CN102120503A - Quantitative steel pipe packing device and packing method thereof - Google Patents

Quantitative steel pipe packing device and packing method thereof Download PDF

Info

Publication number
CN102120503A
CN102120503A CN2010106248676A CN201010624867A CN102120503A CN 102120503 A CN102120503 A CN 102120503A CN 2010106248676 A CN2010106248676 A CN 2010106248676A CN 201010624867 A CN201010624867 A CN 201010624867A CN 102120503 A CN102120503 A CN 102120503A
Authority
CN
China
Prior art keywords
steel pipe
guard
framework
lock part
packing apparatus
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2010106248676A
Other languages
Chinese (zh)
Other versions
CN102120503B (en
Inventor
孙从磊
徐乃池
赵海洲
Original Assignee
Qingjian Group Co Ltd
Qingdao No 1 Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingjian Group Co Ltd, Qingdao No 1 Construction Group Co Ltd filed Critical Qingjian Group Co Ltd
Priority to CN201010624867.6A priority Critical patent/CN102120503B/en
Publication of CN102120503A publication Critical patent/CN102120503A/en
Application granted granted Critical
Publication of CN102120503B publication Critical patent/CN102120503B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a quantitative steel pipe packing device which comprises a bracket, wherein the bracket comprises support legs and enclosure rods connected with the support legs; an operation space containing steel pipes is formed between the support legs and the enclosure rods; and a forming mechanism for fixing and collecting the steel pipes is arranged in the operation space. Through the quantitative steel pipe packing device, the manual labor is greatly saved, and the packed steel pipes can be mechanically hoisted, thereby improving the working efficiency, reducing the construction cost and meeting the requirements on low-carbon economy of the society; meanwhile, the noise pollution in the construction process is reduced, the large-space occupation is avoided, the entire environment of the construction field is improved, and the energy is saved while environment is protected; after the steel pipes are packed by the technology, the working efficiency in loading/unloading and checking is three times of that of the original method; and the working efficiency is greatly improved, the relatively high popularization and application values are realized, and the good economical and social benefits can be produced.

