge joint position of adjacent unit steel plate is provided with hermetically-sealed construction.
2. steel work according to claim 1 is combined dam on an empty stomach, it is characterized in that: described skeleton is to contain vertical beam and the crossbeam that intersects in length and breadth, and vertical beam and crossbeam all adopt i iron or channel-section steel; The vertical beam of described skeleton bottom and the spacing of vertical beam are less than the spacing of the vertical beam and the vertical beam on skeleton top, and the crossbeam of described skeleton bottom and the spacing of crossbeam are less than the spacing of the crossbeam and the crossbeam on skeleton top.
3. steel work according to claim 1 is combined dam on an empty stomach; It is characterized in that: described hermetically-sealed construction contains approximate " several " font weather strip of cross section; Between the slit of two adjacent unit steel plates of the bossing clamping of sealing bar; Two lower edges of sealing bar are fitted in respectively between the surface of unit steel plate and skeleton, and are fixed by described securing member.
4. steel work according to claim 1 is combined dam on an empty stomach; It is characterized in that: described hermetically-sealed construction contains approximate " Ω " font weather strip of cross section; Two lower edges of sealing bar bottom are fitted in respectively between the surface of unit steel plate and skeleton, and are fixed by described securing member; Sealing bar top is cap, and this cap covers outside the seam of adjacent unit steel plate.
5. steel work according to claim 1 is combined dam on an empty stomach, it is characterized in that: be connected through stone bolt between the lower edges of described steel work assembled panel and the riverbed toe board, and be provided with hermetically-sealed construction; Between the edge at dam body two ends and riverbed toe board, being connected of described steel work assembled panel through stone bolt, and be provided with hermetically-sealed construction.
6. steel work according to claim 1 is combined dam on an empty stomach, it is characterized in that: the lower edges of described steel work assembled panel embeds interior one section of riverbed toe board, and is provided with hermetically-sealed construction; In the edge at dam body two ends embeds the riverbed toe board one section of described steel work assembled panel, and be provided with hermetically-sealed construction.
7. steel work according to claim 1 is combined dam on an empty stomach, and it is characterized in that: described concrete bearing platform and concrete buttress are the line of demarcation with the riverbed surface, are concrete bearing platform below, are concrete buttress above.
8. steel work according to claim 1 is combined dam on an empty stomach; It is characterized in that: described concrete bearing platform comprises the half dam body on cushion cap pedestal and its top; The cushion cap pedestal is positioned at the riverbed; The half dam body is positioned at top, riverbed, and described concrete buttress is positioned at half dam body top, the cross sectional shape of half dam body and buttress cross sectional shape coupling.
9. steel work according to claim 1 is combined dam on an empty stomach, and it is characterized in that: be provided with inserts in the cavity between the described buttress, this inserts is a building waste.
10. steel work according to claim 1 is combined dam on an empty stomach, and it is characterized in that: described steel work assembled panel surface is provided with the preserving and sealing coating of polyurea materials.
CN2011100634107A 2011-03-16 2011-03-16 Steel structure open web combined dam Expired - Fee Related CN102155006B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011100634107A CN102155006B (en) 2011-03-16 2011-03-16 Steel structure open web combined dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011100634107A CN102155006B (en) 2011-03-16 2011-03-16 Steel structure open web combined dam

Publications (2)

Publication Number Publication Date
CN102155006A CN102155006A (en) 2011-08-17
CN102155006B true CN102155006B (en) 2012-05-30

Family

ID=44436660

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011100634107A Expired - Fee Related CN102155006B (en) 2011-03-16 2011-03-16 Steel structure open web combined dam

Country Status (1)

