CN102140789A CN 201010505324 CN201010505324A CN102140789A CN 102140789 A CN102140789 A CN 102140789A CN 201010505324 CN201010505324 CN 201010505324 CN 201010505324 A CN201010505324 A CN 201010505324A CN 102140789 A CN102140789 A CN 102140789A
Authority
CN
China
Prior art keywords
jacket
float
barge
shallow water
water jacket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010505324
Other languages
English (en)
Inventor
王翎羽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HAIWANGXING OCEAN ENGINEERING TECHNOLOGY Co LTD TIANJIN CITY
Original Assignee
HAIWANGXING OCEAN ENGINEERING TECHNOLOGY Co LTD TIANJIN CITY
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HAIWANGXING OCEAN ENGINEERING TECHNOLOGY Co LTD TIANJIN CITY filed Critical HAIWANGXING OCEAN ENGINEERING TECHNOLOGY Co LTD TIANJIN CITY
Priority to CN 201010505324 priority Critical patent/CN102140789A/zh
Publication of CN102140789A publication Critical patent/CN102140789A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

一种新的浅水导管架设计及安装方法,其特征在于运输驳采用连体双浮筒驳,或称双浮筒驳。将导管架拖拉到此双浮筒驳上并进行固定,同时在导管架上方导管架上安装平衡浮筒。拖拉到现场附近将平衡浮筒灌水,调整双浮筒驳,解脱尾部轴连接,调载让子船绕着“剩下的轴”缓慢旋转,使导管架翻转处于立正姿态,再通过调载下沉直至就位。就位和初步固定后,解除双浮筒驳和平衡浮筒。本发明的有益效果是,导管架进行海上安装时,不需要动用租金昂贵且资源十分紧张的大型浮吊,降低安装费用,同时减少工作量,缩短海上施工时间。

Description

一种新的浅水导管架设计及安装方法
技术领域
本发明属于海洋工程领域导管架安装方法的创新。
背景技术
导管架是近海平台的一种支撑结构,由钢管焊接而成,一般在陆地上总装后,运到海上安装。导管架体积大、重量大,所以其运输与安装都十分复杂。导管架的运输方式主要有两种:一种是湿运,另一种是驳运。通常的浅水导管架自重大于浮力,因此常采用驳运。采用驳运时,导管架在陆地上总装后,用轨道将其滑到驳船上,绑扎固定后运到海上安装地点,准备下水;若导管架重量较轻,可用大型浮吊将其从驳船上吊下,放入海里,扶正,定位。这种吊装下水方法安装费用比较昂贵,且施工时间比较长。
发明内容
本发明的目的是针对现有技术中存在的上述缺陷,发明一种新的浅水导管架设计及安装方法。其特征在于海上施工时不需要动用租金昂贵且资源十分紧张的大型浮吊,减少费用,同时减少工作量,缩短施工周期。
本发明解决其技术问题所采用的技术方案是运输驳采用连体双浮筒驳或称双浮筒驳。将导管架拖拉到此双浮筒驳上并进行固定,同时在导管架上方导管架上安装平衡浮筒。拖拉到现场附近将平衡浮筒灌水,调整双浮筒驳,解脱尾部轴连接,调载让子船绕着“剩下的轴”缓慢旋转,使导管架翻转处于立正姿态,再通过调载下沉直至就位。就位和初步固定后,解除双浮筒驳和平衡浮筒。
本发明的有益效果是如上所述,导管架进行海上安装时,不需要动用租金昂贵且资源十分紧张的大型浮吊,降低安装费用,同时减少工作量,缩短海上施工时间。
附图说明
以下结合附图及实施例对本发明作进一步说明。
图1是本发明的导管架设计结构图;
图2是本发明的导管架装船固定图;
图3是本发明的导管架调载翻转图;
图4是本发明的导管架竖直状态图;
图5是本发明的导管架入泥就位图;
图6是本发明的导管架安装完成图。
其中:1-双浮筒驳;2-母船;3-子船;4-箱形梁轨道;5-履带吊;6-导管架;7-销孔;8-液压缸;9-平衡浮筒;10-滑行轨道;11-连接轴;12-水面;13-泥面。
具体实施方式
主要施工船舶为海王星公司研发建造的海恩302号组合式工程驳,即双浮筒驳,其中母船2总长99米,型宽32米,型深6.5米,空载吃水3米,满载吃水4.5米,载货量8000吨,锚机8台(舱内),卷扬机4台;子船3总长35.8米,型宽16.5米,型深6.5米。子船3与母船2由两轴11连接,可旋转,可拆卸;250吨履带吊(扶正吊),可拆除,可调整甲板位置;可加装箱型悬挑梁,长24米,宽3米,高3米;一台40吨克令吊5,可拆卸。
双浮筒驳1首先进行码头装船,用两台拖拉绞车将安装有平衡浮筒9的导管架6拖拉到此双浮筒驳1上,并进行固定。
导管架6拖拉装船的步骤为:
●靠泊,调整双浮筒驳1位置使子船3上的滑行轨道10与码头滑道对齐;
●在双浮筒驳1甲板上焊接装船固定结构预安装部分;
●导管架6下部结构连接拖拉缆绳及滑轮组;
●切割导管架6下部结构固定结构;
●拖拉至双浮筒驳1上;
●安装导管架6翻转临时固定结构;
●安装直径4米,长10米的平衡浮筒9,可提供浮力约125吨。
双浮筒驳1到达施工地点后,调整双浮筒驳1位置,抛锚就位,开始进行导管架6的安装。
其中导管架6安装的步骤为:
●将平衡浮筒9灌水,调整双浮筒驳1位置;
●调整子船3,解脱尾部轴7连接;
●调载让子船3绕着“剩下的轴”7缓慢旋转,导管架6翻转入水;
●导管架6下部基础缓慢翻转至竖直状态,履带吊5逐渐受力;
●翻转成竖直状态后,用履带吊5提升导管架1米,让导管架6限位轴脱离甲板上的限位板;
●吊起导管架6后,向后移动5米,让导管架6可以自由下放;
●下放导管架6至泥面13,让导管架6处于稳定状态;
●利用履带吊5回收平衡浮筒9至母船2甲板。