Description

Quantitative packing apparatus of a kind of steel pipe and packaging method thereof
Technical field
The present invention relates to the quantitative packaging method of a kind of steel pipe, also discloses a kind of quantitative packing apparatus of steel pipe of realizing this quantitative packaging method, belongs to the vehicle for construction technical field.
Background technology
Along with the fast development of domestic construction market, steel pipe lease demand is also increasing.Yet construction market steel pipe lease at present generally is manually to load and unload, manually check, use this method and need spend the plenty of time and check, especially under the steel pipe situation different in size in steel pipe loading and unloading and quantity, work efficiency is low, and mistake also very easily appears in the cost height.
Summary of the invention
At the deficiency that prior art exists, technical matters to be solved by this invention is, provide a kind of simple in structure, reduce labour power, reduce the steel pipe loading and unloading, check the time, increase work efficiency, reduce the quantitative packing apparatus of steel pipe and the packaging method thereof of engineering cost.
For solving the problems of the technologies described above, the technical solution used in the present invention is: the quantitative packing apparatus of a kind of steel pipe, comprise support, described support reaches the bar of going along with sb. to guard him that links to each other with supporting leg by supporting leg and forms, supporting leg and go along with sb. to guard him between the bar and to form an operational space that holds steel pipe is provided with in the operational space and is used for fixing, receives the shaping mechanism of putting in order steel pipe.
The quantitative packing apparatus of above-mentioned steel pipe, described supporting leg comprise four vertical rods of vertical setting, and four vertical rods form four stiles of a cuboid framework, and the long limit of described cuboid framework is provided with the bar of going along with sb. to guard him that connects the two ends vertical rod.
The quantitative packing apparatus of above-mentioned steel pipe, described shaping mechanism comprises that a cross-sectional plane is the framework of going along with sb. to guard him of equilateral polygon, composition goes along with sb. to guard him the position-limited edge of framework and the bar of going along with sb. to guard him on the support is fixed, going along with sb. to guard him the keying mouth that is provided with the turnover of permission steel pipe on the framework, the described keying is provided for opening, closing the Lock Part that opens and closes mouth and receive whole steel pipe on the mouth, described Lock Part one end follows the position-limited edge that is adjacent hinged.
The quantitative packing apparatus of above-mentioned steel pipe can be provided with the handle of being convenient to open and close this Lock Part around the Lock Part that an end rotates.
The quantitative packing apparatus of above-mentioned steel pipe, the described framework of going along with sb. to guard him is regular pentagon structure or regular hexagon structure.
The quantitative packing apparatus of above-mentioned steel pipe, the quantity of described shaping mechanism are four, five or six.
The quantitative packing apparatus of above-mentioned steel pipe is provided with the location division of being convenient to the steel tube head alignment at support one end.
A kind of packaging method that uses the quantitative packing apparatus of the described steel pipe of claim 1:
A, with location division and bracket locked, hand-held handle is rotated down opens the Lock Part go along with sb. to guard him on the framework, opens to open and close mouthful;
B, steel pipe that will be to be packed are put into shaping mechanism successively, and steel pipe one end to be packed holds out against the location division on the support, makes its length unanimity;
C, treat that steel pipe fills up and go along with sb. to guard him framework, rotate up handle, close and open and close mouthful, lift handle firmly, make the inwall contact steel pipe of Lock Part, and the section and the adjacent position-limited edge of Lock Part is close as far as possible, make Lock Part press steel pipe, the steel pipe of going along with sb. to guard him in the framework is arranged in regular hexagon;
D, utilize hand baling press and strap that the steel pipe colligation is firm, use mechanical handling to transport trolley.
The advantage of quantitative packing apparatus of steel pipe of the present invention and packaging method thereof is:
1, economic effects.The present invention loads and unloads with original steel pipe, the mode of checking is compared, because packing back steel pipe quantity is definite numerical value, does not need on-the-spot artificial every to check, and has saved artificial greatly.Packing back steel pipe can adopt mechanical handling simultaneously, has improved work efficiency equally, reduces construction cost.Adopting this technology steel pipe to pack, laggard luggage unloads, checks is 3 times of former method work efficiency, and the steel pipe specification is more little big more, and it is big more to save cost.
2, duration effect.Because every bundle steel pipe quantity certain (61 or 91) does not need artificial every to check, and has saved the time greatly.
3, energy-conservation and environmental protection.This programme improves work efficiency in implementation process, cost-cutting meets society's requirement economic to " low-carbon (LC) ", also reduces the noise pollution of work progress simultaneously, avoids occupying large space, improves the integrated environment of camp site, energy-conserving and environment-protective.
4, the value of applying.Adopt this programme can solve the steel pipe loading and unloading, check need the cost plenty of time, an artificial difficult problem, and increase work efficiency, reduce engineering cost, have higher popularization and application values, can produce good economic benefit and social benefit.
Description of drawings
Fig. 1 is the structural representation of the quantitative packing apparatus of steel pipe of the present invention;