Country Link
CN (1) CN102155006B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103031822A (en) * 2011-09-30 2013-04-10 杨清太 Construction method for arched structure thin-layer wall surface water seepage pressure reduction dam
CN102912769B (en) * 2012-10-29 2015-02-04 天津大学 Dragline buttress steel dam
CN107869351B (en) * 2017-11-15 2019-07-19 中国水利水电第十一工程局有限公司 A kind of method of high narrow type large size solution cavity Cavity treatment security protection
CN113322904B (en) * 2021-06-04 2022-08-19 中国电建集团成都勘测设计研究院有限公司 High-spraying impervious wall for covering layer foundation concrete dam and construction method thereof
CN113789759B (en) * 2021-09-24 2022-06-21 中国矿业大学(北京) Assembled arc-shaped artificial dam body of coal mine underground reservoir and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2521254Y (en) * 2002-02-10 2002-11-20 杨继华 Steel cable flexible dam
CN2858770Y (en) * 2005-12-26 2007-01-17 李文良 Steel skeleton construction used for concrete dam
CN101974896A (en) * 2010-10-27 2011-02-16 华北水利水电学院 Buttress-type steel structure dam
CN201972138U (en) * 2011-03-16 2011-09-14 华北水利水电学院 Hollow combined dam with steel structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008184873A (en) * 2007-01-31 2008-08-14 Nippon Steel & Sumikin Metal Products Co Ltd Stone-filled structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2521254Y (en) * 2002-02-10 2002-11-20 杨继华 Steel cable flexible dam
CN2858770Y (en) * 2005-12-26 2007-01-17 李文良 Steel skeleton construction used for concrete dam
CN101974896A (en) * 2010-10-27 2011-02-16 华北水利水电学院 Buttress-type steel structure dam
CN201972138U (en) * 2011-03-16 2011-09-14 华北水利水电学院 Hollow combined dam with steel structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
JP特开2008-184873A 2008.08.14

Also Published As

Publication number Publication date
CN102155006A (en) 2011-08-17

Similar Documents

Publication Publication Date Title
CN102155006B (en) Steel structure open web combined dam
CN106436893A (en) Fully-prefabricated structure and construction method thereof
CN203222815U (en) Composite basement-structure exterior wall construction formed by utilizing underground diaphragm wall
CN205604290U (en) Frame energy dissipation formula of turning up utility tunnel structure
CN201326184Y (en) Connection joint structure for top plate of subway station and bottom plate of foundation pit
CN202416379U (en) Precipitation post-pouring belt capable of stopping dewatering in advance
CN205935184U (en) Take single -side supporting formwork basement outer wall of flexible waterproof layer external mold
CN203856099U (en) Environment-friendly energy-saving cast-in-place heat-insulating windowed composite exterior wall system
CN202416324U (en) Beam and slab structure superposed through top-down beam and down-top slab construction of foundation pit project
CN204662506U (en) A kind of cable communication well
CN201972138U (en) Hollow combined dam with steel structure
CN206035045U (en) Prefabricated assembled underground granary of endocyst plastics
CN206205166U (en) It is a kind of can synchronous crossed construction outer wall of basement waterproofing protection structure
CN103397600A (en) Method for arranging water stops in box body jacking process
CN203412143U (en) Wall body structure of integrally poured building house
CN206189966U (en) Circular underground granary of slot -in type prefabricated assembled of inside and outside equal steel plated
CN206035044U (en) Prefabricated assembled underground granary of plastic cover echelonment
CN206189972U (en) Circular underground granary of prefabricated assembled of outer steel plated echelonment
CN206035052U (en) Prefabricated caulking strips's in area circular underground granary of outer steel plated assembled
CN204609047U (en) A kind of external wall structure of lightgage steel joist building
CN204609078U (en) A kind of floor slab structure of lightgage steel joist building
CN204645097U (en) A kind of hydro-expansive rubber repairs deformation joint structure
CN109267543B (en) Water stop template
CN201137218Y (en) Bottom board post pouring strip indwelling stages temporary protection structure
CN206189964U (en) Circular underground granary of prefabricated assembled of steel plated in slot -in type

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120530

CF01 Termination of patent right due to non-payment of annual fee