Claims (4)

1.一种新的浅水导管架设计及安装方法,其特征在于在导管架上方导管架上安装平衡浮筒,以解决浅水导管架自重大于浮力的问题。
2.根据权利要求1所述的一种新的浅水导管架设计及安装方法,其特征是:当安装有平衡浮筒的导管架拖拉到现场附近后,将平衡浮筒灌水,调整双浮筒驳,解脱尾部轴连接,调载让子船绕着“剩下的轴”缓慢旋转,使导管架处于立正姿态,再通过下沉直至就位。
3.根据权利要求1所述的一种新的浅水导管架设计及安装方法,其特征是:平衡浮筒在完成这次的浅水导管架安装后,利用履带吊回收浮筒至母船甲板,通过拖轮浮拖至码头,吊装上岸后,可以回收达到重复利用。
4.根据权利要求1所述的一种新的导管架设计及安装方法,其特征是:所说的双浮筒驳是采用海王星公司自主研发的海恩302号组合式工程驳。
CN 201010505324 2010-10-13 2010-10-13 一种新的浅水导管架设计及安装方法 Pending CN102140789A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010505324 CN102140789A (zh) 2010-10-13 2010-10-13 一种新的浅水导管架设计及安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010505324 CN102140789A (zh) 2010-10-13 2010-10-13 一种新的浅水导管架设计及安装方法

Publications (1)

Publication Number Publication Date
CN102140789A true CN102140789A (zh) 2011-08-03

Family

ID=44408567

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010505324 Pending CN102140789A (zh) 2010-10-13 2010-10-13 一种新的浅水导管架设计及安装方法

Country Status (1)

Country Link
CN (1) CN102140789A (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102852147A (zh) * 2012-10-09 2013-01-02 中国海洋石油总公司 导管架单扒杆双钩扶正方法
CN103373447A (zh) * 2012-04-13 2013-10-30 上海利策科技股份有限公司 一种导管架拆除船及导管架拆除方法
CN103373446A (zh) * 2012-04-13 2013-10-30 上海利策科技股份有限公司 导管架拆除船及拆除方法
CN103410133A (zh) * 2013-08-20 2013-11-27 中国海洋石油总公司 利用气囊对深水导管架进行海上安装的方法
CN103422483B (zh) * 2013-08-20 2016-05-11 中国海洋石油总公司 浅水导管架浮托安装的方法
WO2017141177A1 (en) * 2016-02-15 2017-08-24 Oceanfront Technology Llc Barge system
CN108884650A (zh) * 2016-02-18 2018-11-23 格林恩特伦斯公司 用于在海洋的海床中安装单柱平台的定位设备和装置
CN112977730A (zh) * 2021-03-08 2021-06-18 凯若普(厦门)技术服务有限公司 一种导管架运输安装系统
CN114620196A (zh) * 2022-03-31 2022-06-14 中海石油(中国)有限公司 导管架浮筒装置及带有浮筒装置三腿导管架安装方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1084923A (zh) * 1992-09-16 1994-04-06 巴西石油公司 支撑海洋平台的带加宽底座的导管架结构
CN101774422A (zh) * 2009-12-30 2010-07-14 天津市海王星海上工程技术有限公司 一种新型海上安装施工资源-组合式工程驳
CN101781887A (zh) * 2009-12-30 2010-07-21 天津市海王星海上工程技术有限公司 一种海上平台上部结构悬挑安装方法
CN201534603U (zh) * 2009-11-20 2010-07-28 中国海洋石油总公司 海洋工程双体船