Fig. 2 is the running condition figure of the quantitative packing apparatus of steel pipe of the present invention;
Fig. 3 for shaping mechanism with go along with sb. to guard him bar welding structural representation;
Fig. 4 is the structural representation of shaping mechanism embodiment 1 among the present invention;
Fig. 5 is the structural representation of shaping mechanism embodiment 2 among the present invention.
The specific embodiment
Below in conjunction with drawings and the specific embodiments the present invention is described in further details;
As Fig. 1, Fig. 2, shown in Figure 3, the quantitative packing apparatus of a kind of steel pipe, comprise support 1, this support 1 reaches the bar 12 of going along with sb. to guard him that links to each other with supporting leg 11 by supporting leg 11 and forms, supporting leg 11 comprises four vertical rods 111 of vertical setting, four vertical rods 111 form four stiles of a cuboid framework, the long limit of described cuboid framework be provided with connect two ends vertical rod 111 go along with sb. to guard him bar 12, supporting leg 11 and go along with sb. to guard him between the bar 12 and to form an operational space 13 that holds steel pipe is provided with in operational space 13 and is used for fixing, receives the shaping mechanism 2 of putting in order steel pipe.This shaping mechanism 2 comprise a cross-sectional plane be equilateral polygon go along with sb. to guard him framework 21, composition is gone along with sb. to guard him the position-limited edge 211 of framework 21 and the bar 12 of going along with sb. to guard him on the support 1 welds, going along with sb. to guard him the keying mouth 22 that is provided with the turnover of permission steel pipe on the framework 21, opening and closing the Lock Part 23 that is provided for opening, close keying mouth 22 on the mouth 22 and receives whole steel pipe, for ease of opening and closing, this Lock Part 23 adopts an end with the position-limited edge 211 pivotally attached modes that are adjacent, and both reduces expenses, and is convenient to again produce.For making things convenient for control lock limiting-members 23, can be provided with the handle 24 of being convenient to open and close this Lock Part 23 around the Lock Part 23 that pin jointed end rotates.This goes along with sb. to guard him framework 21 can be the regular pentagon structure, also can be the regular hexagon structure.In view of the length difference of steel pipe, according to its specification, the quantity of shaping mechanism 2 can be installed four, five or six according to its length.Because steel pipe put into go along with sb. to guard him framework 21 in the alignment of its length be difficult to hold, also inconvenient when tying up and packing, for ease of checking and pack, be provided with the location division 3 of being convenient to the steel tube head alignment at an end of support 1.
As shown in Figure 2, use the method for the quantitative packing apparatus of this steel pipe to the steel pipe packing: at first, location division 3 and support 1 are locked, hand-held handle 24 is rotated down opens the Lock Part 23 of going along with sb. to guard him on the framework 21, opens and opens and closes mouth 22; Secondly, steel pipe to be packed is put into shaping mechanism 2 successively, steel pipe one end to be packed holds out against the location division 3 on the support 1, makes its length unanimity; Then, treat that steel pipe fills up and go along with sb. to guard him framework 21, rotate up handle 24, close and open and close mouth 22, lift handle 24 firmly, make the inwall contact steel pipe of Lock Part 23, and the section 25 of Lock Part 23 is close with adjacent position-limited edge 211 as far as possible, make Lock Part 23 press steel pipe, the steel pipe of going along with sb. to guard him in the framework 21 is arranged in regular hexagon. At last, utilize hand baling press and strap that the steel pipe colligation is firm, use mechanical handling to transport trolley.
As shown in Figure 2, be example with the framework 21 of going along with sb. to guard him of regular hexagonal section, with location division 3 and support 1 locking, hand-held handle 24 is rotated down opens the Lock Part 23 of going along with sb. to guard him on the framework 21, opens to open and close mouthfuls 22; Secondly, steel pipe to be packed is put into shaping mechanism 2 successively, steel pipe one end to be packed holds out against the location division 3 on the support 1, makes its length unanimity; Then, treating that steel pipe fills up goes along with sb. to guard him framework 21; Rotate up handle 24, close and open and close mouth 22, and it is the section 25 of Lock Part 23 is close with adjacent position-limited edge 211 as far as possible, lifting handle 24 firmly makes it press steel pipe, the steel pipe of going along with sb. to guard him in the framework is arranged in regular hexagon, at last, utilize hand baling press and strap that the steel pipe colligation is firm, use mechanical handling to transport trolley.
Consider on-the-spot handling (0.8 ton of the minimum hoisting weight of QTZ40 tower crane), the present invention has designed the packing mechanism of 2 kinds of different steel pipe quantity (61,91), and the every bundle weight of different size is with reference to as follows:
Figure BSA00000420275200031
Embodiment 1:
As above table and shown in Figure 4 adopts the framework 21 of safeguarding of present embodiment to tie up and pack, and can finish length specification is 4 meters, 6 meters; Quantity is 61; Weight is respectively the steel pipe packing of 0.74 ton and 1.10 tons.
Embodiment 2:
As above table and shown in Figure 5 adopts the framework 21 of safeguarding of present embodiment to tie up and pack, and can finish length specification is 1 meter, 1.5 meters, 2 meters, 2,5 meters, 3 meters; Quantity is 91; Weight is respectively the steel pipe packing of 0.28 ton, 1.40 tons, 0.55 ton, 0.70 ton and 0.83 ton.
Certainly, above-mentioned explanation is not to be limitation of the present invention, and the present invention also is not limited to above-mentioned giving an example; those skilled in the art; in essential scope of the present invention, the variation of making, remodeling, interpolation or replacement all should belong to protection scope of the present invention.

