CN102128047A - Gas-slag separation and recovering system for drilling construction - Google Patents
Gas-slag separation and recovering system for drilling construction Download PDFInfo
- Publication number
- CN102128047A CN102128047A CN2011100279073A CN201110027907A CN102128047A CN 102128047 A CN102128047 A CN 102128047A CN 2011100279073 A CN2011100279073 A CN 2011100279073A CN 201110027907 A CN201110027907 A CN 201110027907A CN 102128047 A CN102128047 A CN 102128047A
- Authority
- CN
- China
- Prior art keywords
- gas
- drilling
- tube connector
- drilling construction
- drill
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Abstract
The invention belongs to the field of safety of coal mine downhole gas extraction and drilling construction, and particularly relates to a gas-slag separation and recovering system for drilling construction, which comprises a drill and a water-spraying dust prevention system, wherein a drill stem kit of the drill is provided with a three-way hole packer; the three-way hole packer is connected with a connection pipe; the connection pipe is connected with a transmission pipeline through a three-way pipe; the connection pipe is provided with a throttling valve which is used for controlling the flow of drill cuttings to prevent the transmission pipeline from being blocked by the excessive drill cuttings; one end of the transmission pipeline is connected with a blower, and the other end of the transmission pipeline is connected with a closed space; the other end of the closed space is connected with a negative-pressure drainage pipe connected to a ground gas extraction system; and the closed space is provided with the water-spraying dust prevention system and a slag removal door which are used for separating the drill cuttings. The recovering system provided by the invention can safely and efficiently separate the drill cuttings and gas in the drilling process of the drill in coal mine downhole gas extraction and drilling construction.
Description
Technical field
The invention belongs to coal mine gas extraction borehole construction safety field, particularly relate to a kind of drilling construction gas quarrel separation and recovery system.
Background technology
In the process of projecting coal bed construction base plate protrusion-dispelling boring; gas occurring through regular meeting vomits from boring; spray the phenomenon of a large amount of coal borer bits simultaneously; so just caused that working space gas raises; construction drill is forced to stop work; operation occurs off and on; the blindness construction that local gas transfinites and do not check can appear again; cause the generation of gas accident; can solve drilling construction when holing spray orifice not though traditional employing mine car is collected drilling cuttings and gas, the chance spray orifice of holing just can't solve when serious.A large amount of gas must be discharged into the exhaust ventilation system of mine by booster after working space is gushed out, the gas that ventilation system is discharged can not be recycled, and directly is discharged into airspace, 1m
3The gas emptying is equivalent to 21m
3Carbon dioxide has caused the environment pollution and the wasting of resources to the harm of atmospheric ozone layer.
Summary of the invention
The technical problem to be solved in the present invention provides a kind of recovery system that can separate drilling cuttings and gas under coal mine in the construction mash gas pumping drilling process safely, efficiently.
Content of the present invention is that it comprises rig and watering dust prevention system, the drilling rod of described rig is set with the threeway hole packer, described threeway hole packer is connected with tube connector, tube connector is connected with conveyance conduit by tee piece, described tube connector is provided with control drilling cuttings flow and is unlikely to the choke valve that stops up because of drilling cuttings is excessive to guarantee conveyance conduit, one end of described conveyance conduit is connected with blast fan, the conveyance conduit other end is connected with confined space, the other end of described confined space is connected with the negative pressure releasing pipe that links to each other with ground gas pumping system, and described confined space is equipped with watering dust prevention system and the deslagging door that is used to separate drilling cuttings.
Described tee piece is provided with the throttling gate valve of regulating be used to hole exhaust and drilling cuttings tolerance; The tail end of described threeway hole packer is provided with the joint with packing_seal, and the joint is provided with the moistening feed pipe of blastproof maintenance packing; Being used to of described tee piece connects the angle of two pipelines of blast fan and tube connector less than 90 °; Described tube connector is the flame-retardant and anti-static high-pressure hose.
The invention has the beneficial effects as follows, the present invention utilizes the gas pressure of ejection in the boring and utilizes the air pressure of blast fan to do power, drive methane gas and drilling cuttings, reach methane gas and drilling cuttings are rejected to another space, make working space reach the purpose of safety work, effectively improved the operation work efficiency, guaranteed construction safety, comprehensively recyle the gas resources generating, reduce gas atmosphere airborne release contaminated environment.