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1084923A (zh) * 1992-09-16 1994-04-06 巴西石油公司 支撑海洋平台的带加宽底座的导管架结构
CN201534603U (zh) * 2009-11-20 2010-07-28 中国海洋石油总公司 海洋工程双体船
CN101774422A (zh) * 2009-12-30 2010-07-14 天津市海王星海上工程技术有限公司 一种新型海上安装施工资源-组合式工程驳
CN101781887A (zh) * 2009-12-30 2010-07-21 天津市海王星海上工程技术有限公司 一种海上平台上部结构悬挑安装方法

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103373447B (zh) * 2012-04-13 2015-12-30 上海利策科技股份有限公司 一种导管架拆除船及导管架拆除方法
CN103373447A (zh) * 2012-04-13 2013-10-30 上海利策科技股份有限公司 一种导管架拆除船及导管架拆除方法
CN103373446A (zh) * 2012-04-13 2013-10-30 上海利策科技股份有限公司 导管架拆除船及拆除方法
CN102852147A (zh) * 2012-10-09 2013-01-02 中国海洋石油总公司 导管架单扒杆双钩扶正方法
CN103422483B (zh) * 2013-08-20 2016-05-11 中国海洋石油总公司 浅水导管架浮托安装的方法
CN103410133B (zh) * 2013-08-20 2015-12-23 中国海洋石油总公司 利用气囊对深水导管架进行海上安装的方法
CN103410133A (zh) * 2013-08-20 2013-11-27 中国海洋石油总公司 利用气囊对深水导管架进行海上安装的方法
WO2017141177A1 (en) * 2016-02-15 2017-08-24 Oceanfront Technology Llc Barge system
CN108884650A (zh) * 2016-02-18 2018-11-23 格林恩特伦斯公司 用于在海洋的海床中安装单柱平台的定位设备和装置
CN108884650B (zh) * 2016-02-18 2020-12-11 格林恩特伦斯公司 用于在海洋的海床中安装单柱平台的定位设备和装置、以及安装和拆卸单柱平台的方法
CN112977730A (zh) * 2021-03-08 2021-06-18 凯若普(厦门)技术服务有限公司 一种导管架运输安装系统
CN112977730B (zh) * 2021-03-08 2022-02-25 凯若普(厦门)技术服务有限公司 一种导管架运输安装系统
CN114620196A (zh) * 2022-03-31 2022-06-14 中海石油(中国)有限公司 导管架浮筒装置及带有浮筒装置三腿导管架安装方法
CN114620196B (zh) * 2022-03-31 2023-02-21 中海石油(中国)有限公司 导管架浮筒装置及带有浮筒装置三腿导管架安装方法

Similar Documents

Publication Publication Date Title
CN102140789A (zh) 一种新的浅水导管架设计及安装方法
JP5750537B1 (ja) 洋上構造物の施工方法
CN101774422B (zh) 一种海上安装施工资源-组合式工程驳
CN105035260B (zh) 利用双船浮托整体拆除海上弃置平台上部组块的方法
CN108626078B (zh) 一种海上风机Spar型浮式基础驳船助运扶装工艺
CN101707951A (zh) 运输、竖起和替换近海风力涡轮机的含有转子的机舱的方法以及实施该方法的船只
CN101850831A (zh) 一种大型远洋海工平台生活区总段吊装方法
CN102433890B (zh) 海上漂浮式风机基础及其定位系统
WO2014187977A1 (en) Deep-draft floating foundation for wind turbine with clustered hull and compartmented ballast section and self-erecting pivoting installation process thereof
CN103661827A (zh) 海上潮间带区域的风机总成安装系统及其施工方法
CN109911125A (zh) 一种海上风电基础钢管桩的滚装上船方法
CN103883273A (zh) 利用饱和潜水支持船上的双吊机安装立管的方法
Sharma et al. Issues in offshore platform research-Part 1: Semi-submersibles
CN106828812A (zh) 半潜式深海风电安装平台及其风力发电机组整体安装方法
CN101428712B (zh) 风力发电机组整体牵引装船的方法
CN105151239A (zh) 用于双船浮托整体拆除海上平台上部组块的船侧支撑结构
CN103693170A (zh) 一种漂浮式海上风电组装平台及用该平台组装海上风机的方法
Copple et al. Tension leg wind turbine (TLWT) conceptual design suitable for a wide range of water depths
CN114179983A (zh) 一种浮式风机平台安装方法
CN103373446B (zh) 导管架拆除船及拆除方法
CN102530189A (zh) 用于海洋工程的双体船
CN106232468B (zh) 具有转向架轮的外转塔
CN101761691A (zh) 一种浮管绑扎拖管法工艺
CN102206938A (zh) 一种新的海上平台上部组块安装方法
Crowle et al. Tow Out Calculations for Floating Wind Turbines

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20110803