Claims (8)

1. quantitative packing apparatus of steel pipe, it is characterized in that: comprise support, described support is made up of the supporting leg and the bar of going along with sb. to guard him that links to each other with supporting leg, and supporting leg and go along with sb. to guard him formation one operational space that holds steel pipe between the bar is provided with in the operational space and is used for fixing, receives the shaping mechanism of putting in order steel pipe.
2. the quantitative packing apparatus of steel pipe according to claim 1, it is characterized in that: described supporting leg comprises four vertical rods of vertical setting, four vertical rods form four stiles of a cuboid framework, and the long limit of described cuboid framework is provided with the bar of going along with sb. to guard him that connects the two ends vertical rod.
3. the quantitative packing apparatus of steel pipe according to claim 1, it is characterized in that: described shaping mechanism comprises that a cross-sectional plane is the framework of going along with sb. to guard him of equilateral polygon, composition goes along with sb. to guard him the position-limited edge of framework and the bar of going along with sb. to guard him on the support is fixed, going along with sb. to guard him the keying mouth that is provided with the turnover of permission steel pipe on the framework, the described keying is provided for opening, closing the Lock Part that opens and closes mouth and receive whole steel pipe on the mouth, described Lock Part one end follows the position-limited edge that is adjacent hinged.
4. the quantitative packing apparatus of steel pipe according to claim 3 is characterized in that: can be provided with the handle of being convenient to open and close this Lock Part around the Lock Part that an end rotates.
5. the quantitative packing apparatus of steel pipe according to claim 4 is characterized in that: the described framework of going along with sb. to guard him is regular pentagon structure or regular hexagon structure.
6. the quantitative packing apparatus of steel pipe according to claim 5 is characterized in that: the quantity of described shaping mechanism is four, five or six.
7. the quantitative packing apparatus of steel pipe according to claim 6 is characterized in that: be provided with the location division of being convenient to the steel tube head alignment at support one end.
8. packaging method that uses the quantitative packing apparatus of the described steel pipe of claim 1: it is characterized in that:
A, with location division and bracket locked, hand-held handle is rotated down opens the Lock Part go along with sb. to guard him on the framework, opens to open and close mouthful;
B, steel pipe that will be to be packed are put into shaping mechanism successively, and steel pipe one end to be packed holds out against the location division on the support, makes its length unanimity;
C, treat that steel pipe fills up and go along with sb. to guard him framework, rotate up handle, close and open and close mouthful, lift handle firmly, make the inwall contact steel pipe of Lock Part, and the section and the adjacent position-limited edge of Lock Part is close as far as possible, make Lock Part press steel pipe, the steel pipe of going along with sb. to guard him in the framework is arranged in regular hexagon;
D, utilize hand baling press and strap that the steel pipe colligation is firm, use mechanical handling to transport trolley.
CN201010624867.6A 2010-12-31 2010-12-31 A kind of quantitative steel pipe packing apparatus and packaging method thereof Expired - Fee Related CN102120503B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010624867.6A CN102120503B (en) 2010-12-31 2010-12-31 A kind of quantitative steel pipe packing apparatus and packaging method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010624867.6A CN102120503B (en) 2010-12-31 2010-12-31 A kind of quantitative steel pipe packing apparatus and packaging method thereof

Publications (2)

Publication Number Publication Date
CN102120503A true CN102120503A (en) 2011-07-13
CN102120503B CN102120503B (en) 2015-12-09

Family

ID=44249194

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010624867.6A Expired - Fee Related CN102120503B (en) 2010-12-31 2010-12-31 A kind of quantitative steel pipe packing apparatus and packaging method thereof

Country Status (1)

Country Link
CN (1) CN102120503B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109229518A (en) * 2018-11-20 2019-01-18 袁福英 A kind of working method of steel tube hexagon shape automatic bonding unit