When drilling machine construction is worn coal, to hole the import envelope in fact with threeway hole packer (being the threeway metal tube), drilling rod passes threeway hole packer center and creeps into forward, high pressure gas gas and drilling cuttings are by the boring threeway hole packer of flowing through, at tube connector of threeway hole packer external application, being preferably bourdon tube derives, and inserts conveyance conduit at the tail end of tube connector with a tee piece, conveyance conduit adopts the blast fan air-supply, is preferably Roots blower.Make methane gas and drilling cuttings deliver to a confined space along conveyance conduit, the external mine extraction of confined space system, the extraction system extracts methane gas out in the extraction process, drilling cuttings by watering dust prevention system precipitation separation in confined space, in the drilling construction process, the drilling cuttings of boring ejection and methane gas are in brill outwards in the ejection process, enter conveyance conduit along the threeway hole packer tube connector of flowing through, all in the pipeline of sealing, flow, can not enter working space, can not cause that the working space gas density raises, through after conveyance conduit enters confined space, treat that the gas extraction finishes after, open the air door of confined space, drilling cuttings is cleaned out, and confined space can be made construction drill again again and use.Confined space of the present invention can be that the crossdrift tunnel of a utilization installs fire dam and deslagging door additional, and spatial volume is 100m
2About, do not need to increase too many investment, economical rationality.Watering dust prevention of the present invention system comprises water pump and dispersing device, is used for precipitation and separates drilling cuttings, is beneficial to recycle methane gas.
The present invention is in application process, and the drilling cuttings of ejection is not of uniform size in the boring, and when too big, discharge of pipes is not smooth, and therefore tee piece is provided with a throttling gate valve, regulates for boring exhaust and drilling cuttings tolerance.In addition, boring air pressure hour can normally be discharged for guaranteeing gas and drilling cuttings, and the connecting pipe between threeway hole packer and the tee piece is set to 10m and is advisable.
In practice of construction, existence activity space between drilling rod and the threeway hole packer, the gas in the boring can be discharged by threeway hole packer tail end, for guaranteeing safety, connect a joint at threeway hole packer tail end, an external feed pipe is provided with packing in the feed pipe on joint, often opening feed pipe supplies water, keep packing moistening, prevent that the friction of drilling rod and threeway hole packer from producing spark, security incident such as blast, described packing is often fastening, makes it air tight.
The present invention carries air conducting to go into boring for not making blast fan, and being used to of tee piece connects the angle of two pipelines of blast fan and tube connector less than 90 °, is advisable with 30 °.
Conveyance conduit of the present invention and tube connector adopt the soft releasing pipe of flame-retardant and anti-static high pressure, prevent to produce spark with the drilling cuttings collision, and security incident takes place.
Description of drawings
Accompanying drawing is a structural representation of the present invention.
In the drawings, 1 blast fan, 2 rock mass, 3 threeway hole packers, 4 tube connectors, 5 conveyance conduits, 6 confined spaces, 7 negative pressure releasing pipes, 8 rigs, 9 choke valves, 10 coal bodies, 11 drilling rods, 12 watering dust prevention systems, 13 deslagging doors, 14 peep holes.
The specific embodiment
As shown in drawings, the present invention includes rig 8 and watering dust prevention system 12, the drilling rod 11 that it is characterized in that described rig 8 is set with threeway hole packer 3, described threeway hole packer 3 is connected with tube connector 4, tube connector 4 is connected with conveyance conduit 5 by tee piece, described tube connector 4 is provided with control drilling cuttings flow and is unlikely to the choke valve 9 that stops up because of drilling cuttings is excessive to guarantee conveyance conduit 5, one end of described conveyance conduit 5 is connected with blast fan 1, conveyance conduit 5 other ends are connected with confined space 6, the other end of described confined space 6 is connected with the negative pressure releasing pipe 7 that links to each other with ground gas pumping system, and described confined space 6 is equipped with watering dust prevention system 12 and the deslagging door 13 that is used to separate drilling cuttings.
Described tee piece is provided with the throttling gate valve of regulating be used to hole exhaust and drilling cuttings tolerance; The tail end of described threeway hole packer 3 is provided with the joint with packing_seal, and the joint is provided with the moistening feed pipe of blastproof maintenance packing; Being used to of described tee piece connects the angle of two pipelines of blast fan 1 and tube connector 4 less than 90 °; Described tube connector 4 is the flame-retardant and anti-static high-pressure hose.
Confined space 6 of the present invention is provided with peep hole 14, and peep hole 14 is used to observe the situation in the confined space 6, is used to judge the intensity that when needs to open deslagging door 13 and 12 waterings of watering dust prevention system.
When rig 8 of the present invention is constructed, on hydraulic drill rig 8 commonly used, installed the down-hole percussion drill head additional, adopt and press wind drive down-hole percussion drill head to creep into, solved the problem that the competent bed rate of penetration is slow, work efficiency is low, the compressed air pressure of supplying with rig 8 is controlled at 1-2 atmospheric pressure, and Roots blower 1 adopts NSR-125T type, power 15KW, in use general pressure is at 0.025Mpa, and the pressure of negative pressure releasing pipe 7 generally remains on normal extraction pressure 0.04-0.06Mpa.
During construction drill of the present invention, after starting rig 8, open the construction of pressure ventilation pipe switch air feed, drilling rod 11 passes rock mass 2 and enters coal body 10, start Roots blower 1 simultaneously, open the throttling gate valve to the appropriate location, drilling cuttings behind the drilling construction and gas are disposed to confined space 6 continuously by conveyance conduit 5.
Claims (5)
1. drilling construction gas quarrel separation and recovery system, comprise rig (8) and watering dust prevention system (12), the drilling rod (11) that it is characterized in that described rig (8) is set with threeway hole packer (3), described threeway hole packer (3) is connected with tube connector (4), tube connector (4) is connected with conveyance conduit (5) by tee piece, described tube connector (4) is provided with control drilling cuttings flow and is unlikely to the choke valve (9) that stops up because of drilling cuttings is excessive to guarantee conveyance conduit (5), one end of described conveyance conduit (5) is connected with blast fan (1), conveyance conduit (5) other end is connected with confined space (6), the other end of described confined space (6) is connected with the negative pressure releasing pipe (7) that links to each other with ground gas pumping system, and described confined space (6) is equipped with watering dust prevention system (12) and the deslagging door (13) that is used to separate drilling cuttings.
2. a kind of drilling construction gas quarrel separation and recovery system according to claim 1 is characterized in that described tee piece is provided with the throttling gate valve of regulating be used to hole exhaust and drilling cuttings tolerance.
3. a kind of drilling construction gas quarrel separation and recovery system according to claim 1 is characterized in that the tail end of described threeway hole packer (3) is provided with the joint of using packing_seal, and the joint is provided with the moistening feed pipe of blastproof maintenance packing.
4. a kind of drilling construction gas quarrel separation and recovery system according to claim 1, it is characterized in that described tee piece be used to connect the angle of two pipelines of blast fan (1) and tube connector (4) less than 90 °.
5. a kind of drilling construction gas quarrel separation and recovery system according to claim 1 is characterized in that described tube connector (4) is the flame-retardant and anti-static high-pressure hose.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011100279073A CN102128047B (en) | 2011-01-26 | 2011-01-26 | Gas-slag separation and recovering system for drilling construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011100279073A CN102128047B (en) | 2011-01-26 | 2011-01-26 | Gas-slag separation and recovering system for drilling construction |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102128047A true CN102128047A (en) | 2011-07-20 |
CN102128047B CN102128047B (en) | 2013-11-20 |
Family
ID=44266296
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011100279073A Expired - Fee Related CN102128047B (en) | 2011-01-26 | 2011-01-26 | Gas-slag separation and recovering system for drilling construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102128047B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102425446A (en) * | 2011-12-27 | 2012-04-25 | 重庆市能源投资集团科技有限责任公司 | Gas-residue separating integrated critical pumping device used for coal mine underground hole-drilling |
CN103195469A (en) * | 2013-04-09 | 2013-07-10 | 重庆大学 | Pneumatic type gas and slag separation device and method |
CN104481580A (en) * | 2014-12-23 | 2015-04-01 | 河南理工大学 | Method and device for repairing downhole coal-bed gas extraction drilled hole |
CN105649531A (en) * | 2015-12-21 | 2016-06-08 | 中国石油天然气集团公司 | Drilling equipment without drilling rigs |
CN106437820A (en) * | 2016-12-21 | 2017-02-22 | 重庆南桐矿业有限责任公司 | Current-layer drainage and drilling dustproof flame-retardant structure and operation method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU661116A1 (en) * | 1974-05-05 | 1979-05-05 | Shumko Yurij | Method of degassing worked-out space |
EP0067427A2 (en) * | 1981-06-10 | 1982-12-22 | Maschinenfabrik Korfmann GmbH | Gas suction method in coal mining, and suction pipe to perform this method |
CN200949476Y (en) * | 2006-05-22 | 2007-09-19 | 江西坪湖煤业有限责任公司 | Gas exhausting drilling deslagging duster removing apparatus |
CN201050381Y (en) * | 2007-06-12 | 2008-04-23 | 淮南矿业(集团)有限责任公司 | Blowout preventer for safety drilling of outburst coal seam |
CN201560795U (en) * | 2009-12-15 | 2010-08-25 | 山西晋城无烟煤矿业集团有限责任公司 | Apparatus for controlling dust with wind as medium during boring construction for gas drainage |
-
2011