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4204788A (en) * 1978-07-31 1980-05-27 Massey John P Squaring device for storage of rods, tubes, and like articles
JPH06328293A (en) * 1993-05-14 1994-11-29 Nippon Steel Weld Prod & Eng Co Ltd Manufacture of wire containing additive
CN2367541Y (en) * 1999-04-19 2000-03-08 燕山大学 Middle rod-materiqal bundling machine of weld-buckling type
CN2595668Y (en) * 2003-01-23 2003-12-31 唐山钢铁股份有限公司 Packaging device for pipe shape material
WO2005113123A1 (en) * 2004-05-07 2005-12-01 Basf Aktiengesellschaft Method for structurally filling contact tubes of a bank of contact tubes
CN2811165Y (en) * 2005-06-20 2006-08-30 邯郸钢铁股份有限公司 Finished rod collecting device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4204788A (en) * 1978-07-31 1980-05-27 Massey John P Squaring device for storage of rods, tubes, and like articles
JPH06328293A (en) * 1993-05-14 1994-11-29 Nippon Steel Weld Prod & Eng Co Ltd Manufacture of wire containing additive
CN2367541Y (en) * 1999-04-19 2000-03-08 燕山大学 Middle rod-materiqal bundling machine of weld-buckling type
CN2595668Y (en) * 2003-01-23 2003-12-31 唐山钢铁股份有限公司 Packaging device for pipe shape material
WO2005113123A1 (en) * 2004-05-07 2005-12-01 Basf Aktiengesellschaft Method for structurally filling contact tubes of a bank of contact tubes
CN2811165Y (en) * 2005-06-20 2006-08-30 邯郸钢铁股份有限公司 Finished rod collecting device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109229518A (en) * 2018-11-20 2019-01-18 袁福英 A kind of working method of steel tube hexagon shape automatic bonding unit

Also Published As

Publication number Publication date
CN102120503B (en) 2015-12-09

Similar Documents

Publication Publication Date Title
CN202372357U (en) Load test device for support mechanism of nuclear power plant
CN207511682U (en) A kind of construction site stirrup ships nacelle device
CN201136732Y (en) Special tools for conveying square steel
CN102120503A (en) Quantitative steel pipe packing device and packing method thereof
CN203158194U (en) Bundling device for water transportation of transformer
CN205575411U (en) Building materials handling device
CN205911667U (en) Distribution lines cross arm hoisting support
CN206427326U (en) A kind of tubing hexagon packing fixture
CN204093310U (en) A kind of catalyst shipping unit of inside reactor
CN203544828U (en) Rain-leakage-preventing structure of open top container
CN205257770U (en) Excavator bundle welded tube operation special lifting device
CN206984028U (en) A kind of trolley for improving precast concrete production efficiency
CN202414098U (en) Device for container ship binding test
CN202098670U (en) Wind turbine tower conveying and elevating auxiliary device
CN203064569U (en) Waste collecting box
CN206665992U (en) A kind of plant equipment mast-up
CN206827933U (en) The overhead explosion-proof crane of robot type cutting machine
CN206486043U (en) A kind of equipment for being easy to grinding tool to move and load and unload
CN101597956A (en) Suspended scaffold
CN205906953U (en) Special hoist of poling machine
CN203243899U (en) High-temperature heating and disinfecting device for pickles
CN204124396U (en) Steel frame pipe bundling device
CN204402060U (en) The device of the overall inverted construction of steel work between a kind of multi-layer concrete bent columns
CN208265628U (en) A kind of civil engineering reinforcing bar transfer device
CN202465035U (en) Brick lifting device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Sun Conglei

Inventor after: Zhang Hongbo

Inventor after: Xu Naichi

Inventor after: Zhao Haizhou

Inventor after: Qu Shunkai

Inventor before: Sun Conglei

Inventor before: Xu Naichi

Inventor before: Zhao Haizhou

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20151103

Address after: 266031 Hangzhou Road, Sifang District, Shandong, China, No. 173, No.

Applicant after: Qingdao No.1 Construction Group Co., Ltd.

Address before: 266031 Hangzhou Road, Sifang District, Shandong, China, No. 173, No.

Applicant before: Qingdao No.1 Construction Group Co., Ltd.

Applicant before: Qingjian Group Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151209

Termination date: 20201231

CF01 Termination of patent right due to non-payment of annual fee