- 2011-01-26 CN CN2011100279073A patent/CN102128047B/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU661116A1 (en) * | 1974-05-05 | 1979-05-05 | Shumko Yurij | Method of degassing worked-out space |
EP0067427A2 (en) * | 1981-06-10 | 1982-12-22 | Maschinenfabrik Korfmann GmbH | Gas suction method in coal mining, and suction pipe to perform this method |
CN200949476Y (en) * | 2006-05-22 | 2007-09-19 | 江西坪湖煤业有限责任公司 | Gas exhausting drilling deslagging duster removing apparatus |
CN201050381Y (en) * | 2007-06-12 | 2008-04-23 | 淮南矿业(集团)有限责任公司 | Blowout preventer for safety drilling of outburst coal seam |
CN201560795U (en) * | 2009-12-15 | 2010-08-25 | 山西晋城无烟煤矿业集团有限责任公司 | Apparatus for controlling dust with wind as medium during boring construction for gas drainage |
Non-Patent Citations (3)
Title |
---|
安山林等: "埃克钻机风排钻屑工艺试验", 《中州煤炭》 * |
朱丰玲等: "坪湖矿压风排碴工艺施工抽放钻孔试验", 《江西煤炭科技》 * |
林青等: "喷孔防护装置在突出煤层钻孔施工中的应用", 《煤炭技术》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102425446A (en) * | 2011-12-27 | 2012-04-25 | 重庆市能源投资集团科技有限责任公司 | Gas-residue separating integrated critical pumping device used for coal mine underground hole-drilling |
CN102425446B (en) * | 2011-12-27 | 2013-08-21 | 重庆市能源投资集团科技有限责任公司 | Gas-residue separating integrated critical pumping device used for coal mine underground hole-drilling |
CN103195469A (en) * | 2013-04-09 | 2013-07-10 | 重庆大学 | Pneumatic type gas and slag separation device and method |
CN104481580A (en) * | 2014-12-23 | 2015-04-01 | 河南理工大学 | Method and device for repairing downhole coal-bed gas extraction drilled hole |
CN105649531A (en) * | 2015-12-21 | 2016-06-08 | 中国石油天然气集团公司 | Drilling equipment without drilling rigs |
CN106437820A (en) * | 2016-12-21 | 2017-02-22 | 重庆南桐矿业有限责任公司 | Current-layer drainage and drilling dustproof flame-retardant structure and operation method |
Also Published As
Publication number | Publication date |
---|---|
CN102128047B (en) | 2013-11-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101446178B (en) | Wind pressure air drilling equipment in downhole soft outbursting coal bed and process matched therewith | |
CN102128047B (en) | Gas-slag separation and recovering system for drilling construction | |
CN202176355U (en) | Coal mine downhole drilling hole dust-reducing device | |
CN108678802A (en) | A kind of coal mine bores, punching, takes out integrated outburst prevention device and method | |
CN104481580B (en) | A kind of down-hole coal bed mash gas pumping drilling restorative procedure and the device of use thereof | |
WO2019169734A1 (en) | Integrated apparatus and method for long-distance downhole drilling and fracturing | |
CN110566127B (en) | Hole expanding drilling tool for drilling and hole expanding method thereof | |
CN111441723A (en) | Reverse circulation pipe following drilling construction device for large-diameter down-the-hole hammer | |
CN102747953A (en) | Multiple step type drilling and protecting integrated system and process for soft coal seam | |
CN103277129A (en) | Technology preventing gas on upper corner of coal mining working face from exceeding limit | |
CN204552809U (en) | Drill anti-spray orifice Pre-control System in a kind of colliery | |
CN206942804U (en) | A kind of novel hydropower punching operation machine | |
CN205047184U (en) | Colliery drill in pit with punching process in prevent spouting dust device | |
CN201221361Y (en) | Connecting downhole fully-mechanized mining and digging machine wind and water mixed spraying apparatus | |
CN110905589A (en) | Gas extraction drilling and punching coordination operation system and method | |
CN208416512U (en) | A kind of brill punching press integrated apparatus | |
CN205778536U (en) | A kind of drilling in coal anti-blocking instrument of jet deslagging | |
CN104514504A (en) | Drilling dust collection hood | |
CN204827294U (en) | Punch a hole with blowout preventer's drill way fixed structure in colliery | |
CN108561176B (en) | Automatic blocking and permeability-increasing device and method for gas extraction drilling | |
Qianhui | Research and application of auger-air drilling and sieve tube borehole protection in soft outburst-prone coal seams | |
CN101387203A (en) | Rapid dust removal method and device in tunnel | |
CN204851080U (en) | Mine high efficiency drilling rod | |
CN101122239A (en) | Coalbed drilling hole inside directional dissevering method | |
CN210134806U (en) | Coal seam gas extraction drilling hole repairing equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
DD01 | Delivery of document by public notice | ||
DD01 | Delivery of document by public notice |
Addressee: HUNAN LIDA ENERGY DEVELOPMENT Co.,Ltd. Document name: Notification to Pay the Fees |
|
DD01 | Delivery of document by public notice | ||
DD01 | Delivery of document by public notice |
Addressee: Liu Lian Document name: Notice of termination of patent |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20131120 Termination date: 20200126 |